Professional Documents
Culture Documents
Prepared by:
Module1: Introduction to Earned Value
• How Earned Value Management fits into a Program and Project environment
Module 1 - Introduction 1
Prepared by: Booz Allen Hamilton
What is Earned Value Management?
Module 1 - Introduction 2
Prepared by: Booz Allen Hamilton
Why use Earned Value Management?
Why use Earned Value? For one, it is mandated by some key DOE directives
and guidance that Earned Value will be implemented. The following pages
will discuss these.
Module 1 - Introduction 3
Prepared by: Booz Allen Hamilton
DOE guidance for Earned Value
Module 1 - Introduction 4
Prepared by: Booz Allen Hamilton
DOE guidance for Earned Value
Current Department of Energy policy, DOE Order 413.3, Program and Project
Management for the Acquisition of Capital Assets, states the requirements
for contractor’s project management system
Finally, below let’s look at some Best Practice guidance currently in the DOE.
Module 1 - Introduction 5
Prepared by: Booz Allen Hamilton
Earned Value Management History
With the understanding of what Earned Value is and why it used, let’s take a
brief look at the history of Earned Value.
Following pages will discuss and contrast the different between the two
management approaches.
Module 1 - Introduction 7
Prepared by: Booz Allen Hamilton
Traditional Management
In Traditional management, there are two data sources, the budget (or planned)
expenditures and the actual expenditures. The comparison of budget versus
actual expenditures merely indicates what was planned to be spent versus
what was actually spent at any given time. But how much has been produced?
As you can see, with this approach there is no way to determine the physical
amount of work performed. It does not indicate anything about what has
actually been produced for the amount of money spent nor whether it is being
produced at the rate, or according to the schedule, originally planned. In other
words, it does not relate the true cost performance of the project.
70
As the graph shows,
60
this comparison
50
only represents the
40
relationship of what 30
was budgeted 20
(planned) versus 10
Time Now
Earned Value takes these three data sources and is able to compare the
budgeted value of work scheduled and compare it to the “earned value of
physical work completed” and the actual value of work completed.
Module 1 - Introduction 9
Prepared by: Booz Allen Hamilton
Earned Value Management
Notice the three lines on the graph below. These lines correspond to the three
components of earned value: budget (in red), actual expenditures (in blue),
and the earned value of the production (in black). Note how the budget line is
below both the actual expenditures and the earned value lines. What does
this indicate?
First, it is obvious that the project is expending more (blue line) than it was
budgeted to spend, to date 150
50
trend has occurred since
25
the beginning of the Time Now
0
project. J F M A M J J A S O N D
Budget 5 10 15 20 25 30 35 40 45 50 55 60
But what else can be Actuals 10 20 30 40 50 60
interpreted from the Earned 8 15 25 30 35 45
Forecast 70 80 90 100 110 120
graph? Let’s take a closer
look on the next page.
Module 1 - Introduction 10
Prepared by: Booz Allen Hamilton
Earned Value Management
There are two conclusions the earned value data will immediately let you make;
they deal with schedule and cost variances.
Module 1 - Introduction 12
Prepared by: Booz Allen Hamilton
Earned Value Management
Module 1 - Introduction 13
Prepared by: Booz Allen Hamilton
Summarizing Traditional Management vs. Earned Value
Management
• How much money and time a particular job is likely to require prior to starting
and once stated, how much money was spent at any given time.
• How much money and time a particular job is likely to require prior to starting
and once stated, how much money was spent at any given time.
Plus
• Once started, what work has been accomplished to date for the funds
expended (what you got for what you spent)
• Once started, what the total job will cost at completion, and how long it will
take to complete
Module 1 - Introduction 14
Prepared by: Booz Allen Hamilton
Earned Value in a Management Environment
Understanding how Earned Value fits into the program and project
management environment is also essential.
On the following page we will discuss and define items such as project vs.
program, project management, program management and the relationship
between them.
Module 1 - Introduction 15
Prepared by: Booz Allen Hamilton
What is Program/Project Management?
Module 1 - Introduction 17
Prepared by: Booz Allen Hamilton
Earned Value Management vs Program/Project Management
So far, we have discussed what Earned Value is, why to use it, and how it fits
into a program and project management environment. Next, we need to
discuss the framework needed to implement earned value.
On the following pages these three phases for developing an Earned Value
Management System (EVMS) will be discussed in more detail.
Module 1 - Introduction 19
Prepared by: Booz Allen Hamilton
Inputs needed for Earned Value Management System (EVMS)
As you recall, the first phase of Earned Value is inputs. The inputs required for
an EVMS include:
• Work Breakdown Structure (WBS)
• Organizational Breakdown Structure (OBS)
• Project Schedule WBS/OBS
• Time-phased Baseline Budget Project
Schedule
• Cost/Resource Control Plan Resource Planning
Define/Assign
• Change Control Plan Schedule/Budget
Performance Measurement
Establish Baseline
Early Warning & Detection
Earned Value
These Items are covered in Management
System
Informed Management
Decisions
$$$
If any of these items are not completed or are not completed appropriately, the
use of Earned Value will be compromised and your outputs will not properly
represent the program/project current and future status.
Module 1 - Introduction 20
Prepared by: Booz Allen Hamilton
Earned Value Method needed for Earned Value Management System
(EVMS)
The second phase of Earned Value is the earned value method. The Earned
Value method required for an EVMS include:
• Planned Value (PV), Earned Value (EV) Actual Cost (AC)
• Metrics and Performance Measurements
• Forecasting
WBS/OBS
• Integrated Baseline Review Project
Schedule
Resource Planning
Define/Assign
Schedule/Budget
Performance Measurement
Establish Baseline
These Items are covered in Early Warning & Detection
Earned Value
Informed Management
Modules 5 through 7 Management
System
Decisions
Corrective Actions
Recovering Planning
Accounting
System
$$$
Once again, if any of these items are not completed or are not completed
appropriately, the use of Earned Value will be compromised and your
outputs will not properly represent the program/project current and future
status.
Module 1 - Introduction 21
Prepared by: Booz Allen Hamilton
Outputs needed for Earned Value Management System (EVMS)
The last phase of Earned Value is the outputs. The outputs required for an
EVMS include:
• Reporting requirements
• Proper Analysis of Reports WBS/OBS
• Correct Action taken Project
Schedule
Resource Planning
Define/Assign
Schedule/Budget
Performance Measurement
Establish Baseline
Early Warning & Detection
Earned Value
These Items are covered in Management
System
Informed Management
Decisions
$$$
Even if the first two phases are completed appropriately, improper analysis of
the outputs could cause inappropriate or inadequate actions to be taken
against the program/project and could either create problems that otherwise
would not exist or fail to fix the real problem that does exist.
Module 1 - Introduction 22
Prepared by: Booz Allen Hamilton
Review of Module 1
“You cannot manage what you cannot measure…and what gets measured
gets done.”
--- Bill Hewlett, Hewlett Packard
If you have a firm grasp of the concepts covered in this module, you are ready
to progress to the next modules. Otherwise, review this module again to
ensure you have a solid understanding of the basics of the Earned Value
Management System.
Module 1 - Introduction 24
Prepared by: Booz Allen Hamilton
Earned Value Management Tutorial
Module 2: Work Breakdown Structure
Prepared by:
Module 2: Work Breakdown Structure
This module will include defining and illustrating the following topics:
• WBS dictionary
Over the years, it was determined that project managers needed a tool to help
capture and control their project scope. This led to the development of a
Work Breakdown Structure (WBS).
The Work Breakdown Structure (WBS) is a tool that defines a project and
groups the project’s discrete work elements in a way that helps organize and
define the total work scope of the project. A WBS element may be a product,
data, a service, or any combination. WBS also provides the necessary
framework for detailed cost estimating and control along with providing
guidance for schedule development and control. Additionally the WBS is a
dynamic tool and can be revised and updated as BEST Management
Books
needed by the project manager. 1.
all the work and products 1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3 1.1.1.3.2
After reviewing the WBS on the previous page, an important point needs to be
reviewed. Although a WBS can be depicted so as to look like an
organizational chart, it IS NOT an organizational chart.
BEST Management
Books
1.
Not all projects have a WBS, and it is true that some of these projects have been
successful. So why is a WBS needed? We have already looked at a few
reasons, but in review, the WBS:
– Provides a framework for organizing and managing the approved project
scope
– Helps ensure you have defined all the work that makes up the project
– Provides a framework for planning and controlling cost and schedule
information
– It’s better to be deliberate about planning than rely on luck!
Additionally, when you work for a company or organization that has many
projects being performed simultaneously, each of the projects is competing for
the limited resources available. The WBS enables you to review project
details and distinguish one project’s needs from others within the company or
organization. Why is distinguishing one project from another important? It
enables you to identify resource requirements and allocate resources more
effectively.
In preparing a WBS there are a number of steps that need to be taken to make
sure the WBS developed will help manage your project. Below and on the
following pages we will discuss these steps.
1. Identify final project products necessary for achieving project success. The
WBS should assist the project manager in developing a clear vision of the
end product. You need to answer the following question:
– What must be delivered to achieve project success?
• You may need to review the project scope documents for guidance.
4. Review and refine the WBS until the stakeholders agree with the level of
project planning and reporting.
– Remember that no matter how detailed a WBS is, there are planning
and reporting restrictions a WBS creates. On the following pages, we
will look at examples of these restrictions.
Let’s use the BEST Management Books’ WBS we looked at earlier. Assume
that the WBS was only planned down to the chapters level (see graph
below, left), but after the first month of work, the stakeholder wants reporting
at the subchapter level (see graph below, right). Without restructuring the
WBS and changing the other supporting systems, like cost tracking and
reporting, it is impossible for the project manager to meet the stakeholder’s
request.
Writing Writing
Text Book Text Book
1.1.1 1.1.1
Now let’s reverse the situation. Assume WBS was planned down to the
subchapter level (see graph below, left), but after the first month of work, the
stakeholder wants reporting at the chapter level (see graph below, right). Is
there any restructuring needed to the WBS? The answer is “No”. Since you
planned the work at a level below what is now the stakeholder’s
requirement, you can “roll-up” and meet the stakeholder’s request.
Do you still see a problem with the project WBS? Let’s take a look.
.
Project
Selection
Project
Organization
Organization
Project
Planning
Budget &
Cost
Scheduling
Scheduling
1.1.1.2.2
Project
Controls
1.1.1.1.1 1.1.1.1.2 1.1.1.1.3 1.1.1.2.1 1.1.1.2.3
Module 2 – Work Breakdown Structure 9
Prepared by: Booz Allen Hamilton
Preparing a WBS
Actually, there is not a problem with the WBS structure, but a problem with the
idea of time and cost. The project manager spent time and resources to
define the WBS down to a level that he determined was appropriate. The
only benefit could be that the project manager wishes to manage the
project at the lower level and will roll-up reporting for the stakeholder.
In review, always get stakeholders to agree with the level of project planning
and reporting.
In developing a WBS, one must realize that there are multiple ways to develop
a WBS for any given project. Some ways might be better than others, but
the two most important item to remember are that the WBS must contain all
approved scope and the Project Manager must develop the WBS to reflect
the way he/she intends to manage the project.
On the following two pages are examples of alternative WBS structures for
the BEST Management Books project.
Armed with the basics of the WBS, it is time to examine them in more detail and
to begin to understand how to build one. To do this, let’s look at building a
WBS for the construction of a single family home. First, take a moment to
familiarize yourself with some background information about the construction
company, which appears on the next page.
The ACME Housing Corporation, which you own, has been contracted to build
its first house. You want to be able to manage your projects effectively and
efficiently, so you charge your project managers to develop an appropriate
WBS. You decide to manage the project by the individual tasks necessary to
complete the house.
You hope that this is the first of many houses that ACME will build, so you start
the WBS with ACME in the highest position, or Level 1. Accordingly, Level 1
is given a WBS code of 1. You assign the WBS code of 1 to the highest level
because all future projects (houses) will be summarized at Level 1.
With Level 1 established, you can begin to complete the WBS. But what should
the next level be?
The logical next level for ACME is the project level. Level 2 is the level for each
individual project, or house, that ACME undertakes. As the chart shows
below, Level 2 is identified at the project level: House.
Appropriately, the code for Level 2 corresponds to Level 1. In this case, the
code is 1.1.
Level 1
Level 2
Now the WBS for the housing project is complete, right? Actually, no, the WBS
is not complete. At this point you determine that you want to divide the work
into the major elements needed to build a house. You choose to divide Level
3 into six elements: concrete, framing, plumbing, electrical, interior and
roofing. You realize that these are both major deliverables and milestones for
managing the project. They also enable you to get to your goal of managing
the project by task.
Notice the WBS codes at level 3. Each is unique to the project and starts with
the WBS code from the level above (11.11.1.1). Now lets look and see
if another level is needed.
Level 1
Level 2
Level 3
Module 2 – Work Breakdown Structure 17
Prepared by: Booz Allen Hamilton
WBS: Structure
The ACME WBS is taking shape, but it does not quite define the project at a
level that shows needed tasks for completion. To do this, one more level
needs to be included.
Level 4 of the WBS will enable us to manage
the project as desired. All of our contractors
fit into specific elements at level 4, and so
do all specific departments. As with the Level 1
previous Levels, note the WBS codes that
have been assigned to the tasks and their
Level 2
relationship to the previous Level.
Level 3
Level 4
What do you think? Is the WBS complete? Does it enable the manager to
manage at the task level?
After a review to make sure that only approved scope is included, our WBS is
complete. It does include the necessary components to manage the project
by task.
Now that you understand the WBS and how to assemble one, let’s examine
how it relates to earned value.
In Module 1, we discussed that in implementing earned value, a project
manager must have control of the project’s “triple constraint” (scope,
schedule and cost). Unlike traditional management, which tracks two
components (budget and expenditures), earned value considers three and
provides a more robust understanding of a project’s overall progress and
health.
The WBS is the most important item in defining and controlling the project
scope. How does it control the scope? If the WBS is not developed correctly
and does not capture all the project scope and only the project scope, then
the “earned value” system built using the WBS will be inaccurate. The project
manager will lose control of the project before it even begins.
Now that you have your WBS, let’s take a look on the next page at the other
item needed to properly organize your project.
Once the WBS is complete, the WBS dictionary needs to be the next item
developed. The WBS dictionary is a narrative documentation of the effort
needed to accomplish all work defined in the WBS. The WBS dictionary is
developed for the lowest level element in the WBS only.
To better understand how a WBS and a WBS dictionary work, let’s compare it
to a book and the book’s table of contents:
– The WBS is the table of contents for the project. It captures the
contents in an organized fashion (chapters, subchapter).
– The WBS dictionary is the book itself. It tells the story. In our case the
story is what work will be accomplished and what outputs will be
produced in each of the WBS elements. The total of these descriptions
is how a house will be built and what is needed to build the house.
The WBS dictionary will often lead to the development of the statements of
work (SOW) for the project. SOWs will be discussed in later modules.
Now that our WBS is developed, the appropriate resources and responsibilities
need to assigned. The first step in doing this is developing the
Organizational Breakdown Structure (OBS) for the project. The OBS
indicates the organizational relationships and is used as the framework for
assigning work responsibilities. Below is an example of the OBS for the
ACME house building project. The OBS is structured by Responsible
Department and then by Performing Department at the lowest level. This
Performing Department level is were the responsibility and resource needed
to accomplish the project will be assigned.
PROJECT OFFICE
RESP DEPT
B. Smithers
Merging the WBS and OBS, the project manager creates a Responsibility
Assignment Matrix (RAM). The RAM displays the lowest level of both the
WBS and the OBS. The integration identifies specific responsibility for
specific project tasks. It is at this
point that the project manager
develops control accounts or work
package. Control accounts and
work packages will be discussed
in Module 4. Lets look at what the
RAM may look like on the ACME
house construction project on the
next page.
PERF DEPT 3010
R. Oriely
PLUMBING
RESP DEPT
K. Wells
GAS
R. Lee
Responsibility
RESP DEPT
ELECTICAL
WIRING
P. Ottis
J. Sims
PROJ ECT OFFICE
B. Smithers
RESP DEPT
Assignment Matrix
PERF DEPT 5010
DRYWALL
ROOFING
D. Smith
Y. Taylor
R. Sites
RESP DEPT
P. Tate
M. Manning
MASONRY
T. Greams
RESP DEPT
TEST
R. Kelly
CIVIL
Alternatively, hours and dollars may be used in the RAM rather than an “X”.
Using our ACME House example, the “X” was replaced with the hours
needed to complete the task. Now we see that Mr. Sites has 300 hours to
frame the exterior walls, 250 hours to frame the interior walls and 175 hours
to install the roofing trusses.
CONCRETE FRAMING PLUMBING
1.1.1 1.1.2 1.1.3
Frame Frame Install Install
Pour Pour Exterior Interior Roofing Water Install Gas Install B/K
Foundation Install Patio Stairway Walls Walls Trusse Lines Lines Fixtures
Performing Dept. Manager 1.1.1.1 1.1.1.2 1.1.1.3 1.1.2.1 1.1.2.2 1.1.2.3 1.1.3.1 1.1.3.2 1.1.3.3
CONCRETE
DEPT 6010 Manning 200 125 85
MASONRY
DEPT 6020 Greams 50
TEST
DEPT 6030 Neumann 20 10 5
CARPENTRY
DEPT 5010 Sites 300 250 175
ROOFING
DEPT 5020 Taylor 100
DRYWALL
DEPT 5030 Smith 275
WIRING
DEPT 4010 Johnson
HOOKUP/TIE-IN
DEPT 4020 Ottis
WATER/SEWER
DEPT 3010 Wells 100 15
GAS
DEPT 3020 Oriely 125 25
Module 2 – Work Breakdown Structure 27
Prepared by: Booz Allen Hamilton
Review of Module 2
At this point we have examined the WBS, OBS and RAM. These items are the
start for laying the groundwork for developing an earned value management
system (EVMS). In the next module you will examine these item in more
detail by looking at the development of control accounts, work packages
and the cost estimate.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics for developing a WBS, OBS and
RAM
Prepared by:
Module 3: Project Scheduling
Let’s quickly review what has been covered in the previous modules.
• In Module 2 we discussed
– the first steps in the planning process
– development of the work breakdown structure (WBS)
– organizational breakdown structure (OBS)
– the integration of WBS and OBS in creating the responsibility assignment matrix
(RAM)
• The next step in this process is to develop the project schedule. So the first
question we need to ask is what is scheduling?
…Forming a network of activities and event relationships that portrays the sequential
relations between the tasks in a project…
…Planned completion of a project based on the logical arrangement of activities,
resources…
…Placing the project and its activities in a workable sequenced timetable…
…A detailed outline of activities/tasks with respect to time…
While scheduling is all of these things, the main thing to remember is that
scheduling is the development of planned dates
for performing project activities and meeting milestones.
“I keep six honest serving men (they taught me all I knew); their names
are What and Why and When and How and Where and Who.”
--- Rudyard Kipling
Planning involves making decisions with the objective of influencing the future.
Another way to consider planning is as the “thinking” phase. Defining
activities, their logical sequence, and their relationship to each other are all
planning functions. In planning you answer the following questions:
In what sequence?
• This question involves determining the order in which activities will be
performed to complete the project.
With five main questions answered, only one last question remains: when. This
question involves scheduling.
To satisfy the earned value management system (EVMS) criteria, the schedule
must:
On the following pages, we will discuss the process for developing a project
schedule, including how to ensure it is logical and how to ensure that it
includes all key milestones and deliverables.
For the purpose of explaining the process in detail, we will use the smaller
BEST Management Books project from Module 2 instead of the ACME
House Building project. At the end of the process will will look at the
outcome of using this process on the ACME House Building project.
Here is the initial list of activities for the BEST Project Management book.
There are two things to remember at this stage of the process.
1. The activity list is not a complete list; additions and subtractions will be
made from it.
2. As you develop your list, you may see the need to update the WBS.
Remember the WBS is a dynamic tool, revisions may be needed and
should be expected as the scheduling of activities progresses.
WBS Activity List
1.1 Start Development of Project Management Book
For this example, we will assume
1.1.1.1.1 Writing Project Selection section for Chapter 1 that this is a complete list of
1.1.1.1.2 Writing Project Organization section for Chapter 1
1.1.1.1.3 Writing Project Planning section for Chapter 1
activities, and no revision to the
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 WBS is needed.
1.1.1.2.2 Writing Scheduling section for Chapter 2
1.1.1.2.3 Writing Project Controls section for Chapter 2
1.1.1.3.1 Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
1.1.2.1 Editing Chapter 1
1.1.2.2 Editing Chapter 2
1.1.2.3 Editing Chapter 3
1.1.3 Publishing Project Management Book
1.1 Finished Development of the Project Management Book
Module 3 – Project Scheduling 10
Prepared by: Booz Allen Hamilton
Scheduling – Step 2. Sequence the List of Project Activities
This process requires the project manager, subject matter experts (SME), and
other project team members who are familiar with the nature of the specific
activities to meet, discuss and develop the sequencing of the project
activities. This process is known as “a pencil to paper” process.
Continuing to use our BEST Management book example, we will take a look at
this sequencing process on the next page.
Once the sequence has been established, you need to determine the direct
relationship between each activity. But how does sequencing differ from
identifying the relationships of tasks and activities?
Sequencing is the order of how things will happen. First, second, third, etc. . .
• FS – Finish to Start
• SS – Start to Start
• FF – Finish to Finish
• SF – Start to Finish
Let’s take a closer look at the first three scheduling dependencies. We will not
discuss the last dependence, as it is never used.
The first type of relationship is called Finish to Start (FS). This means that activity
“A” must finish before activity “B” can start.
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Start
You must “Finish” writing the Project Organization section of Chapter 1 before
you can “Start” writing the Project Planning section for Chapter 1.
The second type of relationship is Start to Start (SS). This means that activity “B”
can start as soon as activity “A” starts.
Let’s look at this relationship using the BEST Management Books example:
Start-To-Start
Start BEST
Management
Books Project
SS Writing Project
Selection section
for Chapter 1
You can “Start” writing the Project Selection section for Chapter 1 as soon as
you “Start” the BEST Management Books Project.
Module 3 – Project Scheduling 16
. Prepared by: Booz Allen Hamilton
Types of Scheduling Dependencies
The third type of relationship is Finish to Finish (FF). This means that activity
“B” cannot finish until activity “A” finishes.
Let’s look at this relationship using the BEST Management Books example:
Finish-To-Finish
FF
Editing Chapter 3
Finish BEST
Management
Books Project
You cannot “Finish” the project, Finish BEST Management Book Project,
until you “Finish” Editing Chapter 3.
Module 3 – Project Scheduling 17
Prepared by: Booz Allen Hamilton
Step 3. Determine the Relationship Between Project Activities
Using the relationships we have just described, the BEST Management Books
project activities and the logical relationships among them is diagrammed
below. This is formally known as a Network Diagram.
Start BEST
Finish BEST
Management Book
Management Book
Project
Project
Writing Project FS Writing Project FS
Organization Section Planning Section for Editing Chapter 1 FF
SS FS
for Chapter 1 Chapter 1
FS
Publishing Project
Writing Project Management Book
Selection Section for
FS
Chapter 1
FS
FS
With the relationships defined, we now need to establish the duration for each
activity. Let’s take a look on the next page.
Now that you have the project network diagram, it is time to determine the
duration for each project activity. Once again, just like the sequencing
process: you need to enlist the help of the people or group of people familiar
with the nature of the project.
Establishing the duration of each project activity involves determining the work
periods needed to complete each identified activity. Work periods can be
– hours
– days
– weeks
– months, etc..
Regardless of the exact work period chosen, the period must be consistent for
all activities in the schedule. The project manager and team member(s)
must decide which work period is right for the project.
Two major duration estimating tools can help project managers estimate the
activity duration: the PERT and CPM.
For the activity “Editing Chapter 1,” the following estimates are determined:
– (O) Optimistic estimate = 6 days
– (P) Pessimistic estimate = 18 days
– (M) Most Likely = 9 days
Legend
Time Estimates
• Optimistic (O)
• Pessimistic (P)
• Most Likely (M)
Now let’s look at the duration estimate for the activities in the BEST
Management Books project. For the purposes of this tutorial, it does not
matter which duration estimating method was used.
WBS Activity Description Duration
1.1 Start Development of Project Management Book 0 wks
Here is a list of the activities in 1.1.1.1.1
1.1.1.1.2
Writing Project Selection section for Chapter 1
Writing Project Organization section for Chapter 1
8 wks
10 wks
the BEST Management Books 1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks
Project. The durations for each 1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks
activity have been determined. 1.1.1.2.3
1.1.1.3.1.
Writing Project Controls section for Chapter 2
Writing Auditing section for Chapter 3
7 wks
2 wks
From looking at the chart, what 1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk
1.1.2.1 Editing Chapter 1 8 wks
is the work period chosen by the 1.1.2.2 Editing Chapter 2 8 wks
project manager? 1.1.2.3 Editing Chapter 3 4 wks
1.1.3 Publishing Project Management Book 4 wks
1.1 Finish Development of the Project Management Book 0 wks
The work period is weeks (wks). Remember the selected work period must
be consistent for all activities.
Module 3 – Project Scheduling 22
Prepared by: Booz Allen Hamilton
Scheduling – Quick Review
At this point, you have covered a good bit of information. Take some time now
to review what you have learned before you continue with the module.
So far in this module, we have covered four of the five steps related to project
scheduling:
The final step in this process is to determine the project duration (start and
completion dates) and the start and finish dates for each individual activity.
Take a closer look at this step on the following page.
Usually the project duration and activity start and completion dates are mapped
in a typical scheduling software application. The activities are placed in the
software tool, and the relationships are identified. The software calculates
the dates.
To better understand how the software calculates the dates, we will take a look
at the process known as Forward and Backward Pass.
The Forward Pass determines the The Backward Pass determines the
early start (ES) and the early finish late start (LS) and late finish (LF) of
(EF) of each activity. each activity.
Together, these processes give the total project duration, including the start
and finish dates for each activity. Additionally, the process will determine the
• critical path, which tells you the activities that cannot slip without increasing
the total duration of the project or moving the project completion date, and
• float, which tells you how much certain activities can slip without impacting
the total project duration.
We will look at critical path and float later in the module.
To begin the Forward Pass process, determine a project start date. Looking at
the BEST project, we will use January 1 as the project start date.
Start BEST
Management Book
The first activity that appears in the Network Diagram Project
The early start (ES) is 1/1 since this is the First activity and the start date for
the project is 1/1. The early finish (EF) for this activity is also 1/1 since it is a
milestone and a milestone has no duration.
Using the Network Diagram, the next activity is “Writing Project Selection
section of Chapter 1.” This activity is start to start (SS) with the previous
activity, thus its early start date is 1/1 (see chart). The early finish is
determine by the duration of the activity itself. This activity has a duration of
8 weeks, which translates to a early finish date of 2/25.
Start BEST
Management Book
Project
Writing Project
SS Organization Section
for Chapter 1
FS
Writing Project
Selection Section for
Chapter 1
The next activity is “Writing the Project Organizational section of Chapter 1.” It
is finish to start (FS) with the previous activity. With the FS relationship in
mind, what is the early start date for this activity?
Start BEST
Management Book
Because you must finish writing the Project Project
Writing Project
Selection section before you start writing the SS Organization Section
for Chapter 1
FS
Project Organizational section, the early start Writing Project
Selection Section for
date for the current activity is 2/26. The early Chapter 1
The next activity is “Writing the Project Budget and Cost section of Chapter 2.”
It is finish to start (FS). Can you determine the activity that must finish,
before this activity can start?
Start BEST
Management Book
It is finish to start (FS) with Writing the Project Selection Project
Writing Project
SS
section: because you must finish writing the project FS
Organization Section
for Chapter 1
selection section before you start writing the project Writing Project
Selection Section for
budget and cost section (same as Writing Project Chapter 1
This process is used to determine each activity’s ES and EF. On the page next
is the completed Forward Pass.
Module 3 – Project Scheduling 29
Prepared by: Booz Allen Hamilton
Project Scheduling – Step 5. Determine Project Duration
By looking at the chart below, can you determine the project duration, start and
completion dates?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14
With the Forward Pass complete, let’s look at the Backward Pass. The
Backward Pass calculates the latest date that each activity can start and
finish in order to meet the project end date.
Again, using the BEST Management Books example, let’s now address the
Backward Pass. The chart below contains the Forward Pass information.
Unlike the Forward
Pass, which started 1.1WBS Start Development of Project Activity
Management Book
Duration
0 wks
ES
1/1
EF
1/1
LS LF
with the first activity, 1.1.1.1.1 Writing Project Selection section for Chapter 1
1.1.1.1.2 Writing Project Organization section for Chapter 1
8 wks
10 wks
1/1
2/26
2/25
5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2
the Backward Pass 1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks
9 wks
2/26
5/7
4/29
7/8
will start at the 1.1.1.2.2 Writing Scheduling section for Chapter 2
1.1.1.2.3 Writing Project Controls section for Chapter 2
5 wks
7 wks
4/30
6/4
6/3
7/22
bottom of the chart 1.1.1.3.1. Writing Auditing section for Chapter 3
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3
2 wks
1 wk
7/23
8/6
8/5
8/12
with the last activity 1.1.2.1
1.1.2.2
Editing Chapter 1
Editing Chapter 2
8 wks
8 wks
7/9
7/23
9/2
9/16
and work 1.1.2.3
1.1.3
Editing Chapter 3
Publishing Project Management Book
4 wks
4 wks
8/13
9/17
9/9
10/14
backwards. 1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14
The process works the same as the Forward Pass but in the opposite direction.
Once again using the Network Diagram, the last activity is “Finish the
Development of the Project Management Book” (see below). The late finish
(LF) and the late start (LS) will be the same as the early start (ES) and early
finish (EF) since it is the final activity. Finish BEST
Management Book
Project
Editing Chapter 1 FF
FS
Publishing Project
WBS Activity Duration ES EF LS LF Management Book
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 FS
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
Editing Chapter 2 FS
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 FS
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 Editing Chapter 3
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Looking at the Network Diagram on the previous page, you see that there are
three activities that have a relationship with Publishing Project Management
Book:
– Editing Chapter 1
– Editing Chapter 2
– Editing Chapter 3
Also note that the relationships are all finish to start (FS). With this in mind,
what is the LF and LS for each activity?
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
Module 3 – Project Scheduling 33
Prepared by: Booz Allen Hamilton
Project Scheduling – Step 5. Determine Project Duration
Because “Publishing
WBS Activity Duration ES EF LS LF
Project Management 1.1 Start Development of Project Management Book 0 wks 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25
Book” has an LS of 1.1.1.1.2
1.1.1.2.1
Writing Project Organization section for Chapter 1
Writing Budget and Cost section for Chapter 2
10 wks
9 wks
2/26
2/26
5/6
4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8
9/17 and all three 1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22
activities are finish to 1.1.1.3.1.
1.1.1.3.2
Writing Auditing section for Chapter 3
Writing Administrative Closeout section for Chapter 3
2 wks
1 wk
7/23
8/6
8/5
8/12
start (FS), the late 1.1.2.1
1.1.2.2
Editing Chapter 1
Editing Chapter 2
8 wks
8 wks
7/9
7/23
9/2
9/16
7/23
7/23
9/16
9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
finish (LF) for each 1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
must be 9/16.
How do you determine the late start (LS) for each activity? Subtract the
duration for each activity from LF, as shown in the chart.
Here is the completed list of all the activities, including the early starts (ES),
early finishes (FS), late starts (LS) and late finishes (LF). What can you
determine about the project from this data?
From the Forward Pass information, we know the Project duration, Project
Start, and Completion date.
Now it is time to use the information from the Backward Pass to determine the
project’s critical path.
The Critical Path tells you the activities that cannot slip a day without increasing
the total duration of the project or moving the project completion date. The
critical path is the longest path of logically related activities through the
network which cannot slip without impacting the total project duration.
WBS Activity Duration ES EF LS LF
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14
• If the result is a number greater the zero, then the activity is not on the
critical path and has float.
To better understand critical path, look at the chart. Note a column was
added to calculate float and determine the critical path. From reviewing
the chart, what activities are on the critical path?
WBS Activity Duration ES EF LS LF Float
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1 0
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25 0
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20 14
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29 0
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22 14
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3 0
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22 0
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12 7
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 7
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 14
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 0
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16 7
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 0
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 0
All the activities with zero float are on the Critical Path!!!! But what exactly
does this mean? Take a look on the next page.
The Critical Path tells management the activities that are critical or essential in
completing the project on time. It is also important for management to look
at activities with minor float because any delays in those activities could
cause them to be on the critical path.
WBS Activity Duration ES EF LS LF Float
1.1 Start Development of Project Management Book 0 wks 1/1 1/1 1/1 1/1 0
1.1.1.1.1 Writing Project Selection section for Chapter 1 8 wks 1/1 2/25 1/1 2/25 0
1.1.1.1.2 Writing Project Organization section for Chapter 1 10 wks 2/26 5/6 3/12 5/20 14
1.1.1.2.1 Writing Budget and Cost section for Chapter 2 9 wks 2/26 4/29 2/26 4/29 0
1.1.1.1.3 Writing Project Planning section for Chapter 1 9 wks 5/7 7/8 5/21 7/22 14
1.1.1.2.2 Writing Scheduling section for Chapter 2 5 wks 4/30 6/3 4/30 6/3 0
1.1.1.2.3 Writing Project Controls section for Chapter 2 7 wks 6/4 7/22 6/4 7/22 0
1.1.1.3.1. Writing Auditing section for Chapter 3 2 wks 7/23 8/5 7/30 8/12 7
1.1.1.3.2 Writing Administrative Closeout section for Chapter 3 1 wk 8/6 8/12 8/13 8/19 7
1.1.2.1 Editing Chapter 1 8 wks 7/9 9/2 7/23 9/16 14
1.1.2.2 Editing Chapter 2 8 wks 7/23 9/16 7/23 9/16 0
1.1.2.3 Editing Chapter 3 4 wks 8/13 9/9 8/20 9/16 7
1.1.3 Publishing Project Management Book 4 wks 9/17 10/14 9/17 10/14 0
1.1 Finish Development of the Project Management Book 0 wks 10/14 10/14 10/14 10/14 0
Below is the PERT chart layout of the project. The boxes in red indicate those
activities on the critical path. The blue boxes are for all other activities.
Notice the information in the boxes, it shows the activity name, duration,
early start and finish, and late start and finish. See the legend below for
details.
Writing
WritingProject
Project
Organization
Organizationsection
section Duration
for Chapter 1
Start Development Early Start 10 wks
10 wks Early Finish
of Project
Management Book 2/26/2002 5/6/2002
2/26/2002 5/6/2002
0 days 3/12/2002 5/20/2002
3/12/2002 5/20/2002
1/1/2002 1/1/2002 Late Start Late Finish
1/1/2002 1/1/2002
W riting
W riting Budget and W riting Project Finish Development
W riting Scheduling W riting Auditing Administr ative
Cost section for Controls section for Editing Chapter 3 of the Project
section for Chapter 2 section for Chapter 3 Closeout section
Chapter 2 Chapter 2 4 wks Management Book
5 wks 2 wks for Chapter 3
9 wks 7 wks 8/13/2002 9/9/2002 0 days
4/30/2002 6/3/2002 7/23/2002 8/5/2002 1 wk
2/26/2002 4/29/2002 6/4/2002 7/22/2002 8/20/2002 9/16/2002 10/14/2002 10/14/2002
4/30/2002 6/3/2002 7/30/2002 8/12/2002 8/6/2002 8/12/2002
2/26/2002 4/29/2002 6/4/2002 7/22/2002 10/14/2002 10/14/2002
8/13/2002 8/19/2002
Editing Chapter 2
8 wks
7/23/2002 9/16/2002
7/23/2002 9/16/2002
Now that we have covered the entire process with the BEST Management
project in detail, lets apply it to the ACME House Building project from
Module 2. It reveals the following information:
Activity Duration ES EF LS LF Float
Start House Construction 0 days 1/15 1/15 1/15 1/15 0
Pour foundation 6 days 1/15 1/22 1/15 1/22 0
Install Patio 6 days 1/23 1/30 3/21 3/28 57
Pour stairway 2 days 1/31 2/1 3/29 4/1 59
Concrete Complete 0 days 2/1 2/1 4/1 4/1 59
Frame exterior walls 13 days 1/23 2/8 1/23 2/8 0
Frame interior walls 7 days 2/11 2/19 2/11 2/19 0
Project Duration: Install roofing trusses 4 days 2/20 2/25 2/20 2/25 0
Framing Complete 0 days 2/25 2/25 2/26 2/26 1
55 days Install waterlines 7 days 2/20 2/28 2/25 3/5 5
Install gas lines 3 days 2/22 2/26 3/1 3/5 7
Install B/K fixtures 5 days 3/1 3/7 3/26 4/1 25
Plumbing Complete 0 days 3/7 3/7 4/1 4/1 25
Project Start: Install wiring 5 days 2/20 2/26 2/27 3/5 7
Install outlets/switches 4 days 3/22 3/26 3/22 3/26 0
1/15 Install fixtures
Electrical Complete
4 days
0 days
3/27
4/1
4/1
4/1
3/27
4/1
4/1
4/1
0
0
Install drywall 7 days 3/6 3/14 3/6 3/14 0
Painting 5 days 3/15 3/21 3/15 3/21 0
Install Carpeting 2 days 3/22 3/25 3/29 4/1 7
Project Complete: Interior Complete 0 days 3/25 3/25 4/1 4/1 7
Install felt 4 days 2/26 3/1 2/26 3/1 0
4/1 Install shingles 2 days 3/4 3/5 3/4 3/5 0
Install vents 3 days 3/6 3/8 3/12 3/14 6
Roofing Complete 0 days 3/8 3/8 3/15 3/15 7
House Complete 0 days 4/1 4/1 4/1 4/1 0
At this point, we have examined the first two bullets; the next step in our
process is to reflect the schedule baseline. Take a moment now to
familiarize yourself with this step on the next page.
Baseline is the original approved plan that consists of both schedule and cost.
The baseline is used as the foundation for measuring project performance.
In an Earned Value Management System (EVMS), the schedule and cost
baseline are essential.
The Schedule Baseline is the standard that all schedule performance will be
measured against. It should be approved by the project manager and other
appropriate individuals. Once the project manager approved the project
start, logic, relationships and project duration, the schedule is then
“baselined” to measure schedule performance.
The final step, integrating with the cost baseline, will be discussed in detail in
the next module. For now, take a look at the types of scheduling formats on
the next page.
In reporting and displaying your schedule, there are multiple formats that have
and can be used. We focus on three major formats:
Gantt or Bar chart shows the activity start and end dates as well as the
expected durations. It does not usually show dependencies between tasks.
It is a weak planning tool but is good for tracking and reporting progress to
the project team. Below is a copy of the Gantt chart for the ACME House
Building project.
The Logic or Network Diagram displays the logic relationships of the project
activities. It stresses the logic/interdependencies between activities and is
excellent for reviewing project logic. It is not a good reporting format,
because the time frame is not clear and can at times be confusing. Below is
a partial copy of the Gantt chart for the ACME House Building project.
At this point, you have covered all of the content in Module 4. Take some time
now to review the major items:
• The Critical Path tells you the activities that can not slip a day without
increasing the total duration of the project or moving the project completion
date. It is the longest path of logically related activities through the network
which cannot slip without impacting the total project duration, termed zero
float.
At this point we have examined the basics for developing a project schedule
and schedule baseline. The Schedule Baseline is one of the two most
important items in an earned value management system (EVMS). In the
next module you will examine the other important item in an earned value
management system (EVMS): the cost baseline.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics for developing a project schedule.
Prepared by:
Module 4: Budgeting
• Cost/Schedule Baselines
• WBS Levels: Control Accounts, Work Packages, Planning Packages
• Elements of an Earned Value Contract Baseline
• Proposed Cost and the Contract Budget Baseline
• Control Account Manager Roles and Responsibilities
• Review
Module 4 – Budgeting 1
Prepared by: Booz Allen Hamilton
The Budgeting Process
Module 4 – Budgeting 2
Prepared by: Booz Allen Hamilton
The Budgeting Process
The budgeting process establishes a means for developing and tracking the
cost goals for all contractually authorized work.
One of the key criteria for establishing an earned value management system is
that all major components of a project must be integrated and baselined.
Major components of the earned value management system include scope,
schedule and cost. The cost and schedule performance are measured
against a baseline to help track the progress of the project.
Let’s review the steps required to establish a cost and schedule baseline on the
next page.
Module 4 – Budgeting 3
Prepared by: Booz Allen Hamilton
Establish the Schedule Baseline
ACME Project X
1.0
Module 4 – Budgeting 4
Prepared by: Booz Allen Hamilton
Establish the Schedule Baseline
ACME Project X
1.0
Module 4 – Budgeting 5
Prepared by: Booz Allen Hamilton
Establish the Cost Baseline
ACME Project X
1.0
Module 4 – Budgeting 6
Prepared by: Booz Allen Hamilton
Integrated Scope, Schedule and Cost
ACME Project X
1.0
Now let’s discuss how the budgeting process and the cost/schedule integration
is accomplished in an earned value environment.
Let’s discuss these three key elements in more detail, starting with Control
Accounts, on the next page.
Module 4 – Budgeting 8
Prepared by: Booz Allen Hamilton
Control Accounts
A Control Account is an assigned WBS Level used to monitor the cost and
schedule performance of a significant element of the work. Control
Accounts are also referred to as Cost Accounts. These terms are
interchangeable, however, we will use the term Control Accounts.
The illustration on the following page depicts the ACME House Project WBS
down to the Control Account Level.
Module 4 – Budgeting 9
Prepared by: Booz Allen Hamilton
Control Accounts
For the ACME House project, it was determined that the performance
measurements for the project will be taken at Level 3 (see graphic below).
The project manager and the stakeholders must determine the level at
which the performance measurement will be required.
House Building
Level 2 Project
1.1 Control Account Level
Module 4 – Budgeting 10
Prepared by: Booz Allen Hamilton
Work Packages
The detail that builds up to the Control Account Level is contained in Work
Packages and Planning Packages. Take a moment now to review Work
Packages.
Work Packages (WP) contain a discrete segment of work below the Control
Account level that is defined by
– a description or brief work statement
– starting and ending dates
– completion milestone
– work-in-process measure
– time-phased budget expressed in direct labor (hours and/or dollars),
material, other direct costs and subcontract dollars
It is important that the duration of a Work Package be a relatively short span of
time (normally, but not limited to, six months or less).
Module 4 – Budgeting 11
Prepared by: Booz Allen Hamilton
Planning Packages
As work becomes more clearly defined, Planning Packages are converted into
Work Packages, with the following constraints. These constraints ensure
the initial budget is used appropriately:
Module 4 – Budgeting 12
Prepared by: Booz Allen Hamilton
Work Packages/Planning Packages
Now that you are familiar with work packages and planning packages, take
some time to examine how they appear in the WBS. For the ACME House
project, the Work Packages and Planning Packages will be at Level 4 of
the WBS. This is the level at which detailed budgets will be developed,
statused, and then summarized at the Control Account level for reporting.
Level 3 Concrete
1.1.1
Framing
1.1.2
Plumbing
1.1.3
Electrical
1.1.4
Interior
1.1.5
Roofing
1.1.6
Level 4
Frame Interior Install Outlets/
Install Patio Install Gas Lines Install Carpets Install Shingles
Walls Switches
1.1.1.2 1.1.3.2 1.1.5.2 1.1.6.2
1.1.2.2 1.1.4.2
A Control Account is an assigned WBS Level used to monitor the cost and
schedule performance of a significant element of the work.
Detail below the Control Account Level is contained in Work Packages and
Planning Packages.
If you are unsure about any of these concepts, please go back and review,
otherwise let’s move on to discuss the key elements used to develop,
baseline, and manage an earned value project or contract.
Module 4 – Budgeting 14
Prepared by: Booz Allen Hamilton
Elements of a Contract Baseline
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 15
Prepared by: Booz Allen Hamilton
Total Contract Price
Total Contract Price is the total negotiated contract cost plus profit/fee.
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 16
Prepared by: Booz Allen Hamilton
Total Contract Cost
Total Contract Cost is the total negotiated contract cost without profit/fee.
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 17
Prepared by: Booz Allen Hamilton
Profit/Fee
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 18
Prepared by: Booz Allen Hamilton
Contract Budget Base
The Contract Budget Base (CBB) represents the total budget for all authorized
contractual work, minus Profit/Fee. The CBB can only be modified when duly
authorized changes to the contract are received. CBB is always calculated as
follows:
Control Accounts
Work Packages
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 20
Prepared by: Booz Allen Hamilton
Management Reserve
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 21
Prepared by: Booz Allen Hamilton
Distributed Budgets
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 22
Prepared by: Booz Allen Hamilton
Undistributed Budget
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 23
Prepared by: Booz Allen Hamilton
Proposed Costs and the Contract Budget Base Relationship
To better understand the key elements of the Contract Budget Base, lets walk
through the Proposal Development, Negotiations, and Contract Award
Phases. To begin, first ensure you understand the relationship between the
proposed cost and the established Contract Budget Base.
A proposed cost estimate and a Contract Budget Base are developed in the
same manner. The resources required to complete each defined element of
work are developed in terms of hours. These hours are converted to Labor
Dollars by applying Direct Labor Rates and Indirect Burdens (Direct and
Indirect Costs are discussed on the following page). Costs of purchased
materials and subcontracts (and applicable acquisition overhead rates) as
well as Other Direct Costs (ODC) are also generated and included in the
proposed amount. Module 4 – Budgeting 24
Prepared by: Booz Allen Hamilton
Direct and Indirect Cost Accounting
As mentioned on the previous page, costs include direct and indirect charges.
Direct Costs – Costs applicable to, and identified specifically with, the program
contract Statement of Work.
Examples of Direct Costs: Labor, Travel, Material, Subcontractor Charges
Module 4 – Budgeting 25
Prepared by: Booz Allen Hamilton
Sample Indirect Rate Application
Module 4 – Budgeting 26
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Development
By now you should be familiar with the difference in types of costs, but how
exactly do you go about determining costs in a project? Take some time to
see how to develop a proposed cost using the ACME House Building
project.
Module 4 – Budgeting 27
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Development
To start, we need our ACME House Work Breakdown Structure as shown here.
House Building
Project
1.1
This insures that we develop cost for only approved project scope.
Module 4 – Budgeting 28
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Development
We assigned resources to this task, and based on the Labor Hours, Material,
and ODC Dollars, burdened by all the indirect rates, a Total Price of
$11,574 has been estimated to complete this task.
This process is used to price each WBS element. On the next page is the
completed price for the ACME House.
RES CODE Hours Rate/Hour Prime Overhead G&A COM Fee Total Price
Carpenter 40 $ 25.00 $ 1,000 $ 1,666 $ 422 $ 2 $ 618 $ 3,707
Drywall 40 $ 15.00 $ 600 $ 1,000 $ 253 $ 1 $ 371 $ 2,224
ELEC 4 $ 40.00 $ 160 $ 267 $ 67 $ 0 $ 99 $ 593
ENGE 20 $ 30.36 $ 607 $ 825 $ 226 $ 1 $ 332 $ 1,991
Material 0 $ 2,000 $ 109 $ - $ 1 $ 422 $ 2,531
Other 0 $ 500 $ 27 $ - $ 0 $ - $ 527
Total 104 $ 4,867 $ 3,894 $ 968 $ 5 $ 1,840 $ 11,574
Module 4 – Budgeting 29
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Development
The proposed resources for the entire project have been priced as described
on the previous page. The following chart reflects the Total Price for each
WBS of the ACME Housing Building project.
House Building
Project 1.1
$231,894
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$59,094 $57,905 $25,018 $61,826 $20,447 $7,605
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$3,259
$28,452 $22,026 $8,257 $24,642 $9,312
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$11,574 $14,699 $8,339 $12,353 $2,500 $3,259
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$19,067
$21,180 $8,421 $24,831 $8,635 $1,086
Module 4 – Budgeting 30
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Negotiations
Now let’s review the proposed price and complete the negotiations.
The proposed price is $231,894; however, the buyer of the ACME house can
only afford to pay $220,000. The ACME house builder has agreed to build
the ACME house for $219,999, but some revisions had to be made to the
plans to utilize less expensive materials.
The following summary reflects the negotiated cost and price to build the
ACME House.
Module 4 – Budgeting 31
Prepared by: Booz Allen Hamilton
ACME House Cost Proposal Negotiations
The following summary reflects the negotiated price by WBS to build the
ACME House.
ACME Housing Corporation
1
$219,999
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$47,200 $57,905 $25,018 $61,826 $20,447 $7,605
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$3,259
$20,523 $22,026 $8,257 $24,642 $9,312
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$10,781 $14,699 $8,339 $12,353 $2,500 $3,259
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$15,895
$21,180 $8,421 $24,831 $8,635 $1,086
Module 4 – Budgeting 32
Prepared by: Booz Allen Hamilton
The Budgeting Process
Now that we have a negotiated contract, we can establish the Contract Budget
Base.
The Negotiated Total Cost, without Profit/Fee, for the ACME House equals
$183,852. This will be the basis for developing the Contract Budget
Baseline (CBB). Again, remember that this amount is exclusive of Fee.
Control Accounts
Work Packages
After the Contract Budget Base has been established, the Management
Reserve is established by the Program Manager.
In the case of the ACME House, the Program Manager has decided to
establish a Management Reserve amount equal to 10% of the Contract
Budget Base. This equates to $18,385. The Performance Measurement
Baseline, which equals the CBB – MR, will be established at $165,467.
All of the PMB will be distributed, therefore Distributed Budgets will equal
$165,467, and Undistributed Budget will remain zero.
Total Contract Price
$219,999
Control Accounts
Work Packages
Module 4 – Budgeting 34
Planning Packages
Prepared by: Booz Allen Hamilton
The Budgeting Process
Now that the Management Reserve has been established by the Program
Manager, target budgets are developed and distributed to the Control
Account Managers.
Establishing the target budgets will often be accomplished through a joint effort
by the Program Manager, Team Leaders, and the Control Account
Managers.
Control Accounts
Work Packages
Planning Packages
Module 4 – Budgeting 35
Prepared by: Booz Allen Hamilton
The Budgeting Process
Module 4 – Budgeting 36
Prepared by: Booz Allen Hamilton
The Budgeting Process
The target budget released to the Control Account Manager for 1.1.1 Concrete
is $35,482 ($39,424 – $3,942 = $35,482).
Total Dollars
Negotiated $39,424
MR (10%) -$3,942
Module 4 – Budgeting 37
Prepared by: Booz Allen Hamilton
The Budgeting Process
When detailed planning reveals the target budget established for the control
account is unrealistic (too high or low), the CAM, Team Leader and
Program Manager participate jointly to determine appropriate adjustments.
In some cases, this may require the use of MR.
In the case of the Concrete Control Account, the Control Account Manager has
accepted the budget of $35,482.
Once the budgets have been allocated to the Control Accounts, the Control
Account budgets are further subdivided into work packages and planning
packages.
Module 4 – Budgeting 38
Prepared by: Booz Allen Hamilton
The Budgeting Process
Here’s the distributed budget for the entire ACME WBS. Remember, this does
not include Profit/Fee, or Management Reserve.
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$35,482 $43,432 $18,765 $46,373 $15,711 $5,704
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$2,445
$15,394 $16,521 $6,194 $18,483 $6,984
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$8,166 $11,025 $6,255 $9,265 $2,250 $2,445
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$11,922
$15,887 $6,317 $18,625 $6,477 $815
Work Packages
Module 4 – Budgeting 39
Prepared by: Booz Allen Hamilton
The Budgeting Process
Time phased budgets are prepared for each work package and planning
package. Each work package and planning package contains a budget
divided into time increments (typically monthly) by elements of cost, such as
direct labor, material, subcontract, and other direct cost (ODC).
The development of detail planning for the control account and ultimate
approval of the budget, schedule, and associated Work Authorization
Document (WAD) is accomplished through an iterative process.
Module 4 – Budgeting 40
Prepared by: Booz Allen Hamilton
The Budget Process
The Control Account Manager (CAM) uses work packages and planning
packages to divide the control account into specific manageable and
measurable units of work for the purpose of developing plans and
determining progress.
The sum of the work packages and planning package budgets are equal to the
total budget assigned to the CAM on the work authorization form. The total
budget for the control account is time-phased in hours and dollars.
Module 4 – Budgeting 41
Prepared by: Booz Allen Hamilton
Baseline Documentation
Summaries of schedules and budgets at the work package level are integrated
using a Control Account Plan (CAP). A CAP is a low level detail plan
prepared by the CAM showing time phased planning of tasks and their
associated budget for a Control Account. The CAP also provides brief work
package and milestone descriptions that enable the CAM to clarify and
differentiate the unique content of each work package.
The CAM and Program Control develop the cost and schedule database by
using the control account planning documentation and other data. A series
of checks and balances are performed to ensure the data is consistent.
Upon completion of the baseline development, reports displaying the
planning data as it appears in the system are reviewed and verified for
accuracy.
Module 4 – Budgeting 42
Prepared by: Booz Allen Hamilton
Schedule and Cost Baseline
Below is the time-phased budget for the ACME House Building Project. This
profile represents the cost and schedule baseline in Total Dollars.
Many new terms and concepts were presented in this module. Let’s summarize
what was covered.
The budgeting process establishes a means for developing and tracking the
cost goals for all contractually authorized work.
One of the key criteria for establishing an earned value management system is
that the scope, schedule and cost must be integrated and baselined. The
baseline is what cost and schedule performance is measured against
The Work Breakdown Structure is the
framework used to facilitate the ACME Housing Corporation
1
$165,467
Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
$35,482 $43,432 $18,765 $46,373 $15,711 $5,704
Pour Foundation Frame Exterior Install Water Install Wiring Install Drywall
Install Felt 1.1.6.1
1.1.1.1 Walls 1.1.2.1 Lines 1.1.3.1 1.1.4.1 1.1.5.1
$2,445
$15,394 $16,521 $6,194 $18,483 $6,984
Install Patio Frame Interior Install Gas Lines Install Outlets/ Install Carpets Install Shingles
1.1.1.2 Walls 1.1.2.2 1.1.3.2 Switches 1.1.4.2 1.1.5.2 1.1.6.2
$8,166 $11,025 $6,255 $9,265 $2,250 $2,445
Install Roofing Install B/K Install Fixtures Install Painting Install Vents
Stairway 1.1.1.3
Trusses 1.1.2.3 Fixtures 1.1.3.3 1.1.4.3 1.1.5.3 1.1.6.3
$11,922
$15,887 $6,317 $18,625 $6,477 $815
Module 4 – Budgeting 44
Prepared by: Booz Allen Hamilton
Review of Module 4: Budgeting
A Control Account is an assigned WBS Level used to monitor the cost and
schedule performance of a significant element of the work.
Work Packages (WP) contain a discrete segment of work below the Control
Account level and provide detailed planning for accomplishing the work
within a Control Account.
ACME Housing Corporation
Level 1 1
Planning Packages
House Building
Planning Packages
If you have a firm grasp of the concepts covered in these first four modules,
feel free to progress to the next module. Otherwise, review the modules to
ensure you have a solid understanding of the basics.
Module 4 – Budgeting 47
Prepared by: Booz Allen Hamilton
Earned Value Management Tutorial
Module 5: EVMS Concepts and Methods
Prepared by:
Module 5: EVMS Concepts and Methods
Now lets discuss the basic Earned Value concepts and methods.
Before we start discussing the Earned Value concepts and methods, let’s look
at an overview of the criteria needed for EVMS. There are numerous EVMS
guidelines that have been developed in both the government and
commercial industry.
Industry
• Organization Standard
• Planning and Budgeting Industry
Department
Earned Valueofof
Department
Standard
Defense
• Accounting Management
Defense
Department
Earned
5000.2-R Valueofof
Department
• Analysis and Management Reporting SystemDefense
5000.2-R
Management
Defense
• Revisions and Data Maintenance 5000.2-R
System
5000.2-R
The second category is Planning and Budgeting. Industry Standard Earned Value
Management System
Within Planning and Budgeting the criteria require
• Organization
the following: • Planning & Budgeting
• Accounting
• Analysis & Management Reporting
• Create the Integrated Master Schedule • Revisions & Data Maintenance
• Ensure that the Contract Budget Base (CBB) is reconciled with the Total
Allocated Budget (TAB)
The third category is Accounting. Within Accounting Industry Standard Earned Value
Management System
the criteria require the following:
• Organization
• Planning & Budgeting
• Accounting
• Record direct and indirect costs in accordance • Analysis & Management Reporting
• Revisions & Data Maintenance
with company disclosure statement
The fourth category is Analysis and Management Industry Standard Earned Value
Management System
Reports. Within Analysis and Management
Reports the criteria require the following: • Organization
• Planning & Budgeting
• Accounting
• At least monthly, provide information at the • Analysis & Management
Reporting
Control Account Level necessary for analysis and • Revisions & Data Maintenance
reporting using actual cost data that is
reconcilable with the approved accounting system
• Provide variance reporting of Budget (BCWS), Earned Value (BCWP), and
Actual (ACWP)
The final category is Revisions and Data Industry Standard Earned Value
Management System
Maintenance. Within Revisions and Data
• Organization
Maintenance the criteria require the following: • Planning & Budgeting
• Accounting
• Analysis & Management Reporting
• Establish Change Management System • Revisions & Data Maintenance
In this and succeeding modules we will cover the criteria in the final two
categories: Analysis and Management Reporting, and Revisions and Data
Maintenance.
• Organization
• Planning & Budgeting
• Accounting
• Analysis & Management
Reporting
• Revisions & Data Maintenance
At this point, you should understand that Earned Value helps determine if your
project is on schedule and within budget. It does this by assessing the
project on the basis of cost and schedule as compared to what has been
accomplished.
Cost and Schedule baseline refers to the physical work scheduled and the
approved budget to accomplish the scheduled work. Together, they result
in an important value: Planned Value (PV). PV tells you what you plan to
do. Simply stated,
Current PV is the
approved budget for
Cumulative PV is the sum
activities scheduled to be
of the approved budget
performed during a given
for activities scheduled to
period. This period could
be performed to date.
represent days, weeks,
months,etc.
PV, also known as Budget Cost of Work Scheduled (BCWS), can be defined
as:
4. Budget Scope: develop cost (budget) for all approved scope (Performance
Measurement Baseline)
Based on these figures, we can calculate the cumulative PV and the current
PV.
The Cumulative PV is the total for the elapsed months: January – March. The
cumulative PV is $9,000.
The Current PV is the budget for the current month, March, and equals $3,000.
This example uses dollars as units of measure, but note that you can use any
unit of measurement: hours, days, dollars, etc.
Module 5 – EVMS Concepts and Methods 16
Prepared by: Booz Allen Hamilton
Budget at Completion (BAC)
So far we have discussed the cumulative budget and current budget, but what
about the budget at the end of the project? Earned Value also uses this
figure, termed Budget at Completion (BAC).
Let’s examine BAC using our previous example. Take a look on the next page.
Take a moment to review the Software Design project. Knowing that BAC is
the sum of all budgets allocated to a project, what is the BAC for this
project if Software Design is the complete scope of the project?
Yes, BAC = $15,000. And, in keeping with the previous points about BAC, the
project BAC equals the Project Total PV. The Earned Value calculations
are correct.
As you recall from earlier in the module, three key components are required to
determine the status of projects. So far, we have examined the first: Cost
and Schedule Baseline.
Now let’s turn our attention on the following pages to the second, Actual
Charges.
Actual Cost (AC), also called actual expenditures, is the cost incurred for
executing work on a project. This figure tells you what you have spent and,
as with Planned Value, can be looked at in terms of cumulative and current.
Illustrating again from the Client/Server project example, can you determine
the cumulative AC and current AC? Remember, Cumulative AC is the sum
of the actual cost for activities performed to date, and Current AC is the
actual costs of activities performed during a given period.
The Current AC is the actual cost for the current month, March, and equals
$1,200.
Module 5 – EVMS Concepts and Methods 21
Prepared by: Booz Allen Hamilton
EVMS Basic Concepts
So far, we have examined Cost and Schedule Baseline and Actual Changes.
Now let’s turn our attention on the following pages to the last of the three
components, Actual Charges.
To report the accomplishments of the project, you must apply Earned Value
(EV) to the figures and calculations in the project.
In other words, EV tells you, in physical terms, what the project has
accomplished. As with PV and AC, EV can be presented in a Cumulative
and Current fashion.
The Cumulative EV is the sum of the budget for the activities accomplished to
date: January – March. The cumulative EV is therefore $3,100.
The Current EV is the sum of the budget for the activities accomplished in the
current month, March, and equals $1,000.
Module 5 – EVMS Concepts and Methods 24
Prepared by: Booz Allen Hamilton
Earned Value (EV) example
Armed with a thorough picture of this project’s progress, let’s summarize the
findings we have.
At this point, you should have a solid understanding of the three key earned
value components. Let’s review them now.
• Actual Cost (AC) is determined by the actual cost incurred on the project
• Earned Value (EV) tells you, in physical terms, what the project
accomplished.
• Fixed Formula
• Milestone Weights
• Milestone Weights with % Complete
• Units Complete
• Percent Complete
• Level of Effort
50/50 - 50% is earned when activity starts and the balance is earned on
completion
25/75 - 25% is earned when activity starts and the balance is earned on
completion
Advantages: Works well for short term work packages, and requires minimal
effort to status.
Let’s use this example and see how Milestone Weighting is applied.
For this example, assume that all activities begin and complete as scheduled.
With this in mind, can you determined the earned value as of January 31th?
Time Now
As you can see by the schedule the project has started (1/7). The “Start
Inspection milestone” has been completed, but no value appears for that
milestone. The “Site Inspection Complete” milestone has also been
completed, and its value is 100. There are no more milestones completed
through January, so our Current EV is 100. Because it is the first month for
the control account, the Cumulative EV is also 100. Now lets look at what
has been earned through February.
Module 5 – EVMS Concepts and Methods 32
Prepared by: Booz Allen Hamilton
Earned Value (EV) Methods – Milestone Weighting
As you can see by looking at the schedule below, there are no milestones
scheduled for February (remember we assumed all activities will start and
complete as scheduled), but we have started the Phase 1 Design. What
are the Current EV and Cumulative EV as of February 28th?
Time Now
The Current EV is 0. Remember we can only take “earned” if milestone is
complete. Since there were no milestones scheduled for or accomplished
in February, we have earned no value under the milestone weighting
approach. The Cumulative EV is 100, which includes the 100 from January
and the 0 from February.
Lets take a look at one more month.
Module 5 – EVMS Concepts and Methods 33
Prepared by: Booz Allen Hamilton
Earned Value (EV) Methods – Milestone Weighting
Two milestones are scheduled for March. What is are Current EV and
Cumulative EV as of March 31th?
Time Now
Disadvantages: Does not allow partial credit for in-process work, and requires
detailed milestone planning.
We will now look at the third method for Earned Value Methods
determing EV: Milestone Weights with
Fixed Formula
Percent Complete.The Milestone
Milestone Weights
Weighting with Percent Complete method
Milestone Weights with % Complete
assigns budget value to each milestone, • Units Complete
and it is earned based on the percent of work • Percent Complete
Completed against each individual milestone. • Level of Effort
Like Milestone Weighting, Milestone Weighting
with Percent Complete is used as a method for
work packages with long term durations and ideally
should have milestones each month or
accounting period.
Take a look on the following pages at how using Milestone Weighting with
Percent Complete affects the Building Design example demonstrated
previously using simple Milestone Weighting.
Time Now
Time Now
Using the Building Design schedule, you can see that the Phase 1 Design is
nearly complete by the end of February. For example, lets say that at the
end of February the Phase 1 Design was determined to be 70% complete.
Now let’s take this information and determine the EV for February using the
Milestone Weighting with Percent Complete method and compare.
Time Now
Because it has been determined that you are 70% complete with Phase 1
Design, you can take credit for earning 105 of the 150 for completing
Phase 1 Design in February. See the chart below to compare the two
methods as of February 28th.
Milestone
As of February Milestone Weighting with
28th Weighting Percent
Complete
Current EV 0 105
Cumulative EV 100 205
Time Now
Module 5 – EVMS Concepts and Methods 40
Prepared by: Booz Allen Hamilton
Earned Value (EV) Methods – Milestone Weighting with Percent
Complete
Now let’s look at the Unit Complete method Earned Value Methods
of computing EV.The Unit Complete method
Fixed Formula
uses a physical count to determine what is
Milestone Weights
earned. To use Unit Complete you must have
Milestone Weights with % Complete
units that are identical or similar and they must Units Complete
have the same budget value. • Percent Complete
• Level of Effort
To examine the Unit Complete method, let’s
take a look at a different example on the next
page.
For this example, you must install a total of 40 mainframe computers over five
months. The number of units and the schedule to install them is listed
below. After the 1st month, you have installed 12 mainframes, which
means you are 30% complete with the total job. The earned value analysis
shows that the PV is 10 units($10,000), EV is 12 units($12,000) and the AC
is 12 units ($12,000).
Total Units = 40
If after the 1st month you install 12 main frames, you are 30% complete
PV EV AC
Units 10 12 12
Units ($) $10,000 $12,000 $12,000
Advantages: An objective and easy way of determining the earned value for
an activity.
Take a look on the next page at how Subjective Percent Complete is used.
To use the Subjective Percent Complete method, the value is placed on the
work activity, not the milestone (as in the Milestone Weighting method).
Using the Building Design Project from earlier, this becomes more clear.
Looking at the Site Inspection activity in the schedule below, the start date is
January 7th with a scheduled completion date of January 30th. Let’s status
the activity as of January 15th.
To determine the percent complete for January 15th, the control account
manager (CAM) must use an educated guess to determine the percent
complete of the activity. The CAM must maintain the logic for assessing
each activity’s percent complete.
In this example, the CAM decides that the activity is 45% complete as of
January 15th. Given this, the EV for Site Inspection as of January 15th is 45.
Note: Milestones do not apply to this method. Labor and non-labor must be
identified in separate work packages if this method is applied. This method
is highly subjective, and documentation in support of percent complete
derivations is required.
Time Now
Advantages: This EVM does not require statusing, and is appropriate for
sustaining tasks like Program Management.
At this point, you should have a firm grasp of the EV methods of calculation.
• Fixed Formula
• Milestone Weights
• Milestone Weights with % Complete
• Units Complete
• Percent Complete
• Level of Effort
Now that we are finished reviewing the EV methods, let’s take a look at our
ACME House Building project using the concepts discussed in this module.
Let’s recall, from previous modules, the project baseline (schedule and cost)
for the House Building project. The project start date is 1/15, with an
expected completion date of 4/1. It is now 1/31. The project started on
schedule and needs to be statused as of 1/31. Look at the schedule and
identify the activities that need to be reviewed for status.
Status as of 1/31
Status as of 1/31
Status as of 1/31
Now we need to determine our Earned Value (EV) for each activity. As we
discussed on the previous pages, there are numerous EV methods used
for measuring progress each method more applicable to certain types of
activities than other methods. For example we will use the following EV
methods for, the four activities we are statusing.
Activity EV Method
Pour Foundation Fixed Formula: 0/100
Install Patio Subjective % Complete
Frame Exterior Walls Subjective % Complete
Pour Stairway Fixed Formula: 25/75
Now that we understand what activities need statusing and what method of EV
will be used for each activity, it is time to status the project activities.
To obtain our project activity status, we will need to meet with the Project
Manager or those responsible for the work. In our case, we will need to
meet with the different CAMs or Project Superintendents responsible for
each Control Account. Below are the results of that meeting.
Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
Control Account Activity Start Finish Complete Completion
Concrete Pour Foundation 1/15 1/22 100%
Install Patio 1/23 1/30 100%
Pour Stairway 1/31 25% 2/1
The first activity is Pour Foundation. This activity was scheduled to start on
1/15 and finish on 1/22 (see schedule below). It’s actually started on 1/15
and finished on 1/22 (see status report below). Thus this activity was on
schedule and is 100% complete. What is its Planned Value (PV), Earned
Value (EV), and Actual Cost (AC)?
Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
Control Account Activity Start Finish Complete Completion
Concrete Pour Foundation 1/15 1/22 100%
Install Patio 1/23 1/30 100%
Pour Stairway 1/31 25% 2/1
The Earned Value (EV) is what was actually done as of 1/31. The activity is
100% complete and its EV is $15,394 (100% of PV). Remember you
cannot earn more then was planned. Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
The Actual Cost (AC) is what was Control Account
Concrete
Activity
Pour Foundation
Start
1/15
Finish
1/22
Complete
100%
Completion
obtained from the accounting Framing Frame Exterior Walls 1/23 40% 2/8
The next activity, Install Patio, is handled the same way as the previous
activity. It was completed on schedule and is 100% complete as of 1/31.
Its PV, EV and AC are as follows:
The next two activities are a little different because they are not 100% complete,
and they use two different methods of determining EV.
Let’s take a look at the activity, Frame Exterior Walls first. Check out this activity
on the next page.
The activity, Frame Exterior Walls, was schedule to start on 1/23 and finish
on 2/8. It started on 1/23 and is forecasted to complete on 2/8 (see
status report), thus the activity is on schedule. As of 1/31 the Project
Superintendent said the activity was 40% complete. Remember the EV
method used for this activity is Subjective % Complete. What is our PV,
EV and AC?
The Planned Value is $8,748. Let’s review how the planned value was
determined.
The cost of the activity, $16,521, will be divided by the total duration of the
activity, 17 days, to give us a value of $972 per day. Next we take the
planned start date (1/23) and the status date (1/31) to determine the
amount of days planned (9). Now let’s determine the Planned Value (PV).
The PV is determined by taking the amount of days (9) times the value per day
($972). Our PV is $8,748. Remember that there is a difference between
cumulative and current. For this example they are the same.
Monthly Status Meeting
January 31th, 2002
Actual Actual % Forecast
Now let’s take a look on the next Control Account
Concrete
Activity
Pour Foundation
Start
1/15
Finish
1/22
Complete
100%
Completion
The Earned Value for this activity is determined by taking the activity's total
value, $16,521, and multiplying it by the % complete. In this case, the %
complete is 40%. The EV for this activity, as of 1/31, is $6,608.
The Actual Cost (AC) as derived from the accounting system is $6,250.
The last activity is Pour Stairway. This activity was scheduled to start on 1/31
and finish on 2/1. It started on schedule on 1/31 and is forecasted to
complete on 2/1 (see status report), thus the activity is on schedule. Its EV
method is Fixed Formula 25/75, so its % complete is 25%. Using the
same processes discussed on the previous pages, what is the PV, EV and
AC for this activity?
AC = $3,100 (from accounting system) Framing Frame Exterior Walls 1/23 40% 2/8
The chart below lists the project status results as of 1/31. But what does this
information tell us?
as of 1/31 PV EV AC SV CV SPI CPI
Foundation $15,394 $15,394 $15,850 0 -456 1.00 0.97
Patio $8,166 $8,166 $7,200 0 966 1.00 1.13
Exterior Walls $8,748 $6,608 $6,250 -2,140 358 0.76 1.06
Stairway $5,961 $2,981 $3,100 -2,980 -119 0.50 0.96
Project Total $38,269 $33,149 $32,400 -5,120 749 0.87 1.02
Note: SV = Schedule Variance, CV = Cost Variance, SPI = Schedule Performance Index, CPI = Cost Performance Index
These questions and others will be answered in the next module, Module 6 –
Metrics, Performance Measures and Forecasting where the value of EVM
will become apparent.
Module 5 – EVMS Concepts and Methods 66
Prepared by: Booz Allen Hamilton
Estimate at Completion (EAC)
The Estimate at Completion (EAC) is the actual cost to date plus an objective
estimate of costs for remaining authorized work. The objective in preparing
an EAC is to provide an accurate projection of cost at the completion of the
project. There are multiple ways and varying degrees of detail to calculate
EAC, and they will be covered in a future module. The most common is:
• There are three key components to earned value: Planned Value, Earned
Value and Actual Cost.
– PV (BCWS) is the physical work scheduled or “what you plan to do”.
– EV (BCWP) is the quantification of the “worth” of the work done to date
or “what you physically accomplished”.
– AC (ACWP) is the cost incurred for executing work on a project or “what
you have spent”.
Prepared by:
Module 6: Metrics, Performance Measurements and Forecasting
Let’s quickly review what has been covered in the previous modules.
• There are three key components to earned value: Planned Value, Earned
Value and Actual Cost.
– PV is the physical work scheduled or “what you plan to do”.
– EV is the quantification of the “worth” of the work done to date or “what
you physically accomplished”.
– AC is the cost incurred for executing work on a project or “what you
have spent”.
The next step is to stand back and monitor the progress against the
Performance Measurement Baseline (PMB).
To answer this question, consider the ACME House Building project. You
have two major stakeholders on this project, the Buyer and the Builder. Do
you think they both measure success on the project identically or do you
believe their definition of project success may be different? Let’s take a look
on the next page.
It seems logical to say that they both want a home that provides security,
meets building code, and keeps them warm in the winter and cool in the
summer. Now let’s look at possible differences in the way they define
successful performance on the project.
Buyer Builder
Can you see how different parties or individuals can have conflicting views of
what defines project success?
Module 6 – Metrics, Performance Measures and Forecasting 5
Prepared by: Booz Allen Hamilton
What is Performance Measurement?
The Stakeholders (Buyer and Builder in the ACME House Building Project)
should understand how each party defines project success and what each
party measures to determine that success.
The Cost Management focuses on the cost performance of the project. It looks
at the relationships between the Earned Value (EV) and the Actual Cost
(AC).
Now let’s look at these relationships in more detail on the following pages.
Variance Analyses
Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC)
Performance Indices
Cost Performance Index = Earned Value (EV)/Actual Cost (AC)
The Cost Variance (CV) is the difference between the earned value of work
performed and the actual cost. CV tells you the earned value of work
performed for each dollar’s worth of work scheduled.
Using the ACME Home Building project information from Module 5, let's
calculate the Cost Variance (CV) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250
Stairway $5,961 $2,981 $3,100 Cost
Project Total $38,269 $33,149 $32,400
CV = EV – AC
Cost
CV = $33,149 - $ 32,400 Variance
CV = $749
A Cost Variance of $749 tells you that the project is “Underrun” or under
budget.
Please note that the cost variance, along with all other performance analyses
tools, can be computed (or assessed) in terms of cumulative and current.
Since we are in the first status period in our example, the cumulative and
current are the same.
Cost
The Schedule Variance (SV) is the difference between the earned value of
work performed and the work scheduled. SV tells you the value of work
performed less value of work scheduled.
Using the ACME Home Building project information from Module 5, let's
calculate the Schedule Variance (SV) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250
Stairway $5,961 $2,981 $3,100 Cost
Project Total $38,269 $33,149 $32,400
Schedule
Variance
SV = EV – PV
SV = $33,149 - $38,269
SV = -$5,120
You should have a solid understanding of the cost and schedule variance
calculations and what they mean. Let's review them now.
as of 1/31 PV EV AC SV CV
Foundation $15,394 $15,394 $15,850 0 -456
Patio $8,166 $8,166 $7,200 0 966
Exterior Walls $8,748 $6,608 $6,250 -2,140 358
Stairway $5,961 $2,981 $3,100 -2,980 -119
Project Total $38,269 $33,149 $32,400 -5,120 749
Example 1: Example 2:
PV = $950 PV = $1100
EV = $1000 EV = $1000
AC = $ 900 AC = $1200
Using the ACME Home Building project information, let's calculate the Cost
Performance Index (CPI) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250
Stairway $5,961 $2,981 $3,100 Cost
Project Total $38,269 $33,149 $32,400
CPI = EV/AC
CPI= $33,149/$32,400
CPI = 1.02
A Cost Performance Index (CPI) of 1.02 tells you that your actual costs are
less then what was budgeted.
You are getting $1.02 worth of work for every $1.00 spent.
1.2
1.15
1.1
1.05
CPI1.02
1
0.9
0.85
0.8
Now let's look at some causes of favorable and unfavorable cost performance.
Example 1: Example 2:
PV = $950 PV = $1100
EV = $1000 EV = $1000
AC = $ 900 AC = $1200
Using the ACME Home Building project information, let's calculate the
Schedule Performance Index (SPI) for the project.
as of 1/31 PV EV AC
Foundation $15,394 $15,394 $15,850
Patio $8,166 $8,166 $7,200
Exterior Walls $8,748 $6,608 $6,250
Stairway $5,961 $2,981 $3,100 Cost
Project Total $38,269 $33,149 $32,400
SPI = EV/PV
SPI = $33,149/$38,269
SPI = .87
A Schedule Performance Index (SPI) of .87 tells you that you are behind
schedule. It can be defined in two ways:
1.2
1.15
1.1
1.05
CPI 1.02
1
0.9
SPI 0.87
0.85
0.8
The ACME Home Building Project is 13% behind schedule (SPI = .87) but is
ahead on cost by 2% (CPI = 1.02). In review of the activities, Installation of
the Stairway and Framing the Exterior Walls are the activity causing the
project to be behind (SPI = .50 and .76) schedule. On the cost side, the
Installation of the Patio is costing less then budgeted (CV =$966) and is the
main reason for the project underrunning its budget.
What is the standard reporting variance threshold for a project? Find out on the
next page.
So far we have only looked at how to analyze what has happened on a project
(CV,SV, CPI, SPI). Take some time to review the formulas below.
Tells you what percentage cost varies Tells you what percentage schedule varies from
from what has been earned to date. what has been planned to date.
Cost Performance Index (CPI) = EV/AC Schedule Performance Index (SPI) = EV/PV
If result is less than 1.0, cost is If result is less than 1.0, project is
GREATER than budgeted “BEHIND” schedule
If the result greater than 1.0, cost is If the result greater than 1.0, project is
LESS than budgeted “AHEAD of schedule
Now it is time to learn how to analyze the future or what is expected to happen
on a project given the progress measurements reported to date. Anticipating
future progress requires determining when the project will be completed and
how much it will cost to complete it.
To complete our analysis, we will look at the Estimate at Completion (EAC) and
the Budget at Completion (BAC).
The chart on the following page lists the parameters of the BAC and EAC along
with the other EVM items we have covered.
Module 6 – Metrics, Performance Measures and Forecasting 30
Prepared by: Booz Allen Hamilton
Estimate at Completion
Item Questions
Planned Value (PV) How much work should be done?
Earned Value (EV) How much work was done?
Actual Cost (AC) How much did the work cost?
Budget at Completion (BAC) What is the total job budgeted to cost?
Estimate at Completion (EAC) What do we expect the total job to cost?
Another term you may hear is Latest Revised Estimate (LRE). The LRE is
equal to the EAC.
The EAC is the best estimate of the total cost at the completion of the project.
The EAC is a periodic evaluation of the project status, usually on a monthly
basis or when a significant change happens to the project.
EACs are developed with varying degrees of detail and supporting documents.
A comprehensive EAC is usually prepared annually or if there are any major
changes in the project. The EAC should be reviewed on a monthly basis by
the Control Account Manager (CAM) or those responsible. The EAC is
developed for projects as well as Control Accounts and Work Packages.
There are multiple ways to develop an EAC. The technique selected is
based upon the dollar value of the project, the risk, accounting system
available and the accuracy of the estimates.
Let's take a look on the following pages at the most frequently used EAC
formulas.
Now let's look use the EAC formula for our ACME Home Building project. Take
a look on the next page.
Earlier in this module, we determined the actual cost (AC) for January to be
$32,400. Now we need to determine the Estimate to Complete (ETC) for all
activities. For the two activities that are 100% complete, their actual cost
replaces their ETC (see chart below). For the two activities current being
worked, we will assume that they will be completed as budgeted even though
they have current cost variances (see ETC adjustments below). It will also be
assumed that all other activities will have no adjustments to their ETC.
ACTUALS ETC EAC
By reviewing the Activity January February March April Total
1.1.1.1 Pour foundation $15,850 $15,850
chart to the left you 1.1.1.2 Install Patio
1.1.1.3 Pour stairway
$7,200
$3,100 $8,822
$7,200
$11,922
can see that our 1.1.2.1 Frame exterior walls $6,250 $10,271 $16,521
1.1.2.2 Frame interior walls $11,025 $11,025
new Estimate at 1.1.2.3 Install roofing trusse $15,887 $15,887
1.1.3.1 Install waterlines $6,194 $6,194
Completion (EAC) 1.1.3.2 Install gas lines $6,255 $6,255
1.1.3.3 Install B/K fixtures $6,317 $6,317
is $164,957. 1.1.4.1 Install wiring $18,483 $18,483
1.1.4.2 Install outlets/switches $9,265 $9,265
1.1.4.3 Install fixtures $13,969 $4,656 $18,625
1.1.5.1 Install drywall $6,984 $6,984
Now lets look at the 1.1.5.2 Install Carpeting $2,250 $2,250
same example with 1.1.5.3 Painting
1.1.6.1 Install felt $1,834
$6,477
$611
$6,477
$2,445
some additional 1.1.6.2 Install shingles
1.1.6.3 Install vents
$2,445
$812
$2,445
$812
changes to the $32,400 $85,088 $42,813 $4,656 $164,957
As the project manager you are reviewing your ETC and you get a call from the
carpeting contractor. He tells you that the original budget for installing the
carpet ($2,250) is no longer correct because the price of the carpet
increased. The project manager asks for a new estimate and the carpeting
contractor tells him that it will now cost $3,100. Additionally, your
superintendent tells you that the current ETCs for Framing the Exterior Walls
and Pour Stairway are good, thus the current cost underrun ($358) for
Framing and the cost overrun ($120) for Stairway will be realized at the
completion of each activity.
When using this formula to calculate EAC, you can also include expert opinion,
project and industry trends and other forms of objective analysis.
ACTUALS ETC EAC
Activity January February March April Total
1.1.1.1 Pour foundation $15,850 $15,850
1.1.1.2 Install Patio $7,200 $7,200
1.1.1.3 Pour stairway $3,100 $8,942 $12,042
1.1.2.1 Frame exterior walls $6,250 $9,913 $16,163
1.1.2.2 Frame interior walls $11,025 $11,025
1.1.2.3 Install roofing trusse $15,887 $15,887
1.1.3.1 Install waterlines $6,194 $6,194
1.1.3.2 Install gas lines $6,255 $6,255
1.1.3.3 Install B/K fixtures $6,317 $6,317
1.1.4.1 Install wiring $18,483 $18,483
1.1.4.2 Install outlets/switches $9,265 $9,265
1.1.4.3 Install fixtures $13,969 $4,656 $18,625
1.1.5.1 Install drywall $6,984 $6,984
1.1.5.2 Install Carpeting $3,100 $3,100
1.1.5.3 Painting $6,477 $6,477
1.1.6.1 Install felt $1,834 $611 $2,445
1.1.6.2 Install shingles $2,445 $2,445
1.1.6.3 Install vents $812 $812
$32,400 $84,850 $43,663 $4,656 $165,569
Module 6 – Metrics, Performance Measures and Forecasting 36
Prepared by: Booz Allen Hamilton
Calculating Estimate at Completion
As mentioned earlier, EAC is the best estimate of the total cost at the
completion of the project. It is also used to determine the Variance at
Completion (VAC) for the project. The VAC is calculated as follows:
Now let's determine the VAC for our project as shown on the next page.
In other words, the project is now forecasted to overrun by $102 using this form
of EAC. Remember, this is only one method of forecasting the performance
of the project. Several other methods can be used. Let’s consider those on
the following pages.
This calculation uses the Actual cost, Earned value and Budget at Completion
for the project.
This formula is the easiest to use, but it assumes that the “burn-rate” will be the
same for the remainder of the project.
Let's use our ACME Home Building project to calculate the EAC using this
formula. Take a look on the next page.
as of 1/31 PV EV AC BAC
VAC = BAC – EAC Foundation $15,394 $15,394 $15,850 $15,394
Patio $8,166 $8,166 $7,200 $8,166
VAC = $165,467 - $162,158 Frame exterior Walls $8,748 $6,608 $6,250 $16,521
VAC = 3,309 Stairway $5,961 $2,981 $3,100 $11,922
Frame interior walls $0 $0 $0 $11,025
Install roofing trusse $0 $0 $0 $15,887
Using this EAC calculation, our Install waterlines $0 $0 $0 $6,194
Install gas lines $0 $0 $0 $6,255
project is projected to underrun by Install B/K fixtures $0 $0 $0 $6,317
$3,309. Install wiring $0 $0 $0 $18,483
Install outlets/switches $0 $0 $0 $9,265
Install fixtures $0 $0 $0 $18,625
Now let's look at the next EAC Install felt $0 $0 $0 $2,445
Install shingles $0 $0 $0 $2,445
formula on the next page. Install vents $0 $0 $0 $815
Install drywall $0 $0 $0 $6,984
Painting $0 $0 $0 $6,477
Install Carpeting $0 $0 $0 $2,250
$38,269 $33,149 $32,400 $165,467
Module 6 – Metrics, Performance Measures and Forecasting 40
Prepared by: Booz Allen Hamilton
Calculating Estimate at Completion
EAC = BAC/CPI
This calculation uses the Budget at Completion (BAC) and the Cost
Performance (CPI) Index to calculate EAC.
This formula is also easy to use and assumes that the “burn-rate” remains
constant for the remainder of the project.
This formula is derived from the previous formula and thus should result in the
same EAC figure. Note that with this formula you need additional information
than the previous formula.
Let's use our ACME Home Building project and calculate the EAC using this
formula. Take a look on the next page.
EAC = BAC/CPI
EAC = $165,467/1.02 as of 1/31 PV EV AC SV CV SPI CPI
Foundation $15,394 $15,394 $15,850 0 -456 1.00 0.97
EAC = $162,222 Patio $8,166 $8,166 $7,200 0 966 1.00 1.13
Exterior Walls $8,748 $6,608 $6,250 -2,140 358 0.76 1.06
Stairway $5,961 $2,981 $3,100 -2,980 -119 0.50 0.96
Project Total $38,269 $33,149 $32,400 -5,120 749 0.87 1.02
VAC = BAC – EAC
as of 1/31 PV EV AC BAC
VAC = $165,467 - $162,222 Foundation $15,394 $15,394 $15,850 $15,394
VAC = 3,245 Patio $8,166 $8,166 $7,200 $8,166
Frame exterior Walls $8,748 $6,608 $6,250 $16,521
Stairway $5,961 $2,981 $3,100 $11,922
Using this EAC calculation, our Frame interior walls $0 $0 $0 $11,025
project is projected to underrun by Install roofing trusse $0 $0 $0 $15,887
$3,245. Install waterlines $0 $0 $0 $6,194
Install gas lines $0 $0 $0 $6,255
Install B/K fixtures $0 $0 $0 $6,317
Why is this answer different then the Install wiring $0 $0 $0 $18,483
previous calculation when it was Install outlets/switches $0 $0 $0 $9,265
Install fixtures $0 $0 $0 $18,625
mentioned that the two formulas Install felt $0 $0 $0 $2,445
are derived from each other? Install shingles $0 $0 $0 $2,445
Install vents $0 $0 $0 $815
Install drywall $0 $0 $0 $6,984
Rounding to the second decimal is Painting $0 $0 $0 $6,477
the reason for the $64 difference. Install Carpeting $0 $0 $0 $2,250
$38,269 $33,149 $32,400 $165,467
This formula assumes that the work not yet begun will be completed as
planned.
Let's use our ACME Home Building project and calculate the EAC using this
formula. Take a look on the next page.
[Work Completed
EAC = AC/EV x and in Progress]
+ [Cost of work not yet begun]
You need the chart to the left to
determine the first part of the
formula (actual cost and earned as of 1/31 PV EV AC BAC
value). Foundation $15,394 $15,394 $15,850 $15,394
Patio $8,166 $8,166 $7,200 $8,166
Frame exterior Walls $8,748 $6,608 $6,250 $16,521
AC/EV = $32,400/$33,149 Stairway $5,961 $2,981 $3,100 $11,922
Frame interior walls $0 $0 $0 $11,025
AC/EV = .98 Install roofing trusse $0 $0 $0 $15,887
Install waterlines $0 $0 $0 $6,194
Install gas lines $0 $0 $0 $6,255
To obtain the remaining two parts, Install B/K fixtures $0 $0 $0 $6,317
you will also need to use the chart, Install wiring $0 $0 $0 $18,483
Install outlets/switches $0 $0 $0 $9,265
but some calculations will be Install fixtures $0 $0 $0 $18,625
needed. Install felt $0 $0 $0 $2,445
Install shingles $0 $0 $0 $2,445
Install vents $0 $0 $0 $815
Let's take a look on the next page at Install drywall $0 $0 $0 $6,984
Painting $0 $0 $0 $6,477
the final two part of this formula. Install Carpeting $0 $0 $0 $2,250
$38,269 $33,149 $32,400 $165,467
[Work Completed
EAC = AC/EV x and in Progress]
+ [Cost of work not yet begun]
The project has 4 activities that are
completed and in progress
(Foundation, Patio, Frame exterior as of 1/31 PV EV AC BAC
Foundation $15,394 $15,394 $15,850 $15,394
walls and stairway). The value of Patio $8,166 $8,166 $7,200 $8,166
these activities is obtained by Frame exterior Walls $8,748 $6,608 $6,250 $16,521
using the BAC column. The total Stairway $5,961 $2,981 $3,100 $11,922
Frame interior walls $0 $0 $0 $11,025
for Work Completed and in Install roofing trusse $0 $0 $0 $15,887
Progress is $52,003. Install waterlines $0 $0 $0 $6,194
Install gas lines $0 $0 $0 $6,255
Install B/K fixtures $0 $0 $0 $6,317
The final part is the cost of work not Install wiring $0 $0 $0 $18,483
yet begun. The value for this Install outlets/switches $0 $0 $0 $9,265
section is the sum of the activities Install fixtures $0 $0 $0 $18,625
Install felt $0 $0 $0 $2,445
not yet begun. The total Cost of Install shingles $0 $0 $0 $2,445
work not yet begun is $113,464. Install vents $0 $0 $0 $815
Install drywall $0 $0 $0 $6,984
Painting $0 $0 $0 $6,477
Now let's calculate our EAC. Check Install Carpeting $0 $0 $0 $2,250
it out on the next page. $38,269 $33,149 $32,400 $165,467
[Work Completed
EAC = AC/EV x and in Progress]
+ [Cost of work not yet begun]
EAC = (.98 x $52,003) + $113,464
EAC = $164,427
Now let's look on the next page at our final EAC formula.
This calculation uses the Actual Cost (AC) Budget at Completion (BAC),
Earned Value (EV) and the Cost Performance (CPI) Index to calculate EAC.
Let's use our ACME Home Building project and calculate the EAC using this
formula. Check it out on the next page.
The outcomes of the various methods for computing EAC are shown in the
table below:
EAC Formula EAC VAC
EAC = AC + ETC $165,569 -$102
EAC = AC/EV x BAC $162,158 $3,309
EAC = BAC/CPI $162,222 $3,245
[Work Completed [Cost of work
EAC = AC/EV x and in Progress]
+ not yet begun] $164,427 $1,040
EAC = AC + [1/CPI (BAC-EV)] $162,073 $3,394
In reviewing the EAC formulas, be aware that the formula you use impacts
your project’s EAC. Though all the EAC calculations are correct, choosing
the appropriate formula for your project is important. The EAC formula you
choose should be determined by the specifics of the project.
If you need to review these techniques, please pay close attention to the
assumptions of each.
At this point, you have covered all of the content in Module 6. Take some time
now to review the major items:
• There are multiple methods for determining EAC. Each project needs to be
evaluated to determine which EAC formula best fits the project’s size and
complexity.
At this point we have examined the basic metrics and performance measures
used in EVMS. In the next module you will examine the concepts of
Integrated Baseline Review (IBR), Rebaselining, and Change Control.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics metrics and performance measures
used in EVMS.
Prepared by:
Module 7: Integrated Baseline Review and Change Control
To review some critical terminology and define the framework within which
IBRs are conducted, let’s look back at the previous six modules.
Now let’s discuss the Integrated Baseline Review (IBR), followed by the
Change Control Process.
Because the IBR uses the technical content of the Performance Measurement
Baseline (PMB), it’s important that you have a solid understanding of the
PMB.
Remember the discussion on PMB from Module 4? Let’s quickly review. The
Performance Measurement Baseline (PMB) is the time-phased budget plan
against which contract performance is measured.
Now that we’ve reviewed the PMB and defined the purpose of an IBR, let’s
discuss when an IBR is conducted.
The initial Integrated Baseline Review is typically conducted within six months
after contract award. Integrated Baseline Reviews will also be performed
when work on a production option of a development contract begins or, at
the discretion of the program manager, when a major modification to an
existing contract significantly changes the existing PMB.
When a major event occurs within the life of a program such as a Critical
Design Review (CDR), and a significant shift in the content and/or time-
phasing of the PMB occurs, the Program Manager may conduct a review of
the associated resources and schedules affected by the changes.
Now let’s review the specific IBR objectives, on the next page.
• Ensure that the technical content of Control Account, Work Packages, and
Planning Packages is consistent with the Contract Work Breakdown
Structure (CWBS) and the Contract Statement of Work (SOW)
• Establish a forum through which the government program manager and the
program technical staff gain a sense of ownership of the cost/schedule
management process
Now that we’ve reviewed the IBR objectives, let’s review some of the key
documents required at an IBR. Check these out on the next page.
Module 7 – Integrated Baseline Review and Change Control 8
Prepared by: Booz Allen Hamilton
Integrated Baseline Review (IBR) Checklist
Now that we’ve discussed the key objectives for conducting an IBR and
reviewed the IBR Checklist, let’s review the responsibilities.
The Program Office Technical Team assesses the PMB and identifies risk
areas. The Control Account Managers are responsible for the integrity and
compliance of their Control Accounts/Work Packages.
• The IBR is conducted within six months of the award of a new contract or as
required due to a major change to an existing contract.
• The responsibility for conducting the IBR lies with the Program Manager
and the Program Office Technical Staff.
Now that we’ve discussed the Integrated Baseline Review Process, let’s
discuss what happens when there are changes made to the PMB and the
Change Control Process used to track baseline changes. Take some time
to review this on the following pages.
What types of baseline changes are subject to the change control process? Are
all changes subject to it? Let’s discuss types of baseline changes that would
be subject to the change control process.
We will examine each of these in more detail on the following pages, but first,
take a look on the next page at the types of documentation that must be
completed for these changes.
At this point, you have covered all of the content in Module 7. Take some time
now to review the major items:
At this point we have examined the basic metrics and performance measures
used in EVMS. In the next module you will examine EVMS Reporting.
If you have a firm grasp of the concepts covered in this module, feel free to
progress to the next module. Otherwise, review this module to ensure you
have a solid understanding of the basics metrics and performance
measures used in EVMS.
Prepared by:
Module 8: Government Required Reports
Module 8 – Reporting 1
Prepared by: Booz Allen Hamilton
Review of Previous Modules
Module 8 – Reporting 2
Prepared by: Booz Allen Hamilton
Review of Previous Modules
Now let’s look at the Government reporting requirements for earned value.
Module 8 – Reporting 3
Prepared by: Booz Allen Hamilton
Government Reporting Requirements
There are several reports which may be used for Earned Value Management
Reporting and Analysis.
Module 8 – Reporting 4
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR)
The Cost Performance Report (CPR) is the most comprehensive of the EVMS
reports. It is normally a monthly report and has five different formats.
Generally, all five formats are applied to a contract requiring EVMS. However,
the customer may not require all the reports and may delete one or more.
Most customers will require at least the CPR Format 1 (WBS) and Format 5
(Variance Analysis Report).
Module 8 – Reporting 5
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR)
All Performance Measurement data reported in the CPR are derived from the
formal Earned Value Management System (EVMS).
All reported changes to the project baseline, management reserve (MR) and
contingency should be traceable through the formal Earned Value
Management System (EVMS) and CPR reports.
On the following pages, we will look at examples of the five CPR reports using
the ACME House Building Project.
Module 8 – Reporting 6
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) - Example
First let’s quickly review the projects current status that will be used in the
example reports.
ACME Home Building Project
Project Start date: January 15th as of 1/31 PV EV AC SV CV SPI CPI
Foundation $15,394 $15,394 $15,850 0 -456 1.00 0.97
Patio $8,166 $8,166 $7,200 0 966 1.00 1.13
Status Date: January 31th Exterior Walls $8,748 $6,608 $6,250 -2,140 358 0.76 1.06
Stairway $5,961 $2,981 $3,100 -2,980 -119 0.50 0.96
Project Total $38,269 $33,149 $32,400 -5,120 749 0.87 1.02
Module 8 – Reporting 7
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 1 - WBS
This report also contains data about budget, price, Management Reserve (MR),
Undistributed Budget (UB), and MEAC cases.
A copy of the CPR Format 1 for the ACME Home Building project is on the
following page. Please review the entire report but pay close attention to
the lower section (highlighted red) of the report. This is the Performance
data section that contains the current and cumulative cost and schedule
information for the project.
Module 8 – Reporting 8
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 1 - WBS
1.1.1 Concrete 9,670 8,757 26,150 -912 -17,393 9,670 8,757 26,150 -912 -17,393 11,485 28,873 -17,388
1.1.2 Framing 7,089 5,355 6,250 -1,734 -895 7,089 5,355 6,250 -1,734 -895 27,147 28,041 -893
Module 8 – Reporting 9
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 2 – Organizational
Categories
This report also contains data about budget, price, Management Reserve (MR),
Undistributed Budget (UB), and MEAC cases.
The reporting details in CPR Format 2 are the same as on the CPR Format 1
accept that it is structured by organization.
A copy of the CPR Format 2 for the ACME Home Building project is on
following page. Please review the entire report but pay close attention to
the lower section (highlighted red) of the report. This is the Performance
data section that contains the current and cumulative cost and schedule
information for the project.
Module 8 – Reporting 10
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 2 – Organizational
Categories
Management
Project Management 7,503 5,668 6,250 -1,835 -582 7,503 5,668 6,250 -1,835 -582 19,475 20,057 -582
SubCont
Subcontractor Mgmt 13,203 13,203 15,850 0 -2,647 13,203 13,203 15,850 0 -2,647 36,272 38,919 -2,647
SUBTOTAL 32,821 28,430 32,400 -4,391 -3,970 32,821 28,430 32,400 -4,391 -3,970 72,973 76,941 -3,969
b. COST OF MONEY 19 17 0 -3 17 19 17 0 -3 17 82 65 17
c. GEN & ADMIN 5,429 4,702 0 -726 4,702 5,429 4,702 0 -726 4,702 23,237 18,537 4,700
d. UNDISTRIBUTED BUDGET 0 0 0
e. SUBTOTAL (PM Baseline) 38,269 33,149 32,400 -5,120 749 38,269 33,149 32,400 -5,120 749 165,467 165,569 -102
f. MANAGEMENT RESERVE 18385
g. TOTAL 38,269 33,149 32,400 -5,120 749 38,269 33,149 32,400 -5,120 749 183,852
6. RECONCILIATION TO CONTRACT BUDGET BASE
a. VARIANCE ADJUSTMENT 0 0
b. TOTAL CONTR VARIANCE 0 0 0 0 0
Module 8 – Reporting 11
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 3 – Baseline
c. PM BASELINE
(END OF PERIOD) 38 73 49 5 0 0 0 0 0 0 0 0 0 165
7. MANAGEMENT RESERVE 18
8. TOTAL 184
Module 8 – Reporting 12
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 4 – Staffing
The Cost Performance Report (CPR) Format 4 displays a forecast of hours and
person-months by Organization (Performing/Responsible), and contains
header data showing schedule dates for the contract and the project. This
report also contains program variance thresholds for month, cumulative, and
at-complete percents and values.
COST PERFORMANCE REPORT Form Approved
FORMAT 4 - STAFFING OMB No. 0704-0188
1. CONTRACTOR 2. CONTRACT 3. PROGRAM 4. REPORT PERIOD
a. NAME: ACME Construction a. NAME: ACME Housing a. NAME: ACME Housing a. FROM: 01-JAN-02
b. LOCATION: Denver, CO b. NUMBER: ACME - 1000 b. PHASE (X one) b. TO: 31-JAN-02
c. TYPE: FFP [ ] RDT&E [X] PRODUCTION
d. SHARE RATIO:
5. PERFORMANCE DATA FORECAST (NON - CUMULATIVE)
ACTUAL
END OF SIX MONTH FORECAST BY MONTH
ORGANIZATIONAL ACTUAL CURRENT
CATEGORY CURRENT PERIOD +1 +2 +3 +4 +5 +6 AT
PERIOD (CUM) FEB02 MAR02 APR02 MAY02 JUN02 JUL02 AUG02 SEP02 OCT02 NOV02 DEC02 COMPL
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14) (15)
Construction
Hours 0 0 121 0 0 0 0 0 0 0 0 0 0 343
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 2
Project Management
Hours 0 0 134 0 0 0 0 0 0 0 0 0 0 134
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 1
Subcontractor Mgmt
Hours 0 0 138 0 0 0 0 0 0 0 0 0 0 305
Man Months 0 0 1 0 0 0 0 0 0 0 0 0 0 2
6. TOTAL DIRECT
Hours 0 0 393 0 0 0 0 0 0 0 0 0 0 781
Man Months 0 0 2 0 0 0 0 0 0 0 0 0 0 5
Module 8 – Reporting 13
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 5 – Variance Analyses
Report
The variance reporting thresholds are pre-determined prior to the start of the
program. Explanations and problem analysis reporting is only required for
those variances that breech the pre-set threshold(s). The report will
indicate those variances needing explanation.
Module 8 – Reporting 14
Prepared by: Booz Allen Hamilton
Cost Performance Report (CPR) Format 5 – Variance Analyses
Report
TASK/PROJECT IMPACT:
Task/Project Impact:
Framing the exterior walls will be completed on schedule and no delay will occur to the project complete.
This section is used to explain the impact
to the Control Account and overall
Project.
CORRECTIVE ACTION PLAN:
The current skill mix will be adjusted to complete this activity as scheduled. The ACME project
Corrective Action Plan:
management team is conducting a review of all future work to determine if resource availability will an issue.
This section provides the recovery and
risk mitigation plan.
Preparer: Dept: Initials: Date:
Module 8 – Reporting 15
Prepared by: Booz Allen Hamilton
Cost/Schedule Summary Report (C/SSR)
The final standard EVMS report we will review is the Cost/Schedule Summary
Report (C/SSR).
This report includes cumulative and at complete summaries for each WBS
element, and contains header data showing contractor and contract
information, and MEAC calculations.
This report also contains data about contract price, budget, Management
Reserve (MR), Undistributed Budget (UB), and MEAC cases.
It is very similar to the CPR Format 1 except that the C/SSR has only
cumulative information.
A copy of the C/SSR for the ACME Home Building project in on the following
page.
Module 8 – Reporting 16
Prepared by: Booz Allen Hamilton
Cost/Schedule Summary Report (C/SSR)
6. CONTRACT DATA
a. ORIGINAL CONTRACT TARGET COST b. NEGOTIATED CONTRACT CHANGES c. CURRENT TARGET COST (A + B) d. EST COST OF AUTH UNPR WORK
$0 $0 $0 $0
e. CONTRACT BUDGET BASE (C + D) f. MGMT ESTIMATE AT COMPLETION g. VARIANCE AT COMPLETE (E - F) h. OVER TARGET BASELINE DATE
$0 $0 $0 01-JAN-02
7. PERFORMANCE DATA CUMULATIVE TO DATE AT COMPLETION
BUDGETED COST ACTUAL VARIANCE
ITEM COST
WORK WORK WORK
SCHEDULED PERFORMED PERFORMED SCHEDULED COST BUDGET ESTIMATE VARIANCE
(1) (2) (3) (4) (5) (6) (7) (8) (9)
1.1.1 Concrete 9,670 8,757 26,150 -912 -17,393 11,485 28,873 -17,388
1.1.2 Framing 7,089 5,355 6,250 -1,734 -895 27,147 28,041 -893
Module 8 – Reporting 17
Prepared by: Booz Allen Hamilton
Review Module 8
At this point, you have covered all of the content in Module 8. Take some time
now to review the major items:
Module 8 – Reporting 18
Prepared by: Booz Allen Hamilton
Summary of Module 8
If you have a firm grasp of the concepts covered in this module, along with all
provide modules, you have completed the EVMS tutorial. Otherwise, review
this or any other module to ensure you have a solid understanding of the
Earned Value Management.
Module 8 – Reporting 19
Prepared by: Booz Allen Hamilton