Professional Documents
Culture Documents
A. Mark-ups
Profit 10.00%
Overhead expenses 3.50%
VAT 5.50%
Wastage 5%
T&P 1.5%
Wastage (5%) + T & P (1.5%) 6.50%
Labour & construction work
Ordinary Labour Tk. 245.00 Per day
M.S. Angle, Channel, Z-bar, T-section etc. Tk. 62,500.00 Per ton
M.S. plate or sheet Tk. 85,000.00 Per ton
Painting Tk. 100.00 Per sqm.
Ist class Bricks Tk. 7,500.00 Per % 0 Nos.
Cement Tk. 440.00 Per bag
Earth-cutting & back fill Tk. 145.00 Per cum.
CC (1:2:4) Tk. 6,238.00 Per cum.
Plaster with neat cement finish Tk. 165.00 Per sqm.
Bending cost of tubular post Tk. 40.00 Per meter.
Welding cost of tubular post Tk. 200.00 Per meter.
Sand (F.M. 0.8) bedding Tk. 9.00 Per cft.
M.S & F.I Flat bar Tk. 56,000.00 Per M ton
Nut-Bolt Tk. 9.00 each
G.I pipe & fittings
25 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 311.00 Per meter
30 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 410.00 Per meter
40 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 480.00 Per meter
50 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 630.00 Per meter
65 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 735.00 Per meter
75 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,086.00 Per meter
150 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,800.00 Per meter
100 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,420.00 Per meter
150 x 100 mm /100 x 75 mm G.I. reducer Tk. 1,200.00 Each
100 mm G.I. plug Tk. 308.00 Each
75 mm G.I. plug Tk. 156.00 Each
40 mm G.I. plug Tk. 47.00 Each
25 mm G.I. elbow Tk. 39.00 Each
40 mm G.I. elbow Tk. 82.00 Each
2.5" x 2" size shackle type insulator Tk. 55.00 Each
3.5" x 1/4" size shackle type insulator Tk. 78.00 Each
"GNAT" 25 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 30.82 Per meter
cable/Poly/Supersighn
"ANT" 50 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 58.83 Per meter
cable/Poly/Supersighn
"WASP" 100 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 117.39 Per meter
cable/Poly/Supersighn
RABBIT 50 Sq. mm. BRB /Poly/ Paradise Tk. 73.34 Per meter
DOG 100 sq. mm BRB /Poly/ Paradise Tk. 141.23 Per meter
EASTERN CABLES
IC-2 x 2.5 sq. mm (NYY) single core Tk. 129.00 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 186.20 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 265.00 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 402.60 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 258.00 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 372.40 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 530.00 Per meter
IC-2 x 2.5 sq. mm (NYY) single core Tk. 119.23 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 166.53 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 231.50 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 351.99 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 239.00 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 333.06 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 463.00 Per meter
RR/ TRANSTEC
IC-2 x 2.5 sq. mm (NYY) single core Tk. 118.10 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 164.60 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 228.90 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 348.00 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 236.20 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 329.20 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 457.80 Per meter
Fuse
15 Amps areal fuse Tk. 50.00 Each
30 Amps areal fuse Tk. 60.00 Each
60 Amps areal fuse Tk. 77.00 Each
100 Amps areal fuse Tk. 94.00 Each
Insulator
11 KV. Pin insulator Tk. 650.00 Each
11 KV. Disc. insulator Tk. 1,750.00 Each
Guy insulator Tk. 150.00 Each
Clamp
SUB HEAD - C
(i) 4.76 mm (3/16") thick M.S. sheet 219 Kg. @ Tk. 85.00 Per kg. = Tk. 18,615.00
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75
(i) 4.76 mm (3/16") thick M.S. sheet 192 Kg. @ Tk. 85.00 Per kg. = Tk. 16,288.55
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75
(i) 4.76 mm (3/16") thick M.S. sheet 164 Kg. @ Tk. 85.00 Per kg. = Tk. 13,967.20
Analysis of P.W.D Schedule of Rates for E/M works 2014 5 Sub Head-C
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75
(i) 4.76 mm (3/16") thick M.S. sheet 97 Kg. @ Tk. 85.00 Per kg. = Tk. 8,245.00
(ii) 457 mm x 457 mm x 6.35 mm MS Base Plate 10.4 Kg. @ Tk. 85.00 Per kg. = Tk. 886.55
(i) 4.76 mm (3/16") thick M.S. sheet 55 Kg. @ Tk. 85.00 Per kg. = Tk. 4,675.00
(ii) 305 mm x 305 mm x 6.35 mm MS Base Plate 4.64 Kg. @ Tk. 85.00 Per kg. = Tk. 394.40
(i) 150 mm dia & 3.4 mm thickness G.I. pipe 9.14 meter @ Tk. 1,800.00 Per meter = Tk. 16,452.00
(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16
(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 23,864.91
T&P 1.50% = Tk. 357.97
Tk. 24,222.88
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 200.00
Total = Tk. 24,664.88
Contractor's Profit 10.00% = Tk. 2,466.49
Overhead expenses 3.50% = Tk. 863.27
Tk. 27,994.64
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,629.32
Grand total = Tk. 29,623.96
Rate per No. = Tk. 29,623.96
(i) 150 mm dia & 3.4 mm thickness G.I. pipe 7.62 meter @ Tk. 1,800.00 Per meter = Tk. 13,716.00
(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16
(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 21,128.91
T&P 1.50% = Tk. 316.93
Tk. 21,445.84
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 750.00
Total = Tk. 22,437.84
Contractor's Profit 10.00% = Tk. 2,243.78
Overhead expenses 3.50% = Tk. 785.32
Tk. 25,466.95
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,482.20
Grand total = Tk. 26,949.15
Rate per No. = Tk. 26,949.15
(i) 150 mm dia & 3.4 mm thickness G.I. pipe 6.1 meter @ Tk. 1,800.00 Per meter = Tk. 10,976.40
(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16
(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 18,389.31
T&P 1.50% = Tk. 275.84
Tk. 18,665.15
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 700.00
Total = Tk. 19,607.15
Contractor's Profit 10.00% = Tk. 1,960.71
Overhead expenses 3.50% = Tk. 686.25
Tk. 22,254.11
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,295.21
Grand total = Tk. 23,549.33
Rate per No. = Tk. 23,549.33
(i) 100 mm dia & 3.4 mm thickness G.I. pipe 6.1 meter @ Tk. 1,420.00 Per meter = Tk. 8,659.16
(ii) 75 mm dia & 3.15 mm thickness G.I. pipe 1.52 meter @ Tk. 1,086.00 Per meter = Tk. 1,655.06
(iii) 100 mm x 75 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) 75 mm G.I. plug 1 No. @ Tk. 156.00 Each = Tk. 156.00
(v) 305 x 305 x 6.35 mm MS base plate 10.4 Kg. @ Tk. 85.00 Per kg = Tk. 886.55
= Tk. 12,556.77
T&P 1.50% = Tk. 188.35
Tk. 12,745.13
(vi) Welding charge 0.95 meter @ Tk. 200.00 Per meter = Tk. 190.00
(vii) Carriage L.S. = Tk. 650.00
Total = Tk. 13,585.13
Contractor's Profit 10.00% = Tk. 1,358.51
Overhead expenses 3.50% = Tk. 475.48
Tk. 15,419.12
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 897.41
Grand total = Tk. 16,316.53
Rate per No. = Tk. 16,316.53
(i) 75 mm dia & 3.15 mm thickness G.I. pipe 4.57 meter @ Tk. 1,086.00 Per meter = Tk. 4,966.28
(ii) 50 mm dia & 2.90 mm thickness G.I. pipe 1.52 meter @ Tk. 630.00 Per meter = Tk. 960.12
(iii) 75 mm x 50 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) 75 mm G.I. plug 1 No. @ Tk. 156.00 Each = Tk. 156.00
(v) 305 x 305 x 6.35 mm MS base plate 4.64 Kg. @ Tk. 85.00 Per kg = Tk. 394.40
= Tk. 7,676.80
Analysis of P.W.D Schedule of Rates for E/M works 2014 8 Sub Head-C
T&P 1.50% = Tk. 115.15
Tk. 7,791.95
(vi) Welding charge 0.5 meter @ Tk. 200.00 Per meter = Tk. 100.00
(vii) Carriage L.S. = Tk. 550.00
Total = Tk. 8,441.95
Contractor's Profit 10.00% = Tk. 844.19
Overhead expenses 3.50% = Tk. 295.47
Tk. 9,581.61
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 557.66
Grand total = Tk. 10,139.27
Rate per No. = Tk. 10,139.27
(i) 40 mm dia & 2.90 mm thickness G.I. pipe 3.48 meter @ Tk. 480.00 Per meter = Tk. 1,670.40
(i) 3" x 1/4" M.S. flat bar (2 x 2.5' = 5 ft.) 5.79 Kg. @ Tk. 56.00 Per kg. Tk. 324.24
(ii) "D" & "U" clamp:
1.5" x 1/4" F.I. bar (2 x 2.5' = 5 ft.) 2.89 Kg. @ Tk. 56.00 Per kg. = Tk. 161.84
(iii) Nut & bolt for "D" and "U" clamp 6 Nos. @ Tk. 9.00 Each = Tk. 54.00
= Tk. 540.08
(iv) Add wastage and T & P 6.50% = Tk. 35.11
(v) Hot deep galvanizing L.S. = Tk. 300.00
(vi) Carriage L.S. = Tk. 100.00
Analysis of P.W.D Schedule of Rates for E/M works 2014 14 Sub Head-C
= Tk. 975.19
(vii) Making & welding charge L.S. = Tk. 200.00
Total = Tk. 1,175.19
Contractor's Profit 10.00% = Tk. 117.52
Overhead expenses 3.50% = Tk. 41.13
Tk. 1,333.84
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 77.63
Grand total = Tk. 1,411.47
Rate per No. = Tk. 1,411.47
(i) 3" x 3" x 1/4" M.S.Channel (5 ft.) 11.6 Kg. @ Tk. 62.50 Per kg. Tk. 724.38
(ii) "D" & "U" clamp:
1.5" x 1/4" F.I. bar (5 ft.) 2.89 Kg. @ Tk. 56.00 Per kg. = Tk. 161.84
(iv) Nut & bolt for "D" and "U" clamp 3 Nos. @ Tk. 9.00 Each = Tk. 27.00
= Tk. 913.22
(v) Add wastage and T & P 6.50% = Tk. 59.36
(vi) Hot deep galvanizing L.S. = Tk. 300.00
(vii) Carriage L.S. = Tk. 100.00
= Tk. 1,372.57
(viii) Making & welding charge L.S. = Tk. 200.00
Total = Tk. 1,572.57
Contractor's Profit 10.00% = Tk. 157.26
Overhead expenses 3.50% = Tk. 55.04
Tk. 1,784.87
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 103.88
Grand total = Tk. 1,888.75
Rate per No. = Tk. 1,888.75
SHACKLE/PIN TYPE
6
INSULATOR
6.1 Break-up for 1 No.
(A) Materials
(i) Shackle type porcelain
insulator: size: 2.5" x 2" 1 No. @ Tk. 55.00 Each = Tk. 55.00
(ii) Carriage and T & P L.S. = Tk. 14.70
= Tk. 69.70
(B) Labour L.S = Tk. 12.25
Total = Tk. 81.95
Contractor's Profit 10.00% = Tk. 8.20
Overhead expenses 3.50% = Tk. 2.87
Tk. 93.01
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 5.41
Grand total = Tk. 98.43
Rate per No. = Tk. 98.43
7 STAY
(i) G.I. strand wire (40 rft.) 2.83 Kg. @ Tk. 110.00 Per kg. Tk. 311.30
(ii) to (vi) same as above item = Tk. 461.07
= Tk. 772.37
Carriage and T & P charge L.S. = Tk. 24.50
= Tk. 796.87
(vi) Welding & labour charge L.S. = Tk. 171.50
Total = Tk. 968.37
Contractor's Profit 10.00% = Tk. 96.84
Overhead expenses 3.50% = Tk. 33.89
Tk. 1,099.10
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 63.97
Grand total = Tk. 1,163.07
Rate per No. = Tk. 1,163.07
= Tk. 48.55
Add wastage, T & P etc. 6.50% = Tk. 3.16
Carriage L.S. = Tk. 1.23
= Tk. 52.93
(B) Labour
Drawing charge L.S. =
Tk. 4.90
A+B Total =
Tk. 57.83
Contractor's Profit 10.00% =
Tk. 5.78
Overhead expenses 3.50% =
Tk. 2.02
Tk. 65.63
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 3.82
Grand total = Tk. 69.45
Rate per meter = Tk. 69.45
= Tk. 76.22
Add wastage, T & P etc. 6.50% = Tk. 4.95
Carriage L.S. = Tk. 1.23
= Tk. 82.39
(B) Labour
Drawing charge L.S. =
Tk. 4.90
A+B Total =
Tk. 87.29
Contractor's Profit 10.00% =
Tk. 8.73
Overhead expenses 3.50% =
Tk. 3.06
Tk. 99.08
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 5.77
Grand total = Tk. 104.85
Rate per meter = Tk. 104.85
= Tk. 112.45
Add wastage, T & P etc. 6.50% = Tk. 7.31
Carriage L.S. = Tk. 2.45
= Tk. 122.21
(B) Labour
Drawing charge L.S. = Tk. 6.13
A+B Total = Tk. 128.33
Contractor's Profit 10.00% = Tk. 12.83
Overhead expenses 3.50% = Tk. 4.49
Tk. 145.66
Analysis of P.W.D Schedule of Rates for E/M works 2014 18 Sub Head-C
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 8.48
Grand total = Tk. 154.14
Rate per meter = Tk. 154.14
= Tk. 144.18
Add wastage, T & P etc. 6.50% = Tk. 9.37
Carriage L.S. = Tk. 3.06
= Tk. 156.61
(B) Labour
Drawing charge L.S. = Tk. 7.35
A+B Total = Tk. 163.96
Contractor's Profit 10.00% = Tk. 16.40
Overhead expenses 3.50% = Tk. 5.74
Tk. 186.09
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.83
Grand total = Tk. 196.92
Rate per meter = Tk. 196.92
(A) Materials
(i) "GNAT" 25 sq. mm 1 meter @ Tk. 30.82 Each = Tk. 30.82
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 1.23
= Tk. 32.05
Add wastage, T & P etc. 6.50% = Tk. 2.08
Carriage L.S. = Tk. 1.23
= Tk. 35.35
(B) Labour
Drawing charge L.S. = Tk. 4.90
A+B Total = Tk. 40.25
Contractor's Profit 10.00% = Tk. 4.03
Overhead expenses 3.50% = Tk. 1.41
Tk. 45.69
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 2.66
Grand total = Tk. 48.35
Rate per meter = Tk. 48.35
= Tk. 60.06
Add wastage, T & P etc. 6.50% = Tk. 3.90
Carriage L.S. = Tk. 1.23
Analysis of P.W.D Schedule of Rates for E/M works 2014 19 Sub Head-C
(B) Labour = Tk. 65.18
Drawing charge
L.S. = Tk. 4.90
A+B Total = Tk. 70.08
Contractor's Profit 10.00% = Tk. 7.01
Overhead expenses 3.50% = Tk. 2.45
Tk. 79.54
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 4.63
Grand total = Tk. 84.17
Rate per meter = Tk. 84.17
= Tk. 90.62
Add wastage, T & P etc. 6.50% = Tk. 5.89
Carriage L.S. = Tk. 2.45
= Tk. 98.96
(B) Labour
Drawing charge L.S. = Tk. 6.13
A+B Total = Tk. 105.09
Contractor's Profit 10.00% = Tk. 10.51
Overhead expenses 3.50% = Tk. 3.68
Tk. 119.27
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 6.94
Grand total = Tk. 126.21
Rate per meter = Tk. 126.21
= Tk. 121.07
Add wastage, T & P etc. 6.50% = Tk. 7.87
Carriage L.S. = Tk. 3.06
(B) Labour = Tk. 132.00
Drawing charge
L.S. = Tk. 7.35
Total = Tk. 139.35
Contractor's Profit 10.00% = Tk. 13.93
Overhead expenses 3.50% = Tk. 4.88
Tk. 158.16
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 9.20
Grand total = Tk. 167.36
Rate per meter = Tk. 167.36
= Tk. 78.00
Add wastage, T & P etc. 6.50% = Tk. 5.07
Carriage L.S. = Tk. 3.00
= Tk. 86.07
= Tk. 151.00
Add wastage, T & P etc. 6.50% = Tk. 9.82
Carriage L.S. = Tk. 4.00
= Tk. 164.82
(B) Labour
(i) Drawing charge L.S. = Tk. 9.00
(ii) Materials = Tk. 164.82
Labour = Tk. 9.00
A+B Total = Tk. 173.82
Contractor's Profit 10.00% = Tk. 17.38
Overhead expenses 3.50% = Tk. 6.08
Tk. 197.28
Tk. 1.05820 5.5% = Tk. 11.48
VAT with adjustment factor Grand total = Tk. 208.76
Rate per meter = Tk. 208.76
8.2.4
Break-up for 1 meter
(A) Materials
(i) "DOG" 100 sq. mm 1 meter @ Tk. 141.23 Each = Tk. 141.23
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 6.00
= Tk. 147.23
Add wastage, T & P etc. 6.50% = Tk. 9.57
Carriage L.S. = Tk. 4.00
= Tk. 160.80
(B) Labour
L.S. = Tk. 9.00
(i) Drawing charge = Tk. 160.80
(ii) Materials = Tk. 9.00
A+B Total = Tk. 169.80
Contractor's Profit 10.00% = Tk. 16.98
Overhead expenses 3.50% = Tk. 5.94
Tk. 192.72
Tk. 1.05820 5.5% = Tk. 11.22
VAT with adjustment factor Grand total = Tk. 203.94
Rate per meter = Tk. 203.94
(i) No. 6 to 12 SWG G.I. wire 1 Kg. @ Tk. 110.00 Per kg. = Tk. 110.00
(ii) Add wastage, T & P etc. 6.50% = Tk. 7.15
(iii) Carriage L.S. = Tk. 12.25
= Tk. 129.40
(iv) Drawing charge = Tk. 7.50
Total = Tk. 136.90
Contractor's Profit 10.00% = Tk. 13.69
Overhead expenses 3.50% = Tk. 4.79
Tk. 155.38
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 9.04
Grand total = Tk. 164.42
Rate per kg. = Tk. 164.42
9.2 HDBC
Break-up for 1 Kg.
Analysis of P.W.D Schedule of Rates for E/M works 2014 22 Sub Head-C
(i) HDBC wire 1 Kg. @ Tk. 1,100.00 Per kg. =Tk. 1,100.00
Add wastage, T & P etc. 6.50% =Tk. 71.50
Carriage L.S. =Tk. 12.25
=Tk. 1,183.75
B. Drawing charge =Tk. 9.00
Total =Tk. 1,192.75
Contractor's Profit 10.00% =Tk. 119.28
Overhead expenses 3.50% =Tk. 41.75
Tk. 1,353.77
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 78.79
Grand total = Tk. 1,432.56
Rate per kg. = Tk. 1,432.56
11 Clamps
11.1 Service clamp
Break-up for 1 Set
(i) Cost of service clamp 1 No. @ Tk. 86.00 Each =Tk. 86.00
(ii) T & P charges 1.5% =Tk. 1.13
(iii) Carriage L.S. =Tk. 6.13
(iv) Cost of fixing L.S. =Tk. 36.75
Total =Tk. 130.00
Profit 10.00% =Tk. 13.00
Overhead expenses 3.50% =Tk. 4.55
Tk. 147.55
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 8.59
Grand total = Tk. 156.14
Rate per No. = Tk. 156.14
(i) IC-2 x 2.5 sq. mm NYY Cables. 1 meter @ Tk. 129.00 Per meter =Tk. 129.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.28
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 156.65
Add for wastage & T & P 6.50% =Tk. 10.18
(v) Carriage L.S. =Tk. 1.23
(vi) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 174.18
Contractor's Profit 10.00% = Tk. 17.42
Overhead expenses 3.50% =Tk. 6.10
Tk. 197.69
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 11.51
Grand total = Tk. 209.20
Rate per meter = Tk. 209.20
12.2 With IC-2 x 4 sq. mm single core cable type NYY of M/S
Eastern
Break-upCables.
for 1 meter
(i) IC-2 x 4 sq. mm NYY Cables. 1 meter @ Tk. 186.20 Per meter =Tk. 186.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 213.60
Add for wastage & T & P 6.50% =Tk. 13.88
(v) Carriage L.S. =Tk. 1.23
(vi) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 234.83
Contractor's Profit 10.00% = Tk. 23.48
Overhead expenses 3.50% =Tk. 8.22
Tk. 266.53
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 15.51
Grand total = Tk. 282.04
Rate per meter = Tk. 282.04
12.3 With IC-2 x 6 sq. mm single core cable type NYY of M/S
Eastern
Break-upCables.
for 1 meter
(i) IC-2 x 6 sq. mm NYY Cables. 1 meter @ Tk. 265.00 Per meter = Tk. 265.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 11.03
(iv) Assorted other fixing materials L.S. = Tk. 6.00
= Tk. 291.05
Add for wastage & T & P 6.50% = Tk. 18.92
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Analysis of P.W.D Schedule of Rates for E/M works 2014 25 Sub Head-C
Sub total = Tk. 317.31
Contractor's Profit 10.00% = Tk. 31.73
Overhead expenses 3.50% = Tk. 11.11
Tk. 360.15
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 20.96
Grand total = Tk. 381.11
Rate per meter = Tk. 381.11
12.4 With IC-2 x 10 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
(i) IC-2 x 10 sq. mm NYY Cables. 1 meter @ Tk. 402.60 Per meter
= Tk. 402.60
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 431.22
Add for wastage & T & P 6.50% = Tk. 28.03
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 7.35
Sub total = Tk. 467.82
Contractor's Profit 10.00% = Tk. 46.78
Overhead expenses 3.50% = Tk. 16.37
Tk. 530.98
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 30.90
Grand total = Tk. 561.88
Rate per meter = Tk. 561.88
12.5 With IC-4 x 2.5 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
(i) IC-4 x 2.5 sq. mm NYY Cables. 1 meter @ Tk. 258.00 Per meter
= Tk. 258.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 286.62
Add for wastage & T & P 6.50% = Tk. 18.63
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 312.60
Contractor's Profit 10.00% = Tk. 31.26
Overhead expenses 3.50% = Tk. 10.94
Tk. 354.80
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 20.65
Grand total = Tk. 375.45
Rate per meter = Tk. 375.45
12.6 With IC-4 x 4 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
Analysis of P.W.D Schedule of Rates for E/M works 2014 26 Sub Head-C
(i) IC-4 x 4 sq. mm NYY Cables. 1 meter @ Tk. 372.40 Per meter =Tk. 372.40
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 401.02
Add for wastage & T & P 6.50% =Tk. 26.07
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 9.80
Sub total =Tk. 438.11
Contractor's Profit 10.00% = Tk. 43.81
Overhead expenses 3.50% =Tk. 15.33
Tk. 497.26
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 28.94
Grand total = Tk. 526.20
Rate per meter = Tk. 526.20
12.7 With IC-4 x 6 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
(i) IC-4 x 6 sq. mm NYY Cables. 1 meter @ Tk. 530.00 Per meter =Tk. 530.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 561.07
Add for wastage & T & P 6.50% =Tk. 36.47
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 611.01
Contractor's Profit 10.00% = Tk. 61.10
Overhead expenses 3.50% =Tk. 21.39
Tk. 693.50
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 40.36
Grand total = Tk. 733.86
Rate per meter = Tk. 733.86
(i) IC-2 x 2.5 sq. mm NYY cable 1 meter @ Tk. 119.23 Per meter = Tk. 119.23
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 11.03
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 146.63
Add for wastage & T & P 6.50% = Tk. 9.53
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 163.51
Contractor's Profit 10.00% = Tk. 16.35
Analysis of P.W.D Schedule of Rates for E/M works 2014 27 Sub Head-C
Overhead expenses 3.50% = Tk. 5.72
Tk. 185.58
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.80
Grand total = Tk. 196.38
Rate per meter = Tk. 196.38
(i) IC-2 x 4 sq. mm NYY cable 1 meter @ Tk. 166.53 Per meter =Tk. 166.53
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 193.93
Add for wastage & T & P 6.50% =Tk. 12.61
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 213.88
Contractor's Profit 10.00% = Tk. 21.39
Overhead expenses 3.50% =Tk. 7.49
Tk. 242.75
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 14.13
Grand total = Tk. 256.88
Rate per meter = Tk. 256.88
(i) IC-2 x 6 sq. mm NYY cable 1 meter @ Tk. 231.50 Per meter =Tk. 231.50
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 258.90
Add for wastage & T & P 6.50% =Tk. 16.83
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 4.90
Sub total =Tk. 281.85
Contractor's Profit 10.00% = Tk. 28.18
Overhead expenses 3.50% =Tk. 9.86
Tk. 319.90
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 18.62
Grand total = Tk. 338.52
Rate per meter = Tk. 338.52
(i) IC-2 x 10 sq. mm NYY cable 1 meter @ Tk. 351.99 Per meter =Tk. 351.99
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 380.61
Add for wastage & T & P 6.50% =Tk. 24.74
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 7.35
Sub total =Tk. 413.92
Contractor's Profit 10.00% = Tk. 41.39
Overhead expenses 3.50% =Tk. 14.49
Tk. 469.80
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 27.34
Grand total = Tk. 497.15
Rate per meter = Tk. 497.15
12.12 With IC-4 x 2.5 sq. mm single core cable type NYY
of BRB/Paradise/Poly/ Supershine
(i) IC-4 x 2.5 sq. mm NYY cable 1 meter @ Tk. 239.00 Per meter =Tk. 239.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 267.62
Add for wastage & T & P 6.50% =Tk. 17.40
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 292.37
Contractor's Profit 10.00% = Tk. 29.24
Overhead expenses 3.50% =Tk. 10.23
Tk. 331.83
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 19.31
Grand total = Tk. 351.15
Rate per meter = Tk. 351.15
(i) IC-4 x 4 sq. mm NYY cable 1 meter @ Tk. 333.06 Per meter = Tk. 333.06
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 361.68
Add for wastage & T & P 6.50% = Tk. 23.51
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 9.80
Sub total = Tk. 396.21
Contractor's Profit 10.00% = Tk. 39.62
Analysis of P.W.D Schedule of Rates for E/M works 2014 29 Sub Head-C
Overhead expenses 3.50% = Tk. 13.87
Tk. 449.70
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 26.17
Grand total = Tk. 475.88
Rate per meter = Tk. 475.88
(i) IC-4 x 6 sq. mm NYY cable 1 meter @ Tk. 463.00 Per meter =Tk. 463.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 494.07
Add for wastage & T & P 6.50% =Tk. 32.11
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 539.66
Contractor's Profit 10.00% = Tk. 53.97
Overhead expenses 3.50% =Tk. 18.89
Tk. 612.51
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 35.65
Grand total = Tk. 648.16
Rate per meter = Tk. 648.16
CATENARY SERVICE:
EVANA/MEP/Khawaja/RR/SINGER
12.15 With IC-2 x 2.5 sq. mm single core cable type NYY
of EVANA/MEP/Khawaja/RR/SINGER
(i) IC-2 x 2.5 sq. mm NYY cable 1 meter @ Tk. 118.10 Per meter =Tk. 118.10
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 145.50
Add for wastage & T & P 6.50% =Tk. 9.46
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 162.30
Contractor's Profit 10.00% = Tk. 16.23
Overhead expenses 3.50% =Tk. 5.68
Tk. 184.21
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.72
Grand total = Tk. 194.93
Rate per meter = Tk. 194.93
(i) IC-2 x 4 sq. mm NYY cable 1 meter @ Tk. 164.60 Per meter =Tk. 164.60
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 192.00
Add for wastage & T & P 6.50% =Tk. 12.48
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 211.82
Contractor's Profit 10.00% = Tk. 21.18
Overhead expenses 3.50% =Tk. 7.41
Tk. 240.42
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 13.99
Grand total = Tk. 254.41
Rate per meter = Tk. 254.41
(i) IC-2 x 6 sq. mm NYY cable 1 meter @ Tk. 228.90 Per meter =Tk. 228.90
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 256.30
Add for wastage & T & P 6.50% =Tk. 16.66
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 4.90
Sub total =Tk. 279.08
Contractor's Profit 10.00% = Tk. 27.91
Overhead expenses 3.50% =Tk. 9.77
Tk. 316.75
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 18.44
Grand total = Tk. 335.19
Rate per meter = Tk. 335.19
(i) IC-2 x 10 sq. mm NYY cable 1 meter @ Tk. 348.00 Per meter = Tk. 348.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 376.62
Add for wastage & T & P 6.50% = Tk. 24.48
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 7.35
Analysis of P.W.D Schedule of Rates for E/M works 2014 31 Sub Head-C
Sub total = Tk. 409.68
Contractor's Profit 10.00% = Tk. 40.97
Overhead expenses 3.50% = Tk. 14.34
Tk. 464.98
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 27.06
Grand total = Tk. 492.04
Rate per meter = Tk. 492.04
12.19 With IC-4 x 2.5 sq. mm single core cable type NYY
of EVANA/MEP/Khawaja/RR/SINGER
(i) IC-4 x 2.5 sq. mm NYY cable 1 meter @ Tk. 236.20 Per meter
= Tk. 236.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 264.82
Add for wastage & T & P 6.50% = Tk. 17.21
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 289.38
Contractor's Profit 10.00% = Tk. 28.94
Overhead expenses 3.50% = Tk. 10.13
Tk. 328.45
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 19.12
Grand total = Tk. 347.57
Rate per meter = Tk. 347.57
(i) IC-4 x 4 sq. mm NYY cable 1 meter @ Tk. 329.20 Per meter
= Tk. 329.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 357.82
Add for wastage & T & P 6.50% = Tk. 23.26
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 9.80
Sub total = Tk. 392.10
Contractor's Profit 10.00% = Tk. 39.21
Overhead expenses 3.50% = Tk. 13.72
Tk. 445.04
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 25.90
Grand total = Tk. 470.94
Rate per meter = Tk. 470.94
(i) IC-4 x 6 sq. mm NYY cable 1 meter @ Tk. 457.80 Per meter =Tk. 457.80
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 488.87
Add for wastage & T & P 6.50% =Tk. 31.78
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 534.12
Contractor's Profit 10.00% = Tk. 53.41
Overhead expenses 3.50% =Tk. 18.69
Tk. 606.23
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 35.28
Grand total = Tk. 641.51
Rate per meter = Tk. 641.51
13 SERVICE BRACKET
(i) 25 mm (1") dia G.I. pipe 1.52 meter @ Tk. 311.00 Per meter = Tk. 472.72
(ii) 25 mm elbow 1 No. @ Tk. 39.00 Each = Tk. 39.00
(iii) Clamp 2 Nos. @ Tk. 65.32 Each = Tk. 130.64
(iv) G.I. Bend 1 Set @ Tk. 78.00 Per set. = Tk. 78.00
(v) Sundry materials L.S. = Tk. 49.00
= Tk. 769.36
(vi) T&P 6.50% = Tk. 50.01
(vii) Labour L.S. = Tk. 122.50
(viii) Carriage L.S. = Tk. 36.75
Total = Tk. 978.62
Contractor's Profit 10.00% = Tk. 97.86
Overhead expenses 3.50% = Tk. 34.25
Tk. 1,110.74
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 64.65
Grand total = Tk. 1,175.38
Rate per No. = Tk. 1,175.38
(i) 40 mm (1.5") dia G.I. pipe 1.52 meter @ Tk. 480.00 Per meter = Tk. 729.60
(ii) 40 mm elbow 1 No. @ Tk. 82.00 Each = Tk. 82.00
(iii) Clamp 2 Nos. @ Tk. 65.32 Each = Tk. 130.64
(iv) G.I. Bend 1 Set @ Tk. 78.00 Per set. = Tk. 78.00
(v) Sundry materials L.S. = Tk. 49.00
= Tk. 1,069.24
(vi) T&P 6.50% = Tk. 69.50
(vii) Labour L.S. = Tk. 122.50
(viii) Carriage L.S. = Tk. 49.00
Total = Tk. 1,310.24
Analysis of P.W.D Schedule of Rates for E/M works 2014 33 Sub Head-C
Contractor's Profit 10.00% = Tk. 131.02
Overhead expenses 3.50% = Tk. 45.86
Tk. 1,487.13
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 86.55
Grand total = Tk. 1,573.68
Rate per No. = Tk. 1,573.68
SUB HEAD - C
H.T. AND L.T. OVER HEAD DISTRIBUTION LINES
Sl. No. Description of Items (Sub Head-C) Unit Unit Rate
1.0 MS POLE
Providing following tubular pole fabricated with 4.76 mm (3/16") thick M.S sheet
having different sections with 152.40 mm long M.S. reducing collar joint complete
with M.S base plate, top cover, necessary welding & duly painted with two coats of
superior quality aluminum silver paint over two prime coats of red oxide etc. as
required: -
1.1 Total 12192 mm (40'-0") long having 152.4 mm (6") dia 9144 mm (30') at the Each Tk. 30,780.00
bottom, and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm
x6.35 mm (2'-0" x 2'-0"x 0’-0. 25”) size steel base plate.
1.2 Total 10668 mm (35'-0") long having 152.4 mm (6") dia 7620 mm (25') at the bottom Each Tk. 27,290.00
and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm x6.35 mm
(2'-0" x 2'-0" x 0’-0.25”) size steel base plate.
1.3 Total 9144 mm (30'-0") long having 152.40 mm (6") dia 6096 mm (20') at the Each Tk. 23,790.00
bottom, and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm
x6.35 mm (2'-0"x 2'-0"x 0’-0.25”) size steel base plate.
1.4 Total 7620 mm (25'-0") long having 101.60 mm (4") dia 6096 mm (20') at the Each Tk. 14,880.00
bottom, and 76.20 mm (3") dia 1524 mm (5') at the top with 457 mm x 457 mm
x6.35 mm (1'-6" x 1'-6" x 0'-0.25") size steel base plate.
1.5 Total 6096 mm (20'-0") long having 76.20 mm (3") dia 4572 mm (15') at the bottom, Each Tk. 9,110.00
and 50.80 mm (2") dia 1524 mm (5') at the top with 305 mm x 305 mm x 6.35 mm
(1'-0" x 1'-0" x 0-0.25") size steel base plate.
2.0 GI POLE
Providing following GI pole fabricated with GI pipe complete with GI sockets, M.S.
base plate, top cover, necessary welding as required:-
2.1 Total 12192 mm (40'-0") long having 152.4 mm (150mm) dia( 3.4mm) thickness Each Tk. 29,620.00
9144 mm (30') at the bottom, and 101.60 mm (100 mm) dia (3.4mm) thickness 3048
mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0" x 2'-0" x 0'-0. 25") size
steel base plate.
2.2 Total 10668 mm (35’'-0") long having 152.4 mm (150 mm) dia (3.4mm) Each Tk. 26,950.00
thickness7620 mm (25') at the bottom, and 101.60 mm (100mm) dia(3.4 mm)
thickness 3048 mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0" x 2'-0"
x 0’-0. 25") size steel base plate.
2.3 Total 9144 mm (30'-0") long having 152.4 mm (150 mm) dia (3.4 mm) thickness Each Tk. 23,550.00
6096 mm (20') at the bottom, and 101.60 mm (100 mm) dia (3.4mm) thickness 3048
mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0"x 2'-0"x 0'-0.25") size
steel base plate.
2.4 Total 7620 mm (25'-0") long having 101.6 mm (100mm) dia (3.4 mm) thickness Each Tk. 16,320.00
6096 mm (20') at the bottom, and 76.20 mm (75 mm) dia (3.15 mm) thickness 1524
mm (5') at the top with 457 mm x457 mm x6.35 mm (1'-6"x 1'-6"x 0’-0.25”) size steel
base plate.
PWD Schedule of Rates for E/M Works 2014 93
2.5 Total 6096 mm (20’) long having 76.20 mm (75 mm) dia (3.15 mm) thickness 4572 Each Tk. 10,140.00
mm (15') at the bottom, and 50.80 mm (50 mm) dia (2.90 mm) thickness 1524 mm
(5') at the top, 304 mm x 304 mm x 6.35 mm (1'-0"x 1'-0"x 0'-0.25”) size steel base
plate.
2.6 Total 3048 mm (10-0’) long having 38m (40 mm) dia (2.90mm) thickness with Each Tk. 2,510.00
228.6 mm x 228.6 mm x 4.76 mm (0'-9" x 0'-9" x 0’-3/16") size steel base plate.
2.7.0 Providing Spun type pree-stressed concrete pole fabricateded with high tensile steel
wire (5mm dia) manufactured by government owned company or Bangladesh power
devlopment board as follows.(suitable for using in saline and coastal areas)
2.7.1 Total 15000 mm (49.2') long pole having Top dia 230mm (9"), Bottom dia 390 mm Each Tk. 44,070.00
(15") , wall thickness 55mm (2.16"), weight not less than 1560 kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.
2.7.2 Total 12000 mm (39.37') long pole having Top dia 230mm (9"), Bottom dia 390 mm Each Tk. 29,380.00
(15") , wall thickness 55mm (2.16"), weight 1250kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.
2.7.3 Total 11000 mm (36.00') long pole having Top dia 230mm (9"), Bottom dia 375 mm Each Tk. 25,280.00
(14.76") , wall thickness 55mm (2.16"), weight 1100kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.
2.7.4 Total 9000 mm (29.52') long pole having Top dia 150mm (5.90"), Bottom dia 270 Each Tk. 11,750.00
mm (10.63") , wall thickness 50mm (1.97"), weight 522kg, breaking strength
232kg/sqmm, without bottom plate and carrying charge.
2.7.5 Bottom plate for 9/11/12 meter Spun P.C Pole Each Tk. 128.00
2.7.6 Bottom plate for 15 meter Spun P.C Pole Each Tk. 233.00
3.1 Erection of following tubular pole upto 1828.80 mm (6’) depth by placing the pole
base on one layer of Ist. class brick flat soling over 76.2 mm (3") sand bedding and
making 1:2:4 C.C. work around the pole 304.8 mm (1'-0") below GL & 304.8 mm(1’
ft) above GL, 12.5 mm (1/2") thick cement plaster with neat cement finishing over
concrete surface including proper curing, excavation & refilling and ramming the
loose soil etc. as required.
3.1.1 12192 mm (40’) long MS/GI /Spun P.C pole with 457 mm x 457 mm (1.5’x1.5’) cc Each Tk. 2,313.00
work
3.1.2 10668 mm (35’) long MS/GI /SpunP.C pole with 457.20 mm x 457.20 mm (1.5’x1.5’) Each Tk. 2,253.00
cc work
PWD Schedule of Rates for E/M Works 2014 94
3.2 Erection of following tubular pole upto 1524 mm (5’) depth by placing the pole base
on one layer of Ist. class brick flat soling over 76.2 mm (3”) sand bedding and
making 1:2:4 C.C. work around the pole 304.8 mm (1’)below GL & 304.8 mm(1 ft)
above GL, 12.5 mm (1/2") thick cement plaster with neat cement finishing over
concrete surface including proper curing, excavation & refilling and ramming the
loose soil etc. as required.
3.2.1 9144 mm (30’) long MS/GI /P.C pole with 457 mm x 457mm (1.5’ x 1.5’) cc work. Each Tk. 2,151.00
3.2.2 7620 mm (25’) long MS/GI / Spun P.C pole with 381 mm x 381 mm (1.5’ x 1.5’) cc Each Tk. 2,121.00
work.
3.2.3 6096 mm (20’) long MS/GI pole with 304.8 mm x 304.8 mm (1’ x 1’) cc work. Each Tk. 1,459.00
4.0 Erection of 3048 mm (10') long GI pole upto 609.6 mm (2') depth and making Each Tk. 565.00
228.60 mm x 228.60 mm(0'-9" x 0'-9")1:2:4 C.C. work around the pole from 304.80
mm (1') below GL upto 304.8 mm (1 ft) above GL 76.20 mm (3") thick brick soling
over 76.20 mm (3") layer of sand bedding,12.5 mm (1/2") thick cement plaster and
neat cement finishing over concrete surface including excavation, refilling and
ramming the loose soil surrounding CC work, proper curing etc. complete as
required.
5.1 Providing and fixing 914.4 mm (3'-0") long 3 spool vertical wire rack fabricated with Each Tk. 661.00
38.10 mm x 38.1mm x 6.35 mm (1.5" x 1.5" x 0.25") M.S. angle complete with 3
nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35 mm (1" x ¼") flat
M.S. bar for fixing insulators and clamping the rack respectively including necessary
welding, G.I. nuts, bolts, washer etc. with two coats of aluminum painting over prime
coat of red oxide painting .
5.2 Providing and fixing 1219 mm (4'-0") long 4 spool vertical wire rack fabricated with Each Tk. 1,273.00
38.10 mm x 76.2mm x 38.1 mm x 6.35 mm (1.5" x 3" x 1.5" x 0.25") M.S. Channel
complete with 4 nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35
mm (1" x ¼") flat M.S. bar for fixing insulators and clamping the rack respectively
including necessary welding, G.I. nuts, bolts, washer etc. with two coats of
aluminum painting over prime coat of red oxide painting
5.3 Providing and fixing 1524 mm (5'-0") long 5 spool vertical wire rack fabricated with Each Tk. 1,542.00
38.1 mm x 76.2 mm x 38.1 mm x 6.35 mm (1.5" x 3" x 1.5" x 0.25") M.S. Channel
complete with 5 nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35
mm (1" x ¼") flat M.S. bar for fixing insulators and clamping the rack respectively
including necessary welding, G.I. nuts, bolts, washer etc. with two coats of
aluminum painting over prime coat of red oxide painting
5.4 Provding and fixing 1524 mm (5'-0") long Clamp Bracket fabricated with 76 mm x Each Tk. 1,411.00
6.35 mm thick (3"x1/4" thick) M.S Flat bar complete with 2 Nos of "D" Clamp made
of 38.1 mm x 6.35mm thick x 762mm long (1.5" x 1/4" thick x 2'-6" long ) for fixing
clamp brackets, units & bolts etc. complete (For H.T. line) in/c. hot-deep galvanizing
of the complete cross arm as per direction of E/C.
PWD Schedule of Rates for E/M Works 2014 95
5.5 Provding and fixing 1524 mm (5'-0") long cross arm fabricated with 76 mm x 76 Each Tk. 1,889.00
mmx 6.35 mm thick (3"x3"x1/4"thick) M.S Channel with necessary clamp brackets,
nut bolts etc complete (For H.T.line) in/c hot-deep galvanizing of the complete
cross arm as per direction of E/C
6.1 Providing and fixing 500 volt grade porcelain shackle type insulator of size 63 mm x Each Tk. 98.00
50.8 mm (2.5"x 2”)
6.2 Providing and fixing 500 volt grade porcelain shackle type insulator of size 89 mm x Each Tk. 126.00
76 mm (3.5"x 3”)
6.3 Provding and fixing of 11 KV Porcelain pin insulator and pins in/c. bolts etc. to Each Tk. 847.00
existing pole top as per direction of Engineer in Charge.
6.4 Provding and fixing of 11 KV Porcelain Disc insulator in/c. Conductor clamps ball Each Tk. 2,222.00
eye box, Ball eye hook and pole atachment / Supporting steel work and their
installation at the pole top as per direction of E /C.(2 no.s. in set).
7.0 STAY
Providing and fixing following pole stay made of stranded G.I. wires complete with
anchor plate of size 304.8 mm x 304.8 mm x 6.35 mm (1' x 1'x1/4"), 16 mm (5/8")
dia stay rod of necessary length and frame bolts, guy insulator, nuts, with necessary
adjusting arrangement complete as required to be placed within 30°- 45° angle with
pole.
8.1 Providing and drawing following PVC insulated aluminum stranded conductor in
overhead line at proper sag complete with necessary G.I binding wire as required.
8.2 Providing and drawing followingAluminium conductor steel reinforced (ACSR) Bare
conductor in. Overhead line at proper sag complet with necessary G.I binding wire
as required.
Cables manufactured by Govt. of Bangladesh owned/ shared Company Ltd
(Eastern Cables).
PWD Schedule of Rates for E/M Works 2014 96
Providing and drawing No. 2-10 SWG G.I/hard drawn bare copper wire in overhead
line at proper sag complete with necessary binding wire as required as per direction
of the Engineer.
Providing and fixing standard bi-metallic ‘U’ type service belt complete with 10 mm Per set Tk. 183.00
dia bare copper conductor at the middle and aluminum conductor at the ends with
necessary insulation complete as required.
11.0 CLAMPS
11.1 Providing and fixing standard service clamp for jointing service cable with the Per set Tk. 156.00
overhead conductor complete as required
11.2 Providing and fixing P/G clamp with the conductor ( for H/T line) as per direction of Each Tk. 330.00
E/Ch.
11.3 Providing and fixing of 11 KV.tension clamp to fix at disc insulator, fixing of 11 KV. Each Tk. 823.00
conductor with the tension clamp in/c. Hot deep Galvaniging as per direction of
E/Ch.
11.4 Providing and fixing Riz iron clamp fixing 11KV. pin insulator, top of the H.T. pole Each Tk. 823.00
(with nut bolts) in/c. hot deep galvanizing complete as per direction of E/Ch.
11.5 Providing and fixing clamp type side mounted bracket for fixing 11KV pin insulator Each Tk. 1,549.00
(with nut bolts) in/c. hot deep galvanizing complete as per direction of E/C.
13.1 Providing and fixing of 1524 mm (5') long 25.40 mm (1") dia G.I. pipe service Each Tk. 1,175.00
bracket complete with 1 no. of GI bend 2 Nos fixing clamps of 38.10 mm x 6.35 mm
(1.5"x ¼") size iron flat bar bolts, nuts etc. complete as required.
13.2 Providing and fixing of 1524 mm (5') long 38.1 mm (1.5") dia G.I. pipe service Each Tk. 1,574.00
bracket complete with 1 no. of GI bend 2 Nos fixing clamps of 38.10 mm x 6.35 mm
(1.5" x ¼") size iron flat bar bolts, nuts etc. complete as required.
Providing and fixing 500 Volts grade porcelain base rewireable type aerial service
fuse unit of the following capacity: -
14.1 Suitable for use upto 15 Amps Each Tk. 110.00
14.2 Suitable for use upto 30 Amps Each Tk. 122.00
14.3 Suitable for use upto 60 Amps Each Tk. 136.00
14.4 Suitable for use upto 100 Amps Each Tk. 164.00
SUB HEAD - C
H.T. AND L.T. OVER HEAD DISTRIBUTION
LINES
MS POLE
1.0 Providing following tubular pole fabricated with 4.76 mm (3/16") thick M.S sheet having different sections
with 152.40 mm long M.S. reducing collar joint complete with M.S base plate, top cover, necessary welding
& duly painted with two coats of superior quality aluminum silver paint over two prime coats of red oxide
etc. as required: -
GI POLE
2.0
2.1 40' Each Tk. 29,620.00 Tk. 28,397.00
2.2 35' Each Tk. 26,950.00 Tk. 24,942.00
2.3 30' Each Tk. 23,550.00 Tk. 21,602.00
2.4 25' Each Tk. 16,320.00 Tk. 13,423.00
2.5 20' Each Tk. 10,140.00 Tk. 8,026.00
2.6 10' Each Tk. 2,510.00 Tk. 2,335.00
2.7.0
2.7.1 49.2' Each Tk. 44,070.00
2.7.2 39.37' Each Tk. 29,380.00 Tk. 24,486.00
2.7.3 36' Each Tk. 25,280.00 Tk. 21,066.00
2.7.4 29.51' Each Tk. 11,750.00 Tk. 9,794.00
2.7.5 Bottom plate for 9/11/12 meter Spun P.C Each Tk. 128.00 Tk. 105.00
Pole
2.7.6 Bottom plate for 15 meter Spun P.C Pole Each Tk. 233.00 Tk. 194.00
3.2
3.2.1 30' Each Tk. 2,151.00 Tk. 1,724.00
3.2.2 25' Each Tk. 2,121.00 Tk. 1,676.00
3.2.3 20' Each Tk. 1,459.00 Tk. 1,134.00
4.0 Erection of 3048 mm (10') long GI pole Each Tk. 565.00 Tk. 473.00
upto 609.6 mm (2') depth and making
228.60 mm x 228.60 mm(0'-9" x 0'-9")1:2:4
C.C. work around the pole from 304.80
mm (1') below GL upto 304.8 mm (1 ft)
above GL 76.20 mm (3") thick brick soling
over 76.20 mm (3") layer of sand
bedding,12.5 mm (1/2") thick cement
plaster and neat cement finishing over
concrete surface including excavation,
refilling and ramming the loose soil
surrounding CC work, proper curing etc.
complete as required.
5.4 Provding and fixing 1524 mm (5'-0") long Each Tk. 1,411.00
Clamp Bracket fabricated with 76 mm x
6.35 mm thick (3"x1/4" thick) M.S Flat bar
complete with 2 Nos of "D" Clamp made
of 38.1 mm x 6.35mm thick x 762mm long
(1.5" x 1/4" thick x 2'-6" long ) for fixing
clamp brackets, units & bolts etc. complete
(For H.T. line) in/c. hot-deep galvanizing
of the complete cross arm as per direction
of E/C.
5.5 Provding and fixing 1524 mm (5'-0") long Each Tk. 1,889.00
cross arm fabricated with 76 mm x 76 mmx
6.35 mm thick (3"x3"x1/4"thick) M.S
Channel with necessary clamp brackets,
nut bolts etc complete (For H.T.line) in/c
hot-deep galvanizing of the complete
cross arm as per direction of E/C
6.0 SHACKLE/PIN/DISC TYPE
INSULATOR
6.1 Providing and fixing 500 volt grade Each Tk. 98.00 Tk. 80.00
porcelain shackle type insulator of size 63
mm x 50.8 mm (2.5"x 2”)
6.2 Providing and fixing 500 volt grade Each Tk. 126.00 Tk. 108.00
porcelain shackle type insulator of size 89
mm x 76 mm (3.5"x 3”)
6.3 Provding and fixing of 11 KV Porcelain pin Each Tk. 847.00
insulator and pins in/c. bolts etc. to
existing pole top as per direction of
Engineer in Charge.
6.4 Provding and fixing of 11 KV Porcelain Each Tk. 2,222.00
Disc insulator in/c. Conductor clamps ball
eye box, Ball eye hook and pole
atachment / Supporting steel work and
their installation at the pole top as per
direction of E /C.(2 no.s. in set)
STAY
7.0
7.1 8 SWG 7 strand Each Tk. 1,688.00 Tk. 1,402.00
7.2 10 SWG 7 strand Each Tk. 1,393.00 Tk. 1,148.00
7.3 12 SWG 7 strand Each Tk. 1,163.00 Tk. 976.00
8.1
Cables manufactured by Govt. of
Bangladesh owned/ shared Company Ltd
(Eastern Cables).
8.1.1 IC- 25 sq.mm (GNAT) Per meter Tk. 69.00 Tk. 56.00
8.1.2 IC- 50 sq.mm (ANT) Per meter Tk. 105.00 Tk. 96.00
8.1.3 IC- 75 sq.mm (EARWIG) Per meter Tk. 154.00 Tk. 132.00
8.1.4 IC- 100 sq.mm (WASP) Per meter Tk. 197.00 Tk. 167.00
8.1.5 IC-25 sq.mm (GNAT) Per meter Tk. 48.00 Tk. 51.00
8.1.6 IC-50 sq.mm (ANT) Per meter Tk. 84.00 Tk. 88.00
8.1.7 IC-75 sq.mm (EARWIG) Per meter Tk. 126.00 Tk. 121.00
8.1.8 IC-100 sq.mm (WASP) Per meter Tk. 167.00 Tk. 146.00
8.2 Cables manufactured by Govt. of
Bangladesh owned/ shared Company Ltd
(Eastern Cables).
9.0
Service belt
10.0 Providing and fixing standard bi-metallic Per set Tk. 183.00 Tk. 128.00
‘U’ type service belt complete with 10 mm
dia bare copper conductor at the middle
and aluminum conductor at the ends with
necessary insulation complete as required.
11.0 Clamps
11.1 Providing and fixing standard service Per set Tk. 156.00 Tk. 121.00
clamp for jointing service cable with the
overhead conductor complete as required
11.2 Providing and fixing P/G clamp with the Each Tk. 330.00
conductor ( for H/T line) as per direction
of E/Ch.
11.3 Providing and fixing of 11 KV.tension Each Tk. 823.00
clamp to fix at disc insulator, fixing of 11
KV. conductor with the tension clamp
in/c. Hot deep Galvaniging as per
direction of E/Ch.
11.4 Providing and fixing Riz iron clamp fixing Each Tk. 823.00
11KV. pin insulator, top of the H.T. pole
(with nut bolts) in/c. hot deep galvanizing
complete as per direction of E/Ch.
11.5 Providing and fixing clamp type side Each Tk. 1,549.00
mounted bracket for fixing 11KV pin
insulator (with nut bolts) in/c. hot deep
galvanizing complete as per direction of
E/C.
12.1 IC-2 x 2.5 sq.mm Per meter Tk. 209.00 Tk. 181.00
12.2 IC-2 x 4 sq.mm Per meter Tk. 282.00 Tk. 243.00
12.3 IC-2 x 6 sq.mm Per meter Tk. 381.00 Tk. 331.00
12.4 IC-2 x 10 sq.mm Per meter Tk. 562.00 Tk. 487.00
12.5 IC-4 x 2.5 sq.mm Per meter Tk. 375.00 Tk. 324.00
12.6 IC-4 x 4 sq.mm Per meter Tk. 526.00 Tk. 455.00
12.7 IC-4 x 6 sq.mm Per meter Tk. 734.00 Tk. 635.00
12.8 IC-2 x 2.5 sq.mm Per meter Tk. 196.00 Tk. 158.00
12.9 IC-2 x 4 sq.mm Per meter Tk. 257.00 Tk. 212.00
12.10 IC-2 x 6 sq.mm Per meter Tk. 339.00 Tk. 285.00
12.11 IC-2 x 10 sq.mm Per meter Tk. 497.00 Tk. 420.00
12.12 IC-4 x 2.5 sq.mm Per meter Tk. 351.00 Tk. 281.00
12.13 IC-4 x 4 sq.mm Per meter Tk. 476.00 Tk. 393.00
12.14 IC-4 x 6 sq.mm Per meter Tk. 648.00 Tk. 547.00
12.15 IC-2 x 2.5 sq.mm Per meter Tk. 195.00 Tk. 151.00
12.16 IC-2 x 4 sq.mm Per meter Tk. 254.00 Tk. 202.00
12.17 IC-2 x 6 sq.mm Per meter Tk. 335.00 Tk. 271.00
12.18 IC-2 x 10 sq.mm Per meter Tk. 492.00 Tk. 397.00
12.19 IC-4 x 2.5 sq.mm Per meter Tk. 348.00 Tk. 267.00
12.20 IC-4 x 4 sq.mm Per meter Tk. 471.00 Tk. 372.00
12.21 IC-4 x 6 sq.mm Per meter Tk. 642.00 Tk. 517.00
13.1 Providing and fixing of 1524 mm (5') long Each Tk. 1,175.00 Tk. 1,005.00
25.40 mm (1") dia G.I. pipe service bracket
complete with 1 no. of GI bend 2 Nos
fixing clamps of 38.10 mm x 6.35 mm (1.5"x
¼") size iron flat bar bolts, nuts etc.
complete as required
13.2 Providing and fixing of 1524 mm (5') long Each Tk. 1,574.00 Tk. 1,451.00
38.1 mm (1.5") dia G.I. pipe service bracket
complete with 1 no. of GI bend 2 Nos
fixing clamps of 38.10 mm x 6.35 mm (1.5"
x ¼") size iron flat bar bolts, nuts etc.
complete as required
AERIAL FUSE
14.0 Providing and fixing 500 Volts grade
porcelain base rewireable type aerial
service fuse unit of the following capacity:
-
14.1 Suitable for use upto 15 Amps Each Tk. 110.00 Tk. 101.00
14.2 Suitable for use upto 30 Amps Each Tk. 122.00 Tk. 113.00
14.3 Suitable for use upto 60 Amps Each Tk. 136.00 Tk. 135.00
14.4 Suitable for use upto 100 Amps Each Tk. 164.00 Tk. 155.00
% Change
37.09%
38.14%
39.55%
33.38%
26.21%
4.31%
8.05%
9.02%
21.58%
26.34%
7.49%
New
19.99%
20.00%
19.97%
21.90%
20.10%
24.62%
24.61%
24.77%
26.55%
28.66%
19.45%
-3.92%
0.32%
-4.46%
New
New
22.50%
16.67%
New
New
20.40%
21.34%
19.16%
23.21%
9.38%
16.67%
17.96%
-5.88%
-4.55%
4.13%
14.38%
New
New
New
New
15.49%
0.21%
42.97%
28.93%
New
New
New
New
15.47%
16.05%
15.11%
15.40%
15.74%
15.60%
15.59%
24.05%
21.23%
18.95%
18.33%
24.91%
21.12%
18.46%
29.14%
25.74%
23.62%
23.93%
30.34%
26.61%
24.18%
16.92%
8.48%
8.91%
7.96%
0.74%
5.81%
Index C
i MS POLE
ii GI POLE
iii POLE ERECTION
iv WIRE RACK/ CROSS ARM
v SHACKLE/PIN/DISC TYPE
INSULATOR
vi STAY
vii OVERHEAD AAC /ACSR
CONDUCTOR
viii G.I WIRE / COPPER WIRE
ix SERVICE BELT
x CLAMPS
xi CATENARY WIRING FOR
SERVICE CONNECTION
xii SERVICE BRACKET
xiii AERIAL FUSE