Professional Documents
Culture Documents
% %
S/N Action Items Completion Completion Remarks
Required Achieved
Preparation of below procedures are
currently ongoing:
1. Hydrotest Procedure - Completed
2. Leak Testing Procedure - Completed
3. Chemical Cleaning Procedure -
Completed
4. Lube Oil Flushing Procedure
1 Technical Deliverables 10% 7% 5. Flushing Procedure - Completed
6. Pre-commissioning - Completed
7. Flange Management Procedure -
Completed
8. Drying Procedure - Completed
9. Nitrogen Purging
10. Mobilization Plan - Completed
11. Resource loaded schedule
Documentation Of
4 Equipment/Premobilization 10% 1%
Activities
Consumables/Equipment
5 10% 1%
Identification And Sourcing