Professional Documents
Culture Documents
Feasibility
-The term ‘capital rationing’ refers to the situation where the implicit
assumption within the NPV rule, that capital will always be available to
finance acceptable projects, does not hold.
That is if management cannot raise enough money from the capital
market, then a situation of capital rationing will exist. The management
has to ‘ration out’ the limited amount of investment capital between
the available projects.
-The capital rationing will not exist if management can raise enough
money from banks and financial institutions, but also exists if
the shareholders of the company are not willing to pay more money in
terms of new shares.
(The company can raise the funds internally by the shareholders or
externally through banks and financial institutions.)
-The existence of capital rationing represents a capital market
imperfection: investment funds are no longer freely available at the
market rate of return.
-Given a situation of capital rationing, how does it affect the efficiency
of investment decision advice given by the NPV appraisal technique,
and can NPV be adapted to operate successfully in such situations?
*Hard and soft capital rationing:-
-Hard capital rationing describes the situation where forces external to
the company, usually either the capital market itself or the government
will not supply unlimited amounts of investment capital to a company,
even though the company has identified investment opportunities that
would be able to produce the required return.
-Soft capital rationing arises from forces internal to a company, such
as a capital budget, which limits the amount of capital available for
investments.
Example: Suppose a company has two independent projects (G)
and (H). Both projects required $1000 of investment capital, and
project (G) yields 14% return, whereas project (H) yields 16% return. If
the- company’s cost of capital is 12% and funds are unlimited.
-In this case we will accept both projects because both projects will
produce positive NPV
, but if funds are limited that the company can provide $1000 only
(capital rationing), then the company has to choose between the two
projects to choose the project which produces higher NPV, then
compare between the return of the chosen project and the alternative
return of the capital market.
-To choose among the two situations (unlimited capital and capital
rationing) as follows:-
Unlimited capital Capital rationing
-We will suppose that capital rationing exists at Year 0 as a result that
a company has only capital outlay of $250
-The capital outlay should be applied to projects (B), (A), and part of
(C) and this give the company a total positive NPV of 60.21 which is
the maximum possible total NPV, given the capital expenditure
constraint.
-Therefore, because investment capital is scarce, shareholder wealth
will only rise by 60.21 as a result of investment decisions made.
-The process of selecting projects on the basis of their benefit-cost
ratios ensures that the company will maximize the total amount of
positive gained from the available projects, assuming limited
investment capital.
Example (2): we will assume two separate single period capital
rationing that:-
[1] In the first situation there is straightforward Year 0 rationing.
[2] In the second situation, some positive NPV projects may not be
accepted, but there could be circumstances where there could be
the advantage to accept negative NPV projects.
-Assuming Samar Company is considering the following projects:-
Years
Project 0 1 …….. NPV
(O) - 150 -200 …….. +15
(P) - 120 -100 …….. +33
(Q) - 90 -120 …….. +42
(R) - 200 -80 …….. -14
(S) - 70 +100 …….. +12
(T) - 180 +90 …….. -6
-Based on NPV criteria, management should accept all projects except
the projects (R) and (T).
-Samar management knows that there will be no capital rationing in
year 1, but in year 0 it is willing to expend only $350 in Year 0.
-To solve the problem of single time-period capital rationing situation
at Year 0, we will use benefit-cost ratio rankings as follows:-
Project NPV ÷ Y0 outlay Benefit-cost Ranking
ratio
(O) +15 ÷ 150 +0.1 4
(P) +33 ÷ 120 +0.28 2
(Q) +42 ÷ 90 +0.47 1
(R) -14 ÷ 200 -0.07 ___
(S) +12 ÷ 70 +0.17 3
(T) -6 ÷ 180 -0.03 ___
NPV
Investment decision: 350 available
- 90 invested in project (Q), producing: +42
+260 Balance
- 120 invested in project (P), producing: +33
+140 Balance
- 70 invested in project (S), producing: +12
+70 Balance
-70 invested in (70) of project (O),producing: +7
0 150 +94
-Therefore, the company should undertake projects (Q), (P), (S), and part of (O).
This will generate a total positive NPV of +94 which will be the maximum
possible, even the expenditure constraint.