Project No.

: PIT-H114-15 January 08, 2021

CONTRACT DC-01: PART DESIGN AND CONSTRUCTION OF ELEVATED VIADUCT,


ELEVATED RAMP, SIDING LINE AND TEN ELEVATED STATIONS VIZ. KESHOPUR, PADCHIM
VIHAR, PEERAGARHI, MANGOLPURI, WEST ENCLAVE, PUSHPANJALI, DEEPALI CHOWK,
MADHUBAN CHOWK, PRASHANT VIHAR & NORTH PITAMPURA FROM CHAINAGE 2831.235
MT. TO 15026.166 MT. OF JANAKPURI WEST TO R.K. ASHRAM CORRIDOR (EXTN. OF LINE-
8) OF PHASE IV OF DELHI MRTS

REPORT FOR PILE INTEGRITY TESTING ON 05 NOS. R.C. BORED PILES

1.0 INTRODUCTION

M/s. Geo Dynamics was engaged by M/s. Zed Geotech Pvt. Ltd. to conduct pile integrity testing
(PIT) on r.c. bored piles installed at the above site. The aim of testing was to assess the pile
integrity for potential problems like cross-sectional changes, honeycombing, concrete quality,
continuity etc. The field tests were conducted on 7th January, 2020. The testing was conducted by
Mr. Amit Kumar. The tests were conducted in accordance with ASTM D5882.

This report presents the results of pile integrity testing using the Pile Integrity Tester, PIT, based on
the details available and the site conditions at the time of testing. The report is on the basis of pile
locations and field information provided by you.

2.0 PILE DETAILS

Pile Integrity Testing was conducted on r.c. bored piles with diameter 1200mm. However, diameter
of the pile is not expected to affect the results. Following table summarizes the Individual pile no.
and depths are mentioned in Appendix B of the report inside the graphs.

Pile Details

Type of Pile R.C. Bored

Method of Piling Hydraulic Rig

Liner Depth from test level (m) Unlined

Pile Diameter 1200mm

Pile depths from test level 28.0 m

Concrete Grade M 35

Period of Casting Not available

Soil Data Availability Not available

Note: 1) This test report or part of the same shall not be reproduced without written permission from the GEO DYNAMICS ULR - TC752121000000190F
2) The results are related to the test performed at location shown by client
Doc. No.: F/7.8/01F/Issue No.02/Issue Date: 16-03-2020/ Amend No.:00 / Amend Date: - / Page 3 of 10 CONTROLLED copy