Provide schematic flow diagrams showing rate of wastewater generation including the flow
rate (m3/day) and significant quality parameters concentration from each process unit or
source.
2. DISCHARGE COORDINATES
North : East :
[ ] Yes [ ] No
b) If yes, please provide Best Available Technology (BAT) analysis for the
wastewater pre-treatment (for new and modified facilities only)
ii. Design details of all the effluent handling units with associated PFD's (include
data on design loading rates and design pollutant removal efficiencies)
iii. Treatment chemicals (if any) and the quantity to be used (Insert more rows of
there is a need)
iv. Will the pre-treatment of the wastewater lead to any point source air emissions
[ ] Yes [ ] No
Please confirm that air emissions are included in Form PA-A6 “Fugitive
Emissions”
[ ] Yes [ ] No
Complete the following table providing information on the composition of the wastewater
effluent during normal operations. Where a pre-treatment system is used, include the
influent composition to the pre-treatment system.
W4-2
Facility: ______ Initials: ______
528774545.doc
d) Complete the following table providing information on the composition of the wastewater
effluent during upset conditions/ turnarounds. Where a pre -treatment system is used,
include the influent composition to the pre-treatment system:
W4-3
Facility: ______ Initials: ______
528774545.doc
7. HOLDING POND
a) Provide information on the holding pond that will retain 72 hours of industrial
wastewater
i. Construction/design basis
ii. Dimensions
iii. Inlet and outlet structures
iv. Liner characteristics
v. Oil/water or solids separation devices
b. Siteplan indicating the proposed location of the outfall to the Red Sea
c. Provide location of sampling points, flow meter, flow totalizer, auto-sampling system and
any continuous monitoring analyzers
d. Provide details of the cabin to be built outside facility boundary for housing the auto-
sampling system
Drawing No. _________________
e. Provide details of any continuous monitoring analyzers used for effluent monitoring
Parameter Frequency
Please provide details of the sludge generated from the system (Insert more rows if
necessary.
W4-5
Facility: ______ Initials: ______
528774545.doc
W4-6
Facility: ______ Initials: ______