You are on page 1of 3

Quality Assurance Plan (QAP)

QAP is the document which shows the sequence of Quality Control system (QCS) including
frequency and numbers of tests based on the detail work program.

QAP generally presented by the contractor against the specification of the Employer/Client during
the signing of the contract. QAP is the basic document to control the quality of works for contractor
which also help the client/consultant for the supervision of the quality.

QAP contains the following


a) Quality Control Schedule
- test schedule
- testing program
- list of tests
- laboratory; site trials & trial sections
- construction control test & its frequencies
- numbers of tests to be carried out & list of equipment to conduct them
- list of “critical” acceptance testing procedures
- list of staff assigned to the laboratory, their position & responsibilities
b) List of sources of materials and/or of manufactured articles

Quality Assurance Plan for the construction materials from Natural resources

Nos. of test to be carried out as per


Specification Name of the Remarks
Material Quantity as Frequency the specification
S.NO reference page tests to be
Description per BOQ of Test Carried
no. or clause no. carried out Required Compliance
Out
Gradation      
LAA From each      
quarry
1 Aggregate Water source one    
Absorption set of tests  
FI    
From each
Sand for quarry
2a Gradation      
Concrete works source one
set of tests
From each
Sand for quarry
2b Gradation      
Masonry works source one
set of tests
Water From each      
Absorption quarry
3 Stone
Specific source one
set of tests      
Gravity
Every 50 m3
4 Filter Material Gradation - 1 set of      
tests
Every 1500
Compaction m3 - 1 set of      
Soil for tests
5
embankment
500 m2 one
Field Density      
nos of tests

Every 3000
Compaction m2 - 1 set of      
Subgrade tests
6
Preparation
500 m2 one
Field Density      
nos of tests

Quality Assurance Plan for the construction materials (Factory Manufactured)

Nos. of test to be carried


Manufacture' out as per the specification
Quantity Name of the
Material s Certificate Frequency of
S.NO Specification as pertests to be Remarks
Description Received & Test Requir Carried
BOQ carried out Compliance
Approved ed Out

  Initial setting 2      
  Final setting For each 200 2    
Compressive tons 1 set of  
1 Cement   614 377186 2    
strength tests on each
  test, 3 days supply 2      
  7 days 2      
upto 25 nos
Mass of zinc
  of coils 2 nos        
coating
sampling,
26 to 50 nos
  Adhesion test * of coils-3 nos        
sampling
51 to 150 nos
Uniformity test
  of coils - 5        
2 Gabions 633 37,867.22 *
nos sampling
151 to 3000
  Tensile trest nos of coils-8        
nos sampling
above 300
nos of coils -
           
13 nos
sampling
2 Geotextile   627 3,383.60            

Tensile strength 1      
3 Steel   620 6.68 Each lot
Elongation 1      

QUALITY ASSURANCE PLAN (QAP) Sample (for a road construction project)


Name of Project: Location
(GPS)
Contract No                  
Total Rem
Management of Tests
no of rks
Specificat
BoQ Quantity Test Test
ion Description Frequency
Item as per Unit Require Requir
Clause of works of test *
No. BoQ d ed as At  
Ref.
per (Site/Lab/
BOQ Equipment Others) By
1
1.Grada i   m3        
tion n  
1
i   m3        
2.LL-PI n  
Embankme 1
      m3
nt Filling 3.MDD i   m3        
& OMC n  
1
4. Field i   m2        
Density n  
5. CBR                
1
i   m2        
1.LL-PI n  
1
2.MDD i   m2    
Sub grade 2 & OMC n  
      m
Preparation 1
3. Field i   m2        
Density n  
1
i   m2        
4. CBR n  
1. 1
Gradati i m3        
on n    
1
i m3        
2.LL- PI n    
Supply and
1
laying of
      m3 3. MDD i m3        
Granular
& OMC n    
Subbase
4. 1
Soaked i m3        
CBR n    
1
5. Field i m2        
density n    

You might also like