MONITORING

PEKERJAAN GRC
PROYEK AEON MIXED USE PHASE II – SENTUL CITY
MATERIAL PRODUKSI
Type
No Produksi Terkirim Instal 4%
Panel
1 CL – 1 12 4 3
2 CL – 2 9 4 3
3 CL – 3 13 2 2 96%
4 CL – 4 12 8 7
Produksi Belum Produksi
5 CL – 5 10 8 7
6 CL – 5 “ 9 3 3 TERKIRIM
7 CL – 6 11 1 2 1%
8 CL – 7 13 - -
9 CL – 8 20 - -
10 CL – 9 12 - -
99%
11 CL – 10 - - -
Terkirim Belum Terkirim
12 CL – 11 2 1 -
13 CL - 12 3 - -
INSTAL
14 CL – 12” 3 - -
15 CL – 13 3 - - 1%

16 CL – 14 2 - -
17 CL – 15 - - -
TOTAL 134 30 27 99%

Total Clading : 3353 panel Terinstal Belum Terinstal

MANPOWER
4 Group ( 32 orang )
MATERIAL
Produksi (panel)
Rnc : 28
Real : 53
Dev : + 10
Terkirim (panel)
Rnc : 11
Real : 18
Dev : +5
Instal (panel)
Rnc : 6
Real : 16
Dev : +10

MANPOWER
2 Group ( 8 orang)

Ket :

: Instal

: Gondola 1

: Gondola 2
MATERIAL
Produksi (panel)
Rnc : 28
Real : 53
Dev : + 10
Terkirim (panel)
Rnc : 11
Real : 12
Dev : - 1
Instal (panel)
Rnc : 6
Real : 10
Dev : + 4

MANPOWER
2 Group ( 8 orang)

Ket :

: Instal

: Gondola 1

: Gondola 2
MATERIAL
Produksi (panel)
Rnc : 28
Real : 28
Dev : 0
Terkirim (panel)
Rnc : 11
Real : 0
Dev : - 11
Instal (panel)
Rnc : 6
Real : 0
Dev : - 6

MANPOWER
-

Ket :

: Instal

: Gondola 1

: Gondola 2