Successful EOT Claim – Procedures

Step Input Tools & Techniques Output Notes

- Project baseline
- Project updated documents - Send the delay notice
( RFI – Letters – Material Submittal 1- Discussions with PM to the employer within
High level Event Log
Log – Shop drawing Log – Site 2- Detailed Discussions the period of the
1-Find the vents Detailed Discussions result
Instructions – Inspection requests , with Project Team submitting according to
Delay Notice
… etc. ) your contract
- Project Contract conditions
- Project Specifications

1-Estimate impact
- Project baseline
durations
2-Record Supporting - Delay Notices Update Event Log
2-Estiamte new scope of
Documents - Detailed Discussions result
work durations
- High level Event Log
3-Define relationships
- Send the detailed
impact analysis to the
1-Create Events WBS Revised impacted schedule
employer within the
- Project baseline 2-Create Events Activities Updated Event Log
3-Analyse Delays period of the
- Updated Event Log 3-use As Planned – EOT for Each Event
submitting according to
Impacted Techniques Total EOT
your contract
conditions
Create Narrative report for Narrative report for each
Revised impacted schedule
4-Build the case each Event event
Updated Event Log
Revised impacted schedule

www.planningenginner.net