PROYEK POS LINTAS BATAS NEGARA ( TERPADU ) LONG NAWANG

TANGGAL PENGAJUAN STATUS KETERANGAN


NO JENIS MATERIAL NO TRANSMITTAL LOKASI TEST TANGGAL TEST
PENGAJUAN AWAL REVISI 1 UPDATE REVISI

1 BATA MERAH /FR.11/PP-PLBN LN/VIII/2021 PROYEK 25 June 2021 20 August 2021 CLOSE
2 BESI D-10 /FR.11/PP-PLBN LN/VIII/2021 LAB.BETON & BAHAN BANGUNAN ITS SURABAYA 07 April 2021 20 August 2021 CLOSE
3 BESI D-13 /FR.11/PP-PLBN LN/VIII/2021 LAB.BETON & BAHAN BANGUNAN ITS SURABAYA 07 April 2021 20 August 2021 CLOSE
4 BESI D-16 /FR.11/PP-PLBN LN/VIII/2021 LAB.BETON & BAHAN BANGUNAN ITS SURABAYA 07 April 2021 20 August 2021 CLOSE
5 BESI D-19 /FR.11/PP-PLBN LN/VIII/2021 LAB.BETON & BAHAN BANGUNAN ITS SURABAYA 07 April 2021 20 August 2021 CLOSE
6 BETON K - 175 /FR.11/PP-PLBN LN/VIII/2021 UPTD LAB.BAHAN KONSTRUKSI PURR SAMARINDA 07 December 2020 20 August 2021 CLOSE
7 BETON K - 250 /FR.11/PP-PLBN LN/VIII/2021 UPTD LAB.BAHAN KONSTRUKSI PURR SAMARINDA 07 December 2020 20 August 2021 CLOSE
8 BETON K - 300 /FR.11/PP-PLBN LN/VIII/2021 UPTD LAB.BAHAN KONSTRUKSI PURR SAMARINDA 07 December 2020 20 August 2021 CLOSE
9 BETON K - 350 /FR.11/PP-PLBN LN/VIII/2021 UPTD LAB.BAHAN KONSTRUKSI PURR SAMARINDA 07 December 2020 20 August 2021 CLOSE