TASK Start Date End Date Duration TASK Start Date End Date

Title Planning 22-Feb-21 13-Mar-21 20 Title Planni2/22/2021 3/13/2021


Making of Proposal Paper 13-Mar-21 19-Mar-21 7 Making of P3/13/2021 3/19/2021
Proposal 19-Mar-21 19-Mar-21 1 Proposal 3/19/2021 3/19/2021
Designing 19-Mar-21 22-Mar-21 4 Designing 3/19/2021 3/22/2021
Demonstration 22-Mar-21 26-Mar-21 5 Demonstrat3/22/2021 3/26/2021

TASK Start Date End Date Duration


I. Analysis
a. Brainstorming 8-Mar 10-Mar 3
b. Gathering Information 11-Mar 12-Mar 2
c. Concept Selection 13-Mar 14-Mar 2
d. Documentation 15-Mar 22-Mar 8
e. Analysis Complete 29-Mar 29-Mar 1
II. Design
a. Data Flow Diagram 22-Mar 23-Mar 2
b. Structure Design 24-Mar 25-Mar 2
c. Design Complete 29-Mar 29-Mar 1
III. Development
a. System Module 29-Mar 30-Mar 2
b. Integrating System Module 30-Mar 1-Apr 3
c. Initial Testing 1-Apr 2-Apr 2
d. Development Complete 3-Apr 3-Apr 1
IV. Testing
a. Perform System Testing 4-Apr 5-Apr 2
b. Document Issues Found 5-Apr 5-Apr 1
c. Correct Issues Found 5-Apr 25-May 51
d. Testing Complete 29-May 29-May 1
V. Implementation 11-Jun 11-Jun 1
22-Feb-21 3-Mar-21 12-Mar-21 21-Mar-21 30-Mar-21

Title Planning

Making of Proposal Paper

Proposal

Designing

Demonstration
TASK Start Date End Date Duration TASK
I. Analysis a. Brainstorming
a. Brainstorming 8-Mar 10-Mar 3 b. Gathering Information
b. Gathering Information 11-Mar 12-Mar 2 c. Concept Selection
c. Concept Selection 13-Mar 14-Mar 2 d. Documentation
d. Documentation 15-Mar 22-Mar 8 e. Analysis Complete
e. Analysis Complete 22-Mar 22-Mar 1 a. Data Flow Diagram
II. Design b. Structure Design
a. Data Flow Diagram 22-Mar 23-Mar 2 c. Design Complete
b. Structure Design 24-Mar 25-Mar 2 a. System Module
c. Design Complete 29-Mar 29-Mar 1 b. Integrating System Module
III. Development c. Initial Testing
a. System Module 29-Mar 30-Mar 2 d. Development Complete
b. Integrating System Module 30-Mar 1-Apr 3 a. Perform System Testing
c. Initial Testing 1-Apr 2-Apr 2 b. Document Issues Found
d. Development Complete 3-Apr 3-Apr 1 c. Correct Issues Found
IV. Testing d. Testing Complete
a. Perform System Testing 4-Apr 5-Apr 2 a. Implementation
b. Document Issues Found 5-Apr 5-Apr 1
c. Correct Issues Found 5-Apr 25-May 51 I. Analysis
d. Testing Complete 29-May 29-May 1 II. Design
V. Implementation 29-May 11-Jun 14 III. Development
IV. Testing
V. Implementation

I. ANALYSIS II
8-Mar 13-Mar 18-Mar 23-Mar 28-Mar 22-Mar 23-Mar 24-Mar

a. Brainstorming
a. Data Flow Diagram

b. Gathering Information

c. Concept Selection b. Structure Design

d. Documentation

c. Design Complete
e. Analysis Complete
III. Development I
29-Mar 30-Mar 31-Mar 1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 4-Apr 14-Ap

a. System Module a. Perform System Testing

b. Integrating System Module b. Document Issues Found

c. Initial Testing c. Correct Issues Found

d. Development Complete d. Testing Complete


Start Date End Date Duration
8-Mar 10-Mar 3
11-Mar 12-Mar 2 GANTT CHART
13-Mar 14-Mar 2 8-Mar 23-Mar 7-Apr 22-Apr 7-May 22-May
15-Mar 22-Mar 8 a. Brainstorming
22-Mar 22-Mar 1 b. Gathering Information
22-Mar 23-Mar 2 c. Concept Selection
24-Mar 25-Mar 2 d. Documentation
e. Analysis Complete
29-Mar 29-Mar 1
a. Data Flow Diagram
29-Mar 30-Mar 2 b. Structure Design
30-Mar 1-Apr 3 c. Design Complete
1-Apr 2-Apr 2 a. System Module
3-Apr 3-Apr 1 b. Integrating System Module
c. Initial Testing
4-Apr 5-Apr 2
d. Development Complete
5-Apr 5-Apr 1 a. Perform System Testing
5-Apr 25-May 51 b. Document Issues Found
29-May 29-May 1 c. Correct Issues Found
29-May 11-Jun 14 d. Testing Complete
a. Implementation

8-Mar 22-Mar 15
22-Mar 29-Mar 8
29-Mar 3-Apr 6 GANTT CHART
4-Apr 29-May 56 8-Mar 23-Mar 7-Apr 22-Apr 7-May
29-May 11-Jun 14
I. Analysis

II. Design

III. Development
II. DESIGN
22-Mar 23-Mar 24-Mar 25-Mar 26-Mar 27-Mar 28-Mar 29-Mar 30-Mar 31-Mar IV. Testing

V. Implementation
Flow Diagram

ructure Design

esign Complete
IV. Testing
4-Apr 14-Apr 24-Apr 4-May 14-May 24-May 3-Jun

orm System Testing

ument Issues Found

orrect Issues Found

d. Testing Complete
NTT CHART
7-Apr 22-Apr 7-May 22-May 6-Jun 21-Jun

GANTT CHART
23-Mar 7-Apr 22-Apr 7-May 22-May 6-Jun 21-Jun
TASK Start Date End Date Duration
I. Analysis 8-Mar 12-Mar 5
a. Brainstorming 8-Mar 9-Mar 2
b. Gathering Information 9-Mar 10-Mar 2
8-Mar 22-
c. Concept Selection 10-Mar 11-Mar 2
I. Analysis
d. Documentation 11-Mar 12-Mar 2
e. Analysis Complete 12-Mar 12-Mar 1 a. Brainstorming
II. Design 12-Mar 19-Mar 8
b. Gathering Information
a. Data Flow Diagram 13-Mar 15-Mar 3
b. Structure Design 15-Mar 17-Mar 3 c. Concept Selection

c. Design Complete 17-Mar 19-Mar 3 d. Documentation


III. Development 19-Mar 3-Apr 16
e. Analysis Complete
a. System Module 19-Mar 24-Mar 6
b. Integrating System Module 24-Mar 27-Mar 4 II. Design
c. Initial Testing 27-Mar 30-Mar 4 a. Data Flow Diagram
d. Development Complete 30-Mar 3-Apr 5
b. Structure Design
IV. Testing 4-Apr 29-May 56
a. Perform System Testing 4-Apr 5-Apr 2 c. Design Complete
b. Document Issues Found 5-Apr 5-Apr 1 III. Development
c. Correct Issues Found 5-Apr 25-May 51
d. Testing Complete 25-May 29-May 5 a. System Module

V. Implementation 29-May 11-Jun 14 b. Integrating System Module

c. Initial Testing

d. Development Complete

IV. Testing

a. Perform System Testing

b. Document Issues Found

c. Correct Issues Found

d. Testing Complete

V. Implementation
GANTT CHART
8-Mar 22-Mar 5-Apr 19-Apr 3-May 17-May
I. Analysis

ainstorming

Information

ept Selection

cumentation

is Complete

II. Design

ow Diagram

cture Design

gn Complete

Development

tem Module

tem Module

itial Testing

nt Complete

IV. Testing

tem Testing

ssues Found

ssues Found

ng Complete

lementation
HART
3-May 17-May 31-May 14-Jun 28-Jun