3 - FOWT_Asia_DDE_schedule_20200525_GICON_Rev07_draft.mpp FOWT Pilot - DDE Schedule / Level 2 24.03.

2021

Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
1 1 FOWT Pilot - DDE Schedule / Level 2 11,018 h 01.04.21 31.08.22 356 t
2 1.1 GENERAL 3,788 h 01.04.21 31.08.22 356 t

3 1.1.1 GN-100 PROJECT MANAGEMENT, PLANNING, COORDINATION AND REPORTING GICON 1,518 h 01.04.21 31.08.22 356 t FAD

4 1.1.2 GN-101 INTERFACE MANAGEMENT SUPPORT GICON 280 h 01.04.21 31.08.22 356 t FAD

5 1.1.3 GN-102 OPERATION, INSPECTION & MAINTENANCE PHILOSOPHY; AND MANNING LEVEL STUDY (depending on GICON 140 h 01.04.21 15.06.21 50 t PDI
interaction of WE)

6 1.1.4 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS GICON 44 h 01.04.21 27.05.21 37 t DWA

7 1.1.5 GN-103 Issue technical docs for procurement/ CMS (depending on interaction of the supplier) 0h 28.05.21 28.05.21 0t DWA 28.05.21

8 1.1.6 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS 16 h 28.05.21 17.06.21 15 t DWA

9 1.1.7 GN-103 Ready for handover to GN-105 GICON 0h 17.06.21 17.06.21 0t DWA 17.06.21

10 1.1.8 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS GICON 60 h 18.06.21 30.08.21 52 t DWA

11 1.1.9 GN-104 DEVELOP/ UPDATE OPERATING PROCEDURE GICON 140 h 28.05.21 05.08.21 50 t PDI

12 1.1.10 GN-105 FACILITES STATUS MONITORING (FSM) GICON 200 h 18.06.21 09.09.21 60 t DWA

13 1.1.11 GN-106 ASSET REGISTER, SAP PM MASTER DATA PREPARATION AND UPLOADING GICON 140 h 01.04.21 30.09.21 127 t DWA

14 1.1.12 GN-107 MASTER EQUIPMENT LIST GICON 70 h 22.09.21 30.11.21 50 t KOE

15 1.1.13 GN-108 NON-LABOUR COST YARD 0h 01.04.21 01.04.21 0t FAD 01.04.21

16 1.1.14 GN-109 ENGINEERING COMPUTING AND MAINTENANCE SERVICES GICON 140 h 01.04.21 30.11.21 170 t FAD

17 1.1.15 GN-110 DESIGN BASIS MEMORANDUM (DBM) & BASIS DESIGN VALIDATION AND UPDATE GICON 70 h 01.04.21 31.05.21 39 t KOE

18 1.1.16 GN-111 ELECTRONIC DOCUMENTATION MANAGEMENT SYSTEM (EDMS) GICON 80 h 01.04.21 29.10.21 148 t FAD

19 1.1.17 GN-112 TECHNICAL REQUISITION PACKAGE (TRP) FOR LONG LEAD ITEMS (LLI) AND MAJOR EQUIPMENT GICON 40 h 01.04.21 30.09.21 127 t FAD

20 1.1.18 GN-113 TECHNICAL BID EVALUATION (TBE) FOR LONG LEAD ITEMS (LLI) & MAJOR EQUIPMENT GICON 40 h 20.04.21 30.09.21 116 t FAD

21 1.1.19 GN-114 VENDOR DATA REVIEW AND INCORPORATION (VDR / VDI) GICON 40 h 02.07.21 30.09.21 65 t FAD

22 1.1.20 GN-115 POST AFC SUPPORT – FOLLOW ON ENGINEERING GICON 630 h 01.12.21 31.08.22 186 t FAD

23 1.1.21 GN-116 FINAL DESIGN DOCUMENTATION AND CLOSE OUT REPORT GICON 140 h 06.10.21 31.08.22 226 t FAD

24 1.1.22 GN-117 INSURANCE FOR GICON´s SCOPE OF WORK FOR DDE BY ALLIANZ GICON 0h 01.04.21 01.04.21 0t FAD 01.04.21

25 1.1.23 GN-118 TRAVELING & ACCOMMODATION GICON 0h 01.04.21 01.04.21 0t FAD 01.04.21

26 1.1.24 GN-119 SOFTWARE RENTAL GICON 0h 01.04.21 01.04.21 0t FAD 01.04.21

27 1.2 MECHANICAL 540 h 01.04.21 30.09.21 127 t

28 1.2.1 ME-101 WIND TURBINE DESIGN BASIS ELEON 10 h 01.04.21 01.06.21 40 t FAD

29 1.2.2 ME-102 ANNUAL ENERGY PRODUCTION (AEP) REPORT ELEON 10 h 01.04.21 01.06.21 40 t FAD

30 1.2.3 ME-103 INTEGRATED LOAD ANALYSIS ELEON 10 h 01.04.21 27.07.21 80 t FAD

31 1.2.4 ME-104 TECHNICAL DATASHEET & SPECIFICATION WE 10 h 01.04.21 10.08.21 90 t FAD

32 1.2.5 ME-105 TLP PIPING DESIGN & SPECIFICATION GICON 182 h 01.04.21 17.08.21 95 t JWA

33 1.2.6 ME-105 Issue technical docs for procurement/ piping & fitting (depending on interaction of the supplier) GICON 0h 20.08.21 20.08.21 0t JWA 20.08.21

34 1.2.7 ME-105 TLP PIPING DESIGN & SPECIFICATION GICON 58 h 20.08.21 30.09.21 30 t JWA

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

page 1 GICON/KOE
3 - FOWT_Asia_DDE_schedule_20200525_GICON_Rev07_draft.mpp FOWT Pilot - DDE Schedule / Level 2 24.03.2021

Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
35 1.2.8 ME-106 MATERIAL HANDLING STUDY AND PHILOSOPHY GICON 160 h 01.04.21 30.08.21 104 t FPI

36 1.2.9 ME-107 PDMS 3D MODEL REVIEW GICON 100 h 01.04.21 30.08.21 104 t RKA

37 1.2.10 ME-107 Ready for handover GICON 0h 30.08.21 30.08.21 0t RKA 30.08.21

38 1.3 MATERIAL CORROSION & INSPECTION 245 h 01.06.21 18.10.21 100 t

39 1.3.1 MCI-101 MATERIAL SELECTION AND CORROSION PROTECTION GICON 105 h 01.06.21 23.08.21 60 t KOE

40 1.3.2 MCI-101 CDBM (Corrosion Design Basis Memorandum) GICON 95 h 27.07.21 21.09.21 41 t KOE

41 1.3.3 MCI-101 Issue technical docs for procurement/ painting material (depending on interaction of the supplier) GICON 0h 21.09.21 21.09.21 0t KOE 21.09.21

42 1.3.4 MCI-101 CDBM (Corrosion Design Basis Memorandum) GICON 45 h 22.09.21 18.10.21 19 t KOE

43 1.4 ELECTRICAL 20 h 01.04.21 30.11.21 170 t

44 1.4.1 EL-101 ELECTRICAL DETAILED ENGINEERING DESIGN (GREENFIELD – WIND TURBINE PACKAGE) ELEON 10 h 01.04.21 30.11.21 170 t FAD

45 1.4.2 EL-102 PETRONAS ELECTRICAL SAFETY AND OPERABILITY REVIEW (P-ELSOR) ELEON 10 h 01.04.21 30.11.21 170 t FAD

46 1.5 INSTRUMENTATION 50 h 01.04.21 30.11.21 170 t

47 1.5.1 IN-101 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS JUNCTION BOX LOCATION AND CABLE LAYOUT ELEON 10 h 01.04.21 30.11.21 170 t FAD

48 1.5.2 IN-102 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS DESIGN DRAWINGS ELEON 10 h 01.04.21 30.11.21 170 t FAD

49 1.5.3 IN-103 WIND TURBINE CONTROL PANEL, ELECTRICAL SYSTEMS, FIRE & GAS SYSTEM, CONDITION MONITORING ELEON 10 h 01.04.21 30.11.21 170 t FAD
SYSTEM AND INTEGRATED DISPLAY VIA SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)
SPECIFICATION

50 1.5.4 IN-104 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS EQUIPMENT SPECIFICATIONS AND DATA SHEETS ELEON 10 h 01.04.21 30.11.21 170 t FAD

51 1.5.5 IN-105 TELECOMMUNICATION DESIGN AND ENGINEERING ELEON 10 h 01.04.21 30.11.21 170 t FAD

52 1.6 STRUCTURAL 5,835 h 01.04.21 30.11.21 170 t

53 1.6.1 ST-101 STRUCTURAL BASIS OF DESIGN (BOD) GICON 20 h 01.04.21 01.06.21 40 t KOE

54 1.6.2 ST-102 STABILITY ANALYSIS (depending on interaction of WE) GICON 210 h 20.04.21 14.07.21 60 t HHA

55 1.6.3 ST-103 ERECTION, LOAD-OUT, INTEGRATION ANALYSIS AND DETAILED METHODOLOGY (depending on GICON 180 h 20.07.21 07.10.21 58 t PDI
interaction of WE)

56 1.6.4 ST-104 TRANSPORTATION & INSTALLATION ANALYSIS (depending on interaction of WE) GICON 1,680 h 12.05.21 30.09.21 100 t HHA

57 1.6.5 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 5h 01.04.21 12.04.21 6t IFG

58 1.6.6 ST-105 Issue technical docs for procurement (pre-specification only)/ tendon connector (depending on GICON 0h 13.04.21 13.04.21 0t IFG 13.04.21
interaction of the supplier)

59 1.6.7 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 70 h 13.04.21 19.08.21 91 t IFG

60 1.6.8 ST-105 Issue technical docs for procurement/ tendon connector/ mooring line (depending on interaction of the GICON 0h 20.08.21 20.08.21 0t IFG 20.08.21
supplier)

61 1.6.9 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 5h 20.08.21 30.08.21 7t IFG

62 1.6.10 ST-106 FOUNDATION SYSTEM DESIGN (depending on interaction of WE) GICON 520 h 01.04.21 30.08.21 104 t EHL

63 1.6.11 ST-107 SUBSTRUCTURE DETAILED STRUCTURAL DESIGN & ANALYSIS (depending on interaction of WE) GICON 670 h 03.05.21 30.08.21 84 t IFG

64 1.6.12 ST-108 DYNAMIC/SUBMARINE CABLE DESIGN & ANALYSIS (depending on interaction of WE) GICON 140 h 25.06.21 30.08.21 47 t FAD

65 1.6.13 ST-109 OPERATIONAL & ACCIDENTAL BOAT IMPACT ANALYSIS GICON 200 h 03.05.21 27.07.21 60 t MIK

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

page 2 GICON/KOE
3 - FOWT_Asia_DDE_schedule_20200525_GICON_Rev07_draft.mpp FOWT Pilot - DDE Schedule / Level 2 24.03.2021

Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
66 1.6.14 ST-110 WIND TURBINE DETAILED STRUCTURAL DESIGN & ANALYSIS WE 40 h 01.04.21 02.09.21 107 t FAD

67 1.6.15 ST-110 Alignment with WE WE 0h 02.09.21 02.09.21 0t FAD 02.09.21

68 1.6.16 ST-111 WEIGHT CONTROL & MANAGEMENT GICON 210 h 01.04.21 30.09.21 127 t KOE

69 1.6.17 ST-112 CORROSION / EROSION PROTECTION GICON 105 h 07.05.21 30.08.21 80 t KOE

70 1.6.18 ST-112 Issue technical docs for procurement/ painting material (depending on interaction of the supplier) GICON 0h 21.09.21 21.09.21 0t KOE 21.09.21

71 1.6.19 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 684 h 03.05.21 02.08.21 64 t RKA

72 1.6.20 ST-113 Issue technical docs for procurement/ primary steel GICON 0h 02.08.21 02.08.21 0t RKA 02.08.21

73 1.6.21 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 94 h 03.08.21 13.08.21 9t RKA

74 1.6.22 ST-113 Issue technical docs for procurement/ secondary steel GICON 0h 16.08.21 16.08.21 0t RKA 16.08.21

75 1.6.23 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 122 h 16.08.21 30.08.21 11 t RKA

76 1.6.24 ST-114 CONSTRUCTABILITY STUDY GICON 280 h 20.07.21 30.09.21 53 t PDI

77 1.6.25 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 56 h 03.05.21 27.05.21 17 t JWA

78 1.6.26 ST-115 Issue technical docs for procurement/ pump (ballast & de-ballast), working crane (depending on GICON 0h 28.05.21 28.05.21 0t JWA 28.05.21
interaction of the supplier)

79 1.6.27 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 200 h 28.05.21 20.08.21 61 t JWA

80 1.6.28 ST-115 Issue technical docs for procurement/ pipe head, strand jack, electrical package (E&I,Telecom), GICON 0h 20.08.21 20.08.21 0t JWA 20.08.21
submarine cable, ICCP (depending on interaction of the supplier)

81 1.6.29 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 69 h 23.08.21 20.09.21 21 t JWA

82 1.6.30 ST-115 Issue technical docs for procurement/ miscellaneous, E&I bulk material (depending on interaction of GICON 0h 21.09.21 21.09.21 0t JWA 21.09.21
the supplier)

83 1.6.31 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 95 h 21.09.21 29.10.21 29 t JWA

84 1.6.32 ST-116 STRUCTURAL INTEGRITY, INSPECTION & MAINTENANCE GICON 140 h 01.10.21 30.11.21 43 t PDI

85 1.6.33 ST-117 PROVISION FOR DECOMISSIONING GICON 40 h 17.09.21 30.11.21 53 t JWA

86 1.7 SAFETY (depending on interaction of WE) 540 h 01.04.21 30.11.21 170 t

87 1.7.1 SE-101 OVERALL HAZARD IDENTIFICATION (HAZID) STUDY YARD 140 h 01.04.21 19.10.21 140 t KOE

88 1.7.2 SE-102 INTEGRATED HSE AND FIRE PROTECTION PHILOSOPHY GICON 70 h 03.05.21 10.08.21 70 t GIC-DD

89 1.7.3 SE-103 INTEGRATED ESCAPE ROUTE, FIRE FIGHTING, SAFETY AND LIFE SAVING APPLIANCES, SAFETY SIGN GICON 70 h 04.06.21 09.09.21 70 t GIC-DD
SPECIFICATION, DATAHSEETS AND LAYOUT UPDATE.

90 1.7.4 SE-104 EMERGENCY RESPONSE PLAN (ERP) GICON 70 h 01.04.21 27.07.21 80 t GIC-DD

91 1.7.5 SE-105 NOISE CONTROL STUDY GICON 35 h 28.07.21 21.09.21 40 t MDY (DD)

92 1.7.6 SE-106 AREA NOISE EXPOSURE MONITORING GICON 35 h 22.09.21 16.11.21 40 t MDY (DD)

93 1.7.7 SE-107 ADDENDUM OPERATION HSE CASE YARD 80 h 20.10.21 30.11.21 30 t KOE

94 1.7.8 SE-108 HUMAN FACTORS ENGINEERING (HFE) DESIGN ANALYSIS AND VERIFICATION YARD 40 h 01.04.21 30.11.21 170 t N/A

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress

Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline

Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

page 3 GICON/KOE