MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

1 10-Jun-18 JSI Lean Concrete (LC) Power House Engine E 15 15 6.0 30.0 321 17-Jun-18 8-Jul-18 11.60 77.30 9714-CIV-RFI-66 16.42 109.47 9714-CIV-RFI-100A
2 11-Jun-18 JSI Lean Concrete (LC) Power House Engine C 15 15 7.0 30.0 321 18-Jun-18 9-Jul-18 10.76 71.73 9714-CIV-RFI-66 16.14 107.57 9714-CIV-RFI-100A
3 12-Jun-18 JSI Lean Concrete (LC) Power House Engine A 15 15 10.0 30.0 321 19-Jun-18 10-Jul-18 10.76 71.70 9714-CIV-RFI-66 15.57 103.80 9714-CIV-RFI-100A
4 1-Jul-18 JSI Lean Concrete (LC) Engine Hall Footing PC2 (7ea) 15 15 10.0 30.0 321 8-Jul-18 29-Jul-18 11.61 77.37 9714-CIV-RFI-66 16.13 107.55 9714-CIV-RFI-100A
5 2-Jul-18 JSI Lean Concrete (LC) Fuel Oil Daily Tank - 15 15 10.0 30.0 321 9-Jul-18 30-Jul-18 11.61 77.37 9714-CIV-RFI-66 15.86 105.70 9714-CIV-RFI-100A
6 14-Jul-18 JSI Footing Engine E Footing 30 30 10-15 30.0 435+ SP 21-Jul-18 11-Aug-18 22.37 74.55 9714-CIV-RFI-73A 30.29 100.97 9714-CIV-RFI-119
7 15-Jul-18 JSI Lean Concrete (LC) Water Tank - 15 15 10.0 30.0 321 22-Jul-18 12-Aug-18 11.04 73.60 9714-CIV-RFI-73A 16.14 107.57 9714-CIV-RFI-119
8 15-Jul-18 JSI Lean Concrete (LC) Power House PC4 = 3ea 15 15 10.0 30.0 321 22-Jul-18 12-Aug-18 11.04 73.60 9714-CIV-RFI-73A 16.14 107.57 9714-CIV-RFI-119
9 16-Jul-18 JSI Lean Concrete (LC) Power House PC3 15 15 10.0 30.0 321 23-Jul-18 13-Aug-18 10.76 71.73 9714-CIV-RFI-73A 15.85 105.67 9714-CIV-RFI-119
10 17-Jul-18 JSI Lean Concrete (LC) Power House PC3A 15 15 10.0 30.0 321 24-Jul-18 14-Aug-18 11.04 73.60 9714-CIV-RFI-73A 16.14 107.57 9714-CIV-RFI-119
11 21-Jul-18 JSI Footing Engine C - 30 30 10-15 30.0 435+ SP 28-Jul-18 18-Aug-18 22.08 73.60 9714-CIV-RFI-100A 32.42 108.05 9714-CIV-RFI-159
12 22-Jul-18 JSI Footing + Tie Beam Engine Hall PC-2 + TB3 25 25 10-15 30.0 400 29-Jul-18 19-Aug-18 18.40 73.60 9714-CIV-RFI-100A 29.16 116.64 9714-CIV-RFI-161
13 22-Jul-18 JSI Lean Concrete (LC) Engine D - 15 15 10.0 30.0 321 29-Jul-18 19-Aug-18 11.18 74.53 9714-CIV-RFI-100A 17.27 115.13 9714-CIV-RFI-161
14 22-Jul-18 JSI Lean Concrete (LC) Warehouse - 15 15 10.0 30.0 321 29-Jul-18 19-Aug-18 11.18 74.53 9714-CIV-RFI-100A 17.27 115.13 9714-CIV-RFI-161
15 22-Jul-18 JSI Lean Concrete (LC) Toilet Buiilding - 15 15 8.0 30.0 321 29-Jul-18 19-Aug-18 11.18 74.53 9714-CIV-RFI-100A 17.27 115.13 9714-CIV-RFI-161
16 22-Jul-18 JSI Footing Engine A - 30 30 10-15 30.0 435+SP 29-Jul-18 19-Aug-18 22.65 75.50 9714-CIV-RFI-100A 32.13 107.10 9714-CIV-RFI-161
17 23-Jul-18 JSI Pedestal Engine E 30 30 10-15 30.0 435+SP 30-Jul-18 20-Aug-18 22.93 76.43 9714-CIV-RFI-100A 31.14 103.80 9714-CIV-RFI-161
18 25-Jul-18 JSI Foundation Oil Daily Tank 30 30 10-15 30.0 435+ SP 1-Aug-18 22-Aug-18 22.37 74.55 9714-CIV-RFI-117A 31.29 104.30 9714-CIV-RFI-167
19 26-Jul-18 JSI Lean Concrete (LC) Engine B 15 15 10.0 30.0 321 2-Aug-18 23-Aug-18 11.04 73.60 9714-CIV-RFI-117A 16.14 107.60 9714-CIV-RFI-167
20 27-Jul-18 JSI Footing Power House PC4 = 3ea 25 25 10-15 30.0 400 3-Aug-18 24-Aug-18 18.40 73.60 9714-CIV-RFI-117A 26.47 105.88 9714-CIV-RFI-168
21 29-Jul-18 JSI Lean Concrete (LC) Engine Hall PD1, PC6, TB2 15 15 10.0 30.0 321 5-Aug-18 26-Aug-18 10.76 71.73 9714-CIV-RFI-117A 16.99 113.27 9714-CIV-RFI-184
22 29-Jul-18 JSI Lean Concrete (LC) Sludge Storage Tank 15 15 10.0 30.0 321 5-Aug-18 26-Aug-18 10.76 71.73 9714-CIV-RFI-117A 16.99 113.27 9714-CIV-RFI-184
23 29-Jul-18 JSI Lean Concrete (LC) Lube Oil Storage Tank 15 15 10.0 30.0 321 5-Aug-18 26-Aug-18 10.76 71.73 9714-CIV-RFI-117A 16.99 113.27 9714-CIV-RFI-184
24 29-Jul-18 JSI Lean Concrete (LC) Admin Building 15 15 10.0 30.0 321 5-Aug-18 26-Aug-18 10.76 71.73 9714-CIV-RFI-117A 16.99 113.27 9714-CIV-RFI-184
25 31-Jul-18 JSI Footing Engine D - 30 30 10-15 30.0 435+SP 7-Aug-18 28-Aug-18 22.80 76.00 9714-CIV-RFI-117A 32.13 107.10 9714-CIV-RFI-186
26 1-Aug-18 JSI Pedestal Engine C 30 30 10-15 30.0 435+SP 8-Aug-18 29-Aug-18 27.88 92.93 9714-CIV-RFI-123A 31.14 103.80 9714-CIV-RFI-201
27 1-Aug-18 JSI Pedestal Engine A 30 30 10-15 30.0 435+SP 8-Aug-18 29-Aug-18 27.88 92.93 9714-CIV-RFI-'123A 31.14 103.80 9714-CIV-RFI-201
28 2-Aug-18 JSI Footing Sludge Storage Tank 25 25 10-15 30.0 400 9-Aug-18 30-Aug-18 30.57 122.28 9714-CIV-RFI-124 26.19 104.74 9714-CIV-RFI-202
29 2-Aug-18 JSI Footing Lube Oil Storage Tank 25 25 10-15 30.0 400 9-Aug-18 30-Aug-18 30.57 122.28 9714-CIV-RFI-124 26.19 104.74 9714-CIV-RFI-202
30 3-Aug-18 JSI Footing, Tie Beam, Power House PD-1, PC6, TB2 25 25 10-15 30.0 400 10-Aug-18 31-Aug-18 27.18 108.70 9714-CIV-RFI-125 27.60 110.40 9714-CIV-RFI-203
31 4-Aug-18 JSI Pedestal Power House PC-2 25 25 10-15 30.0 400 11-Aug-18 1-Sep-18 19.25 77.00 9714-CIV-RFI-132A 26.61 106.44 9714-CIV-RFI-204
32 4-Aug-18 JSI Footing, Tie Beam, Power House PD-1, PC6, TB2 25 25 10-15 30.0 400 11-Aug-18 1-Sep-18 19.25 77.00 9714-CIV-RFI-132A 26.61 106.44 9714-CIV-RFI-204
33 5-Aug-18 JSI Pedestal Power House PC-2 , PD1 25 25 10-15 30.0 400 12-Aug-18 2-Sep-18 18.97 75.88 9714-CIV-RFI-142 25.91 103.62 9714-CIV-RFI-205
34 5-Aug-18 JSI Footing Power House PC3B, PC3 25 25 10-15 30.0 400 12-Aug-18 2-Sep-18 18.97 75.88 9714-CIV-RFI-142 25.91 103.62 9714-CIV-RFI-205
35 8-Aug-18 JSI Footing Engine B - 30 30 10-15 30.0 435+SP 15-Aug-18 5-Sep-18 27.88 92.93 9714-CIV-RFI-146 30.29 100.97 9714-CIV-RFI-218
36 9-Aug-18 JSI Footing Power House PC3A, PC3 25 25 10-15 30.0 400 16-Aug-18 6-Sep-18 17.55 70.20 9714-CIV-RFI-147 25.76 103.04 9714-CIV-RFI-219
37 9-Aug-18 JSI Lean Concrete (LC) Transformer Area BAA10, BAA20, BFT10, BFT20 15 15 10.0 30.0 321 16-Aug-18 6-Sep-18 19.67 131.13 9714-CIV-RFI-147 15.57 103.80 9714-CIV-RFI-219
38 9-Aug-18 JSI Lean Concrete (LC) HT&LT Cooling Water Radiator - 15 15 10.0 30.0 321 16-Aug-18 6-Sep-18 19.67 131.13 9714-CIV-RFI-147 15.57 103.80 9714-CIV-RFI-219
39 9-Aug-18 JSI Footing, Tie beam, Slab Admin Building - 25 25 10-15 30.0 435+SP 16-Aug-18 6-Sep-18 19.67 78.68 9714-CIV-RFI-147 25.76 103.04 9714-CIV-RFI-219
40 11-Aug-18 JSI Foundation Raw and Water Tank - 30 30 10-15 30.0 435+SP 18-Aug-18 8-Sep-18 25.34 84.47 9714-CIV-RFI-159 31.57 105.22 9714-CIV-RFI-231

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

41 12-Aug-18 JSI Pedestal Engine B 30 30 10-15 30.0 435+SP 19-Aug-18 9-Sep-18 23.92 79.73 9714-CIV-RFI-161 30.57 101.90 9714-CIV-RFI-233
42 12-Aug-18 JSI Pedestal Engine D 30 30 10-15 30.0 435+SP 19-Aug-18 9-Sep-18 23.92 79.73 9714-CIV-RFI-161 30.57 101.90 9714-CIV-RFI-233
43 12-Aug-18 JSI Lean Concrete (LC) Switch yard 15 15 10.0 30.0 321 19-Aug-18 9-Sep-18 14.44 96.27 9714-CIV-RFI-161 15.29 101.90 9714-CIV-RFI-233
44 12-Aug-18 JSI Lean Concrete (LC) Radiator 15 15 10.0 30.0 321 19-Aug-18 9-Sep-18 14.44 96.27 9714-CIV-RFI-161 15.29 101.90 9714-CIV-RFI-233
45 13-Aug-18 JSI Footing Warehouse, Laboratory, Workshop PC1 25 25 12.0 30.0 400 20-Aug-18 10-Sep-18 22.37 89.48 9714-CIV-RFI-161 26.33 105.32 9714-CIV-RFI-234
46 13-Aug-18 JSI Footing, Tie Beam Powerhouse PC6, TB2,PD1 25 25 12.0 30.0 400 20-Aug-18 10-Sep-18 22.37 89.48 9714-CIV-RFI-161 26.33 105.32 9714-CIV-RFI-234
47 14-Aug-18 JSI Footing, Tie Beam, Slab Toilet Buiilding - 25 25 12.0 30.0 400 21-Aug-18 11-Sep-18 18.40 73.60 9714-CIV-RFI-162 25.48 101.90 9714-CIV-RFI-241
48 14-Aug-18 JSI Foundation Transformer Area BAA10, BAA20 25 25 12.0 30.0 400 21-Aug-18 11-Sep-18 18.40 73.60 9714-CIV-RFI-162 25.48 101.90 9714-CIV-RFI-241
49 14-Aug-18 JSI Foundation Transformer Area 25 25 12.0 30.0 400 21-Aug-18 11-Sep-18 18.40 73.60 9714-CIV-RFI-162 25.48 101.90 9714-CIV-RFI-241
50 15-Aug-18 JSI Foundation Transformer Area BFT10, BFT20 25 25 12.0 30.0 400 22-Aug-18 12-Sep-18 24.07 96.28 9714-CIV-RFI-167 26.75 107.00 9714-CIV-RFI-242
51 15-Aug-18 JSI Pedestal Power House PC3, PC4 25 25 12.0 30.0 400 22-Aug-18 12-Sep-18 24.07 96.28 9714-CIV-RFI-167 26.75 107.00 9714-CIV-RFI-242
52 15-Aug-18 JSI Lean Concrete (LC) Netralisation Pit 15 15 12.0 30.0 321 22-Aug-18 12-Sep-18 11.18 74.53 9714-CIV-RFI-167 16.42 109.47 9714-CIV-RFI-242
53 16-Aug-18 JSI Footing, Tie Beam Switch yard PCD01, PD1 & TB-1 25 25 12.0 30.0 400 23-Aug-18 13-Sep-18 19.39 77.56 9714-CIV-RFI-167 25.76 103.04 9714-CIV-RFI-259
54 18-Aug-18 JSI Footing, Tie Beam HT&LT Cooling Water Radiator PC1, TB2 25 25 11.0 30.0 400 25-Aug-18 15-Sep-18 19.82 79.26 9714-CIV-RFI-169 25.76 103.04 9714-CIV-RFI-261
55 18-Aug-18 JSI Column Toilet Buiilding 6pcs 25 25 12.0 30.0 400 25-Aug-18 15-Sep-18 19.82 79.26 9714-CIV-RFI-169 25.76 103.04 9714-CIV-RFI-261
56 18-Aug-18 JSI Column Admin Building 8pcs 25 25 12.0 30.0 400 25-Aug-18 15-Sep-18 19.82 79.26 9714-CIV-RFI-169 25.76 103.04 9714-CIV-RFI-261
57 19-Aug-18 JSI Lean Concrete (LC) Toxic & Hazard Waste Storage Building 15 15 9.0 30.0 321 26-Aug-18 16-Sep-18 10.75 71.67 9714-CIV-RFI-184 15.29 101.93 9714-CIV-RFI-262
58 19-Aug-18 JSI Lean Concrete (LC) Powerhouse-Annex TB2, PD2, PC6 15 15 10.0 30.0 321 26-Aug-18 16-Sep-18 10.75 71.67 9714-CIV-RFI-184 15.29 101.93 9714-CIV-RFI-262
59 19-Aug-18 JSI Lean Concrete (LC) Powerhouse-Cable trench TB1, Trench 15 15 10.0 30.0 321 26-Aug-18 16-Sep-18 10.75 71.67 9714-CIV-RFI-184 15.29 101.93 9714-CIV-RFI-262
60 20-Aug-18 JSI Footing Transformer Area FW01~05 25 25 10.0 30.0 400 27-Aug-18 17-Sep-18 21.66 86.62 9714-CIV-RFI-185 25.90 103.60 9714-CIV-RFI-273A
61 20-Aug-18 JSI Lean Concrete (LC) Transformer Area FW06~12 25 25 10.0 30.0 400 27-Aug-18 17-Sep-18 21.66 86.62 9714-CIV-RFI-185 25.90 103.60 9714-CIV-RFI-273A
62 21-Aug-18 JSI Column Mosque 12pcs 25 25 10.0 30.0 400 28-Aug-18 18-Sep-18 18.97 75.86 9714-CIV-RFI-186 26.04 104.16 9714-CIV-RFI-273
63 23-Aug-18 JSI Pile Cap & Slab Guard House 25 25 10-15 30.0 435+SP 30-Aug-18 20-Sep-18 19.25 77.00 9714-CIV-RFI-202 26.04 104.16 9714-CIV-RFI-274A
64 23-Aug-18 JSI Footing Tie Beam HT&LT Cooling Water Radiator PC1, TB2 25 25 10-15 30.0 435+SP 30-Aug-18 20-Sep-18 19.25 77.00 9714-CIV-RFI-202 26.04 104.16 9714-CIV-RFI-274A
Pre Pouring Concrete for Slab (PC 7A
65 25-Aug-18 JSI Engine Hall & Power House 25 25 11.0 30.0 435+SP 1-Sep-18 22-Sep-18 19.54 78.14 9714-CIV-RFI-204 26.32 105.28 9714-CIV-RFI-294
& 7B)
66 25-Aug-18 JSI Footing Fire Wall Transformer Area 25 25 11.0 30.0 435+SP 1-Sep-18 22-Sep-18 19.54 78.14 9714-CIV-RFI-204 26.32 105.28 9714-CIV-RFI-294
67 25-Aug-18 JSI Lean Concrete (LC) Neutralization & Oily Water Pit Plan 15 15 7,5 30.0 321 1-Sep-18 22-Sep-18 11.04 73.60 9714-CIV-RFI-204 15.29 101.90 9714-CIV-RFI-294
68 25-Aug-18 JSI Lean Concrete (LC) Fire Wall Transformer Area 15 15 7,5 30.0 321 1-Sep-18 22-Sep-18 11.04 73.60 9714-CIV-RFI-204 15.29 101.90 9714-CIV-RFI-294
69 26-Aug-18 JSI Lean Concrete (LC) CCR -PC7-7A, Cable Tray CCR -PC7-7A, Cable Tray 15 15 5-10 30.0 321 2-Sep-18 23-Sep-18 11.04 73.60 9714-CIV-RFI-205 15.29 101.90 9714-CIV-RFI-295
70 26-Aug-18 JSI Lean Concrete (LC) Power House-Engine Hall PC-5, TB-5, PC-5C,PC5B 15 15 5-10 30.0 321 2-Sep-18 23-Sep-18 11.04 73.60 9714-CIV-RFI-205 15.29 101.90 9714-CIV-RFI-295
71 27-Aug-18 JSI Pre Pouring Concrete for Slab (PC 7A Power House-CCR Slab Cable trench (PC 7A & 7B) 25 25 11.0 30.0 435+SP 3-Sep-18 24-Sep-18 19.11 76.44 9714-CIV-RFI-206 25.61 102.44 9714-CIV-RFI-296
72 27-Aug-18 JSI Pouring Concrete Pile Cap & Slab Neutralization & Oily Water Pit Plan 25 25 11.0 30.0 435+SP 3-Sep-18 24-Sep-18 19.11 76.44 9714-CIV-RFI-206 25.61 102.44 9714-CIV-RFI-296
73 27-Aug-18 JSI Colum Guard House 25 25 11.0 30.0 435+SP 3-Sep-18 24-Sep-18 19.11 76.44 9714-CIV-RFI-206 25.61 102.44 9714-CIV-RFI-296
74 27-Aug-18 JSI Footing Fire Wall Transformer Area 25 25 11.0 30.0 435+SP 3-Sep-18 24-Sep-18 19.11 76.44 9714-CIV-RFI-206 25.61 102.44 9714-CIV-RFI-296
75 30-Aug-18 JSI Lean Concrete (LC) Slab-Toxic And Hazard 15 15 5-10 30.0 321 6-Sep-18 27-Sep-18 11.75 78.33 9714-CIV-RFI-219 15.57 103.80 9714-CIV-RFI-310
76 30-Aug-18 JSI Lean Concrete (LC) Power House 15 15 5-10 30.0 321 6-Sep-18 27-Sep-18 11.75 78.33 9714-CIV-RFI-219 15.57 103.80 9714-CIV-RFI-310
77 30-Aug-18 JSI Wall Cable Trench - Power house 25 25 11.0 30.0 435+SP 6-Sep-18 27-Sep-18 19.96 79.84 9714-CIV-RFI-219 25.62 102.48 9714-CIV-RFI-310
78 30-Aug-18 JSI Footing Tie Beam Annex-Power House 25 25 11.0 30.0 435+SP 6-Sep-18 27-Sep-18 19.96 79.84 9714-CIV-RFI-219 25.62 102.48 9714-CIV-RFI-310
79 1-Sep-18 JSI Pouring Concrete Pile Cap & Slab, Tie Toxic And Hazard 25 25 12.0 30.0 435+SP 8-Sep-18 29-Sep-18 19.68 78.70 9714-CIV-RFI-231 25.90 103.60 9714-CIV-RFI-336
80 1-Sep-18 JSI Lean Concrete (LC) Fire Wall Transformer Area 15 15 5-10 30.0 321 8-Sep-18 29-Sep-18 11.75 78.33 9714-CIV-RFI-231 15.57 103.80 9714-CIV-RFI-336
81 1-Sep-18 JSI Lean Concrete (LC) Bundwall 15 15 5-10 30.0 321 8-Sep-18 29-Sep-18 11.75 78.33 9714-CIV-RFI-231 15.57 103.80 9714-CIV-RFI-336
MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT
MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

82 1-Sep-18 JSI Lean Concrete (LC) Pump House Shelter 15 15 5-10 30.0 321 8-Sep-18 29-Sep-18 11.75 78.33 9714-CIV-RFI-231 15.57 103.80 9714-CIV-RFI-336
83 2-Sep-18 JSI Pouring Concrete Wall Neutralization & Oily Water Pit (GUB09-BB01) 25 25 11.0 30.0 435+SP 9-Sep-18 30-Sep-18 20.10 80.40 9714-CIV-RFI-233 26.18 104.72 9714-CIV-RFI-337
84 2-Sep-18 JSI Pouring Concrete Wall Cable Trench - Power house 25 25 11.0 30.0 435+SP 9-Sep-18 30-Sep-18 20.10 80.40 9714-CIV-RFI-233 26.18 104.72 9714-CIV-RFI-337
85 3-Sep-18 JSI Pouring Concrete Pile Cap & Tie Beam Power house 25 25 11.0 30.0 435+SP 10-Sep-18 1-Oct-18 19.39 77.56 9714-CIV-RFI-234 25.76 103.04 9714-CIV-RFI-338
86 4-Sep-18 JSI Lean Concrete (LC) Water Pit 15 15 5-10 30.0 321 11-Sep-18 2-Oct-18 20.24 134.93 9714-CIV-RFI-241 25.76 171.73 9714-CIV-RFI-338
87 4-Sep-18 JSI Lean Concrete (LC) Sluge Pit 15 15 5-10 30.0 321 11-Sep-18 2-Oct-18 20.24 134.93 9714-CIV-RFI-241 15.57 103.80 9714-CIV-RFI-339
88 4-Sep-18 JSI Lean Concrete (LC) Annex-Power House, Slab 15 15 5-10 30.0 321 11-Sep-18 2-Oct-18 20.24 134.93 9714-CIV-RFI-241 15.57 103.80 9714-CIV-RFI-339
89 4-Sep-18 JSI Footing Tie Beam Bundwall 25 25 5-10 30.0 400 11-Sep-18 2-Oct-18 20.24 80.96 9714-CIV-RFI-241 25.76 103.04 9714-CIV-RFI-339
90 5-Sep-18 JSI Lean Concrete (LC) Toxic and hazard 15 15 5-10 30.0 321 12-Sep-18 3-Oct-18 12.88 85.87 9714-CIV-RFI-242 15.57 103.80 9714-CIV-RFI-340
91 6-Sep-18 JSI Slab Annex-Power House 25 25 5-10 30.0 400 13-Sep-18 4-Oct-18 19.53 78.12 9714-CIV-RFI-259 32.13 128.52 9714-CIV-RFI-341
92 6-Sep-18 JSI Pedestal Annex-Power House 25 25 5-10 30.0 400 13-Sep-18 4-Oct-18 19.53 78.12 9714-CIV-RFI-259 32.13 128.52 9714-CIV-RFI-341
93 6-Sep-18 JSI Footing & Pedestal Swictyard 25 25 5-10 30.0 400 13-Sep-18 4-Oct-18 19.53 78.12 9714-CIV-RFI-259 32.13 128.52 9714-CIV-RFI-341
94 6-Sep-18 JSI Cable Trech - Wall Power House 25 25 5-10 30.0 400 13-Sep-18 4-Oct-18 19.53 78.12 9714-CIV-RFI-259 32.13 128.52 9714-CIV-RFI-341
95 6-Sep-18 JSI Lean Concrete (LC) CCR --Power House 15 15 5-10 30.0 321 13-Sep-18 4-Oct-18 11.60 77.33 9714-CIV-RFI-259 15.57 103.80 9714-CIV-RFI-341
96 7-Sep-18 JSI Footing,Tie beam, Slab Sludge Pit 25 25 5-10 30.0 400 14-Sep-18 5-Oct-18 19.25 77.00 9714-CIV-RFI-260 26.75 107.00 9714-CIV-RFI-371
97 7-Sep-18 JSI Footing,Tie beam, Slab Water Source Pond Plan 25 25 5-10 30.0 400 14-Sep-18 5-Oct-18 19.25 77.00 9714-CIV-RFI-260 26.75 107.00 9714-CIV-RFI-371
98 7-Sep-18 JSI Slab Water PIT/ Sludge PIT 25 25 5-10 30.0 400 14-Sep-18 5-Oct-18 19.25 77.00 9714-CIV-RFI-260 26.75 107.00 9714-CIV-RFI-371
99 8-Sep-18 JSI Pedestal Switchyard PCD01 25 25 5-10 30.0 400 15-Sep-18 6-Oct-18 19.67 78.68 9714-CIV-RFI-261 26.61 106.44 9714-CIV-RFI-372
100 8-Sep-18 JSI Lean Concrete (LC) Power House / Annex Slab 15 15 5-10 30.0 321 15-Sep-18 6-Oct-18 11.60 77.33 9714-CIV-RFI-261 15.57 103.80 9714-CIV-RFI-372
101 9-Sep-18 JSI Slab Annex / Power House 25 25 5-10 30.0 400 16-Sep-18 7-Oct-18 19.67 78.68 9714-CIV-RFI-262 26.61 106.44 9714-CIV-RFI-373
102 9-Sep-18 JSI Pedestal Switchyard 25 25 5-10 30.0 400 16-Sep-18 7-Oct-18 19.67 78.68 9714-CIV-RFI-262 26.61 106.44 9714-CIV-RFI-373
103 10-Sep-18 JSI Lean Concrete (LC) Pump House Shelter 15 15 5-10 30.0 321 17-Sep-18 8-Oct-18 11.75 78.33 9714-CIV-RFI-273A 15.57 103.80 9714-CIV-RFI-374
104 10-Sep-18 JSI Lean Concrete (LC) Toxic And Hazard Slab 15 15 5-10 30.0 321 17-Sep-18 8-Oct-18 11.75 78.33 9714-CIV-RFI-273A 15.57 103.80 9714-CIV-RFI-374
105 11-Sep-18 JSI Lean Concrete (LC) Power House Slab 15 15 5-10 30.0 321 18-Sep-18 9-Oct-18 11.46 76.40 9714-CIV-RFI-273 15.71 104.73 9714-CIV-RFI-375
106 11-Sep-18 JSI Slab, Tie Beam, Footing Toxic And Hazard Slab 25 25 5-10 30.0 400 18-Sep-18 9-Oct-18 20.10 80.40 9714-CIV-RFI-273 26.89 107.56 9714-CIV-RFI-375
107 11-Sep-18 JSI Pedestal Powerhouse PC6PD1 =7ea 25 25 5-10 30.0 400 18-Sep-18 9-Oct-18 20.10 80.40 9714-CIV-RFI-273 26.89 107.56 9714-CIV-RFI-375
108 11-Sep-18 JSI Lean Concrete (LC) Switchyard 15 15 5-10 30.0 400 18-Sep-18 9-Oct-18 11.46 76.40 9714-CIV-RFI-273 15.57 103.80 9714-CIV-RFI-375
109 12-Sep-18 JSI Wall Water PIT 25 25 5-10 30.0 400 19-Sep-18 10-Oct-18 20.10 80.40 9714-CIV-RFI-274 27.46 109.84 9714-CIV-RFI-376
110 12-Sep-18 JSI Slab Annex 25 25 5-10 30.0 400 19-Sep-18 10-Oct-18 20.10 80.40 9714-CIV-RFI-274 27.46 109.84 9714-CIV-RFI-376
111 13-Sep-18 JSI Lean Concrete (LC) Warehouse, workshop, laboratory 25 25 5-10 30.0 400 20-Sep-18 11-Oct-18 18.96 75.84 9714-CIV-RFI-274A 27.32 109.28 9714-CIV-RFI-377
112 13-Sep-18 JSI Wall Sludge Oil PIT 25 25 5-10 30.0 400 20-Sep-18 11-Oct-18 18.96 75.84 9714-CIV-RFI-274A 27.32 109.28 9714-CIV-RFI-377
113 13-Sep-18 JSI Footing, Tie Beam, Slab Pump House Shelter 25 25 5-10 30.0 400 20-Sep-18 11-Oct-18 18.96 75.84 9714-CIV-RFI-274A 27.32 109.28 9714-CIV-RFI-377
114 15-Sep-18 JSI Footing, Tie Beam, Slab Power House/ CCR 25 25 5-10 30.0 400 22-Sep-18 13-Oct-18 19.25 77.00 9714-CIV-RFI-294 27.03 108.12 9714-CIV-RFI-390
115 15-Sep-18 JSI Pedestal Toxic And Hazard 25 25 5-10 30.0 400 22-Sep-18 13-Oct-18 19.25 77.00 9714-CIV-RFI-294 27.03 108.12 9714-CIV-RFI-390
116 16-Sep-18 JSI Ring Beam Admin Building 25 25 5-10 30.0 400 23-Sep-18 14-Oct-18 19.67 78.68 9714-CIV-RFI-295 27.60 110.40 9714-CIV-RFI-391
117 16-Sep-18 JSI Lean Concrete (LC) Gas Metering 15 15 5-10 30.0 321 23-Sep-18 14-Oct-18 11.60 77.33 9714-CIV-RFI-295 16.28 108.53 9714-CIV-RFI-391
118 16-Sep-18 JSI Lean Concrete (LC) Filter Paving Area 15 15 5-10 30.0 321 23-Sep-18 14-Oct-18 11.60 77.33 9714-CIV-RFI-295 16.28 108.53 9714-CIV-RFI-391
119 17-Sep-18 JSI Lean Concrete (LC) Pipe Sleeper 15 15 5-10 30.0 321 24-Sep-18 15-Oct-18 11.60 77.33 9714-CIV-RFI-296 15.99 106.60 9714-CIV-RFI-392
120 17-Sep-18 JSI Lean Concrete (LC) WTP&WWTP 15 15 5-10 30.0 400 24-Sep-18 15-Oct-18 11.60 77.33 9714-CIV-RFI-296 15.99 106.60 9714-CIV-RFI-392
121 18-Sep-18 JSI Slab Switchyard/ Trenching 25 25 5-10 30.0 400 25-Sep-18 16-Oct-18 19.25 77.00 9714-CIV-RFI-297 27.31 109.24 9714-CIV-RFI-393

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

122 18-Sep-18 JSI Lean Concrete (LC) Pipe Sleeper 15 15 5-10 30.0 321 25-Sep-18 16-Oct-18 11.60 77.33 9714-CIV-RFI-297 15.99 106.60 9714-CIV-RFI-393
123 19-Sep-18 JSI Lean Concrete (LC) Pipe Sleeper 15 15 5-10 30.0 321 26-Sep-18 17-Oct-18 11.60 77.33 9714-CIV-RFI-309 16.15 107.67 9714-CIV-RFI-394
124 19-Sep-18 JSI Pedestal Power House PC5A, PC5B 25 25 5-10 30.0 400 26-Sep-18 17-Oct-18 19.67 78.68 9714-CIV-RFI-309 27.32 109.28 9714-CIV-RFI-394
125 20-Sep-18 JSI Ring Beam, Roof Slab Toilet Building 25 25 5-10 30.0 400 27-Sep-18 18-Oct-18 19.53 78.12 9714-CIV-RFI-310 27.74 110.96 9714-CIV-RFI-395
126 20-Sep-18 JSI Lean Concrete (LC) Emergency Diesel Generator 15 15 5-10 30.0 321 27-Sep-18 18-Oct-18 11.60 77.33 9714-CIV-RFI-310 16.98 113.20 9714-CIV-RFI-395
127 20-Sep-18 JSI Lean Concrete (LC) Bundwall 15 15 5-10 30.0 321 27-Sep-18 18-Oct-18 11.60 77.33 9714-CIV-RFI-310 16.98 113.20 9714-CIV-RFI-395
128 20-Sep-18 JSI Lean Concrete (LC) Powerhouse TB5, PC7 15 15 5-10 30.0 321 27-Sep-18 18-Oct-18 11.60 77.33 9714-CIV-RFI-310 16.98 113.20 9714-CIV-RFI-395
129 20-Sep-18 JSI Footing, Tie Beam, Slab Fire Water Pump 25 25 5-10 30.0 400 27-Sep-18 18-Oct-18 19.53 78.12 9714-CIV-RFI-310 27.74 110.96 9714-CIV-RFI-395
130 20-Sep-18 JSI Ring Beam, Roof Slab Toilet 25 25 5-10 30.0 400 27-Sep-18 18-Oct-18 19.53 78.12 9714-CIV-RFI-310 27.74 110.96 9714-CIV-RFI-395
131 21-Sep-18 JSI Footing, Tie Beam, Slab Warehouse, workshop, laboratory 25 25 5-10 30.0 400 28-Sep-18 19-Oct-18 19.67 78.68 9714-CIV-RFI-311 27.31 109.24 9714-CIV-RFI-398
132 21-Sep-18 JSI Lean Concrete (LC) Bundwall 25 25 5-10 30.0 400 28-Sep-18 19-Oct-18 19.67 78.68 9714-CIV-RFI-311 27.31 109.24 9714-CIV-RFI-398
133 22-Sep-18 JSI Wall Switchyard/ Trenching 25 25 5-10 30.0 400 29-Sep-18 20-Oct-18 19.67 78.68 9714-CIV-RFI-336 26.89 107.56 9714-CIV-RFI-399
134 22-Sep-18 JSI Lean Concrete (LC) Power House PC8 TB4 25 25 5-10 30.0 400 29-Sep-18 20-Oct-18 19.67 78.68 9714-CIV-RFI-336 26.89 107.56 9714-CIV-RFI-399
135 22-Sep-18 JSI Entrance/Slab Admin Building Slab 25 25 5-10 30.0 400 29-Sep-18 20-Oct-18 19.67 78.68 9714-CIV-RFI-336 26.89 107.56 9714-CIV-RFI-399
136 23-Sep-18 JSI Ring Balok Mosque 25 25 5-10 30.0 400 30-Sep-18 21-Oct-18 19.53 78.12 9714-CIV-RFI-337 27.32 109.28 9714-CIV-RFI-400
137 23-Sep-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 30-Sep-18 21-Oct-18 19.53 78.12 9714-CIV-RFI-337 27.32 109.28 9714-CIV-RFI-400
138 23-Sep-18 JSI Lean Concrete (LC) Pipe Sleeper 15 15 10-15 30.0 321 30-Sep-18 21-Oct-18 11.46 76.40 9714-CIV-RFI-337 16.56 110.40 9714-CIV-RFI-400
139 24-Sep-18 JSI Footing WTP&WWTP 25 25 10-15 30.0 321 1-Oct-18 22-Oct-18 18.26 73.04 9714-CIV-RFI-338 27.32 109.28 9714-CIV-RFI-401
140 24-Sep-18 JSI Pedestal Control Air 25 25 10-15 30.0 321 1-Oct-18 22-Oct-18 18.26 73.04 9714-CIV-RFI-338 27.32 109.28 9714-CIV-RFI-401
141 25-Sep-18 JSI Footing Gas Metering 25 25 10-15 30.0 400 2-Oct-18 23-Oct-18 18.82 75.28 9714-CIV-RFI-339 27.60 110.40 9714-CIV-RFI-402
142 25-Sep-18 JSI Footing Oil Filter 25 25 10-15 30.0 400 2-Oct-18 23-Oct-18 18.82 75.28 9714-CIV-RFI-339 27.60 110.40 9714-CIV-RFI-402
143 25-Sep-18 JSI Ring Beam Mosque 25 25 10-15 30.0 400 2-Oct-18 23-Oct-18 18.82 75.28 9714-CIV-RFI-339 27.60 110.40 9714-CIV-RFI-402
144 26-Sep-18 JSI Ductbank Swictyard Type C 25 25 10-15 30.0 400 3-Oct-18 24-Oct-18 20.39 81.56 9714-CIV-RFI-340 26.89 107.56 9714-CIV-RFI-441
145 26-Sep-18 JSI Footing Bundwall 25 25 10-15 30.0 400 3-Oct-18 24-Oct-18 20.39 81.56 9714-CIV-RFI-340 26.89 107.56 9714-CIV-RFI-441
146 26-Sep-18 JSI Precast Panel Fence 25 25 10-15 30.0 400 3-Oct-18 24-Oct-18 20.39 81.56 9714-CIV-RFI-340 26.89 107.56 9714-CIV-RFI-441
147 27-Sep-18 JSI Footing, Tie Beam, Slab Power House PC7, TB3, Slab 25 25 10-15 30.0 400 4-Oct-18 25-Oct-18 19.96 79.84 9714-CIV-RFI-341 26.18 104.72 9714-CIV-RFI-442
148 27-Sep-18 JSI Footing, Tie Beam Power House PC1, TB3 25 25 10-15 30.0 400 4-Oct-18 25-Oct-18 19.96 79.84 9714-CIV-RFI-341 26.18 104.72 9714-CIV-RFI-442
149 27-Sep-18 JSI Footing Pipe Rack 25 25 10-15 30.0 400 4-Oct-18 25-Oct-18 19.96 79.84 9714-CIV-RFI-341 26.18 104.72 9714-CIV-RFI-442
150 27-Sep-18 JSI Foundation Pipe Sleeper 25 25 10-15 30.0 400 4-Oct-18 25-Oct-18 19.96 79.84 9714-CIV-RFI-341 26.18 104.72 9714-CIV-RFI-442
151 28-Sep-18 JSI Pedestal Power House PC-1 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
152 28-Sep-18 JSI Pedestal Gas Metering 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
153 28-Sep-18 JSI Pedestal Pipe Rack 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
154 28-Sep-18 JSI Lean Concrete (LC) Pipe Sleeper 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
155 28-Sep-18 JSI Precast Panel Fence 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
156 28-Sep-18 JSI Lean Concrete (LC) Cable Trench Switch yard 25 25 10-15 30.0 400 5-Oct-18 26-Oct-18 19.53 78.12 9714-CIV-RFI-371 27.17 108.68 9714-CIV-RFI-443
157 29-Sep-18 JSI Footing, Tie Beam, Slab WTP&WWTP 25 25 10-15 30.0 400 6-Oct-18 27-Oct-18 19.67 78.68 9714-CIV-RFI-372 27.32 109.28 9714-CIV-RFI-444
158 29-Sep-18 JSI Footing, Tie Beam Pipe Sleeper 25 25 10-15 30.0 400 6-Oct-18 27-Oct-18 19.67 78.68 9714-CIV-RFI-372 27.32 109.28 9714-CIV-RFI-444
159 29-Sep-18 JSI Lean Concrete (LC) Duct Bank Type B 15 15 10-15 30.0 321 6-Oct-18 27-Oct-18 11.60 77.33 9714-CIV-RFI-372 21.79 145.27 9714-CIV-RFI-444
160 29-Sep-18 JSI Lean Concrete (LC) Power House PC-1 15 15 10-15 30.0 321 6-Oct-18 27-Oct-18 11.60 77.33 9714-CIV-RFI-372 21.79 145.27 9714-CIV-RFI-444
161 30-Sep-18 JSI Lean Concrete (LC) Cable Trench Switch yard 15 15 10.0 30.0 321 7-Oct-18 28-Oct-18 19.96 133.07 9714-CIV-RFI-373 21.79 145.27 9714-CIV-RFI-445

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

162 30-Sep-18 JSI Ductbank Ductbank Switch yard Type B 25 25 10.0 30.0 400 7-Oct-18 28-Oct-18 19.96 79.84 9714-CIV-RFI-373 27.74 110.96 9714-CIV-RFI-445
163 30-Sep-18 JSI Footing Sleeper Pipe 25 25 10.0 30.0 400 7-Oct-18 28-Oct-18 19.96 79.84 9714-CIV-RFI-373 27.74 110.96 9714-CIV-RFI-445
164 30-Sep-18 JSI Footing Emergency Diesel Generator (EDG) 25 25 10.0 30.0 400 7-Oct-18 28-Oct-18 19.96 79.84 9714-CIV-RFI-373 27.74 110.96 9714-CIV-RFI-445
165 30-Sep-18 JSI Slab Cable Trench Switch yard 25 25 10.0 30.0 400 7-Oct-18 28-Oct-18 19.96 79.84 9714-CIV-RFI-373 27.74 110.96 9714-CIV-RFI-445
166 1-Oct-18 JSI Lean Concrete (LC) Cable Trench Switch yard 15 15 10.0 30.0 321 8-Oct-18 29-Oct-18 11.60 77.33 9714-CIV-RFI-374 21.37 142.47 9714-CIV-RFI-446
167 2-Oct-18 JSI Footing, Tie Beam Pipe Sleeper 25 25 10-15 30.0 400 9-Oct-18 30-Oct-18 18.96 75.84 9714-CIV-RFI-375 27.04 108.16 9714-CIV-RFI-447
168 2-Oct-18 JSI Pedestal WWTP 25 25 10-15 30.0 400 9-Oct-18 30-Oct-18 18.96 75.84 9714-CIV-RFI-375 27.04 108.16 9714-CIV-RFI-447
169 2-Oct-18 JSI Entrance/Slab Admin Building 25 25 10-15 30.0 400 9-Oct-18 30-Oct-18 18.96 75.84 9714-CIV-RFI-375 27.04 108.16 9714-CIV-RFI-447
170 2-Oct-18 JSI Slab Cable Trench Switch yard 25 25 10-15 30.0 400 9-Oct-18 30-Oct-18 18.96 75.84 9714-CIV-RFI-375 27.04 108.16 9714-CIV-RFI-447
171 2-Oct-18 JSI Entrance/Slab Mosque 25 25 10-15 30.0 400 9-Oct-18 30-Oct-18 18.96 75.84 9714-CIV-RFI-375 27.04 108.16 9714-CIV-RFI-447
172 3-Oct-18 JSI Slab Bondex CCR Elv. 2.800 25 25 10-15 30.0 400 10-Oct-18 31-Oct-18 19.53 78.12 9714-CIV-RFI-376 26.89 107.56 9714-CIV-RFI-448
173 3-Oct-18 JSI Footing, Tie Beam, Slab Power House PC1, 25 25 10-15 30.0 400 10-Oct-18 31-Oct-18 19.53 78.12 9714-CIV-RFI-376 26.89 107.56 9714-CIV-RFI-448
174 3-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 10-Oct-18 31-Oct-18 19.53 78.12 9714-CIV-RFI-376 26.89 107.56 9714-CIV-RFI-448
175 4-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 11-Oct-18 1-Nov-18 18.40 73.60 9714-CIV-RFI-377 27.03 108.12 9714-CIV-RFI-556A
176 4-Oct-18 JSI Wall Bundwall 25 25 10-15 30.0 400 11-Oct-18 1-Nov-18 18.40 73.60 9714-CIV-RFI-377 27.03 108.12 9714-CIV-RFI-556A
177 4-Oct-18 JSI Footing, Tie Beam Pipe Sleeper Radiator 25 25 10-15 30.0 400 11-Oct-18 1-Nov-18 18.40 73.60 9714-CIV-RFI-377 27.03 108.12 9714-CIV-RFI-556A
178 5-Oct-18 JSI Slab Cable Trench Switch yard 25 25 10-15 30.0 400 12-Oct-18 2-Nov-18 18.40 73.60 9714-CIV-RFI-378 27.17 108.68 9714-CIV-RFI-557A
179 6-Oct-18 JSI Slab Bondex CCR 8.300 25 25 10-15 30.0 400 13-Oct-18 3-Nov-18 18.26 73.04 9714-CIV-RFI-390 27.16 108.64 9714-CIV-RFI-581
180 7-Oct-18 JSI Slab/Wall Temporaty Contaiment Pond Pond 4 25 25 10-15 30.0 400 14-Oct-18 4-Nov-18 18.40 73.60 9714-CIV-RFI-391 27.46 109.84 9714-CIV-RFI-582
181 7-Oct-18 JSI Lean Concrete (LC) Temporaty Contaiment Pond Pond 7 25 25 10-15 30.0 400 14-Oct-18 4-Nov-18 18.40 73.60 9714-CIV-RFI-391 27.46 109.84 9714-CIV-RFI-582
182 7-Oct-18 JSI Entrance/Slab Toilet Building 25 25 10-15 30.0 400 14-Oct-18 4-Nov-18 18.40 73.60 9714-CIV-RFI-391 27.46 109.84 9714-CIV-RFI-582
183 7-Oct-18 JSI Entrance/Slab Guard House 25 25 10-15 30.0 400 14-Oct-18 4-Nov-18 18.40 73.60 9714-CIV-RFI-391 27.46 109.84 9714-CIV-RFI-582
184 8-Oct-18 JSI Slab Cable Trench Switch yard 25 25 10-15 30.0 400 15-Oct-18 5-Nov-18 18.96 75.84 9714-CIV-RFI-392 18.40 73.60 9714-CIV-RFI-583
185 8-Oct-18 JSI Slab Parking Motor cycle 25 25 10-15 30.0 400 15-Oct-18 5-Nov-18 18.96 75.84 9714-CIV-RFI-392 18.40 73.60 9714-CIV-RFI-583
186 9-Oct-18 JSI Pavement Arround Bundwall Oil daily Tank 25 25 10-15 30.0 400 16-Oct-18 6-Nov-18 18.68 74.72 9714-CIV-RFI-393 27.03 108.12 9714-CIV-RFI-583A
187 9-Oct-18 JSI Tie Beam Firewall 25 25 10-15 30.0 400 16-Oct-18 6-Nov-18 18.68 74.72 9714-CIV-RFI-393 27.03 108.12 9714-CIV-RFI-583A
188 10-Oct-18 JSI Footing Pipe Sleeper 25 25 10-15 30.0 400 17-Oct-18 7-Nov-18 18.30 73.20 9714-CIV-RFI-394 26.32 105.28 9714-CIV-RFI-583B
189 10-Oct-18 JSI Pedestal Parking Motor cycle 25 25 10-15 30.0 400 17-Oct-18 7-Nov-18 18.30 73.20 9714-CIV-RFI-394 26.32 105.28 9714-CIV-RFI-583B
190 10-Oct-18 JSI Lean Concrete (LC) Bundwall sisi Barat 15 15 10-15 30.0 321 17-Oct-18 7-Nov-18 12.32 82.10 9714-CIV-RFI-394 16.84 112.27 9714-CIV-RFI-583B
191 11-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 18-Oct-18 8-Nov-18 18.54 74.16 9714-CIV-RFI-395 27.03 108.12 9714-CIV-RFI-598
192 12-Oct-18 JSI footing Switchyard PCD06 25 25 10-15 30.0 400 19-Oct-18 9-Nov-18 18.40 73.60 9714-CIV-RFI-398 28.02 112.08 9714-CIV-RFI-599
193 12-Oct-18 JSI Lean Concrete (LC) Drainage Admin 25 25 10-15 30.0 400 19-Oct-18 9-Nov-18 18.40 73.60 9714-CIV-RFI-398 28.02 112.08 9714-CIV-RFI-599
194 13-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 20-Oct-18 10-Nov-18 18.04 72.16 9714-CIV-RFI-399 26.75 107.00 9714-CIV-RFI-600
195 13-Oct-18 JSI Lean Concrete (LC) Under ground Duct Bank EDG 07 15 15 10-15 30.0 321 20-Oct-18 10-Nov-18 12.17 81.13 9714-CIV-RFI-399 15.71 104.73 9714-CIV-RFI-600
196 14-Oct-18 JSI Ductbank Under ground Duct Bank EDG 07 25 25 10-15 30.0 400 21-Oct-18 11-Nov-18 18.26 73.04 9714-CIV-RFI-400 27.03 108.12 9714-CIV-RFI-608
197 14-Oct-18 JSI Footing, Tie Beam Bundwall 25 25 10-15 30.0 400 21-Oct-18 11-Nov-18 18.26 73.04 9714-CIV-RFI-400 27.03 108.12 9714-CIV-RFI-608
198 15-Oct-18 not supply concerete
199 16-Oct-18 JSI wall POND 6 25 25 10-15 30.0 400 23-Oct-18 13-Nov-18 18.82 75.28 9714-CIV-RFI-402 27.32 109.28 9714-CIV-RFI-610
200 16-Oct-18 JSI Slab Cable Trench Switch yard 25 25 10-15 30.0 400 23-Oct-18 13-Nov-18 18.82 75.28 9714-CIV-RFI-402 27.32 109.28 9714-CIV-RFI-610
201 17-Oct-18 JSI Wall Firewall Elv. 1.500 25 25 10-15 30.0 400 24-Oct-18 14-Nov-18 18.68 74.72 9714-CIV-RFI-441 27.17 108.68 9714-CIV-RFI-611

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

202 17-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10-15 30.0 400 24-Oct-18 14-Nov-18 18.68 74.72 9714-CIV-RFI-441 27.17 108.68 9714-CIV-RFI-611
203 18-Oct-18 JSI Wall Cable Trench Switch yard 25 25 10.0 30.0 400 25-Oct-18 15-Nov-18 18.40 73.60 9714-CIV-RFI-442 27.92 111.68 9714-CIV-RFI-613
204 18-Oct-18 JSI Footing Swictyard PCD2,PCD5A,PCD3&PCD5B 25 25 10.0 30.0 400 25-Oct-18 15-Nov-18 18.40 73.60 9714-CIV-RFI-442 27.92 111.68 9714-CIV-RFI-613
205 19-Oct-18 JSI Footing Swictyard PCD2,PCD5A,PCD3&PCD5B 25 25 10.0 30.0 400 26-Oct-18 16-Nov-18 20.66 82.64 9714-CIV-RFI-443 27.03 108.12 9714-CIV-RFI-616
206 19-Oct-18 JSI Wall Bundwall 25 25 10.0 30.0 400 26-Oct-18 16-Nov-18 20.66 82.64 9714-CIV-RFI-443 27.03 108.12 9714-CIV-RFI-616
207 19-Oct-18 JSI Lean Concrete (LC) Cable Trench Mosque 25 25 10.0 30.0 400 26-Oct-18 16-Nov-18 20.66 82.64 9714-CIV-RFI-443 27.03 108.12 9714-CIV-RFI-616
208 20-Oct-18 JSI Footing Swictyard PCD3&PCD5B 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
209 20-Oct-18 JSI Slab CCR-Powerhouse Loading unloading 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
210 20-Oct-18 JSI Wall Cable Trench Switchyard 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
211 20-Oct-18 JSI Lean Concrete (LC) Foundation PC Swictyard 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
212 20-Oct-18 JSI Panel Fence Motor park 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
213 20-Oct-18 JSI Slab Drainage Guard House 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
214 20-Oct-18 JSI Wall Firewall trasformer 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
215 20-Oct-18 JSI Slab Car Park 25 25 7.0 30.0 400 27-Oct-18 17-Nov-18 18.40 73.60 9714-CIV-RFI-444 27.32 109.28 9714-CIV-RFI-622
216 21-Oct-18 not supply concrete
217 22-Oct-18 JSI Wall Bak Kontrol swictyard 25 25 10.0 30.0 400 29-Oct-18 19-Nov-18 18.68 74.72 9714-CIV-RFI-446 26.61 106.44 9714-CIV-RFI-623
218 22-Oct-18 JSI Panel Fence Motor park 25 25 10.0 30.0 400 29-Oct-18 19-Nov-18 18.68 74.72 9714-CIV-RFI-446 26.61 106.44 9714-CIV-RFI-623
219 22-Oct-18 JSI Slab & Wall Cable Trach - Mosque 25 25 10.0 30.0 400 29-Oct-18 19-Nov-18 18.68 74.72 9714-CIV-RFI-446 26.61 106.44 9714-CIV-RFI-623
220 22-Oct-18 JSI Slab Car Park 25 25 10.0 30.0 400 29-Oct-18 19-Nov-18 18.68 74.72 9714-CIV-RFI-446 26.61 106.44 9714-CIV-RFI-623
221 22-Oct-18 JSI Footing Swictyard PCD3&PCD5A 25 25 10.0 30.0 400 29-Oct-18 19-Nov-18 18.68 74.72 9714-CIV-RFI-446 26.61 106.44 9714-CIV-RFI-623
222 23-Oct-18 not supply concrete
223 24-Oct-18 JSI Footing Swictyard PCD2&PCD3 25 25 7.0 30.0 400 31-Oct-18 21-Nov-18 18.25 73.00 9714-CIV-RFI-448 28.17 112.68 9714-CIV-RFI-637
224 24-Oct-18 JSI Wall Bundwall 25 25 7.5 30.0 400 31-Oct-18 21-Nov-18 18.25 73.00 9714-CIV-RFI-448 28.17 112.68 9714-CIV-RFI-637
225 24-Oct-18 JSI Slab Parking Car 25 25 10.0 30.0 400 31-Oct-18 21-Nov-18 18.25 73.00 9714-CIV-RFI-448 28.17 112.68 9714-CIV-RFI-637
226 25-Oct-18 JSI wall Firewall Transformer Second layer elv.3.00 25 25 10.0 30.0 400 1-Nov-18 22-Nov-18 18.82 75.28 9714-CIV-RFI-556A 28.73 114.92 9714-CIV-RFI-638
227 25-Oct-18 JSI Slab Bundwall 25 25 10.0 30.0 400 1-Nov-18 22-Nov-18 18.82 75.28 9714-CIV-RFI-556A 28.73 114.92 9714-CIV-RFI-638
228 25-Oct-18 JSI Slab Drainage (A2) A2 25 25 10.0 30.0 400 1-Nov-18 22-Nov-18 18.82 75.28 9714-CIV-RFI-556A 28.73 114.92 9714-CIV-RFI-638
229 26-Oct-18 JSI Wall Drainage (A2) A2 25 25 10.0 30.0 400 2-Nov-18 23-Nov-18 17.97 71.88 9714-CIV-RFI-557A 26.46 105.84 9714-CIV-RFI-650
230 26-Oct-18 JSI Lean Concrete (LC) Annex 15 15 10.0 30.0 321 2-Nov-18 23-Nov-18 11.75 78.33 9714-CIV-RFI-557A 26.46 176.40 9714-CIV-RFI-650
231 26-Oct-18 JSI Rigid Road & Pavement Depan Admin Build 25 25 10.0 30.0 400 2-Nov-18 23-Nov-18 17.97 71.88 9714-CIV-RFI-557A 26.46 105.84 9714-CIV-RFI-650
232 26-Oct-18 JSI Slab Drainage (A2) A2 25 25 10.0 30.0 400 2-Nov-18 23-Nov-18 17.97 71.88 9714-CIV-RFI-557A 26.46 105.84 9714-CIV-RFI-650
233 27-Oct-18 not supply concrete
234 28-Oct-18 not supply concrete
235 29-Oct-18 JSI Wall Firewall 25 25 30.0 400 5-Nov-18 26-Nov-18 27.46 109.84 9714-CIV-RFI-583 26.47 105.86 9714-CIV-RFI-655
236 29-Oct-18 JSI Lean Concrete (LC) Annex 25 25 30.0 400 5-Nov-18 26-Nov-18 27.46 109.84 9714-CIV-RFI-583 26.47 105.86 9714-CIV-RFI-655
237 29-Oct-18 JSI Foundation Pipe Sleeper for Fuel Oil and Fire Water 25 25 5.0 30.0 400 5-Nov-18 26-Nov-18 27.46 109.84 9714-CIV-RFI-583 26.47 105.86 9714-CIV-RFI-655
238 29-Oct-18 JSI Precast panel Fence 25 25 1.0 30.0 400 5-Nov-18 26-Nov-18 27.46 109.84 9714-CIV-RFI-583 26.47 105.86 9714-CIV-RFI-655
239 30-Oct-18 JSI Wall Bundwall 25 25 30.0 400 6-Nov-18 27-Nov-18 18.54 74.16 9714-CIV-RFI-583A 27.03 108.12 9714-CIV-RFI-656
240 30-Oct-18 JSI Wall Drainage (A2) 25 25 30.0 400 6-Nov-18 27-Nov-18 18.54 74.16 9714-CIV-RFI-583A 27.03 108.12 9714-CIV-RFI-656
241 30-Oct-18 JSI Rigid Road & Pavement Depan Admin Build 25 25 10.0 30.0 400 6-Nov-18 27-Nov-18 18.54 74.16 9714-CIV-RFI-583A 27.03 108.12 9714-CIV-RFI-656

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

242 31-Oct-18 JSI Slab Cable Trench Transformer 25 25 6.0 30.0 400 7-Nov-18 28-Nov-18 18.40 73.60 9714-CIV-RFI-583B 18.54 74.16 9714-CIV-RFI-658
243 31-Oct-18 JSI Slab Drainage Depan Admin 25 25 6.0 30.0 400 7-Nov-18 28-Nov-18 18.40 73.60 9714-CIV-RFI-583B 18.54 74.16 9714-CIV-RFI-658
244 1-Nov-18 JSI Ductbank BD08 25 25 6.0 30.0 400 8-Nov-18 29-Nov-18 18.40 73.60 9714-CIV-RFI-598 26.75 107.00 9714-CIV-RFI-662
245 1-Nov-18 JSI Footing, Tie Beam Slab Power House Annex 25 25 6.0 30.0 400 8-Nov-18 29-Nov-18 18.40 73.60 9714-CIV-RFI-598 26.75 107.00 9714-CIV-RFI-662
246 1-Nov-18 JSI Footing PipeRack 25 25 6.0 30.0 400 8-Nov-18 29-Nov-18 18.40 73.60 9714-CIV-RFI-598 26.75 107.00 9714-CIV-RFI-662
247 1-Nov-18 JSI Wall Drainage A2 25 25 6.0 30.0 400 8-Nov-18 29-Nov-18 18.40 73.60 9714-CIV-RFI-598 26.75 107.00 9714-CIV-RFI-662
248 2-Nov-18 not supply concrete
249 3-Nov-18 JSI Footing Pipe Sleeper Fuel Oil water 13pcs 25 25 30.0 400 10-Nov-18 1-Dec-18 18.82 75.28 9714-CIV-RFI-600 26.32 105.28 9714-CIV-RFI-675
250 3-Nov-18 JSI Pedestal Piperack 2 pcs 25 25 30.0 400 10-Nov-18 1-Dec-18 18.82 75.28 9714-CIV-RFI-600 26.32 105.28 9714-CIV-RFI-675
251 3-Nov-18 JSI Pedestal Anex (PD3) 2 pcs 25 25 30.0 400 10-Nov-18 1-Dec-18 18.82 75.28 9714-CIV-RFI-600 26.32 105.28 9714-CIV-RFI-675
252 3-Nov-18 JSI Lean Concrete (LC) Radiator 25 25 30.0 400 10-Nov-18 1-Dec-18 18.82 75.28 9714-CIV-RFI-600 26.32 105.28 9714-CIV-RFI-675
253 3-Nov-18 JSI Slab Drainage A2 25 25 30.0 400 10-Nov-18 1-Dec-18 18.82 75.28 9714-CIV-RFI-600 26.32 105.28 9714-CIV-RFI-675
254 4-Nov-18 JSI Wall Drainage A2 25 25 30.0 400 11-Nov-18 2-Dec-18 18.40 73.60 9714-CIV-RFI-608 26.75 107.00 9714-CIV-RFI-676
255 4-Nov-18 JSI Precast Panel Fence 25 25 30.0 400 11-Nov-18 2-Dec-18 18.40 73.60 9714-CIV-RFI-608 26.75 107.00 9714-CIV-RFI-676
256 4-Nov-18 JSI Slab Drainage A2 25 25 30.0 400 11-Nov-18 2-Dec-18 18.40 73.60 9714-CIV-RFI-608 26.75 107.00 9714-CIV-RFI-676
257 5-Nov-18 JSI Wall (3rd layer) Firewall 25 25 30.0 400 12-Nov-18 3-Dec-18 18.40 73.60 9714-CIV-RFI-609 26.18 104.72 9714-CIV-RFI-677
258 5-Nov-18 JSI Wall Cable Trench Transformer 25 25 30.0 400 12-Nov-18 3-Dec-18 18.40 73.60 9714-CIV-RFI-609 26.18 104.72 9714-CIV-RFI-677
259 5-Nov-18 JSI Pedestal Parking Car 25 25 30.0 400 12-Nov-18 3-Dec-18 18.40 73.60 9714-CIV-RFI-609 26.18 104.72 9714-CIV-RFI-677
260 6-Nov-18 JSI Foundation Pipe Sleeper Fuel Oil water 25 25 30.0 400 13-Nov-18 4-Dec-18 17.97 71.88 9714-CIV-RFI-610 26.32 105.28 9714-CIV-RFI-686
261 6-Nov-18 JSI Lean Concrete (LC) PipeSleeper Radiator 25 25 30.0 400 13-Nov-18 4-Dec-18 17.97 71.88 9714-CIV-RFI-610 26.32 105.28 9714-CIV-RFI-686
262 6-Nov-18 JSI Lean Concrete (LC) Cable Trench Admin 25 25 30.0 400 13-Nov-18 4-Dec-18 17.97 71.88 9714-CIV-RFI-610 26.32 105.28 9714-CIV-RFI-686
263 6-Nov-18 JSI Foundation Pipe Sleeper Batam 25 25 30.0 400 13-Nov-18 4-Dec-18 17.97 71.88 9714-CIV-RFI-610 26.32 105.28 9714-CIV-RFI-686
264 7-Nov-18 JSI Wall Bundwall 25 25 30.0 400 14-Nov-18 5-Dec-18 17.97 71.88 9714-CIV-RFI-611 26.33 105.32 9714-CIV-RFI-687
265 7-Nov-18 JSI Wall Firewall 25 25 30.0 400 14-Nov-18 5-Dec-18 17.97 71.88 9714-CIV-RFI-611 26.33 105.32 9714-CIV-RFI-687
266 7-Nov-18 JSI Wall Drainage A2 25 25 30.0 400 14-Nov-18 5-Dec-18 17.97 71.88 9714-CIV-RFI-611 26.33 105.32 9714-CIV-RFI-687
267 8-Nov-18 JSI Slab Drainage A2 25 25 30.0 400 15-Nov-18 6-Dec-18 18.23 72.92 9714-CIV-RFI-613 26.04 104.16 9714-CIV-RFI-688
268 8-Nov-18 JSI Slab Cable Trench 25 25 30.0 400 15-Nov-18 6-Dec-18 18.23 72.92 9714-CIV-RFI-613 26.04 104.16 9714-CIV-RFI-688
269 8-Nov-18 JSI Footing Radiator 25 25 30.0 400 15-Nov-18 6-Dec-18 18.23 72.92 9714-CIV-RFI-613 26.04 104.16 9714-CIV-RFI-688
270 9-Nov-18 not supply concrete
271 10-Nov-18 JSI Rigid Road & Pavement Radius depan Toilet 25 25 30.0 400 17-Nov-18 8-Dec-18 18.25 73.00 9714-CIV-RFI-622 26.61 106.44 9714-CIV-RFI-720
272 10-Nov-18 JSI Wall Drainage A2 25 25 30.0 400 17-Nov-18 8-Dec-18 18.25 73.00 9714-CIV-RFI-622 26.61 106.44 9714-CIV-RFI-720
273 11-Nov-18 JSI Rigid Road & Pavement Depan Mosque 25 25 30.0 400 18-Nov-18 9-Dec-18 18.40 73.60 9714-CIV-RFI-623 30.34 121.34 9714-CIV-RFI-721

274 12-Nov-18 JSI Wall Drainage A2 (Dekat Musolla dan PLN 25 25 30.0 400 19-Nov-18 10-Dec-18 18.68 74.72 9714-CIV-RFI-623 27.18 108.72 9714-CIV-RFI-722
-Batam)
275 13-Nov-18 JSI Foundation PipeSleeper Radiator - Annex 25 25 30.0 400 20-Nov-18 11-Dec-18 20.52 82.08 9714-CIV-RFI-636 26.61 106.44 9714-CIV-RFI-723
276 13-Nov-18 JSI Lean Concrete (LC) Drainage A2 Radius Admin 25 25 30.0 400 20-Nov-18 11-Dec-18 20.52 82.08 9714-CIV-RFI-636 26.61 106.44 9714-CIV-RFI-723
277 13-Nov-18 JSI Precast Panel Fence 25 25 30.0 400 20-Nov-18 11-Dec-18 20.52 82.08 9714-CIV-RFI-636 26.61 106.44 9714-CIV-RFI-723
278 15-Nov-18 JSI Top Wall Firewall 4rd Layer 25 25 30.0 400 22-Nov-18 13-Dec-18 19.81 79.24 9714-CIV-RFI-638 26.90 107.58 9714-CIV-RFI-724
279 15-Nov-18 JSI Footing Cooling water 25 25 30.0 400 22-Nov-18 13-Dec-18 19.81 79.24 9714-CIV-RFI-638 26.90 107.58 9714-CIV-RFI-724
280 15-Nov-18 JSI Additonal Repair Footing Switch yard 25 25 30.0 400 22-Nov-18 13-Dec-18 19.81 79.24 9714-CIV-RFI-638 26.90 107.58 9714-CIV-RFI-724
281 16-Nov-18 JSI Rigid Road & Pavement Depan Admin Radius 25 25 30.0 400 23-Nov-18 14-Dec-18 19.96 79.84 9714-CIV-RFI-650 27.46 109.84 9714-CIV-RFI-725

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

282 16-Nov-18 JSI wall Precast Precast Panel Fence 15 25 30.0 400 23-Nov-18 14-Dec-18 19.96 133.07 9714-CIV-RFI-650 27.46 183.07 9714-CIV-RFI-725
283 16-Nov-18 JSI Lean Concrete (LC) Drainage A2 15 25 30.0 400 23-Nov-18 14-Dec-18 19.96 133.07 9714-CIV-RFI-650 27.46 183.07 9714-CIV-RFI-725
284 17-Nov-18 JSI Pedestal Cooling water Tank 25 25 30.0 400 24-Nov-18 15-Dec-18 18.96 75.84 9714-CIV-RFI-653 25.90 103.60 9714-CIV-RFI-726
285 17-Nov-18 JSI Slab Bundwall 25 25 30.0 400 24-Nov-18 15-Dec-18 18.96 75.84 9714-CIV-RFI-653 25.90 103.60 9714-CIV-RFI-726
286 17-Nov-18 JSI Additonal Repair Footing Switch yard 25 25 30.0 400 24-Nov-18 15-Dec-18 18.96 75.84 9714-CIV-RFI-653 25.90 103.60 9714-CIV-RFI-726
287 17-Nov-18 JSI Slab/Entrance Admin Building 25 25 30.0 400 24-Nov-18 15-Dec-18 18.96 75.84 9714-CIV-RFI-653 25.90 103.60 9714-CIV-RFI-726
288 18-Nov-18 JSI Drainage Bundwall 25 25 30.0 400 25-Nov-18 16-Dec-18 19.11 76.42 9714-CIV-RFI-654 25.77 103.08 9714-CIV-RFI-727
289 18-Nov-18 JSI Slab Cable Trench 25 25 30.0 400 25-Nov-18 16-Dec-18 19.11 76.42 9714-CIV-RFI-654 25.77 103.08 9714-CIV-RFI-727
290 18-Nov-18 Footing Switch yard 25 25 30.0 400 25-Nov-18 16-Dec-18 19.11 76.42 9714-CIV-RFI-654 25.77 103.08 9714-CIV-RFI-727
291 19-Nov-18 JSI Slab Drainage 25 25 30.0 400 26-Nov-18 17-Dec-18 19.61 78.42 9714-CIV-RFI-655 26.33 105.30 9714-CIV-RFI-728
292 19-Nov-18 JSI Panel Fence Workshop precast 25 25 30.0 400 26-Nov-18 17-Dec-18 19.61 78.42 9714-CIV-RFI-655 26.33 105.30 9714-CIV-RFI-728
293 19-Nov-18 JSI Lean Concrete (LC) PIT Used Lube Oil Tank 15 15 30.0 310 26-Nov-18 17-Dec-18 11.61 77.37 9714-CIV-RFI-655 17.55 117.00 9714-CIV-RFI-728
294 20-Nov-18 JSI Additonal Repair Footing Switch yard 25 25 30.0 400 27-Nov-18 18-Dec-18 18.40 73.60 9714-CIV-RFI-656 26.90 107.58 9714-CIV-RFI-729
295 20-Nov-18 JSI Wall Drainage A2 Depan admin 25 25 30.0 400 27-Nov-18 18-Dec-18 18.40 73.60 9714-CIV-RFI-656 26.90 107.58 9714-CIV-RFI-729
296 20-Nov-18 JSI wall & Top Slab Box Culvert 25 25 30.0 400 27-Nov-18 18-Dec-18 18.40 73.60 9714-CIV-RFI-656 26.90 107.58 9714-CIV-RFI-729
297 20-Nov-18 JSI Foundation PipeSleeper Dekat Gas metering 25 25 30.0 400 27-Nov-18 18-Dec-18 18.40 73.60 9714-CIV-RFI-656 26.90 107.58 9714-CIV-RFI-729
298 20-Nov-18 JSI Foundation Lighting Pole Precast, 13pcs 25 25 30.0 400 27-Nov-18 18-Dec-18 18.40 73.60 9714-CIV-RFI-656 26.90 107.58 9714-CIV-RFI-729
299 21-Nov-18 JSI Slab Drainage A2 Samping Admin 25 25 30.0 400 28-Nov-18 19-Dec-18 18.54 74.16 9714-CIV-RFI-658 26.61 106.44 9714-CIV-RFI-729A
300 22-Nov-18 not supply concrete
301 23-Nov-18 not supply concrete
302 24-Nov-18 JSI Wall Firewall 25 25 30.0 400 1-Dec-18 22-Dec-18 18.54 74.16 9714-CIV-RFI-675 25.78 103.12 9714-CIV-RFI-740A
303 24-Nov-18 JSI Slab Drainage A2 25 25 30.0 400 1-Dec-18 22-Dec-18 18.54 74.16 9714-CIV-RFI-675 25.78 103.12 9714-CIV-RFI-740A
304 24-Nov-18 JSI Wall Drainage A2 25 25 30.0 400 1-Dec-18 22-Dec-18 18.54 74.16 9714-CIV-RFI-675 25.78 103.12 9714-CIV-RFI-740A
305 24-Nov-18 JSI Foundation Lighting Pole 25 25 30.0 400 1-Dec-18 22-Dec-18 18.54 74.16 9714-CIV-RFI-675 25.78 103.12 9714-CIV-RFI-740A
306 24-Nov-18 JSI Foundation Sleeper Pinggir pagar engine 25 25 30.0 400 1-Dec-18 22-Dec-18 18.54 74.16 9714-CIV-RFI-675 25.78 103.12 9714-CIV-RFI-740A
307 25-Nov-18 JSI Slab & Pedestal PIT Used Lube Oil Tank 25 25 30.0 400 2-Dec-18 23-Dec-18 18.40 73.60 9714-CIV-RFI-676 26.90 107.58 9714-CIV-RFI-742A
308 25-Nov-18 JSI Slab & Wall Drainage A2 25 25 30.0 400 2-Dec-18 23-Dec-18 18.40 73.60 9714-CIV-RFI-676 26.90 107.58 9714-CIV-RFI-742A
309 25-Nov-18 JSI Foundation Sleeper Unloading Pump 25 25 30.0 400 2-Dec-18 23-Dec-18 18.40 73.60 9714-CIV-RFI-676 26.90 107.58 9714-CIV-RFI-742A
310 26-Nov-18 JSI Rigid Road pavement Unloading Pump Truck 25 25 30.0 400 3-Dec-18 24-Dec-18 18.82 75.28 9714-CIV-RFI-677 27.17 108.68 9714-CIV-RFI-755
311 26-Nov-18 JSI Slab & Wall Drainage A2 25 25 30.0 400 3-Dec-18 24-Dec-18 18.82 75.28 9714-CIV-RFI-677 27.17 108.68 9714-CIV-RFI-755
312 27-Nov-18 JSI Precast Panel Fence 25 25 30.0 400 4-Dec-18 25-Dec-18 12.03 48.12 9714-CIV-RFI-686 26.89 107.56 9714-CIV-RFI-756
313 27-Nov-18 JSI Concrete Cover Cable Trench Engine Hall 25 25 30.0 400 4-Dec-18 25-Dec-18 18.82 75.28 9714-CIV-RFI-686 26.89 107.56 9714-CIV-RFI-756
314 27-Nov-18 JSI Wall And Top Culvert & Drainage 25 25 30.0 400 4-Dec-18 25-Dec-18 18.82 75.28 9714-CIV-RFI-686 26.89 107.56 9714-CIV-RFI-756
315 27-Nov-18 JSI Foundation Pipe Sleeper 25 25 30.0 400 4-Dec-18 25-Dec-18 18.82 75.28 9714-CIV-RFI-686 26.89 107.56 9714-CIV-RFI-756
316 28-Nov-18 JSI Precast Panel Fence 15 15 30.0 400 5-Dec-18 26-Dec-18 11.55 77.00 9714-CIV-RFI-687 16.70 111.33 9714-CIV-RFI-757
317 29-Nov-18 JSI Pedestal Lighting Pole 25 25 30.0 400 6-Dec-18 27-Dec-18 18.82 75.28 9714-CIV-RFI-688 26.89 107.56 9714-CIV-RFI-758
318 29-Nov-18 JSI wall Drianage 25 25 30.0 400 6-Dec-18 27-Dec-18 18.82 75.28 9714-CIV-RFI-688 26.89 107.56 9714-CIV-RFI-758
319 30-Nov-18 JSI Slab Drainage 25 25 30.0 400 7-Dec-18 28-Dec-18 18.83 75.30 9714-CIV-RFI-719 26.89 107.56 9714-CIV-RFI-761
320 30-Nov-18 JSI Wall PIT Used Lube Oil Tank 25 25 30.0 400 7-Dec-18 28-Dec-18 18.83 75.30 9714-CIV-RFI-719 26.89 107.56 9714-CIV-RFI-761
321 1-Dec-18 JSI Wall Drainage 25 25 30.0 400 8-Dec-18 29-Dec-18 19.25 77.00 9714-CIV-RFI-720 25.76 103.04 9714-CIV-RFI-762A

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

322 2-Dec-18 JSI Ductbank Ductbank DB 3 25 25 30.0 400 9-Dec-18 30-Dec-18 19.25 77.00 9714-CIV-RFI-721 26.32 105.28 9714-CIV-RFI-762B
323 2-Dec-18 JSI Wall Drainage 25 25 30.0 400 9-Dec-18 30-Dec-18 19.25 77.00 9714-CIV-RFI-721 26.32 105.28 9714-CIV-RFI-762B
324 3-Dec-18 JSI Slab & Wall Drainage 25 25 30.0 400 10-Dec-18 31-Dec-18 18.69 74.74 9714-CIV-RFI-722 26.33 105.30 9714-CIV-RFI-762C
325 4-Dec-18 JSI Rigid Segment 26 & 24B Road & Pavement Segment 25 25 30.0 400 11-Dec-18 1-Jan-19 20.10 80.40 9714-CIV-RFI-723 26.04 104.16 9714-CIV-RFI-765
326 4-Dec-18 JSI Pedestal Lighting Pole 25 25 30.0 400 11-Dec-18 1-Jan-19 20.10 80.40 9714-CIV-RFI-723 26.04 104.16 9714-CIV-RFI-765
327 5-Dec-18 not supply concrete
328 6-Dec-18 not supply concrete
329 7-Dec-18 not supply concrete
330 8-Dec-18 JSI Ductbank Crossing Road 25 25 6.0 30.0 400 15-Dec-18 5-Jan-19 19.55 78.21 9714-CIV-RFI-726 25.47 101.88 9714-CIV-RFI-782
331 8-Dec-18 JSI Rigid Segment 30A & 24A,24C Road & Pavement Segment 25 25 6.0 30.0 400 15-Dec-18 5-Jan-19 19.55 78.21 9714-CIV-RFI-726 25.47 101.88 9714-CIV-RFI-782
332 8-Dec-18 JSI Slab & Wall Drainage 25 25 6.0 30.0 400 15-Dec-18 5-Jan-19 19.55 78.21 9714-CIV-RFI-726 25.47 101.88 9714-CIV-RFI-782
333 8-Dec-18 JSI Rigid Segment 62 Road & Pavement Segment (In front of 25 25 6.0 30.0 400 15-Dec-18 5-Jan-19 19.55 78.21 9714-CIV-RFI-726 25.47 101.88 9714-CIV-RFI-782
Waste Chemical Building)
334 9-Dec-18 JSI Rigid Segment 30C & 32 B Road & Pavement Segment 25 25 9.5 30.0 400 16-Dec-18 6-Jan-19 19.82 79.28 9714-CIV-RFI-727 26.32 105.28 9714-CIV-RFI-784
335 9-Dec-18 JSI Slab & Wall , Top Drainage 25 25 10.0 30.0 400 16-Dec-18 6-Jan-19 19.82 79.28 9714-CIV-RFI-727 26.32 105.28 9714-CIV-RFI-784
336 9-Dec-18 JSI Cover Cable Tranch Engine E 25 25 10.0 30.0 400 16-Dec-18 6-Jan-19 19.82 79.28 9714-CIV-RFI-727 26.32 105.28 9714-CIV-RFI-784
337 10-Dec-18 JSI Footing Fence at West Plant 25 25 8.0 30.0 400 17-Dec-18 7-Jan-19 19.53 78.12 9714-CIV-RFI-728 25.76 103.04 9714-CIV-RFI-803
338 10-Dec-18 JSI Rigid Segment 28 & 32 A & 32 C,30B Road & Pavement Segment 25 25 8.0 30.0 400 17-Dec-18 7-Jan-19 19.53 78.12 9714-CIV-RFI-728 25.76 103.04 9714-CIV-RFI-803
339 10-Dec-18 JSI Slab & Wall Open Drainage 25 25 8.0 30.0 400 17-Dec-18 7-Jan-19 19.53 78.12 9714-CIV-RFI-728 25.76 103.04 9714-CIV-RFI-803
340 11-Dec-18 JSI Rigid Segment 26 A & 25C, 30C Road & Pavement Segment 25 25 8.0 30.0 400 18-Dec-18 8-Jan-19 19.82 79.26 9714-CIV-RFI-729 26.04 104.16 9714-CIV-RFI-804
341 11-Dec-18 JSI Slab Open Drainage 25 25 8.0 30.0 400 18-Dec-18 8-Jan-19 19.82 79.26 9714-CIV-RFI-729 26.04 104.16 9714-CIV-RFI-804
342 11-Dec-18 JSI Footing Lighting Pole 25 25 8.0 30.0 400 18-Dec-18 8-Jan-19 19.82 79.26 9714-CIV-RFI-729 26.04 104.16 9714-CIV-RFI-804
343 12-Dec-18 JSI Rigid Segment 25 B & 25A Road & Pavement Segment 25 25 8.0 30.0 400 19-Dec-18 9-Jan-19 20.10 80.40 9714-CIV-RFI-729A 25.76 103.04 9714-CIV-RFI-805
344 12-Dec-18 JSI Lean Concrete (LC) Open Drainage Near Elevated Guard House 25 25 8.0 30.0 400 19-Dec-18 9-Jan-19 20.10 80.40 9714-CIV-RFI-729A 25.76 103.04 9714-CIV-RFI-805
345 13-Dec-18 JSI Lean Concrete (LC) Elevated Guard House 25 25 8.0 30.0 400 20-Dec-18 10-Jan-19 19.53 78.12 9714-CIV-RFI-739 26.04 104.16 9714-CIV-RFI-811
346 13-Dec-18 JSI Footing & Beam Fence at East Plant 25 25 8.0 30.0 400 20-Dec-18 10-Jan-19 19.53 78.12 9714-CIV-RFI-739 26.04 104.16 9714-CIV-RFI-811
347 13-Dec-18 JSI Slab & Wall Open Drainage 25 25 8.0 30.0 400 20-Dec-18 10-Jan-19 19.53 78.12 9714-CIV-RFI-739 26.04 104.16 9714-CIV-RFI-811
348 14-Dec-18 JSI Rigid Segment 27B& 29A Road & Pavement Segment 25 25 8.0 30.0 400 21-Dec-18 11-Jan-19 19.81 79.24 9714-CIV-RFI-742 26.32 105.28 9714-CIV-RFI-827
349 15-Dec-18 JSI Rigid Segment 27A&31A Road & Pavement Segment 25 25 8.0 30.0 400 22-Dec-18 12-Jan-19 19.53 78.12 9714-CIV-RFI-740A 25.76 103.04 9714-CIV-RFI-828
350 15-Dec-18 JSI Tie Beam Fence at West Plant 25 25 8.0 30.0 400 22-Dec-18 12-Jan-19 19.53 78.12 9714-CIV-RFI-740A 25.76 103.04 9714-CIV-RFI-828
351 16-Dec-18 JSI Road & Pavement Segment 25 25 8.0 30.0 400 23-Dec-18 13-Jan-19 19.54 78.14 9714-CIV-RFI-742A 25.76 103.04 9714-CIV-RFI-837
352 16-Dec-18 JSI Slab And Wall Open Drainage 25 25 8.0 30.0 400 23-Dec-18 13-Jan-19 19.54 78.14 9714-CIV-RFI-742A 25.76 103.04 9714-CIV-RFI-837
353 17-Dec-18 JSI Rigid Segment 34A Road & Pavement Segment 25 25 8.0 30.0 400 24-Dec-18 14-Jan-19 19.53 78.12 9714-CIV-RFI-755 26.04 104.16 9714-CIV-RFI-838
354 17-Dec-18 JSI Footing Lighting Pole 25 25 8.0 30.0 400 24-Dec-18 14-Jan-19 19.53 78.12 9714-CIV-RFI-755 26.04 104.16 9714-CIV-RFI-838
355 18-Dec-18 JSI Rigid Segment 61C & 61B, 34B,34C Road & Pavement Segment 25 25 8.0 30.0 400 25-Dec-18 15-Jan-19 19.25 77.00 9714-CIV-RFI-756 25.76 103.04 9714-CIV-RFI-841
356 18-Dec-18 JSI Footing Lighting Pole 25 25 8.0 30.0 400 25-Dec-18 15-Jan-19 19.25 77.00 9714-CIV-RFI-756 25.76 103.04 9714-CIV-RFI-841
357 18-Dec-18 JSI Slab And Wall Open Drainage 25 25 8.0 30.0 400 25-Dec-18 15-Jan-19 19.25 77.00 9714-CIV-RFI-756 25.76 103.04 9714-CIV-RFI-841
358 19-Dec-18 JSI Footing Lighting Pole 25 25 10.0 30.0 400 26-Dec-18 16-Jan-19 16.70 66.80 9714-CIV-RFI-757 26.32 105.28 9714-CIV-RFI-842
359 19-Dec-18 JSI Rigid Segment 38B,38C Road & Pavement Segment 25 25 10.0 30.0 400 26-Dec-18 16-Jan-19 16.70 66.80 9714-CIV-RFI-757 26.32 105.28 9714-CIV-RFI-842
360 19-Dec-18 JSI Cover Cable Tranch Swictyard 25 25 10.0 30.0 400 26-Dec-18 16-Jan-19 16.70 66.80 9714-CIV-RFI-757 26.32 105.28 9714-CIV-RFI-842
361 20-Dec-18 JSI Rigid Segment 36AB Road & Pavement Segment 25 25 10.0 30.0 400 27-Dec-18 17-Jan-19 18.96 75.84 9714-CIV-RFI-758 25.76 103.04 9714-CIV-RFI-844

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

362 20-Dec-18 JSI Rigid Segment 59BC Road & Pavement Segment 25 25 10.0 30.0 400 27-Dec-18 17-Jan-19 18.96 75.84 9714-CIV-RFI-758 25.76 103.04 9714-CIV-RFI-844
363 21-Dec-18 JSI Rigid Segment 61A, 59C, 40AB Road & Pavement Segment 25 25 10.0 30.0 400 28-Dec-18 18-Jan-19 19.53 78.12 9714-CIV-RFI-761 26.04 104.16 9714-CIV-RFI-846
364 21-Dec-18 JSI Wall Open Drainage 25 25 10.0 30.0 400 28-Dec-18 18-Jan-19 19.53 78.12 9714-CIV-RFI-761 26.04 104.16 9714-CIV-RFI-846
365 22-Dec-18 JSI Rigid Segment Road & Pavement Segment 25 25 10.0 30.0 400 29-Dec-18 19-Jan-19 18.40 73.60 9714-CIV-RFI-762A 26.32 105.28 9714-CIV-RFI-851
366 22-Dec-18 JSI Slab Open Drainage 25 25 10.0 30.0 400 29-Dec-18 19-Jan-19 18.40 73.60 9714-CIV-RFI-762A 26.32 105.28 9714-CIV-RFI-851
367 23-Dec-18 JSI Rigid Segment 23A, 55C Road & Pavement Segment 25 25 10.0 30.0 400 30-Dec-18 20-Jan-19 19.28 77.12 9714-CIV-RFI-762B 26.04 104.16 9714-CIV-RFI-852
368 24-Dec-18
369 25-Dec-18
370 26-Dec-18 JSI Rigid Segment 57C Road & Pavement Segment 25 25 10.0 30.0 400 2-Jan-19 23-Jan-19 18.68 74.72 9714-CIV-RFI-766 26.61 106.44 9714-CIV-RFI-857
371 26-Dec-18 JSI Wall Open Drainage 25 25 10.0 30.0 400 2-Jan-19 23-Jan-19 18.68 74.72 9714-CIV-RFI-766 26.61 106.44 9714-CIV-RFI-857
372 27-Dec-18 JSI Rigid Segment 23B, 42A Road & Pavement Segment 25 25 10.0 30.0 400 3-Jan-19 24-Jan-19 18.96 75.84 9714-CIV-RFI-771 26.32 105.28 9714-CIV-RFI-858
373 27-Dec-18 JSI Pedestal Lighting Pole 25 25 10.0 30.0 400 3-Jan-19 24-Jan-19 18.96 75.84 9714-CIV-RFI-771 26.32 105.28 9714-CIV-RFI-858
374 28-Dec-18 JSI Wall Open Drainage Dekat loading truck 25 25 10.0 30.0 400 4-Jan-19 25-Jan-19 18.68 74.72 9714-CIV-RFI-775 26.05 104.18 9714-CIV-RFI-860
375 29-Dec-18 JSI Rigid Segment 42B Road & Pavement Segment 25 25 10.0 30.0 400 5-Jan-19 26-Jan-19 19.25 77.00 9714-CIV-RFI-782 25.76 103.04 9714-CIV-RFI-862
376 30-Dec-18 JSI Rigid Unloading truck Road & Pavement Segment 25 25 10.0 30.0 400 6-Jan-19 27-Jan-19 18.40 73.60 9714-CIV-RFI-784 26.33 105.30 9714-CIV-RFI-862A
377 30-Dec-18 JSI Foundation fire hydrant 25 25 10.0 30.0 400 6-Jan-19 27-Jan-19 18.40 73.60 9714-CIV-RFI-784 26.33 105.30 9714-CIV-RFI-862A
378 30-Dec-18 JSI Slab Drainage samping engine A 25 25 10.0 30.0 400 6-Jan-19 27-Jan-19 18.40 73.60 9714-CIV-RFI-784 26.33 105.30 9714-CIV-RFI-862A
379 31-Dec-18
380 1-Jan-19
Rigid Segment 51 ABC, Unloading
381 2-Jan-19 JSI Road & Pavement Segment 25 25 10.0 30.0 400 9-Jan-19 30-Jan-19 18.96 75.84 9714-CIV-RFI-805 26.33 105.32 9714-CIV-RFI-891
Truck,
382 3-Jan-19 JSI Rigid Segment 60ABC, 58BC, Road & Pavement Segment 25 25 10.0 30.0 400 10-Jan-19 31-Jan-19 18.68 74.72 9714-CIV-RFI-811 26.33 105.30 9714-CIV-RFI-892
383 3-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 10-Jan-19 31-Jan-19 18.68 74.72 9714-CIV-RFI-811 26.33 105.30 9714-CIV-RFI-892
384 4-Jan-19 JSI Rigid Segment 56A, 54ABC Road & Pavement Segment 25 25 10.0 30.0 400 11-Jan-19 1-Feb-19 18.96 75.84 9714-CIV-RFI-827 26.05 104.18 9714-CIV-RFI-893
385 4-Jan-19 JSI Rigid Rump Warehouse, workshop 25 25 10.0 30.0 400 11-Jan-19 1-Feb-19 18.96 75.84 9714-CIV-RFI-827 26.05 104.18 9714-CIV-RFI-893
386 5-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 12-Jan-19 2-Feb-19 18.96 75.84 9714-CIV-RFI-828 26.33 105.30 9714-CIV-RFI-894
387 6-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 13-Jan-19 3-Feb-19 18.40 73.60 9714-CIV-RFI-837 25.96 103.84 9714-CIV-RFI-895
388 6-Jan-19 JSI Rigid Pavement Road & Pavement Segment Loading Truck, Pump House 25 25 10.0 30.0 400 13-Jan-19 3-Feb-19 18.40 73.60 9714-CIV-RFI-837 25.96 103.84 9714-CIV-RFI-895
389 7-Jan-19 not supply concrete
390 8-Jan-19 JSI Rigid Segment 50ABC, 54C Road & Pavement Segment 25 25 10.0 30.0 400 15-Jan-19 5-Feb-19 18.96 75.84 9714-CIV-RFI-841 26.18 104.72 9714-CIV-RFI-899

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

391 8-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 15-Jan-19 5-Feb-19 18.96 75.84 9714-CIV-RFI-841 26.18 104.72 9714-CIV-RFI-899
392 9-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 16-Jan-19 6-Feb-19 18.68 74.72 9714-CIV-RFI-842 26.04 104.16 9714-CIV-RFI-900
393 10-Jan-19 JSI Rigid Segment 44ABC Road & Pavement Segment 25 25 10.0 30.0 400 17-Jan-19 7-Feb-19 18.68 74.72 9714-CIV-RFI-844 25.76 103.04 9714-CIV-RFI-901
394 10-Jan-19 JSI Slab & Wall Open Drainage & Culvert 25 25 10.0 30.0 400 17-Jan-19 7-Feb-19 18.68 74.72 9714-CIV-RFI-844 25.76 103.04 9714-CIV-RFI-901
395 11-Jan-19 JSI Rigid Segment 41 Road & Pavement Segment 25 25 10.0 30.0 400 18-Jan-19 8-Feb-19 18.96 75.84 9714-CIV-RFI-846 26.33 105.32 9714-CIV-RFI-902
396 11-Jan-19 JSI Rigid Pavement Pump House Road & Pavement Segment 25 25 10.0 30.0 400 18-Jan-19 8-Feb-19 18.96 75.84 9714-CIV-RFI-846 26.33 105.32 9714-CIV-RFI-902
397 12-Jan-19 JSI Rigid Segment 21A Road & Pavement Segment 25 25 10.0 30.0 400 19-Jan-19 9-Feb-19 18.68 74.72 9714-CIV-RFI-851 25.90 103.60 9714-CIV-RFI-903
398 12-Jan-19 JSI Rigid Pavement Pump House Road & Pavement Segment 25 25 10.0 30.0 400 19-Jan-19 9-Feb-19 18.68 74.72 9714-CIV-RFI-851 25.90 103.60 9714-CIV-RFI-903
399 12-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 19-Jan-19 9-Feb-19 18.68 74.72 9714-CIV-RFI-851 25.90 103.60 9714-CIV-RFI-903
400 13-Jan-19 JSI Rigid Segment 49 AB, 39A Road & Pavement Segment 25 25 10.0 30.0 400 20-Jan-19 10-Feb-19 18.96 75.84 9714-CIV-RFI-852 26.61 106.44 9714-CIV-RFI-904
401 14-Jan-19 JSI Rigid Segment Road & Pavement Segment 25 25 10.0 30.0 400 21-Jan-19 11-Feb-19 18.40 73.60 9714-CIV-RFI-853 26.89 107.56 9714-CIV-RFI-905
402 15-Jan-19 JSI Rigid Segment 45 ABC, Road & Pavement Segment 25 25 10.0 30.0 400 22-Jan-19 12-Feb-19 18.40 73.60 9714-CIV-RFI-856 26.61 106.44 9714-CIV-RFI-906
403 16-Jan-19 JSI Wall Open Drainage & Culvert 25 25 10.0 30.0 400 23-Jan-19 13-Feb-19 19.25 77.00 9714-CIV-RFI-857 26.33 105.30 9714-CIV-RFI-907
404 16-Jan-19 JSI Rigid Segment 37ABC Road & Pavement Segment 25 25 10.0 30.0 400 23-Jan-19 13-Feb-19 19.25 77.00 9714-CIV-RFI-857 26.33 105.30 9714-CIV-RFI-907
405 17-Jan-19 JSI Rigid Segment 44C, Rump Engine, Road & Pavement Segment 25 25 10.0 30.0 400 24-Jan-19 14-Feb-19 18.40 73.60 9714-CIV-RFI-858 26.05 104.18 9714-CIV-RFI-908
406 18-Jan-19 JSI Rigid Segment 22ABC, 47ABC Road & Pavement Segment 25 25 10.0 30.0 400 25-Jan-19 15-Feb-19 18.69 74.74 9714-CIV-RFI-860 26.90 107.58 9714-CIV-RFI-909
407 19-Jan-19 JSI Rigid Segment Pump House Road & Pavement Segment 25 25 10.0 30.0 400 26-Jan-19 16-Feb-19 18.97 75.86 9714-CIV-RFI-862 0.00 9714-CIV-RFI-
408 19-Jan-19 JSI Rigid Segment 19 Road & Pavement Segment 25 25 10.0 30.0 400 26-Jan-19 16-Feb-19 18.97 75.86 9714-CIV-RFI-862 0.00 9714-CIV-RFI-
409 20-Jan-19 JSI Rigid Segment 16 Road & Pavement Segment 25 25 10.0 30.0 400 27-Jan-19 17-Feb-19 18.40 73.60 9714-CIV-RFI-862A 0.00 9714-CIV-RFI-
410 20-Jan-19 JSI Slab & Wall Open Drainage & Culvert Unloading Truck 25 25 10.0 30.0 400 27-Jan-19 17-Feb-19 18.40 73.60 9714-CIV-RFI-862A 0.00 9714-CIV-RFI-
411 21-Jan-19 not supply concrete
412 22-Jan-19 JSI Wall Open Drainage & Culvert Pump House 25 25 10.0 30.0 400 29-Jan-19 19-Feb-19 18.97 75.86 9714-CIV-RFI-889 0.00 9714-CIV-RFI-
413 23-Jan-19 JSI Rigid Repair Road & Pavement Switchyard 25 25 10.0 30.0 400 30-Jan-19 20-Feb-19 18.96 75.84 9714-CIV-RFI-891 0.00 9714-CIV-RFI-
414 23-Jan-19 JSI Concrete Cover Cable Trench Switch yard 25 25 10.0 30.0 400 30-Jan-19 20-Feb-19 18.96 75.84 9714-CIV-RFI-891 0.00 9714-CIV-RFI-
415 23-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 30-Jan-19 20-Feb-19 18.96 75.84 9714-CIV-RFI-891 0.00 9714-CIV-RFI-
416 24-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 31-Jan-19 21-Feb-19 18.97 75.86 9714-CIV-RFI-892 0.00 9714-CIV-RFI-
417 25-Jan-19 not supply concrete
418 26-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 2-Feb-19 23-Feb-19 18.97 75.86 9714-CIV-RFI-894 0.00 9714-CIV-RFI-
419 27-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 3-Feb-19 24-Feb-19 18.40 73.60 9714-CIV-RFI-895 0.00 9714-CIV-RFI-
420 28-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 4-Feb-19 25-Feb-19 17.55 70.20 9714-CIV-RFI-896 0.00 9714-CIV-RFI-
421 29-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 5-Feb-19 26-Feb-19 18.40 73.60 9714-CIV-RFI-899 0.00 9714-CIV-RFI-
422 30-Jan-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 6-Feb-19 27-Feb-19 18.12 72.48 9714-CIV-RFI-900 0.00 9714-CIV-RFI-
423 30-Jan-19 JSI Concrete Cover Cable Trench Swithyard 25 25 10.0 30.0 400 6-Feb-19 27-Feb-19 18.12 72.48 9714-CIV-RFI-900 0.00 9714-CIV-RFI-
424 31-Jan-19 not supply concrete
425 1-Feb-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 8-Feb-19 1-Mar-19 17.84 71.34 9714-CIV-RFI-902 0.00
426 2-Feb-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 9-Feb-19 2-Mar-19 18.12 72.46 9714-CIV-RFI-903 0.00 9714-CIV-RFI-
427 3-Feb-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 10-Feb-19 3-Mar-19 18.40 73.60 9714-CIV-RFI-904 0.00 9714-CIV-RFI-
428 4-Feb-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 11-Feb-19 4-Mar-19 18.40 73.60 9714-CIV-RFI-905 0.00 9714-CIV-RFI-
429 5-Feb-19 JSI Foundation Fence Fence Fdn + Beam 25 25 10.0 30.0 400 12-Feb-19 5-Mar-19 17.27 69.06 9714-CIV-RFI-906 0.00 9714-CIV-RFI-
430 6-Feb-19 JSI Cover Concrete Switchyard 25 25 10.0 30.0 400 13-Feb-19 6-Mar-19 18.40 73.60 9714-CIV-RFI-907 0.00 9714-CIV-RFI-
431 7-Feb-19 JSI Cover Concrete Cable Trench Transformer 25 25 10.0 30.0 400 14-Feb-19 7-Mar-19 18.40 73.60 9714-CIV-RFI-908 0.00 9714-CIV-RFI-
MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT
MONITORING SUMMARY POURING CONCRETE & COMPRESSIVE STRENGTH TEST

Date Testing Compressive Strenght Test Result


Plan Actual Site Temp
NO Date Pouring Subcon Structure Type Area ID Foundation
(Mpa) (Mpa) Slump (cm) (⁰C)
Cement 7 Days 28 Days
7 Days 28 Days Average Average
(%) RFI Report No (%) RFI Report No
Mpa Mpa

432 8-Feb-19 JSI Cover Concrete Under Ground Pipe Trench 25 25 10.0 30.0 400 15-Feb-19 8-Mar-19 18.68 74.72 9714-CIV-RFI-909 0.00 9714-CIV-RFI-

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

annex
trench

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

Sisa cor warehouse

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

24m
24m

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT


ONCRETE & COMPRESSIVE STRENGTH TEST

Status Remaks

MONITORING SUMMARY POURING CONCRETE AND COMPRESSIVE STRENGTH TEST RESULT