Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
1 1 FOWT Pilot - DDE Schedule / Level 2 11,018 h 01.04.21 31.08.22 356 t
2 1.1 GENERAL 3,788 h 01.04.21 31.08.22 356 t
3 1.1.1 GN-100 PROJECT MANAGEMENT, PLANNING, COORDINATION AND REPORTING GICON 1,518 h 01.04.21 31.08.22 356 t FAD
4 1.1.2 GN-101 INTERFACE MANAGEMENT SUPPORT GICON 280 h 01.04.21 31.08.22 356 t FAD
5 1.1.3 GN-102 OPERATION, INSPECTION & MAINTENANCE PHILOSOPHY; AND MANNING LEVEL STUDY (depending on GICON 140 h 01.04.21 15.06.21 50 t PDI
interaction of WE)
6 1.1.4 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS GICON 44 h 01.04.21 27.05.21 37 t DWA
7 1.1.5 GN-103 Issue technical docs for procurement/ CMS (depending on interaction of the supplier) 0h 28.05.21 28.05.21 0t DWA 28.05.21
8 1.1.6 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS 16 h 28.05.21 17.06.21 15 t DWA
9 1.1.7 GN-103 Ready for handover to GN-105 GICON 0h 17.06.21 17.06.21 0t DWA 17.06.21
10 1.1.8 GN-103 REMOTE OPERATION AND MONITORING REQUIREMENTS GICON 60 h 18.06.21 30.08.21 52 t DWA
11 1.1.9 GN-104 DEVELOP/ UPDATE OPERATING PROCEDURE GICON 140 h 28.05.21 05.08.21 50 t PDI
12 1.1.10 GN-105 FACILITES STATUS MONITORING (FSM) GICON 200 h 18.06.21 09.09.21 60 t DWA
13 1.1.11 GN-106 ASSET REGISTER, SAP PM MASTER DATA PREPARATION AND UPLOADING GICON 140 h 01.04.21 30.09.21 127 t DWA
16 1.1.14 GN-109 ENGINEERING COMPUTING AND MAINTENANCE SERVICES GICON 140 h 01.04.21 30.11.21 170 t FAD
17 1.1.15 GN-110 DESIGN BASIS MEMORANDUM (DBM) & BASIS DESIGN VALIDATION AND UPDATE GICON 70 h 01.04.21 31.05.21 39 t KOE
18 1.1.16 GN-111 ELECTRONIC DOCUMENTATION MANAGEMENT SYSTEM (EDMS) GICON 80 h 01.04.21 29.10.21 148 t FAD
19 1.1.17 GN-112 TECHNICAL REQUISITION PACKAGE (TRP) FOR LONG LEAD ITEMS (LLI) AND MAJOR EQUIPMENT GICON 40 h 01.04.21 30.09.21 127 t FAD
20 1.1.18 GN-113 TECHNICAL BID EVALUATION (TBE) FOR LONG LEAD ITEMS (LLI) & MAJOR EQUIPMENT GICON 40 h 20.04.21 30.09.21 116 t FAD
21 1.1.19 GN-114 VENDOR DATA REVIEW AND INCORPORATION (VDR / VDI) GICON 40 h 02.07.21 30.09.21 65 t FAD
22 1.1.20 GN-115 POST AFC SUPPORT – FOLLOW ON ENGINEERING GICON 630 h 01.12.21 31.08.22 186 t FAD
23 1.1.21 GN-116 FINAL DESIGN DOCUMENTATION AND CLOSE OUT REPORT GICON 140 h 06.10.21 31.08.22 226 t FAD
24 1.1.22 GN-117 INSURANCE FOR GICON´s SCOPE OF WORK FOR DDE BY ALLIANZ GICON 0h 01.04.21 01.04.21 0t FAD 01.04.21
25 1.1.23 GN-118 TRAVELING & ACCOMMODATION GICON 0h 01.04.21 01.04.21 0t FAD 01.04.21
28 1.2.1 ME-101 WIND TURBINE DESIGN BASIS ELEON 10 h 01.04.21 01.06.21 40 t FAD
29 1.2.2 ME-102 ANNUAL ENERGY PRODUCTION (AEP) REPORT ELEON 10 h 01.04.21 01.06.21 40 t FAD
32 1.2.5 ME-105 TLP PIPING DESIGN & SPECIFICATION GICON 182 h 01.04.21 17.08.21 95 t JWA
33 1.2.6 ME-105 Issue technical docs for procurement/ piping & fitting (depending on interaction of the supplier) GICON 0h 20.08.21 20.08.21 0t JWA 20.08.21
34 1.2.7 ME-105 TLP PIPING DESIGN & SPECIFICATION GICON 58 h 20.08.21 30.09.21 30 t JWA
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
page 1 GICON/KOE
3 - FOWT_Asia_DDE_schedule_20200525_GICON_Rev07_draft.mpp FOWT Pilot - DDE Schedule / Level 2 24.03.2021
Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
35 1.2.8 ME-106 MATERIAL HANDLING STUDY AND PHILOSOPHY GICON 160 h 01.04.21 30.08.21 104 t FPI
36 1.2.9 ME-107 PDMS 3D MODEL REVIEW GICON 100 h 01.04.21 30.08.21 104 t RKA
37 1.2.10 ME-107 Ready for handover GICON 0h 30.08.21 30.08.21 0t RKA 30.08.21
39 1.3.1 MCI-101 MATERIAL SELECTION AND CORROSION PROTECTION GICON 105 h 01.06.21 23.08.21 60 t KOE
40 1.3.2 MCI-101 CDBM (Corrosion Design Basis Memorandum) GICON 95 h 27.07.21 21.09.21 41 t KOE
41 1.3.3 MCI-101 Issue technical docs for procurement/ painting material (depending on interaction of the supplier) GICON 0h 21.09.21 21.09.21 0t KOE 21.09.21
42 1.3.4 MCI-101 CDBM (Corrosion Design Basis Memorandum) GICON 45 h 22.09.21 18.10.21 19 t KOE
44 1.4.1 EL-101 ELECTRICAL DETAILED ENGINEERING DESIGN (GREENFIELD – WIND TURBINE PACKAGE) ELEON 10 h 01.04.21 30.11.21 170 t FAD
45 1.4.2 EL-102 PETRONAS ELECTRICAL SAFETY AND OPERABILITY REVIEW (P-ELSOR) ELEON 10 h 01.04.21 30.11.21 170 t FAD
47 1.5.1 IN-101 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS JUNCTION BOX LOCATION AND CABLE LAYOUT ELEON 10 h 01.04.21 30.11.21 170 t FAD
48 1.5.2 IN-102 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS DESIGN DRAWINGS ELEON 10 h 01.04.21 30.11.21 170 t FAD
49 1.5.3 IN-103 WIND TURBINE CONTROL PANEL, ELECTRICAL SYSTEMS, FIRE & GAS SYSTEM, CONDITION MONITORING ELEON 10 h 01.04.21 30.11.21 170 t FAD
SYSTEM AND INTEGRATED DISPLAY VIA SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)
SPECIFICATION
50 1.5.4 IN-104 INSTRUMENT/TELECOMMUNICATION/FIRE & GAS EQUIPMENT SPECIFICATIONS AND DATA SHEETS ELEON 10 h 01.04.21 30.11.21 170 t FAD
51 1.5.5 IN-105 TELECOMMUNICATION DESIGN AND ENGINEERING ELEON 10 h 01.04.21 30.11.21 170 t FAD
53 1.6.1 ST-101 STRUCTURAL BASIS OF DESIGN (BOD) GICON 20 h 01.04.21 01.06.21 40 t KOE
54 1.6.2 ST-102 STABILITY ANALYSIS (depending on interaction of WE) GICON 210 h 20.04.21 14.07.21 60 t HHA
55 1.6.3 ST-103 ERECTION, LOAD-OUT, INTEGRATION ANALYSIS AND DETAILED METHODOLOGY (depending on GICON 180 h 20.07.21 07.10.21 58 t PDI
interaction of WE)
56 1.6.4 ST-104 TRANSPORTATION & INSTALLATION ANALYSIS (depending on interaction of WE) GICON 1,680 h 12.05.21 30.09.21 100 t HHA
57 1.6.5 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 5h 01.04.21 12.04.21 6t IFG
58 1.6.6 ST-105 Issue technical docs for procurement (pre-specification only)/ tendon connector (depending on GICON 0h 13.04.21 13.04.21 0t IFG 13.04.21
interaction of the supplier)
59 1.6.7 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 70 h 13.04.21 19.08.21 91 t IFG
60 1.6.8 ST-105 Issue technical docs for procurement/ tendon connector/ mooring line (depending on interaction of the GICON 0h 20.08.21 20.08.21 0t IFG 20.08.21
supplier)
61 1.6.9 ST-105 STATION KEEPING SYSTEM DESIGN (depending on interaction of WE) GICON 5h 20.08.21 30.08.21 7t IFG
62 1.6.10 ST-106 FOUNDATION SYSTEM DESIGN (depending on interaction of WE) GICON 520 h 01.04.21 30.08.21 104 t EHL
63 1.6.11 ST-107 SUBSTRUCTURE DETAILED STRUCTURAL DESIGN & ANALYSIS (depending on interaction of WE) GICON 670 h 03.05.21 30.08.21 84 t IFG
64 1.6.12 ST-108 DYNAMIC/SUBMARINE CABLE DESIGN & ANALYSIS (depending on interaction of WE) GICON 140 h 25.06.21 30.08.21 47 t FAD
65 1.6.13 ST-109 OPERATIONAL & ACCIDENTAL BOAT IMPACT ANALYSIS GICON 200 h 03.05.21 27.07.21 60 t MIK
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
page 2 GICON/KOE
3 - FOWT_Asia_DDE_schedule_20200525_GICON_Rev07_draft.mpp FOWT Pilot - DDE Schedule / Level 2 24.03.2021
Nr. Activity CTR-No. Name Responsible Man-hours Start Finish Duration Internal
ID party Responsb.
at GICON März April Mai Juni Juli August September
Oktober NovemberDezemberJanuar Februar März April Mai Juni Juli August September
Oktober
66 1.6.14 ST-110 WIND TURBINE DETAILED STRUCTURAL DESIGN & ANALYSIS WE 40 h 01.04.21 02.09.21 107 t FAD
68 1.6.16 ST-111 WEIGHT CONTROL & MANAGEMENT GICON 210 h 01.04.21 30.09.21 127 t KOE
69 1.6.17 ST-112 CORROSION / EROSION PROTECTION GICON 105 h 07.05.21 30.08.21 80 t KOE
70 1.6.18 ST-112 Issue technical docs for procurement/ painting material (depending on interaction of the supplier) GICON 0h 21.09.21 21.09.21 0t KOE 21.09.21
71 1.6.19 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 684 h 03.05.21 02.08.21 64 t RKA
72 1.6.20 ST-113 Issue technical docs for procurement/ primary steel GICON 0h 02.08.21 02.08.21 0t RKA 02.08.21
73 1.6.21 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 94 h 03.08.21 13.08.21 9t RKA
74 1.6.22 ST-113 Issue technical docs for procurement/ secondary steel GICON 0h 16.08.21 16.08.21 0t RKA 16.08.21
75 1.6.23 ST-113 AFC DRAWINGS & MATERIAL TAKE OFF GICON 122 h 16.08.21 30.08.21 11 t RKA
77 1.6.25 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 56 h 03.05.21 27.05.21 17 t JWA
78 1.6.26 ST-115 Issue technical docs for procurement/ pump (ballast & de-ballast), working crane (depending on GICON 0h 28.05.21 28.05.21 0t JWA 28.05.21
interaction of the supplier)
79 1.6.27 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 200 h 28.05.21 20.08.21 61 t JWA
80 1.6.28 ST-115 Issue technical docs for procurement/ pipe head, strand jack, electrical package (E&I,Telecom), GICON 0h 20.08.21 20.08.21 0t JWA 20.08.21
submarine cable, ICCP (depending on interaction of the supplier)
81 1.6.29 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 69 h 23.08.21 20.09.21 21 t JWA
82 1.6.30 ST-115 Issue technical docs for procurement/ miscellaneous, E&I bulk material (depending on interaction of GICON 0h 21.09.21 21.09.21 0t JWA 21.09.21
the supplier)
83 1.6.31 ST-115 MISCELLANEOUS DESIGN (depending on interaction of WE) GICON 95 h 21.09.21 29.10.21 29 t JWA
84 1.6.32 ST-116 STRUCTURAL INTEGRITY, INSPECTION & MAINTENANCE GICON 140 h 01.10.21 30.11.21 43 t PDI
87 1.7.1 SE-101 OVERALL HAZARD IDENTIFICATION (HAZID) STUDY YARD 140 h 01.04.21 19.10.21 140 t KOE
88 1.7.2 SE-102 INTEGRATED HSE AND FIRE PROTECTION PHILOSOPHY GICON 70 h 03.05.21 10.08.21 70 t GIC-DD
89 1.7.3 SE-103 INTEGRATED ESCAPE ROUTE, FIRE FIGHTING, SAFETY AND LIFE SAVING APPLIANCES, SAFETY SIGN GICON 70 h 04.06.21 09.09.21 70 t GIC-DD
SPECIFICATION, DATAHSEETS AND LAYOUT UPDATE.
90 1.7.4 SE-104 EMERGENCY RESPONSE PLAN (ERP) GICON 70 h 01.04.21 27.07.21 80 t GIC-DD
91 1.7.5 SE-105 NOISE CONTROL STUDY GICON 35 h 28.07.21 21.09.21 40 t MDY (DD)
92 1.7.6 SE-106 AREA NOISE EXPOSURE MONITORING GICON 35 h 22.09.21 16.11.21 40 t MDY (DD)
93 1.7.7 SE-107 ADDENDUM OPERATION HSE CASE YARD 80 h 20.10.21 30.11.21 30 t KOE
94 1.7.8 SE-108 HUMAN FACTORS ENGINEERING (HFE) DESIGN ANALYSIS AND VERIFICATION YARD 40 h 01.04.21 30.11.21 170 t N/A
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress
page 3 GICON/KOE