You are on page 1of 4

Renewable and Sustainable Energy Reviews 81 (2018) 756–759

Contents lists available at ScienceDirect

Renewable and Sustainable Energy Reviews


journal homepage: www.elsevier.com/locate/rser

Project scheduling for constructing biogas plant using critical path method MARK
Samira Zareei
Department of Biosystems Engineering, University of Kurdistan, Sanandaj, Iran

A R T I C L E I N F O A BS T RAC T

Keywords: Population growth and technological progress have led to increased energy demand. While fossil fuels are
Biogas plant currently the main energy resources, they are limited and their combustion causes environmental pollution.
Construction Therefore, alternative energy sources should be considered. For this purpose, biogas can be a convenient
Critical path method renewable energy option, which can be produced from organic wastes, e.g. livestock manure and rural wastes
Project management
which are widely available and accessible. Furthermore, it is considered as a convenient option for rural areas
Scheduling
that do not have access to any gas networks. However, managing a large-scale biogas plant construction project
demands many coordinated activities with varying durations and involves numerous dependencies. Therefore,
this study focuses on application of planning and scheduling for analysis of biogas plant construction project
using critical path method (CPM). The results revealed that the minimum completion time of constructing a
50 m3 biogas plant with fixed dome in Iran would be 38 weeks if no delays postpone the project steps. Also, a
project network is proposed to show the relationships between the activities and monitor the progress of the
project.

1. Introduction emission. Biogas technology, therefore, benefits societies by alleviating


problems with rural wastes and livestock manure, and generating a
Fossil fuel resources are severely limited and their combustion is a renewable energy source [5].
major source of environmental pollution [1]. Therefore, managers in Regardless of the type energy resource, an effective management is
the field of energy are seeking alternatives to fossil fuels and have crucial. Managing a large-scale project needs to coordinate many
considered biogas as a viable alternative source of energy [2]. activities with variable duration and multiple dependencies. In other
Anaerobic digestion is one of the ways of converting biomass to biogas words, scheduling issue is a frequent task in the control of various
[3,4]. Every year, large amounts of livestock manure discharges and systems such as construction processes and careful planning, before
rural waste materials are produced worldwide, which can generate the start of the project, is very important. Specifically, when the energy
environmental pollution. Also, on one side, the human population is to source is biogas, its plant establishment is an expensive and time-
face fossil energy depletion soon [5] while, on the other side, biomass is consuming project. So that the importance of project management, in
abundant and the operation of biogas systems is quite simple. So, it is this case, is obvious [7,8].
intelligent to use animal wastes in order to produce biogas and hence Many different techniques and tools, e.g. Guntt chart, Critical Path
reduce pollution. Method (CPM) and Program Evaluation and Review Technique
In this way, generation of biogas from such residual streams can (PERT), have been developed to support an improved project planning.
add value to them and create noticeable opportunities for development These tools are used seriously by a large majority of project managers
of agricultural and forestry sectors of rural areas. Therefore, biogas to identify critical activities and calculate the minimum time required
production plants in rural areas can gain profits even if they be not for project completion [9–11]. Among these methods, most traditional
supported by any external sector. Furthermore, the plants can get more scheduling techniques employ Gantt chart. Although this method is
credits through treating waste, reducing emissions and producing still a valuable tool, its application is limited for scheduling large-scale
fertilizers [6]. Another factor that can affect the economy of biomass operations. In particular, the bar chart fails to delineate the complex
plant establishment is the kind of biomass or feedstock that is going to interactions and precedence relationships existing among the project
be used for biogas production and its availability. For example, in rural activities. Network-based procedures of PERT and CPM are well known
areas, agricultural residues, manure and crops are more abundant. It is and widely used to assist managers in planning and controlling both
noteworthy that, in the case of using manure, the plant can impact the large and small projects of all types including construction, research,
environment positively since it can treat manure and reduce methane development projects and many others [12–14]. Also, network models

E-mail address: s.zareei@uok.ac.ir.

http://dx.doi.org/10.1016/j.rser.2017.08.025
Received 4 May 2016; Received in revised form 26 May 2017; Accepted 10 August 2017
1364-0321/ © 2017 Elsevier Ltd. All rights reserved.
S. Zareei Renewable and Sustainable Energy Reviews 81 (2018) 756–759

have been used as planning and project controlling techniques in they must all be completed before the activity initiation. Also, the
agricultural projects [15–17]. CPM uses a network to coordinate project network is proposed to illustrate the connections between the
activities, develop schedules and monitor progress of the projects activities and monitor the project progress.
[18,19]. In fact, it is a step-by-step project management technique
that identifies activities on the critical path. It is an approach to project 2.1. Critical path method calculations
scheduling that breaks the project into several work tasks, displays
them in a flow chart and then calculates the project duration based on In order to determine the critical path, five parameters are
estimated durations for each task. It defines tasks that are critical, considered for each activity including the earliest start and finish
time-wise, in completing the project. times, the latest start and finish times, and slack time. For a list of
CPM has been used extensively to calculate operation parameters activities required to complete a project with duration of each activity
including earliest starting time, latest starting time, earliest finish time, and dependency of activities on each other, critical path scheduling for
latest finish time, maximum available time and slack time [20,21]. an activity-on-node network can be formulated, mathematically. Node
However, schedule delays may occur in many of these construction display method for critical path calculation of activity-on-node is
projects and effective project management techniques become impor- presented in Fig. 2.
tant to ensure successful project performance. So that, a poor strategy ES(i) is defined as the earliest start time for activity i, EF(i) is the
can shift all profits towards economic loss [22]. Management of earliest finish time for activity i, LS(i) is the latest start and LF(i) is the
construction projects involves planning tasks from a large number of latest finish time for activity i. The relevant calculations for the node
disciplines, which requires different pieces of information at various numbering algorithm, the forward pass (runs from the first to the last
times. Therefore, a noticeable body of complicated information would node in the network) and the backward pass (runs from the end node
be produced that should be efficiently managed. A management back to the first node in the network) are presented as follows:
solution is application of network analysis which has significant
influence on planning and controlling large projects in many fields, Step 1: the starting activity will be numbered as 0.
such as construction. The project duration will be no longer than the Step 2: the next number will be assigned to any unnumbered activity
longest path through the network. As a consequence, the total time whose predecessor activities are already numbered. Step 2 will be
elapsed for project completion is equivalent to the length of the critical repeated until all activities are numbered.
path, i.e. the longest path through the network. Also, the corresponding
activities are called the critical activities. Any delay in the critical 2.1.1. Forward pass calculation
activities retards the project completion overall time and the project The earliest start and earliest finish times for each activity within
should be managed to avoid delays in any of these activities. the network are computed by forward pass. During the calculations,
In this regard, this study attempts to apply project scheduling for constraints on finish times are concerned through recognizing the
establishing biogas plant with fixed dome in large size (50 m3), by minimum finish time and then subtracting the activity duration (Dj).
critical path method by employing WinQsb software. Moreover, a default earliest start time of day 0 is also insured for all
activities. In the next step, the earliest finish time of each activity is
2. Materials and methods specified.

The study was carried out in Iran, in 2015. Statistics and informa- Step 1: E(0) = 0.
tion about the region circumstances, soil properties and quantity of Step 2: For j = 1,2,3, …, n (where n is the last activity), ES(j) =
input substrate were collected through direct observation, discussion maximum {EF(i)}
with farmers and experts and also using the statistical data of Ministry Step 3: EF(j) = ES(j) + Dj
of Agriculture [23] and Statistical Center of Iran [24].
Planning of biogas plants is basically not easy since considerable 2.1.2. Backward pass calculation
data is required before the engineering design and activities can be Calculations of the backward pass follow a procedure similar to the
started. At first, the project has to be broken into several work tasks forward pass but they focus on the latest finish and start times instead
that consist of primary studies (type of input substrate [25–27], of the earliest times. During the backward pass computation of the
weather condition, local circumstances, soil properties and quantity latest finish time, the latest start time is defined to be consistent with
of input substrate), coordination and negotiation with farmers, selec- the precedence constraints on the activities’ start times. Therefore, the
tion of site and layout of the plant, marketing and financial support, computations involve minimizations over all activities (j) that have (i)
purchase of construction materials and tools, labor hire, ground as their predecessor. Also, at this point, feasibility of the activity
excavation, construction of biogas digester, construction of inlet pit, schedule can be checked and imposed. The rule is that the activity
construction of outlet chamber, construction of gas pipeline, loading schedule is not possible if the late start time is less than the early start
raw materials and biogas production, technical review and reloading time.
with improved variables, farmer training and documentation. For
example, about site selection, the chosen area should be adequate to Step 1: Let L(n) equal to the required completion time of the project.
accommodate all units of the plant; the location of the plant must be at Note: L(n) must equal to/exceed E(n).
least 20 m away from the water sources such as wells, springs, tube Step 2: For i = n-1, n-2, …, 0, LF(i) = minimum {LS(j)}
wells etc. to avoid possible contamination of water sources; and edge of Step 3: LS(i) = LF(i) - Di
the plant foundation should be at least two meters away from houses or
any other building to avoid the risk of any damage being made to them. 2.1.3. Slack time calculation
Fig. 1 shows the layout of the biogas plant with fixed dome. The forward and backward pass calculations on each activity give
Depending on the input substrate and procedure, which is applied several activity time values which include the earliest start time, the
to construction of the biogas plant, the duration of each activity is latest start time, the earliest finish time and the latest finish time,
determined. Then, the estimated duration for each activity is used to directly. In addition, their calculations indirectly result in the activity
calculate the project duration. In the next step, immediate predecessors slack time, i.e. the difference between the earliest and latest time of the
have to be defined for each activity. Immediate predecessor of activity y activity. In fact, slack time is the maximum time interval that the
is activity x that must be completed no later than the starting time of activity can be delayed without retarding project completion [28,29].
activity y. When an activity has more than one immediate predecessor, Slack times are calculated as:

757
S. Zareei Renewable and Sustainable Energy Reviews 81 (2018) 756–759

Fig. 1. Layout of the biogas plant with fixed dome.

3. Results and discussion

Project scheduling is a key factor in successful project management.


If the information be presented in an effective manner, it can aid the
manager in understanding the activities’ multitude and the relation-
ships between the activities. Furthermore, many individuals and
parties are meddled in each project, which need to fully understand
Fig. 2. Node display method for critical path calculation of activity-on-node. their tasks and assignments. In this respect, graphical representation of
the schedules can make it much easier to comprehend the great deal of
S = LS − ES = LF –EF information instead of going through a large set of numerical tables.
This goal can be achieved through employing networks. In network
In the slack time calculations, the non-critical activity is considered
models, based on the critical path duration, the minimum time needed
to be associated with slack time [30,31].
for project completion can be identified. If there is more than one
critical path among the project activities, then project completion can
be delayed upon delay in any activity on any critical path. The results of

Table 1
List of activities for project scheduling of biogas plant construction and computational results using CPM.

Activity description Activity code Immediate Activity time Normal time Slack
predecessor
Earliest start Earliest Latest start Latest
finish finish

Primary studies A – 4 0 4 0 4 0
Coordination and negotiations with farmers B A 2 4 6 5 7 1
Site selection and layout of plant C A 3 4 7 4 7 0
Marketing and financial support D B, C 3 7 10 7 10 0
Purchase of construction materials and tools E D 2 10 12 10 12 0
Labor hire F D 2 10 12 10 12 0
Ground excavation G E, F 3 12 15 12 15 0
Construction of biogas digester H G 4 15 19 15 19 0
Construction of inlet pit I G 2 15 17 17 19 2
Construction of outlet chamber J G 3 15 18 16 19 1
Construction of gas pipe line K H, I, J 2 19 21 19 21 0
Loading raw materials and biogas production L K 6 21 27 21 27 0
Technical review and Reloading with M L 7 27 34 27 34 0
improved variables
Farmer training N M 2 34 36 34 36 0
Documentation and sign off O N, O 2 36 38 36 38 0
Number of critical path (s) 4
Critical path # 1 A-C-D-E-G-H-K-L-M-N-O
Critical path # 2 A-C-D-E-G-H-K-L-M-O
Critical path # 3 A-C-D-F-G-H-K-L-M-N-O
Critical path # 4 A-C-D-F-G-H-K-L-M-O

758
S. Zareei Renewable and Sustainable Energy Reviews 81 (2018) 756–759

Fig. 3. Biogas plant construction project CPM network model.

the computation performed by WinQsb software on the basis of Normal [3] Budzianowski WM. Sustainable biogas energy in Poland: prospects and challenges.
Renew Sustain Energy Rev 2012;16:342–9.
time have been shown in Table 1. [4] Zhang Q, Hu J, Lee DJ. Biogas from anaerobic digestion processes: research
Using the project information from the Table 1, biogas plant updates. Renew Energy 2016;98:108–19.
construction project through CPM network has been drawn in the [5] Maghanaki MM, Ghobadian B, Najafi G, Galogah RJ. Potential of biogas production
in Iran. Renew Sustain Energy Rev 2013;28(0):702–14.
form of an activity-on-node network (Fig. 3). Critical activities dis- [6] Alvarez R, Liden G. Semi-continuous co-digestion of solid slaughterhouse waste,
played with stars, in the network (Fig. 3). Graphical network repre- manure, and fruit and vegetable waste. Renew Energy 2008;33(4):726–34.
sentations rather than a list of activities are helpful for visualization of [7] Bajgain S, Shakya I, Mendis MS. The Nepal biogas support program: a successful
model of public-private partnership for rural household energy supply. Report
the plan and ensuring that mathematical requirements are met. prepared by Biogas Support Program Nepal. Kathmandu, Nepal: Vision Press P.
The results of activity analysis for the project (Table 1) implies that Ltd.; 2005.
there are 4 critical paths and activities A, C, D, E, F, G, H, K, L, M, N [8] Anonymous. Biogas plant construction manual; fixed-dome digester: 4 to 20 cubic
meters. United States Forces – Afghanistan, Joint Engineer Directorate Kabul,
and O are critical. It means that delays in their commencement will
Afghanistan; 2011.
delay the overall project completion time. The total time to complete [9] Yang JB. How the critical chain scheduling method is working for construction.
the project should be 38 weeks if no delays occur. Cost Eng 2007;49(4):25–32.
By comparing the results of the current study with the other studies [10] Fahimifard SM, Kehkha AA. Application of project scheduling in agriculture (case
study: grape garden stabilization). Am- Eurasia J Agric Environ Sci
conducted on similar topics, it can be concluded that scheduling the 2009;5(3):313–21.
case biogas plant construction is a different scenario from those [11] Pollack JB. Project management software usage patterns and suggested research
presented in the literature despite being similar in many aspects directions for future development. Proj Manag J 1998;29:19–29.
[12] Foulds LR, Wilson JM. Scheduling operations for the harvesting of renewable
[7,8]. The differences are caused by factors such as uncertainty of the resources. J Food Eng 2005;70:281–92.
expected duration of each activity. Finally, it should be noted that [13] Awani AO. Project management techniques. Petrocelli Books; 1983. p. 208.
complexity of such projects increases when dependencies of the [14] Hillier FS, Lieberman GJ. Chapter 22: project management with PERT/CPM.
Introduction to operations research. 8th Ed. McGraw-Hill, Boston, MA; 2005.
activities are also considered. [15] Monjezi N, Sheikhdavoodi MJ, Basirzadeh H, Zakidizaji H. Analysis and evaluation
of mechanized greenhouse construction project using CPM methods. Res Appl Sci
3.1. Conclusions Eng Technol 2012;4(18):3267–73.
[16] Chizari AH, Amirnejad H. Management of corn drying factory construction project
using CPM and PERT methods. Agric Econ Dev 1998;29:257–73.
Schedule planning and control are major tasks in construction [17] Abdi R, Ghasemzadeh HR, Abdollahpour S, Sabzeparvar M, Dabbag Mohammadi ,
project management. Moreover, effective project management techni- Nasab A. Modeling and analysis of mechanization projects of wheat production by
GERT networks. Agric Sci China 2010;9(7):1078–83.
ques are important to ensure successful project performance. In this
[18] Duncan WRA. Guide to the project management body of knowledge. Project
regard, the current study applies project scheduling for analysis and management institute standard committee, Pennsylvania USA; 2000. 216 pages.
evaluation of constructing biogas plant with a fixed dome, in Iran, [19] Fox TL, Spence JW. Tools of the trade: a survey of project management tools. Proj
using CPM method with WinQsb software. The critical paths and Manag J 1998;29:20–8.
[20] Smith P. Agricultural project management: monitoring and control of implemen-
activities were defined. The project schedule consisted of minimum tation. Elsevier Applied Science Publisher; 1984. p. 190.
project completion time, earliest and latest start times, earliest and [21] Zargar M. Project control. Parham, Tehran, Iran; 2004. 262 pages.
latest finish times, slack time and critical activities. Computation of [22] Abdallah H, Emara HM, Dorrah HT, Bahgat A. Using ant colony optimization
algorithm for solving project management problems. Expert Syst Appl
these parameters was carried out through activity analysis according to 2009;36:10004–15.
normal time. Results revealed that there were 4 critical paths and A, C, [23] Latifeh N. Research and application of dairy waste into higher value-added
D, E, F, G, H, K, L, M, N and O activities were critical. So that delays in products (dairy products). Iran: Ministry of Agriculture; 2008.
[24] General census report of the agricultural section in Iran. Statistical Centre of Iran
their commencement would delay the overall project completion time. 2014. Available from: 〈http://www.amar.org.ir〉.
The total time to complete the project was calculated to be 38 weeks if [25] Avcioglu AO, Türker U. Status and potential of biogas energy from animal wastes in
no delays happen. The application of CPM can improve the schedules Turkey. Renew Sustain Energy Rev 2012;16(3):1557–61.
[26] Igoni AH, Ayotamuno MJ, Aze CL, Ogaji SOT, Probert SD. Designs of anaerobic
that were used previously. Furthermore, the computational times used
digesters for producing biogas from municipal solid-waste. Appl Energ
in solving general instances of the practical projects are encouraging. 2008;85:430–8.
[27] Yadvika Santosh, Sreekrishnan TR, Kohli S, Rana V. Enhancement of biogas
production from solid substrates using different techniques- A review. Bioresour
References
Technol 2004;95:1–10.
[28] Hajshirmohammadi A. Project management and control: application of CPM,
[1] Afazeli H, Jafari A, Rafiee S, Nosrati M. An investigation of biogas production PERT, PN and GERT methods. Isfahan: Academic Publishing; 2009. p. 500.
potential from livestock and slaughterhouse wastes. Renew Sustain Energy Rev [29] Sabzehparvar M. Project control. Tarmeh Press; 2012. p. 704.
2014;34:380–6. [30] Algarra PN, Argilaga MTA. Time management in the cost evaluation of limited
[2] Noorollahi Y, Kheirrouz M, Farabi-Asl H, Yousefi H, Hajinezhad A. Biogas resource programs. Qual Quant 2005;39:391–411.
production potential from livestock manure in Iran. Renew Sustain Energy Rev [31] Lu M, AbouRizk SM. Simplified CPM/PERT simulation model. J Constr Eng Manag
2015;50:748–54. 2000;126(3):219–26.

759

You might also like