RFI SUMMARY
Contractor: Ashoka BuildCon Ltd

Chainage Detailes of Actual Works


Work done Chainage
Excuted DPR Qty Done Work Done By Remark Strip
Sr.No. RFI No. SubmissionInspection
Date Date Dept. Time Side Description
Chart
From To L B H Unit Qty
1 ABL/NHAI/RW/17-18/ 1 3/11/2017 4/11/2017 ROAD WORK 10.00 AM 0+000 56+889 BHS Project Video Recording Completed Km 56.889
2 ABL/NHAI/RW/17-18/ 2 3/11/2017 4/11/2017 ROAD WORK 2.30 PM 38+700 39+000 LHS Clearing & Grubbing Work Not Done N
3 ABL/NHAI/RW/17-18/ 3 5/11/2017 6/11/2017 ROAD WORK 2.30 PM 40+600 40+880 RHS Clearing & Grubbing 40+600 40+880 DPR-5.11.17 & 6.280 10 Sqm 2800 ABL D
4 ABL/NHAI/RW/17-18/ 4 6/11/2017 7/11/2017 LEVELS 10.00 AM 37+750 42+000 BHS Setting out of TBM & Travers Checking Completed Km 4.25 ABL
5 ABL/NHAI/RW/17-18/ 5 6/11/2017 7/11/2017 ROAD WORK 11.00 AM 37+750 42+000 BHS Inventory of Structure Completed Km 4.25 ABL
6 ABL/NHAI/RW/17-18/ 6 6/11/2017 7/11/2017 ROAD WORK 3.00 AM 40+400 40+600 RHS Clearing & Grubbing Work not Done Sqm Executed dt on 9.11.2017 N
7 ABL/NHAI/RW/17-18/ 7 6/11/2017 7/11/2017 ROAD WORK 3.00 AM 40+400 40+600 BHS Tree Cutting Work not done
8 ABL/NHAI/RW/17-18/ 8 7/11/2017 8/11/2017 ROAD WORK 10.00 AM 44+000 44+000 BHS Calibration cheking of RMC 30 Work not done
9 ABL/NHAI/RW/17-18/ 9 7/11/2017 8/11/2017 LEVELS 9.30 AM 0+000 5+000 BHS Setting out of TBM & Travers Checking Completed Km 5 ABL
10 ABL/NHAI/RW/17-18/ 10 7/11/2017 8/11/2017 ROAD WORK 3.00 PM 40+400 40+600 RHS Clearing & Grubbing 40+460 40+500 DPR-8.11.17 40 10 Sqm 400 ABL D
40+500 40+600 DPR-5.11.17 100 10 Sqm 1000 ABL
11 ABL/NHAI/RW/17-18/ 11
12 ABL/NHAI/RW/17-18/ 12
13 ABL/NHAI/RW/17-18/ 13 7/11/2017 8/11/2017 ROAD WORK 3.30 PM 37+750 38+100 BHS Tree Cutting Work not done
14 ABL/NHAI/RW/17-18/ 14 7/11/2017 8/11/2017 ROAD WORK 4.00 PM 45+500 46+000 RHS Electrical Pole Shifting (MS Pole 15 Nos.) Shifting Work Completed Km 0.5 ESPL D
15 ABL/NHAI/RW/17-18/ 15 8/11/2017 9/11/2017 LEVELS 10.00 AM 5+000 10+000 BHS Setting out of TBM Checking Completed Km 5 ABL
16 ABL/NHAI/RW/17-18/ 16 8/11/2017 9/11/2017 ROAD WORK 11.00 AM 42+300 43+000 LHS Electrical Utility Shifting 11 KVA Line (MS 4 Nos.& RCC 9Shifting Work Completed Km 0.7 ESPL D
17 ABL/NHAI/RW/17-18/ 17 8/11/2017 9/11/2017 ROAD WORK 3.00 PM 40+400 40+550 LHS Clearing & Grubbing Work done 40+400 40+550 DPR-09.11.17 150 10 Sqm 1500 ABL D
18 ABL/NHAI/RW/17-18/ 18 8/11/2017 9/11/2017 ROAD WORK 12.00 PM39+480,43+573,43+810RHS PHED (Hand Pump) shifting Checking Shifting Work Completed Nos 3 Om mati
19 ABL/NHAI/RW/17-18/ 19 9/11/2017 10/11/2017 LEVELS 10.00 AM 10+000 15+000 BHS Setting out of TBM Checking Completed Km 5 ABL
20 ABL/NHAI/RW/17-18/ 20 9/11/2017 10/11/2017 ROAD WORK 11.00 AM 45+800 46+100 LHS Electrical Utility Shifting 11 KVA Line (MS 2 Nos) Shifting Work Completed Km 0.3 ESPL D
21 ABL/NHAI/RW/17-18/ 21 9/11/2017 10/11/2017 ROAD WORK 3.00 PM 40+550 40+700 LHS Clearing & Grubbing Work done 40+550 40+600 DPR-10.11.17 50 10 Sqm 500 ABL Executed dt on 11.11.2017 D
22 ABL/NHAI/RW/17-18/ 22 9/11/2017 10/11/2017 ROAD WORK 11.45 AM41+060,54+940,55+260RHS PHED (Hand Pump) shifting Checking Shifting Work Completed Nos 3 Om mati
23 ABL/NHAI/RW/17-18/ 23
24 ABL/NHAI/RW/17-18/ 24
25 ABL/NHAI/RW/17-18/ 25 10/11/2017 11/11/2017 LEVELS 10.00 AM 15+000 20+000 BHS TBM Level checking Completed Km 5 ABL
26 ABL/NHAI/RW/17-18/ 26 10/11/2017 11/11/2017 ROAD WORK 11.00 AM 40+000 40+500 BHS Electrical Utility Shifting 11 KVA Line ( LHS RCC-10 No Shifting Work Completed Km 0.5 ESPL D
27 ABL/NHAI/RW/17-18/ 27 10/11/2017 11/11/2017 ROAD WORK 12.00 AM 38+900 39+500 LHS Clearing & Grubbing Work done 38+900 39+050 DPR-10.11.17 150 8 Sqm 1200 Dharmshila D

39+200 39+500 DPR-10.11.17 300 8 Sqm 2400 Dharmshila D


28 ABL/NHAI/RW/17-18/ 28 10/11/2017 11/11/2017 ROAD WORK 3.00 PM 40+100 40+400 LHS Clearing & Grubbing 40+150 40+400 DPR-10.11.17 250 10 Sqm 2500 Dharmshila D
29 ABL/NHAI/RW/17-18/ 29 10/11/2017 11/11/2017 ROAD WORK 11.30 AM43+500,43+300,54+750LHS PHED (Hand Pump) shifting Checking Shifting Work Completed Nos 3 Om Mati
30 ABL/NHAI/RW/17-18/ 30 11/11/2017 13/11/2017 LEVELS 10.00 AM 20+000 25+000 BHS TBM Level checking Completed Km 5 ABL
31 ABL/NHAI/RW/17-18/ 31 11/11/2017 13/11/2017 ROAD WORK 11.00 Am 41+900 42+200 RHS Electrical Utility Shifting 11 KVA Line (MS-2 Nos.) Shifting Work Completed Km 0.3 ESPL
32 ABL/NHAI/RW/17-18/ 32 11/11/2017 13/11/2017 ROAD WORK 12.00 AM 39+500 40+100 LHS Clearing & Grubbing 39+500 39+540 DPR-10.11.17 40 8 Sqm 320 Dharmshila D
39+540 39+760 DPR-11.11.17 220 7 Sqm 1540 Dharmshila D
39+760 39+950 DPR-12.11.17 190 7 Sqm 1330 Dharmshila D
39+950 40+060 DPR-13.11.17 110 8 Sqm 880 Dharmshila D
33 ABL/NHAI/RW/17-18/ 33 11/11/2017 13/11/2017 ROAD WORK 3.00 PM 40+400 40+600 LHS Clearing & Grubbing Work not Done Sqm
34 ABL/NHAI/RW/17-18/ 34 11/11/2017 13/11/2017 ROAD WORK 11.45
43+470,46+110,46+225
AM RHS PHED (Hand Pump) shifting Checking Shifting Work Completed Nos 3 Om Mati
35 ABL/NHAI/RW/17-18/ 35 11/11/2017 13/11/2017 STRUCTURE 10.30 AM53+453,54+782,53+453BHS Invert Leveling Check for Existing Culvert Not done
36 ABL/NHAI/RW/17-18/ 36
37 ABL/NHAI/RW/17-18/ 37
38 ABL/NHAI/RW/17-18/ 38
39 ABL/NHAI/LEVELS/17-18/ 39 13/11/2017 14/11/2017 LEVELS 10.00 AM 25+500 30+000 BHS TBM Level checking Completed Km 5 ABL
40 ABL/NHAI/RW/17-18/ 40 13/11/2017 14/11/2017 ROAD WORK 11.00 AM 54+000 55+000 RHS Electrical Utility Shifting 11 KVA Line (MS-13 Nos.) Shifting Work Completed km 1 ESPL D
41 ABL/NHAI/RW/17-18/ 41 13/11/2017 14/11/2017 ROAD WORK 12.00 AM 41+020 41+520 LHS Clearing & Grubbing 41+260 41+430 DPR-13.11.17 170 7 Sqm 1190 Dharmshila D
41+480 41+520 DPR-12.11.17 40 7 Sqm 280 Dharmshila D
42 ABL/NHAI/RW/17-18/ 42 13/11/2017 14/11/2017 ROAD WORK 3.00 PM 39+600 39+950 RHS Clearing & Grubbing 39+600 39+850 DPR-14.11.17 250 7 Sqm 1750 Dharmshila D
39+900 39+950 DPR-13.11.17 50 8 Sqm 400 Dharmshila D
43 ABL/NHAI/RW/17-18/ 43 13/11/2017 14/11/2017 ROAD WORK 11.45
46+920,49+185
AM (RHS),49+185(LHS)PHED (Hand Pump) shifting Checking Shifting Work Completed
44 ABL/NHAI/OTHERS/17-18/ 44 13/11/2017 14/11/2017 OTHERS 9.30 AM 41+000 41+000 Borrow Area Soil Sampling Progress
45 ABL/NHAI/STRUCTURE/17-18/ 45 13/11/2017 14/11/2017 STRUCTURE 10.30 AM 54+782 54+782 BHS Invert Leveling Check for Existing Culvert Completed
46 ABL/NHAI/STRUCTURE/17-18/ 46 13/11/2017 14/11/2017 STRUCTURE 11.00 AM 55+364 55+364 BHS Invert Leveling Check for Existing Culvert Completed
47 47
48 48
49 ABL/NHAI/LEVELS/17-18/ 49 14/11/2017 15/11/2017 LEVELS 10.00 AM 30+000 35+000 BHS TBM Level checking Completed
50 ABL/NHAI/RW/17-18/ 50 14/11/2017 15/11/2017 ROAD WORK 11.00 AM 40+500 41+500 RHS Electrical Utility Shifting 11 KVA Line (13 Nos.) Shifting Work Completed D
51 ABL/NHAI/RW/17-18/ 51 14/11/2017 15/11/2017 ROAD WORK 12.000 PM 39+300 39+600 RHS Clearing & Grubbing Work not done
52 ABL/NHAI/RW/17-18/ 52 14/11/2017 15/11/2017 ROAD WORK 3.00 PM 41+520 41+710 LHS Clearing & Grubbing Work not done
53 ABL/NHAI/STRUCTURE/17-18/ 53 14/11/2017 15/11/2017 STRUCTURE 3.00 PM 51+951 51+951 BHS Invert Leveling Check for Existing Culvert Completed
54 ABL/NHAI/STRUCTURE/17-18/ 54 14/11/2017 15/11/2017 STRUCTURE 3.00 PM 52+365 52+365 BHS Invert Leveling Check for Existing Culvert Completed
55 ABL/NHAI/STRUCTURE/17-18/ 55 14/11/2017 15/11/2017 STRUCTURE 4.00 PM 53+453 53+453 BHS Invert Leveling Check for Existing Culvert Completed
56 56
57 57
58 ABL/NHAI/LEVELS/17-18/ 58 15/11/2017 16/11/2017 LEVELS 10.00 AM 35+000 40+000 BHS TBM Level checking
59 ABL/NHAI/STRUCTURE/17-18/ 59 15/11/2017 16/11/2017 ROAD WORK 11.00 AM 38+500 39+100 LHS Electrical Utility Shifting 11 KVA Line (10 Nos.)
60 ABL/NHAI/STRUCTURE/17-18/ 60 15/11/2017 16/11/2017 ROAD WORK 12.00 PM 39+140 39+300 RHS Clearing & Grubbing
61 ABL/NHAI/STRUCTURE/17-18/ 61 15/11/2017 16/11/2017 ROAD WORK 3.00 PM 40+700 40+850 LHS Clearing & Grubbing
62 ABL/NHAI/MATERIALS/17-18/ 62 15/11/2017 16/11/2017 MATERIALS 3.00 PM 48+330 48+330 BHS Invert Leveling Check for Existing Culvert
63 ABL/NHAI/MATERIALS/17-18/ 63 15/11/2017 16/11/2017 MATERIALS 3.30 PM 48+836 48+836 BHS Invert Leveling Check for Existing Culvert
64 ABL/NHAI/MATERIALS/17-18/ 64 15/11/2017 16/11/2017 MATERIALS 4.00 PM 49+862 49+862 BHS Invert Leveling Check for Existing Culvert

Page 1
C&G Work done but RFI not Raised
From To Side Ex.DPR L B Area
40400 40460 RHS 9.11 60 10 600
40600 40830 LHS 11.11 230 10 2300
40830 40850 LHS 13.11 20 8 160
39950 39970 RHS 13.11 20 8 160
39300 39360 RHS 14.11 60 7 420
41320 41450 RHS 14.11 130 6 780
41540 41660 RHS 14.11 120 7 840
39370 39600 RHS 14.11 230 7 1610
41520 41660 LHS 14.11 140 7 980
39140 39300 RHS 15.11 160 5 800
38800 38900 RHS 15.11 100 7 700
42050 42220 LHS 15.11 170 7 1190
42180 42240 RHS 15.11 60 5 300
10840
RFI qty 19990
30830