Activity ID Activity Name Budgeted Total Cost Mar 2016 Apr 2016 May 2016 Jun 2016 Jul 2016 Aug 2016 Sep 2016 Oct 2016 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 Jun 2017 Jul 2017 Aug 2017 Period Total Total
01-03-2016 - 31-08-2017
Activity ID Activity Name Budgeted Total Cost Mar 2016 Apr 2016 May 2016 Jun 2016 Jul 2016 Aug 2016 Sep 2016 Oct 2016 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 Jun 2017 Jul 2017 Aug 2017 Period Total Total
01-03-2016 - 31-08-2017
p5 Project Management and Other $292,287.30 $328,588.50 $341,732.04 $341,732.04 $341,732.04 $354,875.58 $328,588.50 $354,875.58 $341,732.04 $341,732.04 $354,875.58 $315,444.96 $341,732.04 $341,732.04 $341,732.04 $328,588.50 $354,875.58 $13,143.54 $5,760,000.00 $5,760,000.00
indirect Cost
p50 Backfilling & Disposal in Pipe Line $123,238.50 $123,238.50 $123,238.50
area
p51 Laying Pipe Line, Joining, $1,097,700.45 $232,845.55 $1,330,546.00 $1,330,546.00
Welding as per Specification
p52 Provision of Plant for Pump $700,000.00 $700,000.00 $700,000.00
Installation
p53 Inspection Field Testin g, & $159,600.00 $159,600.00 $159,600.00
approval 1400 m
p54 Excavation, leveling & $141,551.20 $89,238.80 $230,790.00 $230,790.00
Compaction
p55 Lean Concrete Placement below $785.40 $785.40 $785.40
Trust Blocky
p56 Concrete Placement for Trust $7,818.19 $7,818.19 $7,818.19
Block Support
p57 Painting for Pipe Line Support $646,212.00 $646,212.00 $646,212.00
p58 Backfilling & Disposal in Pipe Line $39,847.11 $83,391.38 $123,238.50 $123,238.50
area
p59 Laying Pipe Line, Joining, $99,790.95 $1,230,755.05 $1,330,546.00 $1,330,546.00
Welding as per Specification
p6 Excavation, leveling & $230,790.00 $230,790.00 $230,790.00
Compaction
p60 Provision of Plant for Pump $689,500.00 $10,500.00 $700,000.00 $700,000.00
Installation
p61 Inspection Field Testin g, & $159,600.00 $159,600.00 $159,600.00
approval 1400 m
p62 Excavation, leveling & $230,790.00 $230,790.00 $230,790.00
Compactionn
p63 Lean Concrete Placement below $785.40 $785.40 $785.40
Trust Block
p64 Concrete Placement for Trust $1,174.48 $6,655.40 $7,829.88 $7,829.88
Block Support
p65 Painting for Pipe Line Support $646,212.00 $646,212.00 $646,212.00
p66 Backfilling & Disposal in Pipe Line $123,238.50 $123,238.50 $123,238.50
area
p67 Laying Pipe Line, Joining, $987,930.41 $342,615.59 $1,330,546.00 $1,330,546.00
Welding as per Specification
p68 Provision of Plant for Pump $700,000.00 $700,000.00 $700,000.00
Installation
p69 Inspection Field Testin g, & $159,600.00 $159,600.00 $159,600.00
approval 1400 m
p7 Lean Concrete Placement below $785.40 $785.40 $785.40
Trust Block
p70 Excavation, leveling & $100,009.00 $130,781.00 $230,790.00 $230,790.00
Compactionn
p71 Lean Concrete Placement below $785.40 $785.40 $785.40
Trust Block
p72 Concrete Placement for Trust $7,830.24 $7,830.24 $7,830.24
Block Support
p73 Painting for Pipe Line Support $626,825.64 $19,386.36 $646,212.00 $646,212.00
p74 Backfilling & Disposal in Pipe Line $9,037.49 $114,201.01 $123,238.50 $123,238.50
area
p75 Laying Pipe Line, Joining, $1,330,546.00 $1,330,546.00 $1,330,546.00
Welding as per Specification
p76 Provision of Plant for Pump $427,000.00 $273,000.00 $700,000.00 $700,000.00
Installation
p77 Inspection Field Testin g, & $159,600.00 $159,600.00 $159,600.00
approval 1400 m
p78 Excavation, leveling & $230,790.00 $230,790.00 $230,790.00
Compactionn
p79 Lean Concrete Placement below $761.84 $23.56 $785.40 $785.40
Trust Block
p8 Concrete Placement for Trust $7,830.24 $7,830.24 $7,830.24
Block Support
p80 Concrete Placement for Trust $7,830.24 $7,830.24 $7,830.24
Block Support
p81 Painting for Pipe Line Support $646,212.00 $646,212.00 $646,212.00
p82 Backfilling & Disposal in Pipe Line $118,719.76 $4,518.74 $123,238.50 $123,238.50
area
p83 Laying Pipe Line, Joining, $738,453.03 $592,092.97 $1,330,546.00 $1,330,546.00
Welding as per Specification
p84 Provision of Plant for Pump $700,000.00 $700,000.00 $700,000.00
Installation
p85 Inspection Field Testin g, & $159,600.00 $159,600.00 $159,600.00
approval 1400 m
p86 Excavation, leveling & $578,623.50 $57,226.50 $635,850.00 $635,850.00
Compactionn
p87 Lean Concrete Placement below $571.38 $1,784.82 $2,356.20 $2,356.20
Trust Block
p88 Concrete Placement for Trust $38,835.10 $38,835.10 $38,835.10
Block Support
p89 Painting for Pipe Line Support $415,422.00 $415,422.00 $415,422.00
Activity ID Activity Name Budgeted Total Cost Mar 2016 Apr 2016 May 2016 Jun 2016 Jul 2016 Aug 2016 Sep 2016 Oct 2016 Nov 2016 Dec 2016 Jan 2017 Feb 2017 Mar 2017 Apr 2017 May 2017 Jun 2017 Jul 2017 Aug 2017 Period Total Total
01-03-2016 - 31-08-2017
Total $971,585.80 $3,499,270.44 $5,974,371.59 $4,729,925.62 $6,273,558.00 $6,399,240.25 $7,698,300.12 $11,178,318.37 $2,104,909.61 $808,370.51 $360,901.22 $315,444.96 $341,732.04 $341,732.04 $341,732.04 $328,588.50 $498,875.58 $13,143.54 $52,180,000.24 $52,180,000.24