You are on page 1of 53

PRIMARY INPUTS

A. Mark-ups
Profit 10.00%
Overhead expenses 3.50%
VAT 5.50%
Wastage 5%
T&P 1.5%
Wastage (5%) + T & P (1.5%) 6.50%
Labour & construction work
Ordinary Labour Tk. 245.00 Per day
M.S. Angle, Channel, Z-bar, T-section etc. Tk. 62,500.00 Per ton
M.S. plate or sheet Tk. 85,000.00 Per ton
Painting Tk. 100.00 Per sqm.
Ist class Bricks Tk. 7,500.00 Per % 0 Nos.
Cement Tk. 440.00 Per bag
Earth-cutting & back fill Tk. 145.00 Per cum.
CC (1:2:4) Tk. 6,238.00 Per cum.
Plaster with neat cement finish Tk. 165.00 Per sqm.
Bending cost of tubular post Tk. 40.00 Per meter.
Welding cost of tubular post Tk. 200.00 Per meter.
Sand (F.M. 0.8) bedding Tk. 9.00 Per cft.
M.S & F.I Flat bar Tk. 56,000.00 Per M ton
Nut-Bolt Tk. 9.00 each
G.I pipe & fittings
25 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 311.00 Per meter
30 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 410.00 Per meter
40 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 480.00 Per meter
50 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 630.00 Per meter
65 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 735.00 Per meter
75 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,086.00 Per meter
150 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,800.00 Per meter
100 mm inner dia & 2.65 mm thickness G.I. pipe Tk. 1,420.00 Per meter
150 x 100 mm /100 x 75 mm G.I. reducer Tk. 1,200.00 Each
100 mm G.I. plug Tk. 308.00 Each
75 mm G.I. plug Tk. 156.00 Each
40 mm G.I. plug Tk. 47.00 Each
25 mm G.I. elbow Tk. 39.00 Each
40 mm G.I. elbow Tk. 82.00 Each
2.5" x 2" size shackle type insulator Tk. 55.00 Each
3.5" x 1/4" size shackle type insulator Tk. 78.00 Each

Stay swivel frame and guy insulator Tk. 110.00 Each

Insulated AAC manufactured by Eastern Cables


"GNAT" 25 sq. mm insulated wire (AAC) of Eastern Cable Tk. 46.83 Per meter
"ANT" 50 sq. mm insulated wire (AAC) of Eastern Cable Tk. 74.50 Per meter
EARWIG 75 sq.mm Eastern Cables Tk. 110.00 Per meter
"WASP" 100 sq. mm insulated wire (AAC) of Eastern cable Tk. 140.50 Per meter

Insulated AAC manufactured by M/S Paradise/ BRB/


Supersign/Poly

"GNAT" 25 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 30.82 Per meter
cable/Poly/Supersighn

"ANT" 50 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 58.83 Per meter
cable/Poly/Supersighn

EARWIG 75 sq.mm BRB/Paradise cable/Poly/Supersighn Tk. 88.17 Per meter

"WASP" 100 sq. mm insulated wire (AAC) of BRB/Paradise Tk. 117.39 Per meter
cable/Poly/Supersighn

Aluminium conductor steel reinforced (ACSR) Bare conductor


in. Overhead line at proper sag complet with necessary G.I
binding wire as required.

ACSR manufactured by Eastern Cables

RABBIT 50 Sq. mm. Eastern Cable Tk. 75.00 Per meter


DOG 100 sq. mm Eastern cable Tk. 145.00 Per meter

ACSR manufactured by M/S Paradise/ BRB/ Supersign/Poly

RABBIT 50 Sq. mm. BRB /Poly/ Paradise Tk. 73.34 Per meter
DOG 100 sq. mm BRB /Poly/ Paradise Tk. 141.23 Per meter

G.I. wire Tk. 110.00 Per kg.


HDBC wire Tk. 1,100.00 Per kg.

Service belt Tk. 120.00 Each

Service clamp Tk. 86.00 Each


P.G Clamp Tk. 250.00 Each
11 KV Tension clamp Tk. 650.00 Each
Riz Iron Clamp Tk. 645.00 Each
Clamp Type Side Mounted Bracket Tk. 1,250.00 Each

EASTERN CABLES
IC-2 x 2.5 sq. mm (NYY) single core Tk. 129.00 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 186.20 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 265.00 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 402.60 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 258.00 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 372.40 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 530.00 Per meter

Paradise/ BRB/ Supersign /Poly

IC-2 x 2.5 sq. mm (NYY) single core Tk. 119.23 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 166.53 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 231.50 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 351.99 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 239.00 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 333.06 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 463.00 Per meter

RR/ TRANSTEC

IC-2 x 2.5 sq. mm (NYY) single core Tk. 118.10 Per meter
IC-2 x 4 sq. mm (NYY) single core Tk. 164.60 Per meter
IC-2 x 6 sq. mm (NYY) single core Tk. 228.90 Per meter
IC-2 x 10 sq. mm (NYY) single core Tk. 348.00 Per meter
IC-4 x 2.5 sq. mm (NYY) single core Tk. 236.20 Per meter
IC-4 x 4 sq. mm (NYY) single core Tk. 329.20 Per meter
IC-4 x 6 sq. mm (NYY) single core Tk. 457.80 Per meter

Fuse
15 Amps areal fuse Tk. 50.00 Each
30 Amps areal fuse Tk. 60.00 Each
60 Amps areal fuse Tk. 77.00 Each
100 Amps areal fuse Tk. 94.00 Each

Insulator
11 KV. Pin insulator Tk. 650.00 Each
11 KV. Disc. insulator Tk. 1,750.00 Each
Guy insulator Tk. 150.00 Each

Clamp

P. G Clamp Tk. 250.00 Each


11Kv Tension Clam Tk. 650.00 Each
Riz Clamp Tk. 645.00 Each
Side mounted bracked Tk. 1,250.00 Each
Analysis of P.W.D Schedule of Rates for E/M works 2014 4 Sub Head-C

SUB HEAD - C

OVERHEAD DISTRIBUTION LINES


1 MS POLE
1.1 40 feet long M.S. Tubular pole

Break-up for 1 No.

(i) 4.76 mm (3/16") thick M.S. sheet 219 Kg. @ Tk. 85.00 Per kg. = Tk. 18,615.00
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75

Add wastage & T & P ( for I + ii) 6.50% = Tk. 1,312.46


(iii) Fabrication cost
(a) Bending charge 12.2 meter @ Tk. 40.00 Per meter Tk.= 487.60
(b) Welding charge 14.3 meter @ Tk. 200.00 Per meter Tk.= 2,864.00
(iv) Carriage L.S. Tk.= 200.00
(v) 2 coats S.E. painting over prime coat 5.70 sqm @ Tk. 100.00 Per sqm. Tk.= 570.00
Total Tk.= 25,625.81
Profit 10.00% Tk.= 2,562.58
Overhead expenses 3.50% Tk.= 896.90
Tk. 29,085.30
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,692.79
Grand total = Tk. 30,778.09
Rate per No. = Tk. 30,778.09

Say, Tk. 30,780.00 Each pole

1.2 35 feet long M.S. Tubular pole

Break-up for 1 No.

(i) 4.76 mm (3/16") thick M.S. sheet 192 Kg. @ Tk. 85.00 Per kg. = Tk. 16,288.55
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75

Add wastage & T & P ( for I + ii) 6.50% = Tk. 1,161.24


(iii) Fabrication cost
(a) Bending charge 10.7 meter @ Tk. 40.00 Per meter Tk.= 426.80
(b) Welding charge 12.8 meter @ Tk. 200.00 Per meter Tk.= 2,560.00
(iv) Carriage L.S. Tk.= 200.00
(v) 2 coats S.E. painting over prime coat 5.08 sqm @ Tk. 100.00 Per sqm. Tk.= 508.00
Total Tk.= 22,721.34
Contractor's Profit 10.00% Tk.= 2,272.13
Overhead expenses 3.50% Tk.= 795.25
Tk. 25,788.73
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,500.93
Grand total = Tk. 27,289.66
Rate per No. = Tk. 27,289.66

Say, Tk. 27,290.00 Each pole

1.3 30 feet long M.S. Tubular pole

Break-up for 1 No.

(i) 4.76 mm (3/16") thick M.S. sheet 164 Kg. @ Tk. 85.00 Per kg. = Tk. 13,967.20
Analysis of P.W.D Schedule of Rates for E/M works 2014 5 Sub Head-C
(ii) 609 mm x 609 mm x 6.35 mm MS Base Plate 18.6 Kg. @ Tk. 85.00 Per kg. = Tk. 1,576.75

Add wastage & T & P ( for I + ii) 6.50% = Tk. 1,010.36


(iii) Fabrication cost
(a) Bending charge 9.14 meter @ Tk. 40.00 Per meter Tk.= 365.60
(b) Welding charge 11.3 meter @ Tk. 200.00 Per meter Tk.= 2,256.00
(iv) Carriage L.S. Tk.= 200.00
(v) 2 coats S.E painting over prime coat 4.36 sqm @ Tk. 100.00 Per sqm. Tk.= 435.60
Total Tk.= 19,811.51
Profit 10.00% Tk.= 1,981.15
Overhead expenses 3.50% Tk.= 693.40
Tk. 22,486.06
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,308.71
Grand total = Tk. 23,794.77
Rate per No. = Tk. 23,794.77

Say, Tk. 23,790.00 Each pole

1.4 25 feet long M.S. Tubular pole

Break-up for 1 No.

(i) 4.76 mm (3/16") thick M.S. sheet 97 Kg. @ Tk. 85.00 Per kg. = Tk. 8,245.00
(ii) 457 mm x 457 mm x 6.35 mm MS Base Plate 10.4 Kg. @ Tk. 85.00 Per kg. = Tk. 886.55

Add wastage & T & P ( for I + ii) 6.50% = Tk. 593.55


(iii) Fabrication cost
(a) Bending charge 7.62 meter @ Tk. 40.00 Per meter Tk.= 304.80
(b) Welding charge 9.75 meter @ Tk. 200.00 Per meter Tk.= 1,950.00
(iv) Carriage L.S. Tk.= 150.00
(v) 2 coats S.E painting over prime coat 2.59 sqm @ Tk. 100.00 Per sqm. Tk.= 259.00
Total Tk.= 12,388.90
Contractor's Profit 10.00% Tk.= 1,238.89
Overhead expenses 3.50% Tk.= 433.61
Tk. 14,061.40
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 818.39
Grand total = Tk. 14,879.79
Rate per No. = Tk. 14,879.79

Say, Tk. 14,880.00 Each pole

1.5 20 feet long M.S. Tubular pole

Break-up for 1 No.

(i) 4.76 mm (3/16") thick M.S. sheet 55 Kg. @ Tk. 85.00 Per kg. = Tk. 4,675.00
(ii) 305 mm x 305 mm x 6.35 mm MS Base Plate 4.64 Kg. @ Tk. 85.00 Per kg. = Tk. 394.40

Add wastage & T & P ( for I + ii) 6.50% = Tk. 329.51


(iii) Fabrication cost
(a) Bending charge 6.09 meter @ Tk. 40.00 Per meter = Tk. 243.60
(b) Welding charge 8.23 meter @ Tk. 200.00 Per meter = Tk. 1,646.00
(iv) Carriage L.S. = Tk. 150.00
(v) 2 coats S.E painting over prime coat 1.47 sqm @ Tk. 100.00 Per sqm. = Tk. 147.00
Total = Tk. 7,585.51
Contractor's Profit 10.00% = Tk. 758.55
Overhead expenses 3.50% = Tk. 265.49
Tk. 8,609.55
Analysis of P.W.D Schedule of Rates for E/M works 2014 6 Sub Head-C
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 501.08
Grand total = Tk. 9,110.64
Rate per No. = Tk. 9,110.64

Say, Tk. 9,110.00 Each pole


2.0 G.I. POLE

2.1 40 feet long G.I. pole

Break-up for 1 No.

(i) 150 mm dia & 3.4 mm thickness G.I. pipe 9.14 meter @ Tk. 1,800.00 Per meter = Tk. 16,452.00
(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16
(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 23,864.91
T&P 1.50% = Tk. 357.97
Tk. 24,222.88
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 200.00
Total = Tk. 24,664.88
Contractor's Profit 10.00% = Tk. 2,466.49
Overhead expenses 3.50% = Tk. 863.27
Tk. 27,994.64
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,629.32
Grand total = Tk. 29,623.96
Rate per No. = Tk. 29,623.96

Say, Tk. 29,620.00 Each pole

2.2 35 feet long G.I. pole

Break-up for 1 No.

(i) 150 mm dia & 3.4 mm thickness G.I. pipe 7.62 meter @ Tk. 1,800.00 Per meter = Tk. 13,716.00

(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16

(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 21,128.91
T&P 1.50% = Tk. 316.93
Tk. 21,445.84
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 750.00
Total = Tk. 22,437.84
Contractor's Profit 10.00% = Tk. 2,243.78
Overhead expenses 3.50% = Tk. 785.32
Tk. 25,466.95
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,482.20
Grand total = Tk. 26,949.15
Rate per No. = Tk. 26,949.15

Say, Tk. 26,950.00 Each pole


Analysis of P.W.D Schedule of Rates for E/M works 2014 7 Sub Head-C
2.3 30 feet long G.I. pole

Break-up for 1 No.

(i) 150 mm dia & 3.4 mm thickness G.I. pipe 6.1 meter @ Tk. 1,800.00 Per meter = Tk. 10,976.40
(ii) 100 mm dia & 3.4 mm thickness G.I. pipe 3.05 meter @ Tk. 1,420.00 Per meter = Tk. 4,328.16
(iii) 150 mm x 100 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) G.I. plug 1 No. @ Tk. 308.00 Each = Tk. 308.00
(v) 609 x 609 x 6.35 mm MS base plate 18.6 Kg. @ Tk. 85.00 Per kg = Tk. 1,576.75
= Tk. 18,389.31
T&P 1.50% = Tk. 275.84
Tk. 18,665.15
(vi) Welding charge 1.21 meter @ Tk. 200.00 Per meter = Tk. 242.00
(vii) Carriage L.S. = Tk. 700.00
Total = Tk. 19,607.15
Contractor's Profit 10.00% = Tk. 1,960.71
Overhead expenses 3.50% = Tk. 686.25
Tk. 22,254.11
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,295.21
Grand total = Tk. 23,549.33
Rate per No. = Tk. 23,549.33

Say, Tk. 23,550.00 Each pole

2.4 25 feet long G.I. pole

Break-up for 1 No.

(i) 100 mm dia & 3.4 mm thickness G.I. pipe 6.1 meter @ Tk. 1,420.00 Per meter = Tk. 8,659.16
(ii) 75 mm dia & 3.15 mm thickness G.I. pipe 1.52 meter @ Tk. 1,086.00 Per meter = Tk. 1,655.06
(iii) 100 mm x 75 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) 75 mm G.I. plug 1 No. @ Tk. 156.00 Each = Tk. 156.00
(v) 305 x 305 x 6.35 mm MS base plate 10.4 Kg. @ Tk. 85.00 Per kg = Tk. 886.55
= Tk. 12,556.77
T&P 1.50% = Tk. 188.35
Tk. 12,745.13
(vi) Welding charge 0.95 meter @ Tk. 200.00 Per meter = Tk. 190.00
(vii) Carriage L.S. = Tk. 650.00
Total = Tk. 13,585.13
Contractor's Profit 10.00% = Tk. 1,358.51
Overhead expenses 3.50% = Tk. 475.48
Tk. 15,419.12
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 897.41
Grand total = Tk. 16,316.53
Rate per No. = Tk. 16,316.53

Say, Tk. 16,320.00 Each pole

2.5 20 feet long G.I. pole

Break-up for 1 No.

(i) 75 mm dia & 3.15 mm thickness G.I. pipe 4.57 meter @ Tk. 1,086.00 Per meter = Tk. 4,966.28
(ii) 50 mm dia & 2.90 mm thickness G.I. pipe 1.52 meter @ Tk. 630.00 Per meter = Tk. 960.12
(iii) 75 mm x 50 mm GI reducer 1 No. @ Tk. 1,200.00 Each = Tk. 1,200.00
(iv) 75 mm G.I. plug 1 No. @ Tk. 156.00 Each = Tk. 156.00
(v) 305 x 305 x 6.35 mm MS base plate 4.64 Kg. @ Tk. 85.00 Per kg = Tk. 394.40
= Tk. 7,676.80
Analysis of P.W.D Schedule of Rates for E/M works 2014 8 Sub Head-C
T&P 1.50% = Tk. 115.15
Tk. 7,791.95
(vi) Welding charge 0.5 meter @ Tk. 200.00 Per meter = Tk. 100.00
(vii) Carriage L.S. = Tk. 550.00
Total = Tk. 8,441.95
Contractor's Profit 10.00% = Tk. 844.19
Overhead expenses 3.50% = Tk. 295.47
Tk. 9,581.61
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 557.66
Grand total = Tk. 10,139.27
Rate per No. = Tk. 10,139.27

Say, Tk. 10,140.00 Each pole

2.6 10 feet long G.I. pole

Break-up for 1 No.

(i) 40 mm dia & 2.90 mm thickness G.I. pipe 3.48 meter @ Tk. 480.00 Per meter = Tk. 1,670.40

(ii) 40 mm G.I. plug 1 No. @ Tk. 47.00 Each = Tk. 47.00


(iii) 228 x 228 x 4.76 mm MS base plate 1.96 Kg. @ Tk. 85.00 Per kg = Tk. 166.60
= Tk. 1,884.00
T&P 1.50% = Tk. 28.26
Tk. 1,912.26
(vi) Welding charge 0.12 meter @ Tk. 200.00 Per meter = Tk. 24.00
(vii) Carriage L.S. = Tk. 150.00
Total = Tk. 2,086.26
Contractor's Profit 10.00% = Tk. 208.63
Overhead expenses 3.50% = Tk. 73.02
Tk. 2,367.91
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 137.81
Grand total = Tk. 2,505.72
Rate per No. = Tk. 2,505.72

Say, Tk. 2,510.00 Each pole

Spun P.C POLE

2.7.1 15 Meter long Spun P.C pole 1 No.


Break-up for
(i) Cost of materials 1 Unit @ Tk. 34,450.00 P/Pole = Tk. 34,450.00
Add. Wastage and T & P 6.50% = Tk. 2,239.25
Tk. 36,689.25
Contractor's Profit 10.00% = Tk. 3,668.93
Overhead expenses 3.50% = Tk. 1,284.12
Tk. 41,642.30
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 2,423.62
Grand total = Tk. 44,065.92
Rate per Pole = Tk. 44,065.92

Say, Tk. 44,070.00 Each pole

2.7.2 12 Meter long Spun P.C pole 1 No.


Break-up for
(i) Cost of materials 1 Unit @ Tk. 22,970.00 P/Pole = Tk. 22,970.00
Add. Wastage and T & P 6.50% = Tk. 1,493.05
Analysis of P.W.D Schedule of Rates for E/M works 2014 9 Sub Head-C
Tk. 24,463.05
Contractor's Profit 10.00% = Tk. 2,446.31
Overhead expenses 3.50% = Tk. 856.21
Tk. 27,765.56
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,615.98
Grand total = Tk. 29,381.55
Rate per Pole = Tk. 29,381.55

Say, Tk. 29,380.00 Each pole

2.7.3 11 Meter long Spun P.C pole 1 No.


Break-up for
(i) Cost of materials 1 Unit @ Tk. 19,760.00 P/Pole = Tk. 19,760.00
Add. Wastage and T & P 6.50% = Tk. 1,284.40
Tk. 21,044.40
Contractor's Profit 10.00% = Tk. 2,104.44
Overhead expenses 3.50% = Tk. 736.55
Tk. 23,885.39
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 1,390.15
Grand total = Tk. 25,275.55
Rate per Pole = Tk. 25,275.55

Say, Tk. 25,280.00 Each pole

2.7.4 9 Meter long Spun P.C pole 1 No.


Break-up for
(i) Cost of materials 1 Unit @ Tk. 9,188.00 P/Pole = Tk. 9,188.00
Add. Wastage and T & P 6.50% = Tk. 597.22
Tk. 9,785.22
Contractor's Profit 10.00% = Tk. 978.52
Overhead expenses 3.50% = Tk. 342.48
Tk. 11,106.22
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 646.39
Grand total = Tk. 11,752.62
Rate per Pole = Tk. 11,752.62

Say, Tk. 11,750.00 Each pole

2.7.5 Bottom Plate for 9/11/12 Meter long Spun 1 No.


P.C pole
Break-up for
(i) Cost of materials 1 Unit @ Tk. 100.00 P/Plate = Tk. 100.00
Add. Wastage and T & P 6.50% = Tk. 6.50
Tk. 106.50
Contractor's Profit 10.00% = Tk. 10.65
Overhead expenses 3.50% = Tk. 3.73
Tk. 120.88
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 7.04
Grand total = Tk. 127.91
Rate per Plate = Tk. 127.91

Say, Tk. 128.00 Each plate

2.7.6 Bottom Plate for 15 Meter long Spun P.C 1 No.


pole
Break-up for
(i) Cost of materials 1 Unit @ Tk. 182.00 P/Plate = Tk. 182.00
Analysis of P.W.D Schedule of Rates for E/M works 2014 10 Sub Head-C
Add. Wastage and T & P 6.50% = Tk. 11.83
Tk. 193.83
Contractor's Profit 10.00% = Tk. 19.38
Overhead expenses 3.50% = Tk. 6.78
Tk. 220.00
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 12.80
Grand total = Tk. 232.80
Rate per Plate = Tk. 232.80

Say, Tk. 233.00 Each plate

3.00 POLE ERECTION

3.1.1 40 ft. long G.I./M.S. pole


1 No.
Break-up for
(i) 0.92 x 0.92 x 1.83 m trench cutting 1.53 cum. @ Tk. 145.00 Per cum. Tk. 221.85
(ii) Sand bedding: 0.92 x 0.92 x 0.076 m 0.07 cum. @ Tk. 317.84 Per cum. = Tk. 20.66
(iii) Bricks for soling 26 Nos. @ Tk. 7.50 Each = Tk. 195.00
(iv) C.C work 0.12 cum. @ Tk. 6,238.00 Per cum. = Tk. 748.56
(v) Plaster with NCF. 1.15 sqm @ Tk. 165.00 Per sqm. = Tk. 189.75
= Tk. 1,375.82
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 550.00
compaction
Total = Tk. 1,925.82
Contractor's Profit 10.00% = Tk. 192.58
Overhead expenses 3.50% = Tk. 67.40
Tk. 2,185.80
Tk. 1.05820 5.5% = Tk. 127.22
VAT with adjustment factor Grand total = Tk. 2,313.02
Rate per No. = Tk. 2,313.02

Say, Tk. 2,313.00 Each pole

3.1.2 35 ft. long G.I./M.S. pole


1 No.
Break-up for
(i) 0.92 x 0.92 x 1.83 m trench cutting 1.53 cum. @ Tk. 145.00 Per cum. Tk. 221.85
(ii) Sand bedding: 0.92 x 0.92 x 0.076 m 0.07 cum. @ Tk. 317.84 Per cum. = Tk. 20.66
(iii) Bricks for soling 26 Nos. @ Tk. 7.50 Each = Tk. 195.00
(iv) C.C work 0.12 cum. @ Tk. 6,238.00 Per cum. = Tk. 748.56
(v) Plaster with NCF. 1.15 sqm @ Tk. 165.00 Per sqm. = Tk. 189.75
= Tk. 1,375.82
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 500.00
compaction
Total = Tk. 1,875.82
Cntractor's Profit 10.00% = Tk. 187.58
Overhead expenses 3.50% = Tk. 65.65
Tk. 2,129.05
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 123.91
Grand total = Tk. 2,252.97
Rate per No. = Tk. 2,252.97

Say, Tk. 2,253.00 Each pole

3.2.1 30 ft. long G.I./M.S. pole


Analysis of P.W.D Schedule of Rates for E/M works 2014 11 Sub Head-C
1 No.
Break-up for
(i) 0.92 x 0.92 x 1.52 m trench cutting 1.29 cum. @ Tk. 145.00 Per cum. Tk. 187.05
(ii) Sand bedding: 0.92 x 0.92 x 0.076 m 0.07 cum. @ Tk. 317.84 Per cum. = Tk. 20.66
(iii) Bricks for soling 26 Nos. @ Tk. 7.50 Each = Tk. 195.00
(iv) C.C work 0.12 cum. @ Tk. 6,238.00 Per cum. = Tk. 748.56
(v) Plaster with NCF. 1.15 sqm @ Tk. 165.00 Per sqm. = Tk. 189.75
= Tk. 1,341.02
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 450.00
compaction
Total = Tk. 1,791.02
Contractor's Profit 10.00% = Tk. 179.10
Overhead expenses 3.50% = Tk. 62.69
Tk. 2,032.81
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 118.31
Grand total = Tk. 2,151.12
Rate per No. = Tk. 2,151.12

Say, Tk. 2,151.00 Each pole

3.2.2 25 ft. long G.I./M.S. pole


1 No.
Break-up for
(i) 0.92 x 0.92 x 1.52 m trench cutting 1.29 cum. @ Tk. 145.00 Per cum. Tk. 187.05
(ii) Sand bedding: 0.92 x 0.92 x 0.076 m 0.07 cum. @ Tk. 317.84 Per cum. = Tk. 20.66
(iii) Bricks for soling 26 Nos. @ Tk. 7.50 Each = Tk. 195.00
(iv) C.C work 0.12 cum. @ Tk. 6,238.00 Per cum. = Tk. 748.56
(v) Plaster with NCF. 1.15 sqm @ Tk. 165.00 Per sqm. = Tk. 189.75
= Tk. 1,341.02
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 425.00
compaction
Total = Tk. 1,766.02
Contractor's Profit 10.00% = Tk. 176.60
Overhead expenses 3.50% = Tk. 61.81
Tk. 2,004.43
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 116.66
Grand total = Tk. 2,121.09
Rate per No. = Tk. 2,121.09

Say, Tk. 2,121.00 Each pole

3.2.3 20 ft. long G.I./M.S. pole


1 No.
Break-up for
(i) 0.92 x 0.92 x 1.52 m trench cutting 1.29 cum. @ Tk. 145.00 Per cum. Tk. 187.05
(ii) Sand bedding: 0.92 x 0.92 x 0.076 m 0.07 cum. @ Tk. 317.84 Per cum. = Tk. 20.66
(iii) Bricks for soling 26 Nos. @ Tk. 7.50 Each = Tk. 195.00
(iv) C.C work 0.05 cum. @ Tk. 6,238.00 Per cum. = Tk. 336.85
(v) Plaster with NCF. 0.76 sqm @ Tk. 165.00 Per sqm. = Tk. 125.40
= Tk. 864.96
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 350.00
compaction
Total = Tk. 1,214.96
Contractor's Profit 10.00% = Tk. 121.50
Overhead expenses 3.50% = Tk. 42.52
Tk. 1,378.98
Analysis of P.W.D Schedule of Rates for E/M works 2014 12 Sub Head-C
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 80.26
Grand total = Tk. 1,459.24
Rate per No. = Tk. 1,459.24

Say, Tk. 1,459.00 Each pole

4. 10 ft. long G.I. pole


1 No.
Break-up for
(i) 0.60 x 0.60 x 0.60 m trench cutting 0.22 cum. @ Tk. 145.00 Per cum. Tk. 31.90
(ii) Sand bedding: 0.60 x 0.60 x 0.076 m 0.03 cum. @ Tk. 317.84 Per cum. = Tk. 8.58
(iii) Bricks for soling 12 Nos. @ Tk. 7.50 Each = Tk. 90.00
(iv) C.C work 0.03 cum. @ Tk. 6,238.00 Per cum. = Tk. 180.90
(v) Plaster with NCF. 0.6 sqm @ Tk. 165.00 Per sqm. = Tk. 99.00
= Tk. 410.38
(vi) Labour charge for pole erection, refilling & L.S. = Tk. 60.00
compaction
Total = Tk. 470.38
Contractor's Profit 10.00% = Tk. 47.04
Overhead expenses 3.50% = Tk. 16.46
Tk. 533.89
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 31.07
Grand total = Tk. 564.96
Rate per No. = Tk. 564.96

Say, Tk. 565.00 Each pole

5. WIRE RACK/CROSS ARM

5.1 3-Spool wire rack


1 No.
Break-up for
(i) 1.5" x 1.5" x 1/4" M.S. angle (3 ft.) 3.19 Kg. @ Tk. 62.50 Per kg. Tk. 199.38
(ii) "D" & "U" clamp:
1" x 1/4" F.I. bar (5 ft.) 1.93 Kg. @ Tk. 62.50 Per kg. = Tk. 120.63
(iii) Nut & bolt for "D" and "U" clamp 5 Nos. @ Tk. 9.00 Each = Tk. 45.00
= Tk. 365.00
(iv) Add wastage and T & P 6.50% = Tk. 23.73
(v) Painting 0.21 sqm @ Tk. 100.00 Per sqm.. = Tk. 21.30
(vi) Carriage L.S. = Tk. 30.00
= Tk. 440.03
(vii) Making & welding charge for "D" & "U" clamp = Tk. 110.00

Total = Tk. 550.03


Contractor's Profit 10.00% = Tk. 55.00
Overhead expenses 3.50% = Tk. 19.25
Tk. 624.28
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 36.33
Grand total = Tk. 660.61
Rate per No. = Tk. 660.61

Say, Tk. 661.00 Each

5.2 4-Spool wire rack

Break-up for 1 No.


Analysis of P.W.D Schedule of Rates for E/M works 2014 13 Sub Head-C
(i) 1.5" x 3" x 1.5"x 1/4"
M.S. channel (4 ft.) 8.5 Kg. @ Tk. 62.50 Per kg. Tk. 531.25
(ii) "D" & "U" clamp:
1" x 1/4" F.I. bar (6 ft.) 2.3 Kg. @ Tk. 62.50 Per kg. = Tk. 143.75
(iii) Nut & bolt for "D" and "U" clamp 6 Nos. @ Tk. 9.00 Each = Tk. 54.00
= Tk. 729.00
(iv) Add wastage and T & P 6.50% = Tk. 47.39
(v) Painting 0.5 sqm @ Tk. 100.00 Per sqm. = Tk. 50.00
(vi) Carriage L.S. = Tk. 73.50
= Tk. 899.89
(vii) Making & welding charge for "D" & "U" clamp L.S. = Tk. 160.00

Total = Tk. 1,059.89


Contractor's Profit 10.00% = Tk. 105.99
Overhead expenses 3.50% = Tk. 37.10
Tk. 1,202.97
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 70.01
Grand total = Tk. 1,272.98
Rate per No. = Tk. 1,272.98

Say, Tk. 1,273.00 Each

5.3 5-Spool wire rack


Break-up for 1 No.
(i) 1.5" x 3" x 1.5" x 1/4"
M.S. Channel (4 ft.) 10.6 Kg. @ Tk. 62.50 Per kg. Tk. 665.00
(ii) "D" & "U" clamp:
1" x 1/4" F.I. bar (6 ft.) 2.3 Kg. @ Tk. 62.50 Per kg. = Tk. 143.75
(iii) Nut & bolt for "D" and "U" clamp 7 Nos. @ Tk. 9.00 Each = Tk. 63.00
= Tk. 871.75
(iv) Add wastage and T & P 6.50% = Tk. 56.66
(v) Painting 0.75 sqm @ Tk. 100.00 Per sqm. = Tk. 75.00
(vi) Carriage L.S. = Tk. 85.75
= Tk. 1,089.16
(vii) Making & welding charge for "D" & "U" clamp L.S. = Tk. 195.00

Total = Tk. 1,284.16


Contractor's Profit 10.00% = Tk. 128.42
Overhead expenses 3.50% = Tk. 44.95
Tk. 1,457.53
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 84.83
Grand total = Tk. 1,542.36
Rate per No. = Tk. 1,542.36

Say, Tk. 1,542.00 Each

5.4 CROSS ARM

Break-up for 1 No.

(i) 3" x 1/4" M.S. flat bar (2 x 2.5' = 5 ft.) 5.79 Kg. @ Tk. 56.00 Per kg. Tk. 324.24
(ii) "D" & "U" clamp:
1.5" x 1/4" F.I. bar (2 x 2.5' = 5 ft.) 2.89 Kg. @ Tk. 56.00 Per kg. = Tk. 161.84
(iii) Nut & bolt for "D" and "U" clamp 6 Nos. @ Tk. 9.00 Each = Tk. 54.00
= Tk. 540.08
(iv) Add wastage and T & P 6.50% = Tk. 35.11
(v) Hot deep galvanizing L.S. = Tk. 300.00
(vi) Carriage L.S. = Tk. 100.00
Analysis of P.W.D Schedule of Rates for E/M works 2014 14 Sub Head-C
= Tk. 975.19
(vii) Making & welding charge L.S. = Tk. 200.00
Total = Tk. 1,175.19
Contractor's Profit 10.00% = Tk. 117.52
Overhead expenses 3.50% = Tk. 41.13
Tk. 1,333.84
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 77.63
Grand total = Tk. 1,411.47
Rate per No. = Tk. 1,411.47

Say, Tk. 1,411.00 Each

5.5 CROSS ARM

Break-up for 1 No.

(i) 3" x 3" x 1/4" M.S.Channel (5 ft.) 11.6 Kg. @ Tk. 62.50 Per kg. Tk. 724.38
(ii) "D" & "U" clamp:
1.5" x 1/4" F.I. bar (5 ft.) 2.89 Kg. @ Tk. 56.00 Per kg. = Tk. 161.84
(iv) Nut & bolt for "D" and "U" clamp 3 Nos. @ Tk. 9.00 Each = Tk. 27.00
= Tk. 913.22
(v) Add wastage and T & P 6.50% = Tk. 59.36
(vi) Hot deep galvanizing L.S. = Tk. 300.00
(vii) Carriage L.S. = Tk. 100.00
= Tk. 1,372.57
(viii) Making & welding charge L.S. = Tk. 200.00
Total = Tk. 1,572.57
Contractor's Profit 10.00% = Tk. 157.26
Overhead expenses 3.50% = Tk. 55.04
Tk. 1,784.87
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 103.88
Grand total = Tk. 1,888.75
Rate per No. = Tk. 1,888.75

Say, Tk. 1,889.00 Each

SHACKLE/PIN TYPE
6
INSULATOR
6.1 Break-up for 1 No.
(A) Materials
(i) Shackle type porcelain
insulator: size: 2.5" x 2" 1 No. @ Tk. 55.00 Each = Tk. 55.00
(ii) Carriage and T & P L.S. = Tk. 14.70
= Tk. 69.70
(B) Labour L.S = Tk. 12.25
Total = Tk. 81.95
Contractor's Profit 10.00% = Tk. 8.20
Overhead expenses 3.50% = Tk. 2.87
Tk. 93.01
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 5.41
Grand total = Tk. 98.43
Rate per No. = Tk. 98.43

Say, Tk. 98.00 Each

6.2 Break-up for 1 No.


(A) Materials
Analysis of P.W.D Schedule of Rates for E/M works 2014 15 Sub Head-C
(i) Shackle type porcelain insulator:
size: 3.5" x 3" 1 No. @ Tk. 78.00 Each = Tk. 78.00
(ii) Carriage and T & P L.S. = Tk. 14.70
= Tk. 92.70
(B) Labour L.S = Tk. 12.25
Total = Tk. 104.95
Contractor's Profit 10.00% = Tk. 10.50
Overhead expenses 3.50% = Tk. 3.67
Tk. 119.12
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 6.93
Grand total = Tk. 126.05
Rate per No. = Tk. 126.05

Say, Tk. 126.00 Each

6.3 Materials 1 No.


(A)
(i) 11 KV pin insulator and Pin, bolt etc. compt. 1 No. @ Tk. 650.00 Each = Tk. 650.00

(ii) Carriage and T & P L.S. = Tk. 30.00


= Tk. 680.00
(B) Labour/Fixing Charge L.S = Tk. 25.00
Total = Tk. 705.00
Contractor's Profit 10.00% = Tk. 70.50
Overhead expenses 3.50% = Tk. 24.68
VAT with adjustment factor Tk. 800.18
Tk. 1.05820 5.5% = Tk. 46.57
Grand total = Tk. 846.75
Rate per No. = Tk. 846.75

Say, Tk. 847.00 Each

6.4 Break-up for 1 Set


(A) Materials
(i) 11 KV Disc insulator in/c conductor clump 1 Set @ Tk. 1,750.00 P/Set = Tk. 1,750.00
Ball eye hook etc. compt. (2 Nos in a Set).

(ii) Carriage and T & P L.S. = Tk. 50.00


= Tk. 1,800.00
(B) Labour/Fixing Charge L.S = Tk. 50.00
Total = Tk. 1,850.00
Contractor's Profit 10.00% = Tk. 185.00
Overhead expenses 3.50% = Tk. 64.75
Tk. 2,099.75
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 122.21
Grand total = Tk. 2,221.96
Rate per Set. = Tk. 2,221.96

Say, Tk. 2,222.00 P/Set

7 STAY

7.1 Over-head pole stay: 8 SWG-7 strand G.I. stay


Break-up for 1 No.
(i) G.I. strand wire (40 rft.) 6.36 Kg. @ Tk. 110.00 Per kg. Tk. 699.60
(ii) Stay plate (1' x 1' x 1/4") and 5/8" dia M.S. L.S. = Tk. 100.00
rod (6 rft.)
(iii) Stay swivel frame etc. 1 Nos. @ Tk. 110.00 Each = Tk. 110.00
Analysis of P.W.D Schedule of Rates for E/M works 2014 16 Sub Head-C
(iv) "D" clamp (1" x 1/4") 1 No. @ Tk. 71.07 Each = Tk. 71.07
(v) Nuts. bolts, binding wire etc. sundry L.S. = Tk. 30.00
materials.
(vi) Guy Insulator 1 No. @ Tk. 150.00 Each = Tk. 150.00
Tk. 1,160.67
Carriage and T & P charge L.S. = Tk. 24.50
Tk. 1,185.17
(vii) Welding & labour charge L.S. = Tk. 220.50
Total = Tk. 1,405.67
Contractor's Profit 10.00% = Tk. 140.57
Overhead expenses 3.50% = Tk. 49.20
Tk. 1,595.44
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 92.86
Grand total = Tk. 1,688.29
Rate per No. = Tk. 1,688.29

Say, Tk. 1,688.00 Each

7.2 Over-head pole stay: 10 SWG-7 strand G.I. stay


Break-up for 1 No.
(i) G.I. strand wire (40 rft.) 4.24 Kg. @ Tk. 110.00 Per kg. Tk. 466.40
(ii) to (vi) same as above item = Tk. 461.07
= Tk. 927.47
Carriage and T & P charge L.S. = Tk. 24.50
= Tk. 951.97
(vi) Welding & labour charge L.S. = Tk. 208.25
Total = Tk. 1,160.22
Contractor's Profit 10.00% = Tk. 116.02
Overhead expenses 3.50% = Tk. 40.61
Tk. 1,316.85
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 76.64
Grand total = Tk. 1,393.49
Rate per No. = Tk. 1,393.49

Say, Tk. 1,393.00 Each

7.3 Over-head pole stay: 12 SWG-7 strand G.I. stay


Break-up for 1 No.

(i) G.I. strand wire (40 rft.) 2.83 Kg. @ Tk. 110.00 Per kg. Tk. 311.30
(ii) to (vi) same as above item = Tk. 461.07
= Tk. 772.37
Carriage and T & P charge L.S. = Tk. 24.50
= Tk. 796.87
(vi) Welding & labour charge L.S. = Tk. 171.50
Total = Tk. 968.37
Contractor's Profit 10.00% = Tk. 96.84
Overhead expenses 3.50% = Tk. 33.89
Tk. 1,099.10
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 63.97
Grand total = Tk. 1,163.07
Rate per No. = Tk. 1,163.07

Say, Tk. 1,163.00 Each

8 OVERHEAD ACC/ ACSR CONDUCTOR

Insulated AAC manufactured by Eastern Cables


Analysis of P.W.D Schedule of Rates for E/M works 2014 17 Sub Head-C
8.1.1 Break-up for 1 meter
(A) Materials
(i) "GNAT" 25 sq. mm 1 meter @ Tk. 46.83 Each = Tk. 46.83
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 1.72

= Tk. 48.55
Add wastage, T & P etc. 6.50% = Tk. 3.16
Carriage L.S. = Tk. 1.23
= Tk. 52.93
(B) Labour
Drawing charge L.S. =
Tk. 4.90
A+B Total =
Tk. 57.83
Contractor's Profit 10.00% =
Tk. 5.78
Overhead expenses 3.50% =
Tk. 2.02
Tk. 65.63
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 3.82
Grand total = Tk. 69.45
Rate per meter = Tk. 69.45

Say, Tk. 69.00 Per meter

8.1.2 Break-up for 1 meter


(A) Materials
(i) ANT 50 sq. mm 1 meter @ Tk. 74.50 Each = Tk. 74.50
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 1.72

= Tk. 76.22
Add wastage, T & P etc. 6.50% = Tk. 4.95
Carriage L.S. = Tk. 1.23
= Tk. 82.39
(B) Labour
Drawing charge L.S. =
Tk. 4.90
A+B Total =
Tk. 87.29
Contractor's Profit 10.00% =
Tk. 8.73
Overhead expenses 3.50% =
Tk. 3.06
Tk. 99.08
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 5.77
Grand total = Tk. 104.85
Rate per meter = Tk. 104.85

Say, Tk. 105.00 Per meter

8.1.3 Break-up for 1 meter


(A) Materials
(i) EARWIG 75 sq. mm 1 meter @ Tk. 110.00 Each = Tk. 110.00
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 2.45

= Tk. 112.45
Add wastage, T & P etc. 6.50% = Tk. 7.31
Carriage L.S. = Tk. 2.45
= Tk. 122.21
(B) Labour
Drawing charge L.S. = Tk. 6.13
A+B Total = Tk. 128.33
Contractor's Profit 10.00% = Tk. 12.83
Overhead expenses 3.50% = Tk. 4.49
Tk. 145.66
Analysis of P.W.D Schedule of Rates for E/M works 2014 18 Sub Head-C
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 8.48
Grand total = Tk. 154.14
Rate per meter = Tk. 154.14

Say, Tk. 154.00 Per meter

8.1.4 Break-up for 1 meter


(A) Materials
(i) "WASP" 100 sq. mm 1 meter @ Tk. 140.50 Each = Tk. 140.50
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 3.68

= Tk. 144.18
Add wastage, T & P etc. 6.50% = Tk. 9.37
Carriage L.S. = Tk. 3.06
= Tk. 156.61
(B) Labour
Drawing charge L.S. = Tk. 7.35
A+B Total = Tk. 163.96
Contractor's Profit 10.00% = Tk. 16.40
Overhead expenses 3.50% = Tk. 5.74
Tk. 186.09
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.83
Grand total = Tk. 196.92
Rate per meter = Tk. 196.92

Say, Tk. 197.00 Per meter

Insulated AAC manufactured by M/S Paradise/ BRB/ Supersign/Poly


8.1.5 Break-up for 1 meter

(A) Materials
(i) "GNAT" 25 sq. mm 1 meter @ Tk. 30.82 Each = Tk. 30.82
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 1.23

= Tk. 32.05
Add wastage, T & P etc. 6.50% = Tk. 2.08
Carriage L.S. = Tk. 1.23
= Tk. 35.35
(B) Labour
Drawing charge L.S. = Tk. 4.90
A+B Total = Tk. 40.25
Contractor's Profit 10.00% = Tk. 4.03
Overhead expenses 3.50% = Tk. 1.41
Tk. 45.69
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 2.66
Grand total = Tk. 48.35
Rate per meter = Tk. 48.35

Say, Tk. 48.00 Per meter

8.1.6 Break-up for 1 meter


(A) Materials
(i) ANT 50 sq. mm 1 meter @ Tk. 58.83 Each = Tk. 58.83
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 1.23

= Tk. 60.06
Add wastage, T & P etc. 6.50% = Tk. 3.90
Carriage L.S. = Tk. 1.23
Analysis of P.W.D Schedule of Rates for E/M works 2014 19 Sub Head-C
(B) Labour = Tk. 65.18
Drawing charge
L.S. = Tk. 4.90
A+B Total = Tk. 70.08
Contractor's Profit 10.00% = Tk. 7.01
Overhead expenses 3.50% = Tk. 2.45
Tk. 79.54
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 4.63
Grand total = Tk. 84.17
Rate per meter = Tk. 84.17

Say, Tk. 84.00 Per meter

8.1.7 Break-up for 1 meter


(A) Materials
(i) EARWIG 75 sq. mm 1 meter @ Tk. 88.17 Each = Tk. 88.17
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 2.45

= Tk. 90.62
Add wastage, T & P etc. 6.50% = Tk. 5.89
Carriage L.S. = Tk. 2.45
= Tk. 98.96
(B) Labour
Drawing charge L.S. = Tk. 6.13
A+B Total = Tk. 105.09
Contractor's Profit 10.00% = Tk. 10.51
Overhead expenses 3.50% = Tk. 3.68
Tk. 119.27
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 6.94
Grand total = Tk. 126.21
Rate per meter = Tk. 126.21

Say, Tk. 126.00 Per meter

8.1.8 Break-up for 1 meter


(A) Materials
(i) "WASP" 100 sq. mm 1 meter @ Tk. 117.39 Each = Tk. 117.39
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 3.68

= Tk. 121.07
Add wastage, T & P etc. 6.50% = Tk. 7.87
Carriage L.S. = Tk. 3.06
(B) Labour = Tk. 132.00
Drawing charge
L.S. = Tk. 7.35
Total = Tk. 139.35
Contractor's Profit 10.00% = Tk. 13.93
Overhead expenses 3.50% = Tk. 4.88
Tk. 158.16
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 9.20
Grand total = Tk. 167.36
Rate per meter = Tk. 167.36

Say, Tk. 167.00 Per meter

ALUMINIUM CONDUCTOR STEEL REINFORCED

8.2.1 ACSR manufactured by Eastern Cables


Analysis of P.W.D Schedule of Rates for E/M works 2014 20 Sub Head-C
Break-up for 1 meter
(A) Materials
(i) "RABBIT" 50 sq. mm 1 meter @ Tk. 75.00 Each = Tk. 75.00
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 3.00

= Tk. 78.00
Add wastage, T & P etc. 6.50% = Tk. 5.07
Carriage L.S. = Tk. 3.00
= Tk. 86.07

(B) Labour L.S. = Tk. 6.00


Total = Tk. 92.07
Contractor's Profit 10.00% = Tk. 9.21
Overhead expenses 3.50% = Tk. 3.22
Tk. 104.50
Tk. 1.05820 5.5% = Tk. 6.08
VAT with adjustment factor Grand total = Tk. 110.58
Rate per meter = Tk. 110.58

Say, Tk. 111.00 Per meter

8.2.2 Break-up for 1 meter


(A) Materials
(i) "DOG" 100 sq. mm 1 meter @ Tk. 145.00 Each = Tk. 145.00
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 6.00

= Tk. 151.00
Add wastage, T & P etc. 6.50% = Tk. 9.82
Carriage L.S. = Tk. 4.00
= Tk. 164.82
(B) Labour
(i) Drawing charge L.S. = Tk. 9.00
(ii) Materials = Tk. 164.82
Labour = Tk. 9.00
A+B Total = Tk. 173.82
Contractor's Profit 10.00% = Tk. 17.38
Overhead expenses 3.50% = Tk. 6.08
Tk. 197.28
Tk. 1.05820 5.5% = Tk. 11.48
VAT with adjustment factor Grand total = Tk. 208.76
Rate per meter = Tk. 208.76

Say, Tk. 209.00 Per meter

ACSR manufactured by M/S Paradise/ BRB/ Supersign/Poly


8.2.3 1 meter
(A) Break-up for
(i) Materials 1 meter @ Tk. 73.34 Each = Tk. 73.34
(ii) "RABBIT" 50 sq. mm L.S. = Tk. 3.00
Assorted sundry materials, PVC tape etc. = Tk. 76.34

6.50% = Tk. 4.96


Add wastage, T & P etc. L.S. = Tk. 3.00
Carriage = Tk. 84.30
(B) Labour
(i) Drawing charge L.S. = Tk. 6.00
(ii) Materials = Tk. 84.30
Analysis of P.W.D Schedule of Rates for E/M works 2014 21 Sub Head-C
Labour = Tk. 6.00
A+B Total = Tk. 90.30
Contractor's Profit 10.00% = Tk. 9.03
Overhead expenses 3.50% = Tk. 3.16
Tk. 102.49
Tk. 1.05820 5.5% = Tk. 5.97
VAT with adjustment factor Grand total = Tk. 108.46
Rate per meter = Tk. 108.46

Say, Tk. 108.00 Per meter

8.2.4
Break-up for 1 meter
(A) Materials
(i) "DOG" 100 sq. mm 1 meter @ Tk. 141.23 Each = Tk. 141.23
(ii) Assorted sundry materials, PVC tape etc. L.S. = Tk. 6.00

= Tk. 147.23
Add wastage, T & P etc. 6.50% = Tk. 9.57
Carriage L.S. = Tk. 4.00
= Tk. 160.80
(B) Labour
L.S. = Tk. 9.00
(i) Drawing charge = Tk. 160.80
(ii) Materials = Tk. 9.00
A+B Total = Tk. 169.80
Contractor's Profit 10.00% = Tk. 16.98
Overhead expenses 3.50% = Tk. 5.94
Tk. 192.72
Tk. 1.05820 5.5% = Tk. 11.22
VAT with adjustment factor Grand total = Tk. 203.94
Rate per meter = Tk. 203.94

Say, Tk. 204.00 Per meter

9 G.I WIRE / COPPER WIRE

9.1 G.I. WIRE


Break-up for 1 Kg.

(i) No. 6 to 12 SWG G.I. wire 1 Kg. @ Tk. 110.00 Per kg. = Tk. 110.00
(ii) Add wastage, T & P etc. 6.50% = Tk. 7.15
(iii) Carriage L.S. = Tk. 12.25
= Tk. 129.40
(iv) Drawing charge = Tk. 7.50
Total = Tk. 136.90
Contractor's Profit 10.00% = Tk. 13.69
Overhead expenses 3.50% = Tk. 4.79
Tk. 155.38
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 9.04
Grand total = Tk. 164.42
Rate per kg. = Tk. 164.42

Say, Tk. 164.00 Per kg.

9.2 HDBC
Break-up for 1 Kg.
Analysis of P.W.D Schedule of Rates for E/M works 2014 22 Sub Head-C
(i) HDBC wire 1 Kg. @ Tk. 1,100.00 Per kg. =Tk. 1,100.00
Add wastage, T & P etc. 6.50% =Tk. 71.50
Carriage L.S. =Tk. 12.25
=Tk. 1,183.75
B. Drawing charge =Tk. 9.00
Total =Tk. 1,192.75
Contractor's Profit 10.00% =Tk. 119.28
Overhead expenses 3.50% =Tk. 41.75
Tk. 1,353.77
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 78.79
Grand total = Tk. 1,432.56
Rate per kg. = Tk. 1,432.56

Say, Tk. 1,433.00 Per kg.

10. Service belt


Break-up for 1 Set
(i) Cost of service belt 1 No. @ Tk. 120.00 Each = Tk. 120.00
(ii) T & P charges 1.5% = Tk. 1.80
(iii) Carriage L.S = Tk. 6.13
(iv) Cost of fixing L.S = Tk. 24.50
Total = Tk. 152.43
Contractor's Profit 10.00% = Tk. 15.24
Overhead expenses 3.50% = Tk. 5.33
Tk. 173.00
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.07
Grand total = Tk. 183.07
Rate per No. = Tk. 183.07

Say, Tk. 183.00 Per set

11 Clamps
11.1 Service clamp
Break-up for 1 Set
(i) Cost of service clamp 1 No. @ Tk. 86.00 Each =Tk. 86.00
(ii) T & P charges 1.5% =Tk. 1.13
(iii) Carriage L.S. =Tk. 6.13
(iv) Cost of fixing L.S. =Tk. 36.75
Total =Tk. 130.00
Profit 10.00% =Tk. 13.00
Overhead expenses 3.50% =Tk. 4.55
Tk. 147.55
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 8.59
Grand total = Tk. 156.14
Rate per No. = Tk. 156.14

Say, Tk. 156.00 Per set.

11.2 P.G clamp


Break-up for 1 No.
(i) Cost of P.G clamp 1 No. @ Tk. 250.00 Each = Tk. 250.00
(ii) Carriage L.S. = Tk. 10.00
(iii) Cost of fixing L.S. = Tk. 15.00
Total = Tk. 275.00
Profit 10.00% = Tk. 27.50
Overhead expenses 3.50% = Tk. 9.63
Tk. 312.13
Analysis of P.W.D Schedule of Rates for E/M works 2014 23 Sub Head-C
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 18.17
Grand total = Tk. 330.29
Rate per No. = Tk. 330.29

Say, Tk. 330.00 Per set.

11.3 11 KV Tension clamp


Break-up for 1 No.
(i) Cost of 11 KV Tension clamp 1 No. @ Tk. 650.00 Each = Tk. 650.00
(ii) Carriage L.S. = Tk. 15.00
(iii) Cost of fixing L.S. = Tk. 20.00
Total = Tk. 685.00
Profit 10.00% = Tk. 68.50
Overhead expenses 3.50% = Tk. 23.98
Tk. 777.48
Tk. 1.05820 5.5% = Tk. 45.25
VAT with adjustment factor Grand total = Tk. 822.72
Rate per No. = Tk. 822.72

Say, Tk. 823.00 Per set.

11.4 Riz Iron Clamp


Break-up for 1 No.
(i) Cost of Riz Iron Clamp 1 No. @ Tk. 645.00 Each = Tk. 645.00
(ii) Carriage L.S. = Tk. 15.00
(iii) Cost of fixing L.S. = Tk. 25.00
Total = Tk. 685.00
Profit 10.00% = Tk. 68.50
Overhead expenses 3.50% = Tk. 23.98
Tk. 777.48
Tk. 1.05820 5.5% = Tk. 45.25
VAT with adjustment factor Grand total = Tk. 822.72
Rate per No. = Tk. 822.72

Say, Tk. 823.00 Per set.

11.5 Clamp Type Side Mounted Bracket


Break-up for 1 No.
(i) Cost of Clamp Type Side Mounted Bracket 1 No. @ Tk. 1,250.00 Each = Tk. 1,250.00

(ii) Carriage L.S. = Tk. 15.00


(iii) Cost of fixing L.S. = Tk. 25.00
Total = Tk. 1,290.00
Profit 10.00% = Tk. 129.00
Overhead expenses 3.50% = Tk. 45.15
Tk. 1,464.15
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 85.21
Grand total = Tk. 1,549.36
Rate per No. = Tk. 1,549.36

Say, Tk. 1,549.00 Per set.

12. CATENARY SERVICE


CATENARY SERVICE: WITH EASTERN CABLES
Analysis of P.W.D Schedule of Rates for E/M works 2014 24 Sub Head-C
12.1 With IC-2 x 2.5 sq. mm single core cable
type NYY of M/S Eastern Cables.

Break-up for 1 meter

(i) IC-2 x 2.5 sq. mm NYY Cables. 1 meter @ Tk. 129.00 Per meter =Tk. 129.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.28
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 156.65
Add for wastage & T & P 6.50% =Tk. 10.18
(v) Carriage L.S. =Tk. 1.23
(vi) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 174.18
Contractor's Profit 10.00% = Tk. 17.42
Overhead expenses 3.50% =Tk. 6.10
Tk. 197.69
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 11.51
Grand total = Tk. 209.20
Rate per meter = Tk. 209.20

Say, Tk. 209.00 Per meter

12.2 With IC-2 x 4 sq. mm single core cable type NYY of M/S
Eastern
Break-upCables.
for 1 meter

(i) IC-2 x 4 sq. mm NYY Cables. 1 meter @ Tk. 186.20 Per meter =Tk. 186.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 213.60
Add for wastage & T & P 6.50% =Tk. 13.88
(v) Carriage L.S. =Tk. 1.23
(vi) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 234.83
Contractor's Profit 10.00% = Tk. 23.48
Overhead expenses 3.50% =Tk. 8.22
Tk. 266.53
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 15.51
Grand total = Tk. 282.04
Rate per meter = Tk. 282.04

Say, Tk. 282.00 Per meter

12.3 With IC-2 x 6 sq. mm single core cable type NYY of M/S
Eastern
Break-upCables.
for 1 meter

(i) IC-2 x 6 sq. mm NYY Cables. 1 meter @ Tk. 265.00 Per meter = Tk. 265.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 11.03
(iv) Assorted other fixing materials L.S. = Tk. 6.00
= Tk. 291.05
Add for wastage & T & P 6.50% = Tk. 18.92
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Analysis of P.W.D Schedule of Rates for E/M works 2014 25 Sub Head-C
Sub total = Tk. 317.31
Contractor's Profit 10.00% = Tk. 31.73
Overhead expenses 3.50% = Tk. 11.11
Tk. 360.15
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 20.96
Grand total = Tk. 381.11
Rate per meter = Tk. 381.11

Say, Tk. 381.00 Per meter

12.4 With IC-2 x 10 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter

(i) IC-2 x 10 sq. mm NYY Cables. 1 meter @ Tk. 402.60 Per meter
= Tk. 402.60
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 431.22
Add for wastage & T & P 6.50% = Tk. 28.03
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 7.35
Sub total = Tk. 467.82
Contractor's Profit 10.00% = Tk. 46.78
Overhead expenses 3.50% = Tk. 16.37
Tk. 530.98
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 30.90
Grand total = Tk. 561.88
Rate per meter = Tk. 561.88

Say, Tk. 562.00 Per meter

12.5 With IC-4 x 2.5 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter

(i) IC-4 x 2.5 sq. mm NYY Cables. 1 meter @ Tk. 258.00 Per meter
= Tk. 258.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 286.62
Add for wastage & T & P 6.50% = Tk. 18.63
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 312.60
Contractor's Profit 10.00% = Tk. 31.26
Overhead expenses 3.50% = Tk. 10.94
Tk. 354.80
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 20.65
Grand total = Tk. 375.45
Rate per meter = Tk. 375.45

Say, Tk. 375.00 Per meter

12.6 With IC-4 x 4 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
Analysis of P.W.D Schedule of Rates for E/M works 2014 26 Sub Head-C

(i) IC-4 x 4 sq. mm NYY Cables. 1 meter @ Tk. 372.40 Per meter =Tk. 372.40
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 401.02
Add for wastage & T & P 6.50% =Tk. 26.07
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 9.80
Sub total =Tk. 438.11
Contractor's Profit 10.00% = Tk. 43.81
Overhead expenses 3.50% =Tk. 15.33
Tk. 497.26
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 28.94
Grand total = Tk. 526.20
Rate per meter = Tk. 526.20

Say, Tk. 526.00 Per meter

12.7 With IC-4 x 6 sq. mm single core cable type NYY of M/S
Eastern Cables.
Break-up for 1 meter
(i) IC-4 x 6 sq. mm NYY Cables. 1 meter @ Tk. 530.00 Per meter =Tk. 530.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 561.07
Add for wastage & T & P 6.50% =Tk. 36.47
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 611.01
Contractor's Profit 10.00% = Tk. 61.10
Overhead expenses 3.50% =Tk. 21.39
Tk. 693.50
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 40.36
Grand total = Tk. 733.86
Rate per meter = Tk. 733.86

Say, Tk. 734.00 Per meter

CATENARY SERVICE: BRB/Paradise/Poly/ Supershine

12.8 IC-2 x 2.5 sq. mm single core cable type NYY


of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-2 x 2.5 sq. mm NYY cable 1 meter @ Tk. 119.23 Per meter = Tk. 119.23
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 11.03
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 146.63
Add for wastage & T & P 6.50% = Tk. 9.53
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 163.51
Contractor's Profit 10.00% = Tk. 16.35
Analysis of P.W.D Schedule of Rates for E/M works 2014 27 Sub Head-C
Overhead expenses 3.50% = Tk. 5.72
Tk. 185.58
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.80
Grand total = Tk. 196.38
Rate per meter = Tk. 196.38

Say, Tk. 196.00 Per meter

12.9 With IC-2 x 4 sq. mm single core cable type NYY


of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-2 x 4 sq. mm NYY cable 1 meter @ Tk. 166.53 Per meter =Tk. 166.53
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 193.93
Add for wastage & T & P 6.50% =Tk. 12.61
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 213.88
Contractor's Profit 10.00% = Tk. 21.39
Overhead expenses 3.50% =Tk. 7.49
Tk. 242.75
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 14.13
Grand total = Tk. 256.88
Rate per meter = Tk. 256.88

Say, Tk. 257.00 Per meter

12.10 With IC-2 x 6 sq. mm single core cable type NYY


of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-2 x 6 sq. mm NYY cable 1 meter @ Tk. 231.50 Per meter =Tk. 231.50
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 258.90
Add for wastage & T & P 6.50% =Tk. 16.83
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 4.90
Sub total =Tk. 281.85
Contractor's Profit 10.00% = Tk. 28.18
Overhead expenses 3.50% =Tk. 9.86
Tk. 319.90
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 18.62
Grand total = Tk. 338.52
Rate per meter = Tk. 338.52

Say, Tk. 339.00 Per meter

12.11 With IC-2 x 10 sq. mm single core cable


type NYY
of BRB/Paradise/Poly/ Supershine
Analysis of P.W.D Schedule of Rates for E/M works 2014 28 Sub Head-C
Break-up for 1 meter

(i) IC-2 x 10 sq. mm NYY cable 1 meter @ Tk. 351.99 Per meter =Tk. 351.99
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 380.61
Add for wastage & T & P 6.50% =Tk. 24.74
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 7.35
Sub total =Tk. 413.92
Contractor's Profit 10.00% = Tk. 41.39
Overhead expenses 3.50% =Tk. 14.49
Tk. 469.80
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 27.34
Grand total = Tk. 497.15
Rate per meter = Tk. 497.15

Say, Tk. 497.00 Per meter

12.12 With IC-4 x 2.5 sq. mm single core cable type NYY
of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-4 x 2.5 sq. mm NYY cable 1 meter @ Tk. 239.00 Per meter =Tk. 239.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 12.25
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 267.62
Add for wastage & T & P 6.50% =Tk. 17.40
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 292.37
Contractor's Profit 10.00% = Tk. 29.24
Overhead expenses 3.50% =Tk. 10.23
Tk. 331.83
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 19.31
Grand total = Tk. 351.15
Rate per meter = Tk. 351.15

Say, Tk. 351.00 Per meter

12.13 With IC-4 x 4 sq. mm single core cable type NYY


of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-4 x 4 sq. mm NYY cable 1 meter @ Tk. 333.06 Per meter = Tk. 333.06
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 361.68
Add for wastage & T & P 6.50% = Tk. 23.51
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 9.80
Sub total = Tk. 396.21
Contractor's Profit 10.00% = Tk. 39.62
Analysis of P.W.D Schedule of Rates for E/M works 2014 29 Sub Head-C
Overhead expenses 3.50% = Tk. 13.87
Tk. 449.70
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 26.17
Grand total = Tk. 475.88
Rate per meter = Tk. 475.88

Say, Tk. 476.00 Per meter

12.14 With IC-4 x 6 sq. mm single core cable type NYY


of BRB/Paradise/Poly/ Supershine

Break-up for 1 meter

(i) IC-4 x 6 sq. mm NYY cable 1 meter @ Tk. 463.00 Per meter =Tk. 463.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 494.07
Add for wastage & T & P 6.50% =Tk. 32.11
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 539.66
Contractor's Profit 10.00% = Tk. 53.97
Overhead expenses 3.50% =Tk. 18.89
Tk. 612.51
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 35.65
Grand total = Tk. 648.16
Rate per meter = Tk. 648.16

Say, Tk. 648.00 Per meter

CATENARY SERVICE:
EVANA/MEP/Khawaja/RR/SINGER

12.15 With IC-2 x 2.5 sq. mm single core cable type NYY
of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-2 x 2.5 sq. mm NYY cable 1 meter @ Tk. 118.10 Per meter =Tk. 118.10
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 145.50
Add for wastage & T & P 6.50% =Tk. 9.46
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 162.30
Contractor's Profit 10.00% = Tk. 16.23
Overhead expenses 3.50% =Tk. 5.68
Tk. 184.21
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 10.72
Grand total = Tk. 194.93
Rate per meter = Tk. 194.93

Say, Tk. 195.00 Per meter

12.16 With IC-2 x 4 sq. mm single core cable type NYY


Analysis of P.W.D Schedule of Rates for E/M works 2014 30 Sub Head-C
of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-2 x 4 sq. mm NYY cable 1 meter @ Tk. 164.60 Per meter =Tk. 164.60
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 192.00
Add for wastage & T & P 6.50% =Tk. 12.48
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 6.13
Sub total =Tk. 211.82
Contractor's Profit 10.00% = Tk. 21.18
Overhead expenses 3.50% =Tk. 7.41
Tk. 240.42
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 13.99
Grand total = Tk. 254.41
Rate per meter = Tk. 254.41

Say, Tk. 254.00 Per meter

12.17 With IC-2 x 6 sq. mm single core cable type NYY


of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-2 x 6 sq. mm NYY cable 1 meter @ Tk. 228.90 Per meter =Tk. 228.90
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 11.03
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 256.30
Add for wastage & T & P 6.50% =Tk. 16.66
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 4.90
Sub total =Tk. 279.08
Contractor's Profit 10.00% = Tk. 27.91
Overhead expenses 3.50% =Tk. 9.77
Tk. 316.75
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 18.44
Grand total = Tk. 335.19
Rate per meter = Tk. 335.19

Say, Tk. 335.00 Per meter

12.18 With IC-2 x 10 sq. mm single core cable type NYY


of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-2 x 10 sq. mm NYY cable 1 meter @ Tk. 348.00 Per meter = Tk. 348.00
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 376.62
Add for wastage & T & P 6.50% = Tk. 24.48
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 7.35
Analysis of P.W.D Schedule of Rates for E/M works 2014 31 Sub Head-C
Sub total = Tk. 409.68
Contractor's Profit 10.00% = Tk. 40.97
Overhead expenses 3.50% = Tk. 14.34
Tk. 464.98
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 27.06
Grand total = Tk. 492.04
Rate per meter = Tk. 492.04

Say, Tk. 492.00 Per meter

12.19 With IC-4 x 2.5 sq. mm single core cable type NYY
of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-4 x 2.5 sq. mm NYY cable 1 meter @ Tk. 236.20 Per meter
= Tk. 236.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 264.82
Add for wastage & T & P 6.50% = Tk. 17.21
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 6.13
Sub total = Tk. 289.38
Contractor's Profit 10.00% = Tk. 28.94
Overhead expenses 3.50% = Tk. 10.13
Tk. 328.45
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 19.12
Grand total = Tk. 347.57
Rate per meter = Tk. 347.57

Say, Tk. 348.00 Per meter


12.20 With IC-4 x 4 sq. mm single core cable type NYY
of EVANA/MEP/Khawaja/RR/SINGER

Break-up for 1 meter

(i) IC-4 x 4 sq. mm NYY cable 1 meter @ Tk. 329.20 Per meter
= Tk. 329.20
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg = Tk. 9.02
(iii) Binding aluminium clip L.S. = Tk. 12.25
(iv) Assorted other fixing materials L.S. = Tk. 7.35
= Tk. 357.82
Add for wastage & T & P 6.50% = Tk. 23.26
(iv) Carriage L.S. = Tk. 1.23
(v) Labour charge L.S. = Tk. 9.80
Sub total = Tk. 392.10
Contractor's Profit 10.00% = Tk. 39.21
Overhead expenses 3.50% = Tk. 13.72
Tk. 445.04
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 25.90
Grand total = Tk. 470.94
Rate per meter = Tk. 470.94

Say, Tk. 471.00 Per meter

12.21 With IC-4 x 6 sq. mm single core cable type NYY


of EVANA/MEP/Khawaja/RR/SINGER
Analysis of P.W.D Schedule of Rates for E/M works 2014 32 Sub Head-C
Break-up for 1 meter

(i) IC-4 x 6 sq. mm NYY cable 1 meter @ Tk. 457.80 Per meter =Tk. 457.80
(ii) 8 No. SWG G.I. wire 0.08 Kg. @ Tk. 110.00 Per kg =Tk. 9.02
(iii) Binding aluminium clip L.S. =Tk. 14.70
(iv) Assorted other fixing materials L.S. =Tk. 7.35
=Tk. 488.87
Add for wastage & T & P 6.50% =Tk. 31.78
(iv) Carriage L.S. =Tk. 1.23
(v) Labour charge L.S. =Tk. 12.25
Sub total =Tk. 534.12
Contractor's Profit 10.00% = Tk. 53.41
Overhead expenses 3.50% =Tk. 18.69
Tk. 606.23
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 35.28
Grand total = Tk. 641.51
Rate per meter = Tk. 641.51

Say, Tk. 642.00 Per meter

13 SERVICE BRACKET

13.1 With 25 mm (1") dia G.I. pipe

Break-up for 1 No.

(i) 25 mm (1") dia G.I. pipe 1.52 meter @ Tk. 311.00 Per meter = Tk. 472.72
(ii) 25 mm elbow 1 No. @ Tk. 39.00 Each = Tk. 39.00
(iii) Clamp 2 Nos. @ Tk. 65.32 Each = Tk. 130.64
(iv) G.I. Bend 1 Set @ Tk. 78.00 Per set. = Tk. 78.00
(v) Sundry materials L.S. = Tk. 49.00
= Tk. 769.36
(vi) T&P 6.50% = Tk. 50.01
(vii) Labour L.S. = Tk. 122.50
(viii) Carriage L.S. = Tk. 36.75
Total = Tk. 978.62
Contractor's Profit 10.00% = Tk. 97.86
Overhead expenses 3.50% = Tk. 34.25
Tk. 1,110.74
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 64.65
Grand total = Tk. 1,175.38
Rate per No. = Tk. 1,175.38

Say, Tk. 1,175.00 Each

13.2 With 40 mm (1.5") dia G.I. pipe


Break-up for 1 No.

(i) 40 mm (1.5") dia G.I. pipe 1.52 meter @ Tk. 480.00 Per meter = Tk. 729.60
(ii) 40 mm elbow 1 No. @ Tk. 82.00 Each = Tk. 82.00
(iii) Clamp 2 Nos. @ Tk. 65.32 Each = Tk. 130.64
(iv) G.I. Bend 1 Set @ Tk. 78.00 Per set. = Tk. 78.00
(v) Sundry materials L.S. = Tk. 49.00
= Tk. 1,069.24
(vi) T&P 6.50% = Tk. 69.50
(vii) Labour L.S. = Tk. 122.50
(viii) Carriage L.S. = Tk. 49.00
Total = Tk. 1,310.24
Analysis of P.W.D Schedule of Rates for E/M works 2014 33 Sub Head-C
Contractor's Profit 10.00% = Tk. 131.02
Overhead expenses 3.50% = Tk. 45.86
Tk. 1,487.13
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 86.55
Grand total = Tk. 1,573.68
Rate per No. = Tk. 1,573.68

Say, Tk. 1,574.00 Each

14. Arial fuse

14.1 15 Amps Arial fuse


Break-up for 1 No.
(i) Cost of 15 Amps Arial fuse 1 No. @ Tk. 50.00 Each = Tk. 50.00
(ii) Carriage L.S. = Tk. 2.45
= Tk. 52.45
(iii) T & P Charge L.S. = Tk. 2.45
(iv) Labour charge L.S. = Tk. 36.75
Sub total = Tk. 91.65
Contractor's Profit 10.00% = Tk. 9.17
Overhead expenses 3.50% = Tk. 3.21
Tk. 104.02
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 6.05
Grand total = Tk. 110.08
Rate per No. = Tk. 110.08

Say, Tk. 110.00 Each

14.2 30 Amps Arial fuse


Break-up for 1 No.
(i) Cost of 30 Amps Arial fuse 1 No. @ Tk. 60.00 Each = Tk. 60.00
(ii) Carriage L.S. = Tk. 2.45
= Tk. 62.45
(iii) T & P Charge L.S. = Tk. 2.45
(iv) Labour charge L.S. = Tk. 36.75
Sub total = Tk. 101.65
Contractor's Profit 10.00% = Tk. 10.17
Overhead expenses 3.50% = Tk. 3.56
Tk. 115.37
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 6.71
Grand total = Tk. 122.09
Rate per No. = Tk. 122.09

Say, Tk. 122.00 Each

14.3 60 Amps Arial fuse


Break-up for 1 No.
(i) Cost of 60 Amps Arial fuse 1 No. @ Tk. 77.00 Each = Tk. 77.00
(ii) Carriage L.S. = Tk. 2.45
= Tk. 79.45
(iii) T & P Charge L.S. = Tk. 3.68
(iv) Labour charge L.S. = Tk. 30.00
Sub total = Tk. 113.13
Contractor's Profit 10.00% = Tk. 11.31
Overhead expenses 3.50% = Tk. 3.96
Tk. 128.40
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 7.47
Grand total = Tk. 135.87
Analysis of P.W.D Schedule of Rates for E/M works 2014 34 Sub Head-C
Rate per No. = Tk. 135.87

Say, Tk. 136.00 Each

14.4 100 Amps Arial fuse


Break-up for 1 No.
(i) Cost of 100 Amps Arial fuse 1 No. @ Tk. 94.00 Each = Tk. 94.00
(ii) Carriage L.S. = Tk. 2.45
= Tk. 96.45
(iii) T & P Charge L.S. = Tk. 3.68
(iv) Labour charge L.S. = Tk. 36.75
Sub total = Tk. 136.88
Contractor's Profit 10.00% = Tk. 13.69
Overhead expenses 3.50% = Tk. 4.79
Tk. 155.35
VAT with adjustment factor Tk. 1.05820 5.5% = Tk. 9.04
Grand total = Tk. 164.39
Rate per No. = Tk. 164.39

Say, Tk. 164.00 Each


PWD Schedule of Rates for E/M Works 2014 92

SUB HEAD - C
H.T. AND L.T. OVER HEAD DISTRIBUTION LINES
Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

1.0 MS POLE
Providing following tubular pole fabricated with 4.76 mm (3/16") thick M.S sheet
having different sections with 152.40 mm long M.S. reducing collar joint complete
with M.S base plate, top cover, necessary welding & duly painted with two coats of
superior quality aluminum silver paint over two prime coats of red oxide etc. as
required: -

1.1 Total 12192 mm (40'-0") long having 152.4 mm (6") dia 9144 mm (30') at the Each Tk. 30,780.00
bottom, and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm
x6.35 mm (2'-0" x 2'-0"x 0’-0. 25”) size steel base plate.

1.2 Total 10668 mm (35'-0") long having 152.4 mm (6") dia 7620 mm (25') at the bottom Each Tk. 27,290.00
and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm x6.35 mm
(2'-0" x 2'-0" x 0’-0.25”) size steel base plate.

1.3 Total 9144 mm (30'-0") long having 152.40 mm (6") dia 6096 mm (20') at the Each Tk. 23,790.00
bottom, and 101.60 mm (4") dia 3048 mm (10') at the top with 609 mm x 609 mm
x6.35 mm (2'-0"x 2'-0"x 0’-0.25”) size steel base plate.

1.4 Total 7620 mm (25'-0") long having 101.60 mm (4") dia 6096 mm (20') at the Each Tk. 14,880.00
bottom, and 76.20 mm (3") dia 1524 mm (5') at the top with 457 mm x 457 mm
x6.35 mm (1'-6" x 1'-6" x 0'-0.25") size steel base plate.

1.5 Total 6096 mm (20'-0") long having 76.20 mm (3") dia 4572 mm (15') at the bottom, Each Tk. 9,110.00
and 50.80 mm (2") dia 1524 mm (5') at the top with 305 mm x 305 mm x 6.35 mm
(1'-0" x 1'-0" x 0-0.25") size steel base plate.

2.0 GI POLE

Providing following GI pole fabricated with GI pipe complete with GI sockets, M.S.
base plate, top cover, necessary welding as required:-

2.1 Total 12192 mm (40'-0") long having 152.4 mm (150mm) dia( 3.4mm) thickness Each Tk. 29,620.00
9144 mm (30') at the bottom, and 101.60 mm (100 mm) dia (3.4mm) thickness 3048
mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0" x 2'-0" x 0'-0. 25") size
steel base plate.

2.2 Total 10668 mm (35’'-0") long having 152.4 mm (150 mm) dia (3.4mm) Each Tk. 26,950.00
thickness7620 mm (25') at the bottom, and 101.60 mm (100mm) dia(3.4 mm)
thickness 3048 mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0" x 2'-0"
x 0’-0. 25") size steel base plate.

2.3 Total 9144 mm (30'-0") long having 152.4 mm (150 mm) dia (3.4 mm) thickness Each Tk. 23,550.00
6096 mm (20') at the bottom, and 101.60 mm (100 mm) dia (3.4mm) thickness 3048
mm (10') at the top with 609 mm x 609 mm x 6.35 mm (2'-0"x 2'-0"x 0'-0.25") size
steel base plate.

2.4 Total 7620 mm (25'-0") long having 101.6 mm (100mm) dia (3.4 mm) thickness Each Tk. 16,320.00
6096 mm (20') at the bottom, and 76.20 mm (75 mm) dia (3.15 mm) thickness 1524
mm (5') at the top with 457 mm x457 mm x6.35 mm (1'-6"x 1'-6"x 0’-0.25”) size steel
base plate.
PWD Schedule of Rates for E/M Works 2014 93

Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

2.5 Total 6096 mm (20’) long having 76.20 mm (75 mm) dia (3.15 mm) thickness 4572 Each Tk. 10,140.00
mm (15') at the bottom, and 50.80 mm (50 mm) dia (2.90 mm) thickness 1524 mm
(5') at the top, 304 mm x 304 mm x 6.35 mm (1'-0"x 1'-0"x 0'-0.25”) size steel base
plate.

2.6 Total 3048 mm (10-0’) long having 38m (40 mm) dia (2.90mm) thickness with Each Tk. 2,510.00
228.6 mm x 228.6 mm x 4.76 mm (0'-9" x 0'-9" x 0’-3/16") size steel base plate.

Spun P.C POLE

2.7.0 Providing Spun type pree-stressed concrete pole fabricateded with high tensile steel
wire (5mm dia) manufactured by government owned company or Bangladesh power
devlopment board as follows.(suitable for using in saline and coastal areas)

2.7.1 Total 15000 mm (49.2') long pole having Top dia 230mm (9"), Bottom dia 390 mm Each Tk. 44,070.00
(15") , wall thickness 55mm (2.16"), weight not less than 1560 kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.

2.7.2 Total 12000 mm (39.37') long pole having Top dia 230mm (9"), Bottom dia 390 mm Each Tk. 29,380.00
(15") , wall thickness 55mm (2.16"), weight 1250kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.

2.7.3 Total 11000 mm (36.00') long pole having Top dia 230mm (9"), Bottom dia 375 mm Each Tk. 25,280.00
(14.76") , wall thickness 55mm (2.16"), weight 1100kg, breaking strength
512kg/sqmm, without bottom plate and carrying charge.

2.7.4 Total 9000 mm (29.52') long pole having Top dia 150mm (5.90"), Bottom dia 270 Each Tk. 11,750.00
mm (10.63") , wall thickness 50mm (1.97"), weight 522kg, breaking strength
232kg/sqmm, without bottom plate and carrying charge.

2.7.5 Bottom plate for 9/11/12 meter Spun P.C Pole Each Tk. 128.00

2.7.6 Bottom plate for 15 meter Spun P.C Pole Each Tk. 233.00

3.0 POLE ERECTION

3.1 Erection of following tubular pole upto 1828.80 mm (6’) depth by placing the pole
base on one layer of Ist. class brick flat soling over 76.2 mm (3") sand bedding and
making 1:2:4 C.C. work around the pole 304.8 mm (1'-0") below GL & 304.8 mm(1’
ft) above GL, 12.5 mm (1/2") thick cement plaster with neat cement finishing over
concrete surface including proper curing, excavation & refilling and ramming the
loose soil etc. as required.

3.1.1 12192 mm (40’) long MS/GI /Spun P.C pole with 457 mm x 457 mm (1.5’x1.5’) cc Each Tk. 2,313.00
work

3.1.2 10668 mm (35’) long MS/GI /SpunP.C pole with 457.20 mm x 457.20 mm (1.5’x1.5’) Each Tk. 2,253.00
cc work
PWD Schedule of Rates for E/M Works 2014 94

Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

3.2 Erection of following tubular pole upto 1524 mm (5’) depth by placing the pole base
on one layer of Ist. class brick flat soling over 76.2 mm (3”) sand bedding and
making 1:2:4 C.C. work around the pole 304.8 mm (1’)below GL & 304.8 mm(1 ft)
above GL, 12.5 mm (1/2") thick cement plaster with neat cement finishing over
concrete surface including proper curing, excavation & refilling and ramming the
loose soil etc. as required.

3.2.1 9144 mm (30’) long MS/GI /P.C pole with 457 mm x 457mm (1.5’ x 1.5’) cc work. Each Tk. 2,151.00

3.2.2 7620 mm (25’) long MS/GI / Spun P.C pole with 381 mm x 381 mm (1.5’ x 1.5’) cc Each Tk. 2,121.00
work.

3.2.3 6096 mm (20’) long MS/GI pole with 304.8 mm x 304.8 mm (1’ x 1’) cc work. Each Tk. 1,459.00

4.0 Erection of 3048 mm (10') long GI pole upto 609.6 mm (2') depth and making Each Tk. 565.00
228.60 mm x 228.60 mm(0'-9" x 0'-9")1:2:4 C.C. work around the pole from 304.80
mm (1') below GL upto 304.8 mm (1 ft) above GL 76.20 mm (3") thick brick soling
over 76.20 mm (3") layer of sand bedding,12.5 mm (1/2") thick cement plaster and
neat cement finishing over concrete surface including excavation, refilling and
ramming the loose soil surrounding CC work, proper curing etc. complete as
required.

5.0 WIRE RACK/ CROSS ARM

5.1 Providing and fixing 914.4 mm (3'-0") long 3 spool vertical wire rack fabricated with Each Tk. 661.00
38.10 mm x 38.1mm x 6.35 mm (1.5" x 1.5" x 0.25") M.S. angle complete with 3
nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35 mm (1" x ¼") flat
M.S. bar for fixing insulators and clamping the rack respectively including necessary
welding, G.I. nuts, bolts, washer etc. with two coats of aluminum painting over prime
coat of red oxide painting .

5.2 Providing and fixing 1219 mm (4'-0") long 4 spool vertical wire rack fabricated with Each Tk. 1,273.00
38.10 mm x 76.2mm x 38.1 mm x 6.35 mm (1.5" x 3" x 1.5" x 0.25") M.S. Channel
complete with 4 nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35
mm (1" x ¼") flat M.S. bar for fixing insulators and clamping the rack respectively
including necessary welding, G.I. nuts, bolts, washer etc. with two coats of
aluminum painting over prime coat of red oxide painting

5.3 Providing and fixing 1524 mm (5'-0") long 5 spool vertical wire rack fabricated with Each Tk. 1,542.00
38.1 mm x 76.2 mm x 38.1 mm x 6.35 mm (1.5" x 3" x 1.5" x 0.25") M.S. Channel
complete with 5 nos of ‘U’ clamp and 2 nos of ‘D’ clamp made of 25.4 mm x 6.35
mm (1" x ¼") flat M.S. bar for fixing insulators and clamping the rack respectively
including necessary welding, G.I. nuts, bolts, washer etc. with two coats of
aluminum painting over prime coat of red oxide painting

5.4 Provding and fixing 1524 mm (5'-0") long Clamp Bracket fabricated with 76 mm x Each Tk. 1,411.00
6.35 mm thick (3"x1/4" thick) M.S Flat bar complete with 2 Nos of "D" Clamp made
of 38.1 mm x 6.35mm thick x 762mm long (1.5" x 1/4" thick x 2'-6" long ) for fixing
clamp brackets, units & bolts etc. complete (For H.T. line) in/c. hot-deep galvanizing
of the complete cross arm as per direction of E/C.
PWD Schedule of Rates for E/M Works 2014 95

Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

5.5 Provding and fixing 1524 mm (5'-0") long cross arm fabricated with 76 mm x 76 Each Tk. 1,889.00
mmx 6.35 mm thick (3"x3"x1/4"thick) M.S Channel with necessary clamp brackets,
nut bolts etc complete (For H.T.line) in/c hot-deep galvanizing of the complete
cross arm as per direction of E/C

6.0 SHACKLE/PIN/DISC TYPE INSULATOR

6.1 Providing and fixing 500 volt grade porcelain shackle type insulator of size 63 mm x Each Tk. 98.00
50.8 mm (2.5"x 2”)

6.2 Providing and fixing 500 volt grade porcelain shackle type insulator of size 89 mm x Each Tk. 126.00
76 mm (3.5"x 3”)
6.3 Provding and fixing of 11 KV Porcelain pin insulator and pins in/c. bolts etc. to Each Tk. 847.00
existing pole top as per direction of Engineer in Charge.
6.4 Provding and fixing of 11 KV Porcelain Disc insulator in/c. Conductor clamps ball Each Tk. 2,222.00
eye box, Ball eye hook and pole atachment / Supporting steel work and their
installation at the pole top as per direction of E /C.(2 no.s. in set).

7.0 STAY

Providing and fixing following pole stay made of stranded G.I. wires complete with
anchor plate of size 304.8 mm x 304.8 mm x 6.35 mm (1' x 1'x1/4"), 16 mm (5/8")
dia stay rod of necessary length and frame bolts, guy insulator, nuts, with necessary
adjusting arrangement complete as required to be placed within 30°- 45° angle with
pole.

7.1 8 SWG 7 strand Each Tk. 1,688.00


7.2 10 SWG 7 strand Each Tk. 1,393.00
7.3 12 SWG 7 strand Each Tk. 1,163.00

8.0 OVERHEAD AAC /ACSR CONDUCTOR

8.1 Providing and drawing following PVC insulated aluminum stranded conductor in
overhead line at proper sag complete with necessary G.I binding wire as required.

Cables manufactured by Govt. of Bangladesh owned/ shared Company Ltd


(Eastern Cables).

8.1.1 IC- 25 sq.mm (GNAT) Per meter Tk. 69.00


8.1.2 IC- 50 sq.mm (ANT) Per meter Tk. 105.00
8.1.3 IC- 75 sq.mm (EARWIG) Per meter Tk. 154.00
8.1.4 IC- 100 sq.mm (WASP) Per meter Tk. 197.00

With Conductor manufactured by BRB/ Paradise/ BBS/ Poly/ Supersign/


Citizen/ Evana/ Khawaja / MEP or equivalent accepted/approved by the
Engineer.

8.1.5 IC-25 sq.mm (GNAT) Per meter Tk. 48.00


8.1.6 IC-50 sq.mm (ANT) Per meter Tk. 84.00
8.1.7 IC-75 sq.mm (EARWIG) Per meter Tk. 126.00
8.1.8 IC-100 sq.mm (WASP) Per meter Tk. 167.00

8.2 Providing and drawing followingAluminium conductor steel reinforced (ACSR) Bare
conductor in. Overhead line at proper sag complet with necessary G.I binding wire
as required.
Cables manufactured by Govt. of Bangladesh owned/ shared Company Ltd
(Eastern Cables).
PWD Schedule of Rates for E/M Works 2014 96

Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

8.2.1 IC- 50 Sq.mm (RABBIT) Per meter Tk. 111.00


8.2.2 IC- 100 Sq.mm (DOG) Per meter Tk. 209.00

With Conductor manufactured by BRB/ Paradise/ BBS/Poly/


Supersign/Citizen/ Evana/ Khawaja /MEP or equivalent accepted/approved by
the Engineer.

8.2.3 IC- 50 Sq.mm (RABBIT) Per meter Tk. 108.00


8.2.4 IC- 100 Sq.mm (DOG) Per meter Tk. 204.00

9.0 G.I WIRE / COPPER WIRE

Providing and drawing No. 2-10 SWG G.I/hard drawn bare copper wire in overhead
line at proper sag complete with necessary binding wire as required as per direction
of the Engineer.

9.1 G.I. wire Per Kg Tk. 164.00


9.2 H.D.B.C. wire. Per Kg Tk. 1,433.00

10.0 SERVICE BELT

Providing and fixing standard bi-metallic ‘U’ type service belt complete with 10 mm Per set Tk. 183.00
dia bare copper conductor at the middle and aluminum conductor at the ends with
necessary insulation complete as required.

11.0 CLAMPS

11.1 Providing and fixing standard service clamp for jointing service cable with the Per set Tk. 156.00
overhead conductor complete as required

11.2 Providing and fixing P/G clamp with the conductor ( for H/T line) as per direction of Each Tk. 330.00
E/Ch.

11.3 Providing and fixing of 11 KV.tension clamp to fix at disc insulator, fixing of 11 KV. Each Tk. 823.00
conductor with the tension clamp in/c. Hot deep Galvaniging as per direction of
E/Ch.

11.4 Providing and fixing Riz iron clamp fixing 11KV. pin insulator, top of the H.T. pole Each Tk. 823.00
(with nut bolts) in/c. hot deep galvanizing complete as per direction of E/Ch.

11.5 Providing and fixing clamp type side mounted bracket for fixing 11KV pin insulator Each Tk. 1,549.00
(with nut bolts) in/c. hot deep galvanizing complete as per direction of E/C.

12.0 CATENARY WIRING FOR SERVICE CONNECTION


Catenary wiring with the following PVC insulated and sheathed cables (NYY)
properly clipped with 8 SWG G.I. supporting wire properly strained with clamps,
nuts, bolts etc. including shackle type insulator at both ends.

Cables manufactured by Govt. of Bangladesh owned/ shared Company Ltd


(Eastern Cables).

12.1 IC-2 x 2.5 sq.mm Per meter Tk. 209.00


12.2 IC-2 x 4 sq.mm Per meter Tk. 282.00
PWD Schedule of Rates for E/M Works 2014 97

Sl. No. Description of Items (Sub Head-C) Unit Unit Rate

12.3 IC-2 x 6 sq.mm Per meter Tk. 381.00


12.4 IC-2 x 10 sq.mm Per meter Tk. 562.00
12.5 IC-4 x 2.5 sq.mm Per meter Tk. 375.00
12.6 IC-4 x 4 sq.mm Per meter Tk. 526.00
12.7 IC-4 x 6 sq.mm Per meter Tk. 734.00

Cables manufactured by Paradise/ BRB or any other company(s) having valid


test sirtificate form inter-nationally accrediped laboratouray
accepted/approved by the Engineer.

12.8 IC-2 x 2.5 sq.mm Per meter Tk. 196.00


12.9 IC-2 x 4 sq.mm Per meter Tk. 257.00
12.10 IC-2 x 6 sq.mm Per meter Tk. 339.00
12.11 IC-2 x 10 sq.mm Per meter Tk. 497.00
12.12 IC-4 x 2.5 sq.mm Per meter Tk. 351.00
12.13 IC-4 x 4 sq.mm Per meter Tk. 476.00
12.14 IC-4 x 6 sq.mm Per meter Tk. 648.00

Cables manufactured by BBS/MEP/Poly/Supersign/Fecto


industries(citizen)/Evana/Khawaja(777 energy cable)/
RR/SINGER/Macro/Transcom(Transtec)/SQ/Dunlop/Yasin or equivalent
accepted/approved by the Engineer.

12.15 IC-2 x 2.5 sq.mm Per meter Tk. 195.00


12.16 IC-2 x 4 sq.mm Per meter Tk. 254.00
12.17 IC-2 x 6 sq.mm Per meter Tk. 335.00
12.18 IC-2 x 10 sq.mm Per meter Tk. 492.00
12.19 IC-4 x 2.5 sq.mm Per meter Tk. 348.00
12.20 IC-4 x 4 sq.mm Per meter Tk. 471.00
12.21 IC-4 x 6 sq.mm Per meter Tk. 642.00

13.0 SERVICE BRACKET

13.1 Providing and fixing of 1524 mm (5') long 25.40 mm (1") dia G.I. pipe service Each Tk. 1,175.00
bracket complete with 1 no. of GI bend 2 Nos fixing clamps of 38.10 mm x 6.35 mm
(1.5"x ¼") size iron flat bar bolts, nuts etc. complete as required.

13.2 Providing and fixing of 1524 mm (5') long 38.1 mm (1.5") dia G.I. pipe service Each Tk. 1,574.00
bracket complete with 1 no. of GI bend 2 Nos fixing clamps of 38.10 mm x 6.35 mm
(1.5" x ¼") size iron flat bar bolts, nuts etc. complete as required.

14.0 AERIAL FUSE

Providing and fixing 500 Volts grade porcelain base rewireable type aerial service
fuse unit of the following capacity: -
14.1 Suitable for use upto 15 Amps Each Tk. 110.00
14.2 Suitable for use upto 30 Amps Each Tk. 122.00
14.3 Suitable for use upto 60 Amps Each Tk. 136.00
14.4 Suitable for use upto 100 Amps Each Tk. 164.00
SUB HEAD - C
H.T. AND L.T. OVER HEAD DISTRIBUTION
LINES
MS POLE

Sl. Unit Unit Rate (2013) Unit Rate


Description of Items (Sub Head-C)
No. (2011)

1.0 Providing following tubular pole fabricated with 4.76 mm (3/16") thick M.S sheet having different sections
with 152.40 mm long M.S. reducing collar joint complete with M.S base plate, top cover, necessary welding
& duly painted with two coats of superior quality aluminum silver paint over two prime coats of red oxide
etc. as required: -

1.1 40' Each Tk. 30,780.00 Tk. 22,452.00

1.2 35' Each Tk. 27,290.00 Tk. 19,756.00

1.3 30' Each Tk. 23,790.00 Tk. 17,048.00

1.4 25' Each Tk. 14,880.00 Tk. 11,156.00

1.5 20' Each Tk. 9,110.00 Tk. 7,218.00

GI POLE

2.0
2.1 40' Each Tk. 29,620.00 Tk. 28,397.00
2.2 35' Each Tk. 26,950.00 Tk. 24,942.00
2.3 30' Each Tk. 23,550.00 Tk. 21,602.00
2.4 25' Each Tk. 16,320.00 Tk. 13,423.00
2.5 20' Each Tk. 10,140.00 Tk. 8,026.00
2.6 10' Each Tk. 2,510.00 Tk. 2,335.00

Spun P.C POLE

2.7.0
2.7.1 49.2' Each Tk. 44,070.00
2.7.2 39.37' Each Tk. 29,380.00 Tk. 24,486.00
2.7.3 36' Each Tk. 25,280.00 Tk. 21,066.00
2.7.4 29.51' Each Tk. 11,750.00 Tk. 9,794.00
2.7.5 Bottom plate for 9/11/12 meter Spun P.C Each Tk. 128.00 Tk. 105.00
Pole
2.7.6 Bottom plate for 15 meter Spun P.C Pole Each Tk. 233.00 Tk. 194.00

3.0 POLE ERECTION


3.1
3.1.1 40' Each Tk. 2,313.00 Tk. 1,856.00
3.1.2 35' Each Tk. 2,253.00 Tk. 1,808.00

3.2
3.2.1 30' Each Tk. 2,151.00 Tk. 1,724.00
3.2.2 25' Each Tk. 2,121.00 Tk. 1,676.00
3.2.3 20' Each Tk. 1,459.00 Tk. 1,134.00

4.0 Erection of 3048 mm (10') long GI pole Each Tk. 565.00 Tk. 473.00
upto 609.6 mm (2') depth and making
228.60 mm x 228.60 mm(0'-9" x 0'-9")1:2:4
C.C. work around the pole from 304.80
mm (1') below GL upto 304.8 mm (1 ft)
above GL 76.20 mm (3") thick brick soling
over 76.20 mm (3") layer of sand
bedding,12.5 mm (1/2") thick cement
plaster and neat cement finishing over
concrete surface including excavation,
refilling and ramming the loose soil
surrounding CC work, proper curing etc.
complete as required.

5.0 WIRE RACK/ CROSS ARM

5.1 3' Each Tk. 661.00 Tk. 688.00

5.2 4' Each Tk. 1,273.00 Tk. 1,269.00

5.3 5' Each Tk. 1,542.00 Tk. 1,614.00

5.4 Provding and fixing 1524 mm (5'-0") long Each Tk. 1,411.00
Clamp Bracket fabricated with 76 mm x
6.35 mm thick (3"x1/4" thick) M.S Flat bar
complete with 2 Nos of "D" Clamp made
of 38.1 mm x 6.35mm thick x 762mm long
(1.5" x 1/4" thick x 2'-6" long ) for fixing
clamp brackets, units & bolts etc. complete
(For H.T. line) in/c. hot-deep galvanizing
of the complete cross arm as per direction
of E/C.

5.5 Provding and fixing 1524 mm (5'-0") long Each Tk. 1,889.00
cross arm fabricated with 76 mm x 76 mmx
6.35 mm thick (3"x3"x1/4"thick) M.S
Channel with necessary clamp brackets,
nut bolts etc complete (For H.T.line) in/c
hot-deep galvanizing of the complete
cross arm as per direction of E/C
6.0 SHACKLE/PIN/DISC TYPE
INSULATOR

6.1 Providing and fixing 500 volt grade Each Tk. 98.00 Tk. 80.00
porcelain shackle type insulator of size 63
mm x 50.8 mm (2.5"x 2”)
6.2 Providing and fixing 500 volt grade Each Tk. 126.00 Tk. 108.00
porcelain shackle type insulator of size 89
mm x 76 mm (3.5"x 3”)
6.3 Provding and fixing of 11 KV Porcelain pin Each Tk. 847.00
insulator and pins in/c. bolts etc. to
existing pole top as per direction of
Engineer in Charge.
6.4 Provding and fixing of 11 KV Porcelain Each Tk. 2,222.00
Disc insulator in/c. Conductor clamps ball
eye box, Ball eye hook and pole
atachment / Supporting steel work and
their installation at the pole top as per
direction of E /C.(2 no.s. in set)

STAY
7.0
7.1 8 SWG 7 strand Each Tk. 1,688.00 Tk. 1,402.00
7.2 10 SWG 7 strand Each Tk. 1,393.00 Tk. 1,148.00
7.3 12 SWG 7 strand Each Tk. 1,163.00 Tk. 976.00

8.0 OVERHEAD AAC /ACSR


CONDUCTOR

8.1
Cables manufactured by Govt. of
Bangladesh owned/ shared Company Ltd
(Eastern Cables).

8.1.1 IC- 25 sq.mm (GNAT) Per meter Tk. 69.00 Tk. 56.00
8.1.2 IC- 50 sq.mm (ANT) Per meter Tk. 105.00 Tk. 96.00
8.1.3 IC- 75 sq.mm (EARWIG) Per meter Tk. 154.00 Tk. 132.00
8.1.4 IC- 100 sq.mm (WASP) Per meter Tk. 197.00 Tk. 167.00

With Conductor manufactured by BRB/


Paradise/BBS/Poly/ Supersign/Citizen/
Evana/ Khawaja /MEP or equivalent
approved by the Engineering-in-Charge

8.1.5 IC-25 sq.mm (GNAT) Per meter Tk. 48.00 Tk. 51.00
8.1.6 IC-50 sq.mm (ANT) Per meter Tk. 84.00 Tk. 88.00
8.1.7 IC-75 sq.mm (EARWIG) Per meter Tk. 126.00 Tk. 121.00
8.1.8 IC-100 sq.mm (WASP) Per meter Tk. 167.00 Tk. 146.00
8.2 Cables manufactured by Govt. of
Bangladesh owned/ shared Company Ltd
(Eastern Cables).

8.2.1 IC- 50 Sq.mm (RABBIT) Per meter Tk. 111.00


8.2.2 IC- 100 Sq.mm (DOG) Per meter Tk. 209.00

With Conductor manufactured by BRB/


Paradise/ BBS/Poly/ Supersign/Citizen/
Evana/ Khawaja /MEP or equivalent
approved by the Engineering-in-Charge

8.2.3 IC- 50 Sq.mm (RABBIT) Per meter Tk. 108.00


8.2.4 IC- 100 Sq.mm (DOG) Per meter Tk. 204.00

9.0

9.1 G.I. wire Per Kg Tk. 164.00 Tk. 142.00


9.2 H.D.B.C. wire. Per Kg Tk. 1,433.00 Tk. 1,430.00

Service belt

10.0 Providing and fixing standard bi-metallic Per set Tk. 183.00 Tk. 128.00
‘U’ type service belt complete with 10 mm
dia bare copper conductor at the middle
and aluminum conductor at the ends with
necessary insulation complete as required.

11.0 Clamps
11.1 Providing and fixing standard service Per set Tk. 156.00 Tk. 121.00
clamp for jointing service cable with the
overhead conductor complete as required

11.2 Providing and fixing P/G clamp with the Each Tk. 330.00
conductor ( for H/T line) as per direction
of E/Ch.
11.3 Providing and fixing of 11 KV.tension Each Tk. 823.00
clamp to fix at disc insulator, fixing of 11
KV. conductor with the tension clamp
in/c. Hot deep Galvaniging as per
direction of E/Ch.
11.4 Providing and fixing Riz iron clamp fixing Each Tk. 823.00
11KV. pin insulator, top of the H.T. pole
(with nut bolts) in/c. hot deep galvanizing
complete as per direction of E/Ch.
11.5 Providing and fixing clamp type side Each Tk. 1,549.00
mounted bracket for fixing 11KV pin
insulator (with nut bolts) in/c. hot deep
galvanizing complete as per direction of
E/C.

CATENARY WIRING FOR


SERVICE CONNECTION

12.0 Catenary wiring with the following PVC Tk. 181.00


insulated and sheathed cables (NYY)
properly clipped with 8 SWG G.I.
supporting wire properly strained with
clamps, nuts, bolts etc. including shackle
type insulator at both ends.

Cables manufactured by Govt. of


Bangladesh owned/ shared Company Ltd
(Eastern Cables).

12.1 IC-2 x 2.5 sq.mm Per meter Tk. 209.00 Tk. 181.00
12.2 IC-2 x 4 sq.mm Per meter Tk. 282.00 Tk. 243.00
12.3 IC-2 x 6 sq.mm Per meter Tk. 381.00 Tk. 331.00
12.4 IC-2 x 10 sq.mm Per meter Tk. 562.00 Tk. 487.00
12.5 IC-4 x 2.5 sq.mm Per meter Tk. 375.00 Tk. 324.00
12.6 IC-4 x 4 sq.mm Per meter Tk. 526.00 Tk. 455.00
12.7 IC-4 x 6 sq.mm Per meter Tk. 734.00 Tk. 635.00

With Cables manufactured by


BRB/Paradise/ BBS/Poly /Supersign
EVANA/ Khawaja/MEP/Citizen(Fecto
Industries) or equivalent approved by the
Engineering-in-Charge

12.8 IC-2 x 2.5 sq.mm Per meter Tk. 196.00 Tk. 158.00
12.9 IC-2 x 4 sq.mm Per meter Tk. 257.00 Tk. 212.00
12.10 IC-2 x 6 sq.mm Per meter Tk. 339.00 Tk. 285.00
12.11 IC-2 x 10 sq.mm Per meter Tk. 497.00 Tk. 420.00
12.12 IC-4 x 2.5 sq.mm Per meter Tk. 351.00 Tk. 281.00
12.13 IC-4 x 4 sq.mm Per meter Tk. 476.00 Tk. 393.00
12.14 IC-4 x 6 sq.mm Per meter Tk. 648.00 Tk. 547.00

Cables of RR/ SINGER/Macro/


Transcom(Transtec) or equivalent
approved by the Engineering-in-Charge

12.15 IC-2 x 2.5 sq.mm Per meter Tk. 195.00 Tk. 151.00
12.16 IC-2 x 4 sq.mm Per meter Tk. 254.00 Tk. 202.00
12.17 IC-2 x 6 sq.mm Per meter Tk. 335.00 Tk. 271.00
12.18 IC-2 x 10 sq.mm Per meter Tk. 492.00 Tk. 397.00
12.19 IC-4 x 2.5 sq.mm Per meter Tk. 348.00 Tk. 267.00
12.20 IC-4 x 4 sq.mm Per meter Tk. 471.00 Tk. 372.00
12.21 IC-4 x 6 sq.mm Per meter Tk. 642.00 Tk. 517.00

13.0 SERVICE BRACKET

13.1 Providing and fixing of 1524 mm (5') long Each Tk. 1,175.00 Tk. 1,005.00
25.40 mm (1") dia G.I. pipe service bracket
complete with 1 no. of GI bend 2 Nos
fixing clamps of 38.10 mm x 6.35 mm (1.5"x
¼") size iron flat bar bolts, nuts etc.
complete as required

13.2 Providing and fixing of 1524 mm (5') long Each Tk. 1,574.00 Tk. 1,451.00
38.1 mm (1.5") dia G.I. pipe service bracket
complete with 1 no. of GI bend 2 Nos
fixing clamps of 38.10 mm x 6.35 mm (1.5"
x ¼") size iron flat bar bolts, nuts etc.
complete as required

AERIAL FUSE
14.0 Providing and fixing 500 Volts grade
porcelain base rewireable type aerial
service fuse unit of the following capacity:
-
14.1 Suitable for use upto 15 Amps Each Tk. 110.00 Tk. 101.00
14.2 Suitable for use upto 30 Amps Each Tk. 122.00 Tk. 113.00
14.3 Suitable for use upto 60 Amps Each Tk. 136.00 Tk. 135.00
14.4 Suitable for use upto 100 Amps Each Tk. 164.00 Tk. 155.00
% Change

et having different sections


p cover, necessary welding
wo prime coats of red oxide

37.09%

38.14%

39.55%

33.38%

26.21%

4.31%
8.05%
9.02%
21.58%
26.34%
7.49%

New
19.99%
20.00%
19.97%
21.90%

20.10%
24.62%
24.61%

24.77%
26.55%
28.66%

19.45%

-3.92%

0.32%

-4.46%

New

New
22.50%

16.67%

New

New

20.40%
21.34%
19.16%

23.21%
9.38%
16.67%
17.96%

-5.88%
-4.55%
4.13%
14.38%
New
New

New
New

15.49%
0.21%

42.97%

28.93%

New

New

New
New

15.47%
16.05%
15.11%
15.40%
15.74%
15.60%
15.59%

24.05%
21.23%
18.95%
18.33%
24.91%
21.12%
18.46%

29.14%
25.74%
23.62%
23.93%
30.34%
26.61%
24.18%

16.92%

8.48%

8.91%
7.96%
0.74%
5.81%
Index C

3 Sub Head-C:- H.T. AND L.T. OVER HEAD DISTRIBUTION LINES

i MS POLE
ii GI POLE
iii POLE ERECTION
iv WIRE RACK/ CROSS ARM
v SHACKLE/PIN/DISC TYPE
INSULATOR
vi STAY
vii OVERHEAD AAC /ACSR
CONDUCTOR
viii G.I WIRE / COPPER WIRE
ix SERVICE BELT
x CLAMPS
xi CATENARY WIRING FOR
SERVICE CONNECTION
xii SERVICE BRACKET
xiii AERIAL FUSE

You might also like