Professional Documents
Culture Documents
31 10 00 10-P6000CFP-000-PV - A
31 10 00 10-P6000CFP-000-PV - A
10-P6000CFP-000-PV
Clean Fuels Project 2020 REV. A, 20-Mar.-13
Page 1 of 6
Project Variation
Project Variation to
Project Variation
Record of Revisions
Project Variation
1.0 INTRODUCTION
DEP 31.10.00.10 - Gen, Positive Material Identification (PMI) Program dated September
2011, is adopted for the Clean Fuels Project (CFP) subject to the modification noted in this
project variation. This PV (Project Variation) shall be included, as a requirement, wherever
DEP 31.10.00.10 -Gen is referenced in any other project documents, including all DEPs.
In general, the requirements stated in this PV have precedence over, and supersede those
in the Shell DEPs. Any discrepancy between this PV and other Clean Fuels Project
documents shall be brought to the attention of the Company for review and direction.
Delete “If the function of the overlay is corrosion protection, a volumetric or surface
analysis shall be completeted at a minimum depth of 1.5 mm (0.060 inch) below the
process-contacted surface.”
Replace with “If the function of the overlay is corrosion protection, a volumetric or
surface analysis shall be completed at a minimum depth of 2.5 mm (0.1 inch) below
the process-contacted surface.”
Delete “If the function of the overlay is to assure product purity only, the sample shall
be taken at a minimum depth of 1 mm (0.040) inch”
Replace with “If the function of the overlay is to assure product purity only, the
sample shall be taken at a minimum depth of 1.5 mm (0.060) inch”
Project Variation
Add “To prevent damage to the gasket surface only the X-ray fluorescence method
of PMI may be used.”
2.6 Section 5
First paragraph
Delete “Refer to (4.6) ….”
Replace with “Refer to (4.7) ….”
Third paragraph
Delete “Shell Technical Authority”
Replace with “PMC/Principal”
In addition the requirements listed above the minimum requirements shall apply
A) Piping/Instrument piping
i) Sample PMI shall be carried out for 5% of each heat number for materials
(minimum 3) other than carbon steel during receiving inspection. If quantity is
less than 3, all items shall be PMI tested. PMI during receiving inspection is
applicable for all grades of stainless steels also.
ii) 100 % PMI shall be performed on completed piping systems (including welds),
after field installation of pipe spools but before release for testing as per
SHELL DEP 31.10.00.10-Gen. However for D category fluid service and SS
grade 304 in any service, only 10% PMI is required to be performed.
B) Equipment
i) Sample PMI shall be carried out of each purchase order line item during
receiving inspection at Site. 10% of components/parts of each item/equipment
Project Variation
ii) PMI test shall be performed for 10% of the attachment welds for piping as well
as equipment.
a) 100% PMI of materials & welds other than carbon steel at the material
fabricator / supplier’s works prior to delivery.
b) 100% PMI shall be carried out also for all internal parts other than carbon
steel.
c) 100 PMI check shall be performed for 10% of the attachment welds.
Delete “If the function of the overlay is corrosion protection, a volumetric or surface
analysis shall be completeted at a minimum depth of 1.5 mm (0.060 inch) below the
process-contacted surface.“
Replace with “If the function of the overlay is corrosion protection, a volumetric or
surface analysis shall be completed at a minimum depth of 2.5 mm (0.1 inch) below
the process-contacted surface.”
Project Variation
Delete “If the function of the overlay is to assure product purity only, the sample shall
be taken at a minimum depth of 1 mm (0.040) inch. “
Replace with “If the function of the overlay is to assure product purity only, the
sample shall be taken at a minimum depth of 1.5 mm (0.060) inch”
Delete
0.5 % to 0.75 % max Ni in base material and <1.1 % Ni for weld deposits.
0.1 % to 0.3 % Al.
0.2 % to 0.5 % Ti.
Add