You are on page 1of 4

Student Name: Trần Minh Hoàng

Student ID: IELSIU18042

HOMEWORK – SUPPLY CHAIN DESIGN


CHAPTER 5: CAPACITY PLANNING

Question 1: (25 points)


Melanie is the manager of the Clean Machine car wash and has gathered the following
information. Customers arrive at a rate of eight per hour according to a Poisson distribution.
The car washer can service an average of ten cars per hour with service times described by an
exponential distribution. Melanie is concerned about the server’s performance and she has
asked you to calculate the following system characteristics:
µ (per hr) 10
λ (per hr) 8

(a) Average system utilization


λ 8
p= = =0.8
µ 10
(b) Average number of customers in the system
λ 8
L= = =4
µ−λ 10−8
(c) Average number of customers waiting in line
p × L=0.8× 4=3.2
(d) The average time a customer spends in the system
1
W= =0.5
µ− λ
(e) The average time a customer spends waiting in line
p ×W =0.5 ×0.8=0.4
(f) The probability of having more than three customers in the system

P 3=1−( 1− p ) × ( 1+ p2 + p3 + p )=0.4096
(g) The probability of having more than four customers in the system

P 4=1− (1−p ) × ( 1+ p2+ p 3+ p+ p 4 ) =0.3277

Question 2: (30 points)


If Melanie adds an additional server at Clean Machine car wash, the service rate changes to
an average of 16 cars per hour. The customer arrival rate is 10 cars per hour. Melanie has
asked you to calculate the following system characteristics:
µ (per hr) 16
λ (per hr) 10
Servers 2

1
Student Name: Trần Minh Hoàng
Student ID: IELSIU18042

0! 1
1! 1
2! 2
λ/µ 0.625
1-p 0.688
3! 6
4! 24

(a) Average system utilization


10
p= =0.313
16 ×2

(b) The probability that no customers are in the system


Po=¿
(c) Average number of customers waiting in line

p × Po ×0.625 2
Lq= =0.068
0.6882 × 2
(d) The average time a customer spends waiting in line
Lq 0.068
Wq= = =0.0068
λ 10
(e) The average time a customer spends in the system
1 1
W =Wq+ =0.0068+ =0.069
µ 16
(f) Average number of customers in the system
L=λ × W =10 × 0.069=0.69
(g) The probability of having more than three customers in the system

0.6253
P 3=Po × =0.010657
6×2
(h) The probability of having more than four customers in the system
0.6254
P 4=Po × =0.000833
24 ×22

Question 3: (10 points)


An automobile brake supplier operates on two 8-hour shifts, 5 days per week, 52 weeks per
year. The table below shows time standards, lot sizes, and demand forecasts for three
components. Because of demand uncertainties, the operations manager obtained three
demand forecasts (pessimistic, expected and optimistic). The manager believes that a 20%
capacity cushion is best.

2
Student Name: Trần Minh Hoàng
Student ID: IELSIU18042

  Processing, p Setup, s Lot size, Q Demand Forecast, D


(unit/hour) (hour/lot) (pair/lot) (pair)
Component A 0.05 1 60 18,000
Component B 0.2 4.5 80 13,000
Component C 0.05 8.2 120 25,000

(a) What is the minimum number of machines needed?

D D

M=
[ ( )]
Dp+
Q
s
[ ( )]
product 1
+…+ Dp+
Q
s
product n

C
[ ( )]
N 1−
100

18,000 13,000 25,000

¿
[ 18,000∗0.05+ ( )][
60 (
1 + 13,000∗0.2+
80 )
∗4.5 + 25,000∗0.05+
120][ ∗8.2 ( ) ] ¿ 2.25
20
8∗2∗5∗52∗ 1−
100 [ ( )]
There are 2 options: 2 machines with overtime functioning or get 3 new machines
(b) If the operation currently has two machines, what is the capacity gap?
The capacity gap is: 2.25−2=0.25
→ There should be 1 additional machine, unless the supplier runs 2 overtime machines.

Question 4: (15 points)


Bob Greer operates Bob's Garage and Manhole Cover Recycling Center at
the corner of Lookout Highway and Ruff Road. Bob's Garage has one bay dedicated to wheel
alignments. Although the recycling center is open at night, the garage normally is open only
on weekdays from 7 A.M to 7 P.M and on Saturdays from 7 A.M to noon. An alignment
takes an average of 60 minutes to complete, although Bob charges customer for two hours
according to a nationally published mechanic’s labor-standard manual. During March, the
height of pothole season, Bob’s Garage is open from 6 A.M to 10 P.M on weekdays and from
6 A.M to 6 P.M on Saturdays.
(a) What are the garage’s peak and effective capacities, in alignments per week?
As an alignments takes 1 hour to be finish
The total available time in a normal week ¿ 12∗5+ 5=65 hours => 65 alignments a week
The total available time in a peak week ¿ 16∗5+12=92 hours => 92 alignment a week
Bob charges customer for two hours for each alignment.
 The peak capacity in this case is 92/2 = 46 alignments a week.
 The effective capacity in this case is 65/2 = 32.5 alignments a week.

(b) During the second week in March, Bob’s Garage completed 90 alignments.
What is the utilization as a percent of peak capacity?

3
Student Name: Trần Minh Hoàng
Student ID: IELSIU18042

What is the utilization as a percent of effective capacity?


The utilization as percent and the peak capacity in this case is (90/92)*100% = 97.82%
The utilization as percent and the effective capacity in this case is (90/65)*100% = 138.46%

(c) Then, what is the capacity cushion as a percent of peak capacity?


What is the capacity cushion as a percent of effective capacity?
The capacity cushion as percent of peak capacity = 100% - 97.82% = 2.18%
The capacity cushion as a percent of effective capacity¿ 100 %−138.46 %=−38.46 %

Question 5: (20 points)


Roche Brothers is considering a capacity expansion of its supermarket. The landowner will
build the addition to suit in return for $200,000 upon completion and a 5-year lease.
The increase in rent for the addition is $10,000 per month. The annual sales projected through
year 5 follow. The current effective capacity is equivalent to 500,000 customers per
year. Assume a 2 percent pretax profit on sales.
(a) If Roche expands its capacity to serve 700,000 customers per year now (end of year
0), what are the projected annual incremental pretax cash flows attributable to this
expansion?
The capacity is currently 500,000 customers annually. Incremental cashflow when Roche is
expanding its capacity to 700,000 by the end of the year 0:
Year 0: Cash flow=−$ 200,000
Year1: Demand=560,000 ; Cash flow=60,000∗2 %∗50−10,000 ×12=−$ 60,000
Year2:Demand=600,000 ; Cash flow =100,000∗2 %∗53−10,000 ×12=−$ 14,000
Year3: Demand=685,000 ; Cash flow=185,000∗2 %∗56−10,000 ×12=$87,200
Year4: Demand=700,000 ; Cash flow=200,000∗2 %∗60−10,000 ×12=$ 120,000
Year5:Demand=715,000 ; Cash flow=200,000∗2 %∗64−10,000 ×12=$ 136,000

(b) If Roche expands its capacity to serve 700,000 customers per year at the end of year
2, the landowner will build the same addition for $240,000 and a 3-year lease at
$12,000 per month. What are the projected annual incremental pretax cash flows
attributable to this expansion alternative?

Year 1 2 3 4 5
Customers 560,000 600,000 685,000 700,000 715,000
Average Sales per Customer $ 50.00 $ 53.00 $ 56.00 $ 60.00 $ 64.00

Y ear 0 :Cash flow=0.(serve at theend of year 2)


Year 1 : Demand=560,000 cus ; Cash flow =0.(serve at the end of year 2)
Year 2 : Demand=600,000 cus ; Cash flow =−$ 240,000.
Year 3 : Demand=685,000 cus ; Cash flow=185,000 × ( 2 % × $ 56 )−$ 12,000× 12=$ 63,200.
Year 4 : Demand=700,000 cus ; Cash flow =200,000 × ( 2 % × $ 60 )−$ 12,000× 12=$ 96,000.
Year 5 : Demand=715,000 cus ; Cash flow=200,000 × ( 2 % × $ 64 )−$ 12,000 ×12=$ 112,000.

You might also like