Professional Documents
Culture Documents
Fdocuments - in Distillery Condensate and Spent Leese Treatment For Complete Reuse
Fdocuments - in Distillery Condensate and Spent Leese Treatment For Complete Reuse
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 9, September 2014)
313
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 9, September 2014)
TABLE II 4. Anaerobic digestion followed by controlled land
CHARACTERISTICS OF DISTILLERY CONDENSATE application.
For A 300 KLPD Distillery 5. Raw spentwash composting.
Sr. No. Parameter Value Method 4, 5 and 6 are now more or less discontinued
because of higher land requirement and lesser treatment
1. Volume (m3) 800 – 1000 efficiencies. Method 1 and 2 are now the methods now in
2. C.O.D. (mg/L) 6000 – 10000 practice in the distillery sector. However, concentration and
3. B.O.D.5 (mg/L) 3000 – 6000 incineration is now being slowly rejected because of its
higher capital and recurring cost and therefore
C. Distillery spentleese
concentration and composting is now dominantly practiced.
Spentleese is another type of effluent which is generated Concentration of spentwash is critical as the immense
from the Recovery columns of the distillation process. The volume of raw spentwash requires extremely extensive
effluent is mainly characterized by rogue alcohols, which treatments which are not only financially challenging but
get entrained in the spentleese due to change in the are also very high maintenance and less efficient.
conditions of the columns, which thereby affect the Concentration of spentwash significantly reduces the
parameters of the stream significantly. The parameters of treatment expenditures and also reduces the land
the spentleese are as given below. requirement to a great extent whenever an industry is
TABLE III planning to adopt composting as an option.
CHARACTERISTICS OF DISTILLERY SPENTLEESE
B. Distillery condensate and Spentleese
For A 300 KLPD Distillery The characteristics of the condensate and Spentleese
Sr. No. Parameter Value depict the need of biological treatment in order to
3 effectively reduce the organic matter content. Several
1. Volume (m ) 200 – 300
methods were discussed, and after detailed brainstorming
2. C.O.D. (mg/L) 8000 – 16000
on design considerations for the volume in question, i.e
3. B.O.D.5 (mg/L) 4000 – 8000 1200 m3/day, a conventional mode of Anaerobic Digestion
followed by Aerobic System was adopted.
III. DISTILLERY EFFLUENT TREATMENTS The process flow of the method adopted is as given
A. Distillery spentwash below:
The spentwash quantity generated from the process
varies from distillery to distillery. The quantity can also
depend on the type of process changes which may have
been implemented in a unit as well. It was seen from
practical observations at the study site that the spentwash
generation in the distillery (having a production capacity
was in the range of 4 – 6 L / L of alcohol because of a
change in the process which was implemented, wherein
spentwash recycle for certain columns was being carried
out for an undisclosed process.
However, even this quantity is still higher, and the
treatment cost and the required end results may not yet be
achieved. The Ministry of Environment and Forests
(MoEF) has now prescribed 5 specific treatment methods
for the proper disposal of the spentwash generated. The
methods are as given below:
1. Concentration and incineration
2. Concentration and composting
3. Anaerobic digestion followed by two – stage aeration FIGURE I TREATMENT PROCESS FOR DISTILLERY AND SPENTLEESE
and composting. TREATMENT
314
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 9, September 2014)
C. Treatment process description e. Two Stage Aeration Clarification System: The effluent
a. Equalization Tank: The condensate and Spentleese after anaerobic treatment contains significantly reduced
generated in the distillery process is collected in a 1 – day amounts of organic load. This effluent is then further
lagoon near the distillery, and from here, the effluent is treated in an Aerobic process scheme. In generalized terms,
pumped to the Condensate Treatment Plant. Here, the the system used in the present process is called commonly
effluent pH is neutralized using Caustic Soda or Lime. as Activated Sludge Process. However, in order to have a
Preferably, lime is utilized as a first preference as the end better efficiency and reduced economic burdens, an
use of water does not rely on the TDS of the water and advanced ASP mode in the form of Extended Aeration,
therefore, moderate TDS in the water is acceptable. The which works on the principle of low F: M Ratio, was
Equalization tank is designed for a retention time of 8 hrs. utilized in two stages. Utilization of two stages was carried
The main aim of the equalization tank is to equalize the out because of the end use requirement of the water.
flow and characteristics and load the effluent to the further Therefore, the second stage of extended aeration system
treatment at a constant uninterrupted rate. acted more like a polishing treatment rather than an
extensive biological treatment.
b. Anaerobic Digester: In order to limit the energy
requirement for the treatment process, an initial phase of f. Tertiary Treatment: As a polishing treatment for
biological treatment in the form of Anaerobic digester was confirmation of consistent efficiency, a Multimedia
provided. This digester was a Completely Stirred Type filtration unit for removal of any trace suspensions, and an
Reactor (CSTR). However, instead of the conventional Activated Carbon filter to cope with any colour or trace
agitator based mixing system, a newer advanced mode of organics was provided. The backwash frequency for the
Pump Sparging was applied. The system was designed units was regularized to once in 2 days, which was
keeping in mind the mixing speed required which is effectively practiced and gave satisfactory results.
approximately 4 times that of the inlet flow. This flow was
confirmed through practical studies on site. The digester IV. TREATMENT STABILIZATION PHASE
was commissioned and stabilized by the procedure Any biological treatment requires a phase of
discussed later, and then, it was continuously fed with the stabilization before actual loading of the effluent. Similarly
effluent for more than 190 days. The digester dimensions for this project, a stabilization phase for the commissioning
were 12 m dia x (10+1) m Height. of the biological units was carried out. The phases involved
c. Degasser Tower: The effluent after the biodigestion in the stabilization are as given below:
process contains mainly remaining organic solids and gases A. Digester Charging: In this phase, the digester was
like Ammonia, Hydrogen sulfide etc, which are entrapped loaded with cowdung, nutrients and enriched culture. The
in the effluent. If this effluent is directly subjected to the quantity of the cowdung loading (in Tons) was typically 2
aerobic treatment, it can result in toxic effects on the – 4% of the digester volume. The nutrient addition was
aerobic bacterial culture. Therefore, it is necessary to carriedut only on requirement of the process. The total
provide a treatment mode suitable for dispersion of these cowdung that was used in the stabilization of the above
gases. In order to achieve this, a degasser system based on digester was approximately 30 Tons, and the nutrients used
diffused air diffusion was provided. This system proved in the stabilization phase were approximately 500 Kgs all
effective for the complete removal of the entrapped gases together. The charging phase of the digester consisted of
to the maximum extent. loading the ingredients in the unit, and keeping the unit
d. Lamella Clarifier: This settling system is utilized in under constant agitation without external additions for 2 – 3
order to maintain the biomass culture in the anaerobic days.
digester. The recirculation pattern of the lamella clarifier B. Digester Loading: After 2 – 3 days steady period, the
was kept at 100%. Due to this, the balance of the microbial effluent loading based on the COD load was initiated. The
mass in the digester was kept constant. Biodigester sludge loading was on the basis of COD Load because of the fact
i.e. anaerobic sludge is naturally light in nature nd that in anaerobic reactors, quantity of organic load supplied
therefore, does not settle easily. Therefore, a specialized is more critical than the volume of the effluent. The loading
treatment scheme wherein aided settling is necessary phase continued for 30 days wherein the COD load was
without coagulant addition. For this purpose a specialized increased gradually keeping a constant difference between
settling scheme in the form of Plate based settling is the increases, and thereby avoiding any shockloads.
utilized.
315
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 9, September 2014)
TABLE IV D. End use of the treated water: The water after this
DIGESTER LOADING CYCLE extensive treatment was enough to replace the water
Sr. Flow COD COD Load Remarks demand of the distillery by almost 80% wherein the water
No. (m3/hr) (mg/L) (Kg/m3.hr) was used in fermenter makeup, cooling tower makeup and
other non – critical processes in the distillery. This
1. 10 6000 60 Loading Initiated
significantly decreased the financial load, and also, reduced
2. 10 6200 62 the dependence of the distillery on the external water
3. 15 5800 87 Increased by approx. source by a large extent.
30Kg/m3.d
4. 15 6000 90 V. RESULTS AND OBSERVATIONS
5. 11 10800 118.8 Flow decreased
Regular analysis of the effluent was carried out in order
suitably so that
to observe the health of the Condensate and Spentleese
consistent loading treatment scheme. The cumulative results analysis is as
increase @ 30Kg/m3.d given below.
is maintained
6. 12 9600 115.6
7. 20 7200 144
8. 20 7600 152
9. 26 7000 182
10. 26 6800 176.8
11. 18 6600 118.8 Loading decreased due
to sudden pH drop.
Loading rate decreased
to <120Kg/m3d
12. 18 6900 124.2
13. 22 6800 149.6
14. 21 7500 157.5
15. 25 7500 187.5
16. 28 6500 182
17.
C. Aeration Tank Charging: The charging / commissioning FIGURE II VARIATION IN COD FROM INLET TO OUTLET
of the Aerobic phase was initiated on the 5 day of the
digester loading phase. The day was calculated using the
amount of time required for the digester to overflow and
the time required for the same effluent to reach the
Aeration Tank – I. The charging phase for aeration tank
comprised of filling the tank to 40% capacity with fresh
water on the 3rd Day of the digester loading and addition of
the enriched aerobic microbial culture in sufficient quantity
along with nutrients. This steady stage continued uptil the
5th day when the digester effluent began to reach the unit.
Similar calculations and additions were carried out on the
second stage aeration phase, which began on the 9 th day of
the digester loading phase.
316
International Journal of Emerging Technology and Advanced Engineering
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 9, September 2014)
Water after this extensive treatment was enough to The amount of investment required for the project is
replace the water demand of the distillery by almost 80% roughly 1 – 2% of the capital cost of the distillery, and
wherein the water was used in fermenter makeup, cooling which can reduce the expenditure of the factory on water
tower makeup and other non – critical processes in the significantly. This is a ground breaking design which has
distillery. This significantly decreased the financial load, been incorporated by the authors firm in more than 10
and also, reduced the dependence of the distillery on the distilleries in India.
external water source by a large extent.
Furthermore, since the water requirement dropped REFERENCES
significantly, the dependence of the factory on the external [1] Apte S. S., 2011, Anaerobic Filter for Distillery Condensate
Treatment – Optimization of Anaerobic Filter System for Distillery
water source was negligible, and the internal usages were Condensate Generated from Volume Reduction of Spentwash, LAP
also controlled through in – plant measures, utilizing Lambert Academic Publishing GmbH & Co. KG, ISBN: 978-3-
which, the factory made a significant monetary profit. The 8473-4713-2
photographs of the Distillery and Spentleese treatment unit [2] Baez – Smith C., 2006, Anaerobic Digestion of Vinasse for
are given below: Production of Methane in the Sugar Can Distillery, Proceedings of
SPRI Conference on Sugar Processing
[3] Bortone G., 2009, Integrated anaerobic / aerobic biological treatment
VI. CONCLUSIONS for intensive swine production, Bioresource Technology, Elsevier
The study that was conducted in the project was based Publication, Vol. 100, pp. 5424 – 5430.
on actual data generated through practical operations of the [4] Chen Y. and Cheng J. J., 2005, Anaerobic Processes in Waste
Treatment, Water Environment Research, Water Environment
treatment scheme employed. The design was carried out by Federation Publication, Vol. 77(6), pp. 1347 – 1388.
the primary author and the plant erected on the same basis.
The treatment proved to be a critical initiative for the
proper disposal of the spentwash from the distillery which
is a major environmentally dangerous wastewater stream.
317