You are on page 1of 16

PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA

KABUPATEN SERANG
PROPINSI BANTEN

RENCANA ANGGARAN BIAYA ( RAB )

Provinsi : Banten No RAB : 01


Kabupaten : Serang Program : P3MD
Kecamatan : Jenis Kegiatan : Rabat beton
Desa : Ukuran Dimensi : 600 x 4 x 0,15

Volume
URAIAN Dari Dari Dana Satuan Katagori Harga Satuan Jumlah Jumlah Dana Desa
Total Biaya Rp. Swadaya Rp. Rp.
Swadaya Desa
I. BAHAN
1.1 Beton Readymix K250 367.20 0.00 367.20 M3 I-b 900,000.00 0.00 330,480,000.00
1.2 Papan Bekesting 3.00 0.00 3.00 M3 I-a 3,000,000.00 0.00 9,000,000.00
1.3 Paku 5-10 cm 15.00 0.00 15.00 Kg I-b 13,500.00 0.00 202,500.00
1.4 Minyak Bekesting 5.00 0.00 5.00 Ltr I-b 16,500.00 0.00 82,500.00
1.5 Sirtu 86.40 0.00 86.40 M3 I-a 250,000.00 0.00 21,600,000.00
1.6 Plastik cor 2,581.20 0.00 2,581.20 M2 I-b 2,500.00 0.00 6,453,000.00
1.7 Batu Scroup/3/4 46.44 0.00 46.44 M3 I-a 200,000.00 0.00 9,288,000.00
1.8 Besi 10 mm 192.60 0.00 192.60 Kg I-b 15,000.00 0.00 2,889,000.00
Sub Total 1) 0.00 379,995,000.00
II. ALAT
2.1 Ember 5.00 0.00 5.00 Bh II-a 11,000.00 0.00 55,000.00
2.2 Benang 5.00 0.00 5.00 Pak II-a 15,000.00 0.00 75,000.00
2.3 Cangkul 1.00 0.00 1.00 Bh II-a 73,500.00 0.00 73,500.00
2.4 Papan Proyek 1.00 0.00 1.00 Bh II-a 150,000.00 0.00 150,000.00
2.5 Prasasti Marmer 1.00 0.00 1.00 Bh II-a 350,000.00 0.00 350,000.00
2.6 Uji Kualitas 1.00 0.00 1.00 Ls II-b 3,000,000.00 0.00 3,000,000.00
2.7 Uji Coring ( Min 10 Titik ) 1.00 0.00 1.00 Ls II-b 3,900,000.00 0.00 3,900,000.00
2.8 Mobilisasi Alat Coring 1.00 0.00 1.00 Ls II-b 500,000.00 500,000.00

Sub Total 2) 0.00 8,103,500.00


III. UPAH
3.1 Pekerja 423.00 0.00 423 HOK III-a 130,000.00 0.00 54,990,000.00
3.2 Tukang 102.60 0.00 103 HOK III-a 150,000.00 0.00 15,389,550.00
3.3 Mandor 39.00 0.00 39 HOK III-a 150,000.00 0.00 5,850,000.00
Sub Total 3) 0.00 76,229,550.00
IV. BOP TPK
4.1 Ketua 1.00 0.00 1 Org III-a 850,000.00 0.00 850,000.00
4.2 Sekretaris 1.00 0.00 1 Org III-a 710,000.00 0.00 300,000.00
4.3 Anggota 1.00 0.00 1 Org III-a 540,000.00 0.00 250,000.00
Sub Total 4) 0.00 1,400,000.00
Sumber Dana Jumlah 465,728,050

Diketahui Diverifikasi Oleh Dibuat oleh


Kepala Desa PDTI TPK / Kader Desa

(........................................... ) (…………………..…..) (…………………………………….)


PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN
Kabupaten : Serang Jenis Prasarana : Jalan Rabat beton
Kecamatan : TAKE OFF SHEET Lokasi :
Desa : Volume : 600 x 4 x 0,15

JALAN RABAT BETON


Mutu Beton :

0.15
4

1 VOLUME BETON
Panjang : L1 : 2.50 m
Lebar : B : 4.00 m
Tebal : t : 0.15 m

V 1 (1 block) = L1 x B x t x 1 = 1.5 m3

L total :L : 600 m ; n= L/L1 = 240

V total = V1 x n = 360 m3

2 VOLUME BEKESTING

pb : Panjang : 2 x L + B x (n+1) x 1 = 969 m


tb : Tinggi : t = 0.15 m

Luas : pb x tb = 145 m2

3 x pakai, V = 48.45 m2

Besi 12 mm panjang 30 cm per patok 2,5 m 3 Buah


Kebutuhan Besi = = ( 0,3 x 3 )
0.9 m
Jumlah Total = 216 m
Batang = 18 Btg
Besi 12 m / meter 10.7 Kg
Jumlah Besi ( Kg ) 192.6 Kg

3 SIRTU

Lapisan perata
t = 0.03 m

V= Lxt xB = 72 m3

4 VOLUME KEBUTUHAB PLASTIK COR


Luas =(B x Ltot)+(tx(2L + 2B))
= 2581.2 m2

5 Perbaikan badan jalan


vol kerusakan = 38.7
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN

KEBUTUHAN BAHAN UNTUK PERBAIKAN BADAN JALAN & PERATAAN


Kecamatan : Desa :
Jenis Kerusakan : Berlubang
Tingkat kerusakan : Ringan
Jenis bahan yang dibutuhkan :

Estimasi ukuran kerusakan


Patok
b l t Volume

P0
50 2.00 25.00 0.05 2.50
P1
100 2.50 25.00 0.10 6.25
P2
150 2.50 25.00 0.05 3.13
P3
200 2.50 10.00 0.10 2.50
P4
250 2.50 10.00 0.01 0.25
P5
300 2.50 10.00 0.05 1.25
P6
350 -
P7
400 -

450
P9
500 2.50 15.00 0.15 5.63
P10
550 2.50 15.00 0.15 5.63
P11
600 2.50 15.00 0.15 5.63
P12
650 -
P13
700 -
P14
750 -
P15
800 2.50 15.00 0.15 5.63

850 2.50 15.00 0.15 5.63

900 2.50 15.00 0.15 5.63

950 -

1000 - - - -

TOTAL 195 49.625 M3

HOK Penghamparan 2 m3/ perhari

b = kesimpulan lebar kerusakan hasil pengamatan oleh Kasi Pembangunan dan TPK
l = kesimpulan panjang kerusakan hasil pengamatan oleh Kasi Pembangunan dan TPK
t = kesimpulan kedalaman dari kerusakan hasil pengamatan Kasi Pembangunan dan TPK

TPK Kasi Pembangunan

(…………………………..) (……………………………….)
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN

DAFTAR HARGA SATUAN

Harga
Satuan di Ongkos Harga di
No Jenis Material Satuan Keterangan
toko / Angkut Lokasi
sumber
BAHAN
1 Semen 50 kg Zak 69000 69,000
2 Spleet m3 267000 267,000
3 Pasir Beton m3 241000 241,000
4 Pasir Urug m3 160000 160,000
5 Batu Belah m3 250000 250,000
6 Tripleks lbr 55000 55,000
7 Papan Begesting (kelas IV) m3 3000000 3,000,000
8 Kayu Kelas IV m3 3000000 3,000,000
9 Minyak Begesting ltr 16500 16,500
10 Plastik (Alas Cor) m 2500 2,500
11 paku kg 13500 13,500
12 Sirtu m3 250000 250,000
13 Beton Ready Mix K250 m3 900000 900,000
14 Cat Lapangan Kg 57000 57,000
15 Buis Beton D-40 Bh 125000 125,000
16 Besi Beton D-10 Bh 98000 98,000
17 Besi Beton D-6 Bh 65000 65,000
18 Kawat Beton Bh 23000 23,000
19 Besi 10 mm Kg 15000 15,000
20 Dolken btg 26000 26,000
21 Batu Scroup m3 200000 200,000
ALAT -
1 Cangkul bh 75000 75,000
2 Sekop bh 55000 55,000
3 Ember bh 11000 11,000
4 Selang water pass m 2000 2,000
5 Sendok semen bh 15000 15,000
6 Benang pak 48000 48,000
7 Sewa Molen hari 300000 300,000
8 Prasasti bh 350000 350,000
9 Papan Proyek bh 150000 150,000
10 Kuas 3" bh 10000 10,000
11 Sewa Mobil Dramtruck hari 700000 700,000
PEKERJA -
1 Pekerja HOK 130000 130,000 18,571
2 Tukang HOK 150000 150,000 21,429
3 Mandor HOK 150000 150,000 21,429
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN

ANALISA HARGA SATUAN

AHSP PU KAB SERANG


Beton mutu sedang fc’= 20 MPa (K-250) (Ready Mix) Harga Satuan V.Lapangan Volume 396,180,000.00
Beton Readymix ( K250 ) 1.0200 M3 900,000.00 360 367.200 330,480,000.00
Tenaga
Pekerja 1.0000 OH 130,000.00 360 360.000 46,800,000.00
Tukang 0.2500 OH 150,000.00 360 90.000 13,500,000.00
Mandor 0.1000 OH 150,000.00 360 36.000 5,400,000.00

Bekesting, per m2 14,444,835.00


Papan Bekesting 0.045 M3 3,000,000.00 48.45 3.000 9,000,000.00
Paku 5-10 cm 0.3 Kg 13,500.00 48.45 14.535 196,222.50
Minyak Bekesting 0.1 Ltr 16,500.00 48.45 4.845 79,942.50
Pekerja 0.52 HOK 130,000.00 48.45 25.194 3,275,220.00
Tukang Kayu 0.26 HOK 150,000.00 48.45 12.597 1,889,550.00
Mandor 0.026 HOK 150,000.00 48.45 1.2597 3,900.00

Sirtu per m3 24,210,000.00


Sirtu 1.2 M3 250,000.00 72 86.400 21,600,000.00
Pekerja 0.25 HOK 130,000.00 72 18.000 2,340,000.00
Mandor 0.025 HOK 150,000.00 72 1.800 270,000.00

Plastik Alas Cor/ m2 6,453,000.00


Plastik cor 1 m2 2,500.00 2581.2 2581.200 6,453,000.00

Perbaikan badan jalan 11,803,500.00


Batu scroup 1.2 m3 200,000.00 38.7 46.440 9,288,000.00
Pekerja 0.5 Hok 130,000.00 38.7 19.350 2,515,500.00
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN

918,000.0000

130,000.00
37,500.00
15,000.0000
1,100,500.0000

135,000.00
4,050.00

67,600.00
39,000.00
245,650.00
PROGRAM PEMBANGUNAN PEMBERDAYAAN MASYARAKAT DESA
KABUPATEN SERANG
PROPINSI BANTEN
Dana Desa

Dana Desa
TA. 2016

Propinsi : Banten
Kabupaten : Serang
Kecamatan : Ciruas

Talaga
Jenis Prasarana
Rabat Beton
Lokasi
Kp Kolelet
JUDUL GAMBAR

Gambar potongan memanjang

Dibuat oleh :
Kasi Pembangunan/TPK

Diperiksa Oleh :

Kasi Perencanaan

(………………………………)
Diketahui Oleh
Kepala Desa

Dana Desa
DOKUMENTASI FOTO PERENCANAAN DANA DESA (P3MD) T. A 2020
KABUPATEN :
Serang

KECAMATAN :
Mancak

DESA :
Bale Kencana

KONDISI : 0 %

KEGIATAN :

Jalan Rabat Beton

LOKASI :
P0

KABUPATEN :
Serang

KECAMATAN :
Mancak

DESA :
Bale Kencana

KONDISI : 0 %

KEGIATAN :

Jalan Rabat Beton

LOKASI :
P3

KABUPATEN :
Serang

KECAMATAN :
Mancak

DESA :
Bale Kencana

KONDISI : 0 %

KEGIATAN :

Jalan Rabat Beton

LOKASI :
P11
REKAPITULASI KEBUTUHAN BAHAN, ALAT D
Kabupaten : Serang
Kecamatan :
Desa : ........................

BATU SCROPP

BATU SIRTU

BEKESTING

BEKESTING
MINYAK

PAKU
KAYU
Pekerjaan

I PEKERJAAN GALIAN
II PEKERJAAN PEMERATAAN BADAN JALAN 46.44
III PEKERJAAN PEMERATAAN SIRTU 86.40
IV PEKERJAAN BEKESTING 3.00 4.85 14.54
V PEKERJAAN PLASTIK COR
VI PEKERJAAN READYMIX

TOTAL 46.44 86.40 3.00 4.85 14.54


HAN BAHAN, ALAT DAN UPAH
Jenis Prasarana :
Volume :

Mandor ( OH )
Pekerja Galian

Pekerja ( OH )

Tukang ( OH )
PLASTIK COR
Besi 10 mm

READYMIX

( OH ) 19.35
18.00 1.80
192.60 25.19 12.60 1.26
2,581.20
367.20 360.00 90.00 36.00

192.60 367.20 2,581.20 - 422.54 102.60 39.06


No Nama Pekerjaan Nama Item Volume Satuan Volume Satuan
1 Pekerjaan Galian
Pekerja - Jam - OH
Tukang - Jam - OH
Mandor - Jam - OH

2 Pekerjaan Readymix
Pekerja 360.00 OH 360.00 OH
Tukang 90.00 OH 90.00 OH
Mandor 36.00 Oh 36.00 OH
Keterangan

1 Oh = 7 Jam Waktu Kerja


1 Oh = 7 Jam Waktu Kerja
1 Oh = 7 Jam Waktu Kerja

1 Oh = 7 Jam Waktu Kerja


1 Oh = 7 Jam Waktu Kerja
1 Oh = 7 Jam Waktu Kerja

You might also like