SCHEDULE OF PRICE

(To be filled in by Tenderer)

INSTALLATION & COMMISSIONING OF 11 KV CABLES – 400 Kms

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

1. MAKING TRIAL TRENCHES * 3,000 80AED+66AED+46AE


** Make necessary Trial Trenches required for Cu.m D+60AED+60AED+60
following purposes: Drilling purposes, AED+60AED+60AED
locating spare ducts across roads, proposing (Item 1 to 2.8)
route revision requirements, corridor
checking, cable identification, 132 kV NOC
purposes, shutdown and intermediate Joint
Pit, if any, as directed by DEWA engineer and
submit the necessary sketches in the required
format, with photographs.
2

Excavate cable trench along the road or


across the road. Excavation may consists of
all types of soils including breaking of
2.1 existing concrete & old foundations. 20 Km

2.2 Trench Area Less Than (Width X Depth) = 0.40


Sq.m 170 km

B/w 0.41 mtr width & 1.0 mtr depth & 0.5
2.3 metre minimum width & 1.2 m. deep- 1 or 2
cables. (Area - 0.41 Sq.m to 0.6 Sq.m) 4 Km

B/w 0.61 mtr width & 1.0 mtr depth & 0.75
2.4 metre minimum width & 1.2 m. deep- 3 cables. 4 Km
(Area - 0.61 Sq.m to 0.90 Sq.m)

B/w 0.91 mtr width & 1.0 mtr depth & 0.9
metre minimum width & 1.3 m. deep – 4 cables.
(Area - 0.91 Sq.m to 1.17 Sq.m)

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

2.5 B/w 1.18 mtr width & 1.0 mtr depth & 1.1
metre minimum width & 1.3 m. deep – 5 cables.
4 Km
(Area – 1.18 Sq.m to 1.43 Sq.m)

2.6 B/w 1.44 mtr width & 1.0 mtr depth & 2.0
metre minimum width & 1.5 m. deep – 10 cables. 4 Km
(Area – 1.44 Sq.m to 3.00 Sq.m)
2.7 B/w 3.10 mtr width & 1.0 mtr depth & 3.0 metre
minimum width & 1.5 m. deep
4 Km
(Area – 3.10 Sq.m to 4.50 Sq.m)

2.8 Trench Area Greater Than (Width X Depth)= 4 Km


4.51 Sq.m

Note: * - Trial Trenches made to locate the existing services will be payable, if they are backfilled with necessary compaction as per DEWA / DM / RTA
standards, soon after identification, as per the instructions of DEWA. The rate quoted is inclusive of the cost for backfilling. However, charges for
reinstatement of disturbed tiled/ asphalt areas shall be paid under the applicable item in the schedule of prices.
** For payment of jointing pits ref: pages TSPEC-3 & 11, item-3.1 & 5.
Trial pit for drilling purpose is not payable if drilling is done. It is already included in item 17.1.
ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

Collect and transport cable drums from DEWA


compound or from any place in Dubai as
instructed by DEWA engineer and lay in trench Check How many cable
3.#
on 10 cm bed of fine sand completely clear of drums and how much
stones or other sharp materials or lay through trailer shifts then
ducts the following: 11 kV, 240 / 300 sq.mm., calculate
3 Core, XLPE Aluminium/Copper Conductor Cable
(Cable to be supplied by DEWA):

3.1 Single cable (1 x 116) -------------- 116 Km

3.2 Two cables (2 x 50)=------------------ 50 Km

3.3 Three cables ( 3 x 4 )-------------------- 4 Km

3.4 Four cables ( 4 x 4 )------------------- 4 Km

3.5 Five cables (5 x 4)----------------- 4 Km

3.6 Six to Ten cables (6 x 4)-------------- 4 Km

3.7 Eleven to Fifteen cables (11 x 4)----- 4 Km

3.8 Sixteen to Twenty cables (16 x 4)----- 4 Km

Cable Laying in Tray/Riser at inside -----


3.9 4 Km
building/tower, up to substation/RMU room

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

3.10** FIBER OPTIC DUCT:
Collect & Transport FO duct drum from dewa
store and lay in already excavated trench or
lay through duct along with 11kV power cable
including the jointing of duct via straight
connector and End caps, if required. Fiber 60 Km
optical flexible duct, HDPE, 45mm outer
diameter, 4 way micro ducts (4X20mm).

Duct Integrity Check for the Section /ducts


installed (End to End) between Substations to
substation OR Substation to Duct end in
trench, which ever applicable at site for FO
Cable (item 3.11 to item 3.13) below

60 Nos.
3.11 Air Blow test
60 Nos.
3.12 Sponge test
60 Nos.
3.13 Mandrill test

# - Cables to be supplied by DEWA. Rate quoted for cable installation should include pulling of cables up to the designated panels installed in any
floor of a substation, wherever applicable.

The contractor has to provide the required shoring arrangements for deep excavations with necessary supporting arrangements for the existing utilities
in the excavated trench , as deemed necessary.

Pl refer Item No.3.2 on page TSPEC -3 for ‘Guidelines for laying multiple cables’.

Detailed Photographs of cables laid to be submitted by the contractor at 50 metre intervals and costs for the same to be considered during quoting of
rates for cable laying.

Under rare circumstances, the contractor may be made to lay more than 20 cables, as per the instructions of the department head, For cables > 20 Nos
Please refer Note No 11, Page COMM-24.
** - FO duct & connector to be supplied by DEWA. For procedure, please refer Technical spec. page: TSPEC 5 item 3.4

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)
4. * Backfill trench with fine sand clear of stones 30AED+46AED+60AE
or other sharp material/ Red desert dune sand D+55AED+55AED+55
as per the approved cross-section drawing AED+75AED+50AED
(enclosed). Above the top of the cable, (ITEM No. 4.1 to 4.8)
carefully place PVC cable tape with ends
physically interlocked to each other (or the
duct across the road), backfill and
consolidate at two separate levels the
remainder of the trench with materials removed
from Item 2.1 to 2.8 (excluding asphalted
materials, stones etc.) including insertion of
plastic marker tape & Allen marking required
4.1 where duct is provided. 20 Km

4.2 Trench Area Less Than (Width X Depth) = 0.40 170 Km


Sq.m

4.3 B/w 0.41 mtr width & 1.0 mtr depth & 0.5 metre 4 Km
minimum width & 1.2 m. deep- 1 or 2 cables.
(Area - 0.41 Sq.m to 0.6 Sq.m)
4.4 4 Km
B/w 0.61 mtr width & 1.0 mtr depth & 0.75
metre minimum width & 1.2 m. deep- 3 cables.
4.5 (Area - 0.61 Sq.m to 0.90 Sq.m ) 4 Km

B/w 0.91 mtr width & 1.0 mtr depth & 0.9 metre
4.6 minimum width & 1.3 mtr. deep – 4 cables. 4 Km
(Area - 0.91 Sq.m to 1.17 Sq.m )

B/w 1.18 mtr width & 1.0 mtr depth & 1.1 metre
minimum width & 1.3 m. deep – 5 cables. (Area
– 1.18 Sq.m to 1.43 Sq.m )

B/w 1.44 mtr width & 1.0 mtr depth & 2.00
metre minimum width & 1.5 m. deep – 10 cables.
(Area – 1.44 Sq.m to 3.00 Sq.m)

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

4.7 B/w 3.10 mtr width & 1.0 mtr depth & 3.0 metre 4 Km
minimum width & 1.5 m. deep
(Area – 3.10 Sq.m to 4.50 Sq.m)
4.8 Trench Area Greater Than ( Width X Depth ) = 4 Km
4.51 Sq.m.

Backfilling will be paid under Item no’s 4.1 to 4.8


* - The rate quoted for backfilling should include the transportation costs for removed tiles / cut portions of asphalt, and excavated material
to and from the actual site to temporary storage locations, as applicable and as per the directions of DM/RTA , after obtaining necessary approvals from
DM/RTA, for temporary site locations.
#- Importing of fine ‘Red Desert Dune Sand ’is in the scope of the contractor

4.9# IMPORTING OF RED DESERT SAND FOR BACKFILLING
Import Red Desert Dune sand, at the discretion 5,000
of DEWA representative, for backfilling works Cu metre
for sites where three or more cables are laid
including Carting away of the surplus
excavated materials to designated Dubai
Municipality dumping areas.
4.10* 20,000
DUBAI SMART SOIL which is SPECIAL BACK FILL Cu metre
MATERIAL (SBM) FOR BACKFILLING:
Importing of special backfilling material
(Dubai Smart Soil) for back filling the
trench, where multiple cables in trench either
near 132 KV substation or wherever as required
at the discretion of Dewa engineer as per
cross section drawings (enclosed) with proper
compaction layer by layer including insertion
of Geotextile material (As required at the
discretion of DEWA Engineer), plastic marker
tape, Allen marking tape and compaction test
at DM laboratories only.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

5 Bulk Excavation & Filling 100
5.1 Submit longitudinal profile drawing along the cu metre
road in Micro station/ AutoCAD format,
indicating the levels of existing ground,
existing road and proposed cable levels and
Cut and fill in all types of soils and/ or
rock grade and level as directed by the
Engineer including transporting the excess cut
soil to low laying area for filling along the
route or to any other fill area approved by
5.2 Dubai Municipality, Watering & Compaction and 100
provide the profile drawings after leveling/ cu metre
cutting.

Extra earth filling not covered in Item 5.1 in


low laying area wherever required or as 70,000
6.## directed by Engineer including transport, Sq.m
grade, level etc.(approved material to be
imported from approved borrow pits)

6.1 Removal and Re-instatement of various types of -


pavements detailed below:
[Rate for this will be applicable to all sub-
items, i.e. (6.1) to (6.11]

6.2 To remove and to reinstate 60/80 mm thick -


interlocking concrete blocks of required
colour after compacting road base (150 mm
thick )and laying washed/ crushed sand bedding
6.3 of 50mm thickness(sand particle size -
– 0 to 5mm) -

- do - but 60 cm x 60 cm x 6 cm thick
hydraulically pressed cement concrete tiles
instead of 60 mm thick interlocking block

- do - but 40 cm x 40 cm x 6 cm thick
hydraulically pressed cement concrete tiles.
## - Replacement of broken items under 6 is in the scope of the contractor. Please refer Item No. 5 in the ‘Notes –below & Item No.15.1 –page TSPEC- 17. The contractor
shall be responsible for providing proper safety arrangements, until final completion of works, strictly as per the DEWA/ DM / RTA requirements.
#- Importing of fine ‘Red Desert Dune Sand ’is in the scope of the contractor.
* - For “Dubai Smart Soil”/SBM procedure, please refer Technical spec. Page: TSPEC-16, 17.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

- do - but 30 cm x 30 cm x 6 cm thick -
6.4 hydraulically pressed cement concrete tiles.

To remove and to reinstate 15 cm thick cast- -


in-situ concrete paving laid on compacted sand
6.5 overlaid with 1000 guage polythene sheet.
Concrete to be of strength 250 kg. per sq.mtr
after 28 days.
-
- do - but 10 cm. thick cast-in-situ concrete
6.6 paving - -

To remove and to reinstate paved area


6.7 comprising of cement concrete chequered tiles
of original colour as required, of size 30 cm
x 30 cm x 3 cm complete with preparation of -
required concrete and cement sand mortar
bedding. - -
6.8
- do - but size 20 cm x 20 cm x 3 cm thick
6.9 tiles. -

To remove and to reinstate paved area -


comprising of Terrazzo tiles, to match the
existing of size 30 cm x 30 cm x 5 cm thick -
6.10 complete with preparation of required concrete
and cement sand mortar bedding .
6.11 -

- do - but size 30 cm x 30 cm x 3 cm thick


tiles

- do - but size 20 cm x 20 cm x 2 cm thick


tiles
ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

6.12 To remove and to re-install marble stone/ 1,000


special tiles belonging to DM/RTA of different Sq.m
colours, sizes and quality to match with the
actual requirement
6.13 500
To remove (only) various types of pavements as Sq.m
detailed in 6.1 to 6.12 above (Re- instatement
shall be done by others) and stack removed
tiles/blocks properly for re- use/remove
debris from site and dispose off to DM
approved sites. It should include removal,
6.14 reinstatement and compaction of road base
layer. 500
Sq.m
To reinstate (only) various types of pavements
as detailed in 6.1 to 6.12 above (Removal
shall be done by others) and remove debris
6.15 from site and dispose off to DM approved
sites.

6.15.1 To remove and to reinstate using the following 1000 sq.m


in the temporary road/shoulder/parking etc. to
6.15.2 the original state: 100 sq.m

Road Base

Wet mix layer

Note: Provision of Road Base is in the scope of the contractor.


Important Note: Road Asphalting works to be carried out by RTA/DM approved road contractor.
ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

7. Asphalted Roads/Parkings and Road shoulders To
7.1 remove (only) old asphalt and to re- instate *10,000
* upto road base level for paved road or Sq. metre
asphalted parking, including trimming of old
asphalt, back-filling with similar pavement
materials in layers, compaction etc.
complete as per specifications (asphalt re-
instatement will be done by others)
7.2
To remove (only) old asphalt and to re- *1,000
instate upto road base level for asphalted Sq.m
road shoulder including trimming of old
asphalt, back-filling with similar pavement
materials in layers, compaction etc. complete
as per specifications (asphalt re- instatement *10,000
7.3 ## will be done by others) Sq.m

To re-instate items covered under 7.1 & 7.2


7.4 with temporary asphalt.

To re-instate items covered under 7.1 & 7.2


with Hot asphalt as per RTA standard
(permanent) with min 50mm wearing course and
50-150mm asphalt road base layer in following
items including Road/parking marking,
cutting/trimming and carting away existing
7.4.1 cold asphalt to designated DM yard etc. 1,000sq.m
complete. The work to be carried out by
7.4.2 RTA/DEWA approved road contractor. 500 sq.m

7.4.3 In carriageway------------------------------ 500 sq.m

In parking lot------------------------------

In Asphalt shoulder/hard shoulder-----------

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs) VAT Total with VAT
(Dhs) (Dhs)

7.5 To remove (only) hard shoulders consisting of *500


bitumen and single size gravel spread Sq.m
uniformly and back-fill with similar pavement
material in layers upto original shoulder
level, compaction etc. complete as per
8. specification

To remove and to reinstate edge following


8.1 types of kerbs with PCC bedding and supporting 600 mtr
haunches:
8.2 800 mtr
Road upstand kerbs--------------------------

9.** Heel kerbs --------------------------

Horticulture
Remove and dispose horticulture as per the
DM/Developer/Pvt. Horticulture NOC condition
- including safe storage of sweet soil /
repair of irrigation pipes in case of any
damage (sweet soil to be replaced if
disturbed). This should include removal,
shifting, modification or diversion of
irrigation system if necessary. (unit of
measurement applicable as per site
requirement; metre/sq.m/Nos/Each etc)
* Measurement only for asphalt portion (Payment for cable laying excavation and backfilling will be made under respective item numbers)
# - Provision of Road Base is in the scope of the contractor.
# - UPVC Ducts shall be supplied by DEWA.
## - Provision of Cold Asphalt(temporary)is in the scope of the contractor. The contractor should send ‘Request for Reinstatement by Permanent asphalt
to DEWA’ as per the format, immediately after providing temporary asphalt.
**Main Contractor should appoint DM/Pvt Developer approved specialised landscaping Contractor to carry out the job.
They should be responsible for Coordination, submission of proposals & As-built’s as well as obtaining final completion from relevant
authorities.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE Total Price (Dhs) VAT Total with VAT
(DHS.) (Dhs) (Dhs)

9.1 Removal Of Horticulture

9.1.1 Grass 4,000


Sq.m
9.1.2 Ground Cover -------------------------------- 2,000
Sq.m

9.1.3 Shrubs 800


Nos

9.1.4 Hedges 400


Nos/Sq.m

9.1.5 Flowers 1,200


Sq.m

9.1.6 Any other Items, which is not mentioned above


but available at site 200
Sq.m

9.2 Reinstatement / Re-plantations of affected soft


landscape area as per DM/Developer/Pvt. NOC
Conditions. This should include restoration/re
instalment
of irrigation system.

9.2.1 Grass 4,000


Sq.m
9.2.2 Ground Cover -------------------------------- 2,000
Sq.m
UNIT PRICE VAT Total with VAT
ITEM NO. DESCRIPTION OF WORKS QUANTITY Total Price (Dhs)
(DHS.) (Dhs) (Dhs)

9.2.3 Shrubs -------------------------------- 800


Nos

9.2.4 Hedges -------------------------------- 400


Nos/Sq.m

9.2.5 Flowers -------------------------------- 1,200


Sq.m

9.2.6 Any other Items, which is not mentioned above 200Sq.m


but available at site

Note:- Main Contractor should appoint DM/RTA approved specialised Horticulture/landscaping Contractor to carry out the job.

10 Collect, transport and install in already # 12,500


excavated----- trench 150/ 200 mm dia. Upto 2 Metre
way ducts

11 Collect, transport and install in already # 1,500


excavated ----trench 150/ 200 mm dia. B/w 3 way Metre
& 6 way ducts

12 Collect, transport and install in already # 1,000


excavated ---trench 150/ 200 mm dia. B/w 7 way Metre
& 10 way ducts

13 Collect, transport and install in already # 350


excavated trench 150/ 200 mm dia. B/w 11 way & metre
18 way ducts # - Measurement only for installed
ducts (Payment for cable laying excavation and
backfilling will be made under respective item
numbers )

UNIT PRICE VAT Total with VAT


ITEM NO. DESCRIPTION OF WORKS QUANTITY Total Price (Dhs)
(DHS.) (Dhs) (Dhs)

14 Collect and transport Cable Jointing Kits (to


be supplied by DEWA) from DEWA Stores and carry
out the following cable jointing works.
Preparation of Joint pits shall be claimed
under item#1. Please refer
TSPEC-13.

14.1 Heat Shrinkable type Straight Joint for 11 kV, 1,300 Nos. 980Dhs
# 3 Core, 240/300 sq.mm. XLPE Cable (Aluminum or
Copper Conductor)
14.2 Cold Shrinkable type Straight Joint for 11 15
# kV, 3 Core, 240/300 sq.mm. XLPE Cable (Aluminum Nos. 800Dhs
or Copper Conductor)
14.3 Heat Shrinkable type Transition Joint for 11 20 980Dhs
# kV, 3 Core, Aluminium PLY 300 sq.mm. Cable to Nos.
240/300 sq.mm. (Aluminium or Copper Conductor)
XLPE Cable -

14.4 Heat Shrinkable PILC – PILC Straight through 10 800Dhs


# Joints for 11kV, 3Core, 300 sq.mm PILC Cables Nos
(Al or Cu conductor)

14.5# Pre-Molded Joints (Al/Cu conductor cable) 10 Nos 800Dhs


15 # Collect & transport Cable Termination Kit (to 600 1300Dhs
be supplied by DEWA) and terminate one end of nos
either of the cable indicated above in
Sr.No.14.1 to 14.4 or any other equivalent
size. (Note: Crimping sockets will be available
in equipment cable boxes or will be supplied by
DEWA)

16 De compounding of cable boxes for 11kV 10 800Dhs


switchgear termination works / Removal of Nos.
Termination from the decompounded cable boxes

# - Joints/ Terminations shall be provided by DEWA , Please refer TSPEC -19 regarding the ‘ Cable Jointing and Termination works ’. The co-ordinates
for the joints to be made available in the As-Built drawings submitted by the contractor. Return of scrap / balance cable pieces to DEWA stores, is in
the scope of the contractor.

VAT Total with VAT


ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price (Dhs)
(Dhs) (Dhs)

DRILLING ACROSS ROADS/SERVICES AND DUCT

17 EXTENSION
17.1 Supply & Install 150 mm internal dia. Class C 12,800
uPVC ducts by Thrust Boring method or 160mm LM.
outer dia. HDPE ducts by directional drilling,
including necessary trial pits, drill pits in
all types of soil/pavements including asphalt,
and reinstatement* to its original condition
including necessary Field Density Tests &

Reports as per DEWA/RTA standards (Permanent


asphalt in RTA areas only shall be arranged by
DEWA) and preparation of all necessary
documents**as required to process bore hole &
drilling NOCs and for DEWA quality records
such as level sheets, drilling profile, key
plan, as built etc.
Supply & Install 160 mm HDPE/150 mm uPVC Class 1,280
17.2 C Pipes from drill pits to cable corridor or LM
as instructed by DEWA including excavation* of
trenches, socket/butt fusion welding,
workmanship, backfilling, reinstatement* to
original finish etc. complete (Permanent
asphalt in RTA areas only shall be arranged by
DEWA).
17.3 Submission of Profile Drawings reflecting the 300
site condition and existing services & all Nos.
other supporting documents**such as traffic

diversion proposal, pre & post drive levels,


site photographs, Parking meter details etc.
for processing Road cutting/Drilling NOC from
RTA/Developer/other Authorities/Utilities and
for DEWA quality records.(Drilling profile &
bore hole profile drawing are not payable in
case drilling is done.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE Total Price (Dhs) VAT Total with VAT
(DHS.) (Dhs) (Dhs)

17.4. Making bore holes, * as per pre-requisite for


processing drilling NOC by RTA, in all types of
soils and hard strata, along with submission of
All relevant sample/test records, reports by a
Dubai Municipality approved soil laboratory as
17.4a instructed by DEWA engineer, for a depth of 40 Nos.
17.4b 6M 40 Nos.
17.4c 9M 40 Nos.
17.5 12M 20
Recording & submission of road datum levels Loc.
before and after NDRC work, using 3D imaging
survey equipment to process NOC for major dual
18 carriageway crossings (as required by RTA) as 200
instructed by DEWA engineer. Nos.
To make cable entry holes 150-200 mm dia.
18.1 Average wall thickness between 250 - 600 mm in 25
substations by core cutting method Nos.
19.1 To make cable entry holes, average wall 1,000 Nos.
## thickness above 600 mm in substations by core
cutting method
19.2 To carry out sealing works to the cable entry 100
holes in substation masonry/ concrete walls Nos.
with approved fire sealing and Polyurethane
19.3 based water sealing material 100
To supply and install pressure testing plugs to Nos.
arrest water leakage in future ducts in
substation basement. It should include fire
19.4 sealing 100
To supply and Install mechanical rubber seal, sq.m
which should have EDPM based rubber body and
stainless steel fittings in order to arrest
water seepage through cable entry holes in
waterlogged areas.
To reinstate fire sealing work underneath 11kV
switchgear panels in 132kV S/stn. After cable
termination.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE Total Price (Dhs) VAT Total with VAT
(DHS.) (Dhs) (Dhs)

20. To carryout site survey on receipt of approved 500


CAR and arrange demarcation and level of cable Nos
route. (please refer notes 18)
Submission of Profile Drawings
21. Submit longitudinal profile drawing along the
road in Micro station/ AutoCAD format, 10 Kms
indicating the levels of existing ground,
existing road and proposed cable levels due to
site constraints ,as directed by DEWA engineer.
(Specimen attached)

## Provision of Cable Protection Concrete slabs, Materials required for Fire and water sealant is in the scope of the contractor and to be approved by
DEWA.
*-Protection of roads by shoring & services by means of steel plate supports, wooden boxes etc.as required by the concerned authorities. Dewatering for
identifying services and for the execution of drilling (including well point method). Site safety arrangements in accordance with prevailing DEWA/RTA
standards and any amendments thereof during the contract period including concrete barriers etc. Obtaining permit to work and service drawing from
developers, consultants, service authorities and entry passes where applicable. Payment of fees for Permit to work, entry passes, service drawings,
Traffic police approval etc. Supply & Installation of duct markers in RTA roads and for service line crossings.
**- All documents including but not limited to traffic diversions proposal plan & cross sectional drawings for drilling, road cutting or Bore Holes
using AutoCAD drawing up to A1 size, hard and soft copies (for taking pre-drive levels, monitoring the drilling and for emergency road blocking) for
obtaining drilling/road cutting NOCs. Site photographs, level sheets and all other documents required are included.
Notes:
1. Ducts, sockets, ropes and end caps for drilling and duct extension shall be provided by the contractor, material approval from DEWA
to be obtained by the contractor for prior use.
2. Road works to be carried out by RTA/DM approved road contractor
3. Horticulture/landscaping Main Contractor should appoint DM/RTA approved specialised Horticulture and landscaping Contractor to carry
out the job.
ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price VAT Total with VAT
(Dhs) (Dhs) (Dhs)

22. Provide Cable Protection Precast Concrete slabs 10Dhs S. No.22 &


## of dimension (50 cms X 20cms X 5cms) as per the 2,000 Nos 325Dhs for S. No. 30 &
RTA requirement to protect cables laid at 110Dhs S.No. 29 &
shallow depths due to presence of existing 45000Dhs for S. No. 26
services / site constraints ,after availing
permission from RTA for such works.
23. 600 Nos
** Provide sealing of cable ends by H.S end caps,
as directed by DEWA representative/ while
return of balance cables to DEWA stores or for
cases involving leaving the cancelled cables
underground, as directed by DEWA engineer.
24. 250 Cu.m
CROSSING OF DEWA HV CABLES ACROSS THE GAS/
FUEL PIPELINE.
Taking of Trial Pits manually to determine
depth of Gas/ Fuel pipeline, Submitting the
proposal drawings indicating the levels of the
pipeline and method statement for crossing as
required by the gas authority to avail final
NOC and execution of work with proper safety
arrangements and including De- Watering
arrangements, if required, as per the approved
method statement, in strict compliance to the
NOC conditions and terms and conditions of the
gas authority.
Backfilling in layers as per the approved
25. method statement and Provision of route markers
### to identify the cable crossings. (ALL CO- 20 Km
ORDINATION WITH THE GAS AUTHORITIES TO BE DONE
BY THE CONTRACTOR.)

Lowering/ Re-arrange the existing HV cables


(may be live) to a new/ widened trench, with
necessary protective, support/hanging
arrangement as the work progresses, if
required, as per the instructions of DEWA.

ITEM NO. DESCRIPTION OF WORKS QUANTITY UNIT PRICE (DHS.) Total Price VAT Total with VAT
(Dhs) (Dhs) (Dhs)

Diversion of existing cables during shutdown 1 Km


26 works, relocation of cables from plot to HV
* corridor wherever part of the existing cable
can be utilized, instead of laying new
cables.

Dewatering by well points, as directed by DEWA 100 Nos


27 with necessary arrangements for shoring /
** discharging .( All required permissions from
DM & utilities to be arranged by the
contractor)

Prepare and submit Soft and Hard copies of As- 200 Km


28 Laid / As-Built drawings for the 11kv cables
*** laid/Fibre Optic duct laid including co-
ordinates for jointing/Fibre Optic Connectors
and drilling under road.
Note: Price should be for the Route length
only, irrespective of quantity of cables.

Recovery of cancelled redundant cables


29 including returning the usable/scrap pieces to 10 Kms

DEWA stores/contractor stores for identifying


and reusing cables in good condition, as per
the instructions of DEWA
Repair sheath damages found in the existing

30 cables using H.S repair sleeves supplied by 100 Nos


DEWA, as per the instructions of DEWA Engineer
Supply and provide vertical cable support

31 inside 132 kv basement fabricated out of MS- 100 Nos


angle unistrut angles and other required
arrangements, as per the normal DEWA practice,
as per the written instruction from Manager.

TOTAL TENDER PRICE – (Dhs)