Activities Type Starting Finish PROGRESS UPTO Activity Status Actual MPR MPR WEIGHT MPR
30-4-2021 Status Item % ACTIVITY %
Purchase order for F&G Detectors P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.14 0.04 0.04
Purchase order for ESD Valves P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.15 0.04 0.04
Purchase order for logic solver and ESD cabinet P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.16 0.04 0.04
Purchase order for pressure transmitters P.O 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.17 0.04 0.04
purchase order for cables P.O 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.22 0.04 0.04
purchase order for cable trays and conduits P.O 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.23 0.04 0.04
purchase order for junction boxes and cable glands P.O 05/09/2020 07/09/2020 30/04/2021 Completed 2.2.2.24 0.04 0.04
purchase order for piping material P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.6 0.04 0.04
purchase order for valves larger than 2 inch P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.7 0.04 0.04
purchase order for smaller than 2 inch P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.8 0.04 0.04
purchase order for insulation and fire proofing P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.9 0.04 0.04
purchase order for pressure safety valves P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.10 0.04 0.04
purchase order for paint P.O 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.11 0.04 0.04
PURCHASE order for contro valves P.O 20/08/2020 27/08/2020 30/04/2021 Completed 2.2.6.9 0.05 0.05
PurchaSE order for blowdown valves P.O 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.10 0.05 0.05
Purchase order for PLC/DCS P.O 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.11 0.05 0.05
PURCHASE ORDER for field instruments P.O 19/10/2020 03/11/2020 30/04/2021 Completed 2.2.6.19 0.05 0.05
purchase order for cables P.O 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.20 0.05 0.05
purchase order for cable trays and conduits P.O 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.21 0.05 0.05
purchase order for junction boxesand cable glnds P.O 21/11/2020 28/11/2020 30/04/2021 Completed 2.2.6.22 0.05 0.05
purchase order for FM200 System P.O 15/08/2020 19/08/2020 30/04/2021 Completed 2.2.4.7 0.03 0.03
Purchase Order for Compressors and Dryers P.O 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.12 0.02 0.02
Purchase Order for piping and valves P.O 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.13 0.02 0.02
Purchase Order for Pressure Regulating Valves P.O 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.14 0.02 0.02
Purchase Order for Moisture Analysers P.O 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.15 0.02 0.02
Purchase Order for Telephone System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.9 0.02 0.02
Purchase Order for Intercom System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.10 0.02 0.02
Purchase Order for CCTV System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.11 0.02 0.02
Purchase Order for Communication Cables P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.12 0.02 0.02
Purchase Order for Fire Alarm System P.O 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.13 0.02 0.02
Purchase Order for Power Supply Cables P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.15 0.02 0.02
Purchase Order for Power Transformers P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.16 0.02 0.02
Purchase Order for LV Switchgear and MCC's P.O 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.17 0.02 0.02
Purchase Order for Cable Trays & Conduits P.O 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.18 0.02 0.02
Purchase Order for Junction Boxes and Cable Glands P.O 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.19 0.02 0.02
Purchase Order for UPS P.O 15/10/2020 20/10/2020 30/04/2021 Completed 2.2.5.20 0.01 0.01
Purchase Order for Grounding P.O 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.23 0.01 0.01
Purchase Order for Lighting P.O 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.24 0.01 0.01
F&G Detectors for ESD System P.O 14/10/2020 18/04/2021 30/04/2021 Completed 3.2.3.3.1 2.4 2.4
ESD VALVES P.O 14/10/2020 01/08/2021 30/04/2021 Not Completed 3.2.1.5.1 5.23
logic solver and ESD Cabinets P.O 14/10/2020 23/05/2021 30/04/2021 Not Completed 3.2.3.2 6.08
pressure transmitters P.O 14/10/2020 25/03/2021 30/04/2021 Completed 3.2.3.3.2 0.2 0.2
cables P.O 05/09/2020 14/02/2021 30/04/2021 Completed 3.2.3.4.1 0.39 0.39
cable tray and conduits P.O 05/09/2020 14/02/2021 30/04/2021 Completed 3.2.3.5.1 0.13 0.13
junction box and cables glands P.O 24/09/2020 29/03/2021 30/04/2021 Completed 3.2.3.5.3 0.21 0.21
tie-in and welding P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.2 0.14 0.14
valves larger than 2 inch P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.7 1.54 1.54
valves sma;;er than 2inch P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.6 0.7 0.7
insulation and fire proofing P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.9 0.28 0.28
pressure safety valves P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.1.4 0.84 0.84
painting and wrapping P.O 16/11/2020 27/04/2021 30/04/2021 Completed 3.2.5 0.33 0.33
CONROL Valves P.O 22/09/2020 02/08/2021 30/04/2021 Not Completed 3.2.1.3 4.28
blowdown valves P.O 17/10/2020 03/08/2021 30/04/2021 Not Completed 3.2.1.5.2 2.6
PLC/DCS P.O 17/10/2020 25/05/2021 30/04/2021 Not Completed 3.2.3.1 6.42
Field instrurmtns P.O 21/11/2020 25/05/2021 30/04/2021 Not Completed 3.2.3.3.3 15.31
cables P.O 21/11/2020 02/05/2021 30/04/2021 Not Completed 3.2.3.4.2 1.04
cable tray and conduits P.O 21/11/2020 02/05/2021 30/04/2021 Not Completed 3.2.3.5.2 0.26
junction boxes and cable glands P.O 15/12/2020 19/06/2021 30/04/2021 Not Completed 3.2.3.5.4 0.41
Bulk material P.O 31+12-2020 31/05/2021 30/04/2021 Not Completed 3.2.3.7 0.34
Compressors&Dryers P.O 25/11/2020 22/06/2021 30/04/2021 Not Completed 3.2.7.1 1.63
Piping and Valves P.O 25/11/2020 18/05/2021 30/04/2021 Not Completed 3.2.7.2 0.16
Pressure Regulating Valves P.O 23/12/2020 24/08/2021 30/04/2021 Not Completed 3.2.7.3 0.16
moisture analyzer P.O 23/12/2020 20/07/2021 30/04/2021 Not Completed 3.2.3.6 0.34
Telephone System P.O 01/08/2020 21/01/2021 30/04/2021 Completed 3.2.4.1 0.33 0.33
Intercom System P.O 01/08/2020 21/01/2021 30/04/2021 Completed 3.2.4.2 0.55 0.55
CCTV System P.O 01/08/2020 02/02/2021 30/04/2021 Completed 3.2.4.4 1.17 1.17
Fire Alarm system P.O 01/08/2020 02/02/2021 30/04/2021 Completed 3.2.4.3 1.2 1.2
communication cables P.O 01/08/2020 10/01/2021 30/04/2021 Completed 3.2.3.4.3 0.26 0.26
13.8 KV Cable Connection & Installation P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.1 0.93 0.93
power cables P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.4 0.68 0.68
Power Transformers P.O 15/10/2020 16/06/2021 30/04/2021 Not Completed 3.2.2.3 1.27
LV swithgear and MCCs P.O 15/10/2020 24/05/2021 30/04/2021 Not Completed 3.2.2.2 3.46
Bus bar ducts P.O 15/10/2020 24/05/2021 30/04/2021 Not Completed 3.2.2.9 0.68
cable tray and conduits P.O 15/10/2020 27/03/2021 30/04/2021 Completed 3.2.2.5.1 0.2 0.2
junction boxes and cable glands P.O 15/10/2020 07/04/2021 30/04/2021 Completed 3.2.2.5.2 0.23 0.23
UPS P.O 17/11/2020 03/06/2021 30/04/2021 Not Completed 3.2.2.6 0.34
grounding material P.O 28/11/2020 27/04/2021 30/04/2021 Completed 3.2.2.7 0.17 0.17
lighting material P.O 28/11/2020 27/04/2021 30/04/2021 Completed 3.2.2.8 0.51 0.51
MPR MPR
Starting PROGRESS UPTO ACTIVITY MPR
PURCHASE ORDERS Finish Date WEIGHT ACTIVITY
Date 30-04-2021 STATUS Item
% %
1 Purchase order for F&G Detectors 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.14 0.04 0.04
2 Purchase order for ESD Valves 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.15 0.04 0.04
3 Purchase order for logic solver and ESD cabinet 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.16 0.04 0.04
4 Purchase order for pressure transmitters 12/09/2020 27/09/2020 30/04/2021 Completed 2.2.2.17 0.04 0.04
5 purchase order for cables 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.22 0.04 0.04
6 purchase order for cable trays and conduits 16/08/2020 18/08/2020 30/04/2021 Completed 2.2.2.23 0.04 0.04
7 purchase order for junction boxes and cable glands 05/09/2020 07/09/2020 30/04/2021 Completed 2.2.2.24 0.04 0.04
8 purchase order for piping material 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.6 0.04 0.04
9 purchase order for valves larger than 2 inch 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.7 0.04 0.04
10 purchase order for smaller than 2 inch 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.8 0.04 0.04
11 purchase order for insulation and fire proofing 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.9 0.04 0.04
12 purchase order for pressure safety valves 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.10 0.04 0.04
13 purchase order for paint 22/10/2020 29/10/2020 30/04/2021 Completed 2.2.3.11 0.04 0.04
14 PURCHASE order for contro valves 20/08/2020 27/08/2020 30/04/2021 Completed 2.2.6.9 0.05 0.05
15 PurchaSE order for blowdown valves 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.10 0.05 0.05
16 Purchase order for PLC/DCS 22/09/2020 29/09/2020 30/04/2021 Completed 2.2.6.11 0.05 0.05
17 PURCHASE ORDER for field instruments 19/10/2020 03/11/2020 30/04/2021 Completed 2.2.6.19 0.05 0.05
18 purchase order for cables 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.20 0.05 0.05
19 purchase order for cable trays and conduits 19/10/2020 26/10/2020 30/04/2021 Completed 2.2.6.21 0.05 0.05
20 purchase order for junction boxesand cable glnds 21/11/2020 28/11/2020 30/04/2021 Completed 2.2.6.22 0.05 0.05
21 purchase order for FM200 System 15/08/2020 19/08/2020 30/04/2021 Completed 2.2.4.7 0.03 0.03
22 Purchase Order for Compressors and Dryers 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.12 0.02 0.02
23 Purchase Order for piping and valves 28/10/2020 08/11/2020 30/04/2021 Completed 2.2.8.13 0.02 0.02
24 Purchase Order for Pressure Regulating Valves 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.14 0.02 0.02
25 Purchase Order for Moisture Analysers 25/11/2020 06/12/2020 30/04/2021 Completed 2.2.8.15 0.02 0.02
26 Purchase Order for Telephone System 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.9 0.02 0.02
27 Purchase Order for Intercom System 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.10 0.02 0.02
28 Purchase Order for CCTV System 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.11 0.02 0.02
29 Purchase Order for Communication Cables 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.12 0.02 0.02
30 Purchase Order for Fire Alarm System 09/07/2020 14/07/2020 30/04/2021 Completed 2.2.7.13 0.02 0.02
31 Purchase Order for Power Supply Cables 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.15 0.02 0.02
32 Purchase Order for Power Transformers 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.16 0.02 0.02
33 Purchase Order for LV Switchgear and MCC's 23/09/2020 28/09/2020 30/04/2021 Completed 2.2.5.17 0.02 0.02
34 Purchase Order for Cable Trays & Conduits 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.18 0.02 0.02
35 Purchase Order for Junction Boxes and Cable Glands 01/03/2020 05/03/2020 30/04/2021 Completed 2.2.5.19 0.02 0.02
36 Purchase Order for UPS 15/10/2020 20/10/2020 30/04/2021 Completed 2.2.5.20 0.01 0.01
37 Purchase Order for Grounding 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.23 0.01 0.01
38 Purchase Order for Lighting 26/10/2020 10/11/2020 30/04/2021 Completed 2.2.5.24 0.01 0.01
1.21