Commissioning consists of a series of tests and activities that validate the
construction and prepare a plant for operation.
This is generally considered in two phases:
Phase Activity Milestone
Pre-commissioning Conformity Checks Ready for Commissioning
Static Tests Mechanical Completion
Hydrotests
Flushing & Cleaning
Commissioning Energisation Ready for Start-up
Dynamic Tests
Equipment Running-In
Utilities Start-Up
Pre-Start-Up Activities
Operational Tests