Professional Documents
Culture Documents
Telecommunications
Engineering Standard
ESM 102
COMMUNICATION OUTDOOR
CABLING STANDARD
Version 2.0
Disclaimer
This document was prepared for use on the RailCorp Network only.
RailCorp makes no warranties, express or implied, that compliance with the contents of this document shall be
sufficient to ensure safe systems or work or operation. It is the document user’s sole responsibility to ensure that the
copy of the document it is viewing is the current version of the document as in use by RailCorp.
RailCorp accepts no liability whatsoever in relation to the use of this document by any party, and RailCorp excludes
any liability which arises in any manner by the use of this document.
Copyright
The information in this document is protected by Copyright and no part of this document may be reproduced, altered,
stored or transmitted by any person without the prior consent of RailCorp.
Document control
Version Date Summary of change
1.0 September 2007 First issue
2.0 July 2011 Application of TMA 400 format. Changes as noted in
summary of change table below.
© RailCorp Page 2 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
Contents
1 Introduction .............................................................................................................................5
2 Scope and application ............................................................................................................5
3 References...............................................................................................................................5
3.1 Australian standards .................................................................................................................5
3.2 International standards..............................................................................................................6
3.3 RailCorp documents..................................................................................................................6
3.4 RailCorp drawings.....................................................................................................................6
4 Terms and definitions.............................................................................................................7
5 Cables and cabling works - general......................................................................................7
5.1 Cables .......................................................................................................................................8
5.2 Composite cables......................................................................................................................8
5.3 Optic fibre cable ........................................................................................................................8
5.3.1 SMOF fibre specification............................................................................................8
5.3.2 Optical fibre cable construction .................................................................................8
5.3.3 Optical fibre cables sizes ...........................................................................................8
5.4 Copper communications cable..................................................................................................9
5.4.1 Copper cable (outdoor)..............................................................................................9
5.4.2 Fire safe copper cable (for tunnels)...........................................................................9
5.4.3 Cable identification codes........................................................................................10
6 Cable route – general............................................................................................................10
6.1 Compliance to SPG 0705........................................................................................................10
6.2 Cable route life span ...............................................................................................................10
6.3 Cable route construction types ...............................................................................................10
6.4 GLT .........................................................................................................................................10
6.5 Tracing of cable route location................................................................................................11
6.6 Aerial cable .............................................................................................................................11
6.7 Separation from other services ...............................................................................................11
6.7.1 Separation from HV - additional requirements ........................................................11
6.8 Diverse cable routes ...............................................................................................................12
6.8.1 Diversity via different rail line (ring diversity) ...........................................................12
6.8.2 Diversity via path off the rail corridor .......................................................................12
6.8.3 Diversity provided by parallel pit and pipe, GST troughing etc................................12
6.8.4 Aerial routes as diverse cable routes ......................................................................12
6.8.5 HV Power Cables route as diverse cable route.......................................................12
6.8.6 Signal cable route as diverse cable route................................................................12
6.9 Hazardous locations................................................................................................................13
6.9.1 Catch points.............................................................................................................13
6.9.2 High voltage locations..............................................................................................13
6.9.3 Construction rules for Hazardous EPR Zones ........................................................13
7 Cable route capacity .............................................................................................................13
7.1 Pit and pipe capacity ...............................................................................................................14
7.2 GST capacity...........................................................................................................................14
© RailCorp Page 3 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
© RailCorp Page 4 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
1 Introduction
This standard sets out minimum requirements for the provision, installation, termination
and management of outdoor communications cables within the RailCorp Communications
network.
The requirements of this standard are in addition to the Australian Standards, they do not
replace them. If there is a conflict between this standard and the Australian Standards,
then the Australian Standards shall be adhered to and the Chief Engineer,
Telecommunications, of Chief Engineers Division shall be notified immediately.
Additional requirements to those specified in this standard also apply for special
situations such as cables in tunnels, aerial cable, cables associated with high voltage
installations.
3 References
© RailCorp Page 5 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
© RailCorp Page 6 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
Hazardous EPR Zone zone where the earth potential rise exceeds 430 V AC under
power system fault condition;
High voltage as defined in AS/NZS 3000 and AS/ACIF S009. Note that in this standard
the high voltage shall also include the 1500VDC positive and negative feeders that supply
the overhead traction power, as these feeders regularly exceed 1500VDC.
Pipe continuous or jointed pipe forming a sealed conduit between two terminations.
Pipe, conduit and duct are interchangeable terms in this standard.
Trunk route A route that interconnects two or more communications equipment rooms or
main communications nodes, or between train stations.
Non-trunk route A feeder route to an equipment site, usually less than 500m, not
designed to house trunk cables.
This document
© RailCorp Page 7 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
5.1 Cables
All cables used and the method of construction shall be in accordance with specifications
quoted in this standard.
Where different grades of single-mode fibre are incorporated into a cable, each tube shall
contain one grade only. Where non-zero dispersion shifted fibres (ITU G.655) are
incorporated, they shall occupy the first tube(s) of that cable.
Note that ESM 105 prohibits the use of communications trunk optic fibre cables for
interconnecting local signalling equipment between adjacent signalling bungalows, relay
rooms and location cases.
The sizes of optical fibre cables shall be 12, 24, 48, 72, 96, 144, cores or higher. Optical
fibre cable construction types shall be used in the environment it was designed for.
• General Installation - Cable suitable for general installation in the rail environment
by way of hauling into underground ducts, hauling into above Ground Steel
Troughing (GST) and laying in Ground Level concrete Troughing (GLT). Can be
used in all locations except for underground tunnels or stations or other
underground facilities.
• Fire Safe - Cable for installation in underground stations or other underground
facilities and tunnels. Can be used in all locations however not practical to use in
long section of small diameter HDPE pipe.
• Blown Cable - Cable for installation by way of air/gas blowing through small
diameter HDPE continuous conduits. This cable may only be used where the route
is predominantly small diameter HDPE continuous pipe and installation is by way
of blowing.
At the completion of a cable installation project, all cables shall have a minimum 75% of
fibres that are unused (dark fibres) and available for service restoration and future
expansion. The size of any trunk (or long haul) cable shall not be less than 96 cores.
With regard to trunk cable, if there is no existing cable or no ring cable to provide
diversity, two new trunk cables in different routes shall be installed at the time of
construction. Diversity provided by a fibre swap arrangement with other organisations or
© RailCorp Page 8 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
carriers is deemed to meet this requirement so a second new cable is not required. See
Section 6.8 for diverse cable routes.
• The cable shall have 10, 20, 30, 50, or 100 pairs as required.
• The cable shall have:
• The cable shall have 10, 20, 30, 50, or 100 pairs as required.
• The cable shall have:
© RailCorp Page 9 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
The cable shall conform to the requirements of AS/CA S008 and the relevant fire safe
specifications, including AS/NZS 1660.5.2, AS/NZS 1660.5.3, and AS/NZS 1660.5.4.
Except for cable ladder, rack or cable tray which is acceptable in tunnels etc, cable route
construction type shall be in the preference in order of:
b) GST,
c) Aerial cables.
No new direct buried cable is allowed, except for the last 5m accessing existing direct
buried cable network.
6.4 GLT
GLT shall only be used as a last resort.
a) Shall not exceed 5m, unless with the written acceptance of the as per
TMM C001.
© RailCorp Page 10 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
• SPM 0885
• The aerial cable shall be at least 5m clearance from ground level.
• The aerial cable shall be at least 4.5m clearance from GST.
• The aerial cable shall be installed in accordance with the specifications required by
RailCorp Chief Electrical Engineer.
Where communications cables are in the same trench as signalling and power cables, it
is mandatory that Communications cables shall be housed in conduits.
Unless special dispensation is provided by TMM C001, signalling and electrical conduit
shall not pass through or enter pits dedicated for communications cabling, nor shall
communications conduits pass through or enter pits dedicated for electrical or signalling
cables except for the exemption provided below.
In locations where there are no dedicated communications cable pits or where it would be
uneconomical to provide such a pit for a single service, and it is required that a service be
run to a signalling location, then a communications cables designated for signalling
services may pass through a signalling pit but shall do so with in a subduct so as to
comply with AS/ACIF S009.
Examples of such a service are signalling post phones and data links to signal locations.
For the purposes of separation, both negatives and positives of the1500 volt DC traction
feeders shall be considered as HV cables.
© RailCorp Page 11 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
6.8.3 Diversity provided by parallel pit and pipe, GST troughing etc
Diversity may be provided by parallel cable routes of GST / Troughing / Pit and Pipe with
an acceptable separation between the different routes. Such separation shall be
approved by the design approval authority. As a guide, the normal requirement would be:
whichever is greater.
Cables attached to two adjacent tunnels of the same route, are deemed to comply as
diverse cable routes. Cables attached to opposite sides of a single tunnel are not
considered as diverse cable routes.
© RailCorp Page 12 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
High voltage locations located outside the rail corridor, owned and operated by others
such as Energy Australia, must also be taken into consideration.
Joints in copper communications cables shall not be permitted within a Hazardous EPR
Zone.
Where a trunk cable route consists of pipes, the unused capacity shall not be less than
one additional unused pipe, or 50% of the total capacity, which ever is greater. For trunk
route under line crossings this shall be increased to two unused pipes or 60% of the total
capacity whichever is greater.
© RailCorp Page 13 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
Either a complete trough with individual lid or white pipe in a shared trough shall be
dedicated for the sole use of RailCorp’s’ communications.
8.1 Conduits
This section specifics the type of conduits to be used for cable route construction.
• Except where installation conditions would make it impractical, pit and conduit
construction shall be used for all new cable routes.
• Where possible, 100mm conduit shall be used for all new projects
For all pit and conduit cable route, the following conduits are approved for use.
PVC conduits shall be jointed by solvent welding, with the ends forced well into the
socket.
© RailCorp Page 14 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
HDPE conduits shall be jointed by either a pressure fitting such as shown in drawing
XXX-CA0311 (see Section 3.4 or Section 8.1.2) or by thermal welding using purpose
designed thermal welding couplers. Conduit ends shall be cut cleanly and at right angles
with all burrs removed and forced well into the coupler socket before the heating or
clamping process. The finished joint shall be gas tight.
Figure 1 - A poorly installed cable route with voids between conduits and surrounding
soil leading to the deformation or collapse of the conduit.
Conduits shall be placed in the trench and the fill placed around the conduits so that as
far as possible the fill and surrounding soil and or rock shall exert an even pressure on
the entire surface of the conduit. To this end installers shall insure that there are no voids
between the conduit(s) and/or surrounding soil and/or rock. This is best achieved by
laying conduits a layer at a time with spacers every 3 metres along the cable route and
between the conduits to ensure that the voids can be filled with sand or other suitable
material to completely fill any voids.
© RailCorp Page 15 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
Figure 2 - A cross-section and prospective of a correctly installed cable route with pine
battens to ensure that there no voids between conduits and surrounding fill.
Crashed rock, finely divided road base, or sand shall bed and cover the conduits and fill
the spaces between conduits. The conduits shall be covered to a thickness of not less
than 100mm over the uppermost conduit. The remainder of the trench shall be filled with
clean fill, free of broken concrete, rubble, wood, glass, rubbish, steel or other metallic
objects and free of stones which would not pass through a 50mm sieve.
If a signal tracer wire is required, it shall be a white polyethylene insulated stainless steel
wire, installed in the trench over the conduits at a nominal depth of 500mm below finished
surface level.
Cable marker tape as per specification SPG 0705 shall be installed over the cable route
at a depth of 300mm. See drawings 112000/5/4, 112000/5/5 and 112000/5/6.
Trenches are to be excavated so that conduits can be laid with 300 mm clearance all
round from other obstructions, unless otherwise approved by RailCorp.
The trench shall be compacted in accordance with SPG 0705. This compaction of the soil
in the trench shall not cause the conduits to be deformed.
© RailCorp Page 16 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
Pre-cast concrete cable pits manufactured in accordance with specification SPM 0123
shall not be installed closer than two (2) metres from any power pole or overhead wiring
structure, or the foot and/or the edge of a retaining wall.
Pits that are required to be closer to the track or structures than these limitations shall be
purpose designed and shall require the approval of Chief Engineer Civil or his appointed
representative.
As shown in drawing MET-OT 0042, two identical identification labels shall be mounted
on each pit; one on the pit lid and the other mounted on the inside wall of cable pits
approximately 50mm from top in an easily accessible location. Pit identification labels
shall be controlled by the TNC group
• Underline crossing
• Under road crossing
• Where a building, maintenance facility, paved area or station exists
• Where access to constructing a new cable route in future becomes high risk due to
limited access
a) The purpose of the route is for the installation of non metallic fibre cable only, in
the present and in the future; and
in which case the pits shall be no more than 250m apart, or less than 500m if the route
between the pits is straight.
© RailCorp Page 17 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0
RailCorp Engineering Standard — Telecommunications
Communication Outdoor Cabling Standard ESM 102
8.3 Mandrelling
All conduits installed shall pass the mandrelling test by pulling a mandrel of a diameter
90% of the internal pipe diameter, upon backfilling and compaction. The mandrelling test
shall be witnessed by an authorised RailCorp staff or representative.
The cable route, either pipe or GST, shall remain usable at all times, the cross sectional
area of the GST, pipe etc shall not be diminished by pressure or aging during the
maintainable period of the cable route, which shall include all GST, bores, pits and pipes
and others. Conduits shall not be deformed to less than 90% of the internal diameter of
the pipe. Similarly, for GST, less than 10% of the internal area is lost due to changes in
GST shapes.
All spare pipes shall be cleaned by the mandrelling test (refer to “Mandrelling”, see
Section 8.3), each pipe shall have draw rope suitably anchored at each end of the pipe
and then sealed with proprietary end caps to stop the ingress of foreign particles.
10 Historical names
References to previous organisational names (viz “Rail Access Corporation”, “Rail
Infrastructure Corporation”, “Argus Communications” etc or their abbreviations) in
requirements for marking of cables, conduits etc specified in Annexes shall be replaced
by “RailCorp”.
11 Documentation
All cabling and cable route construction works shall be recorded in accordance with
SPM 0073.
© RailCorp Page 18 of 18
Issued July 2011 UNCONTROLLED WHEN PRINTED Version 2.0