Wireless Andon Implementation Schedule

TIMELINE
NO ACTIVITY DUE DATE PIC
SEPT OCT NOV
1 Preparation 17-Sep-18
Create andon calling flow concept 10-Sep-18 Kuat & Arland
Machine 6-Sep-18 Kuat & Arland
Material 6-Sep-18 Kuat & Arland
Mold
Mapping area & calculate andon button 6-Sep-18 Kuat & Arland
needed in d7 10-Sep-18 Kuat,
Pak Agus, Kuat
Pak Agus,
Analyze hardware requirement 17-Sep-18 Pak Dodo
2 Concept Validation 5-Oct-18
Discuss with Production & IT team 1-Oct-18 Prod & IT
Concept review & validation 5-Oct-18 Prod & IT
3 Hardware Preparation 18-Oct-18
Wirelles Andon System (Button, Receiver) 12-Oct-18 Pak Agus, Kuat
Speaker & Rotary Lamp 12-Oct-18 Pak Agus
Display 50 inch 16-Oct-18 Pak Dodo
PC Server 15-Oct-18 Pak Dodo
Display 32 inch 15-Oct-18 Pak Dodo
4 Installation 26-Oct-18
Hardware installation 24-Oct-18 Pak Dodo
System installation 25-Oct-18 Pak Eddy
Button registration 26-Oct-18 Pak Agus
5 Trial
Wireless Andon training for TL, mechanic & 30-Oct-18
mold 29-Oct-18 Pak Agus,Kuat
Machine
Material
Mold
Wireless Andon training for Operator,
mechanic & mold 29-Oct-18 Pak Agus,Kuat
Machine
Material
Mold
Wireless Andon Trial 30-Oct-18 Production
Production Team,
Team
6 Review 9-Nov-18 Pak Agus, Kuat

Need to Prepare Qty 17 18 19


Andon Button Sticker 100
Penguat Tegangan 1
Toa Speaker 5
Rotary Lamp 1
Buzzer 1
Display Bracket 1
Display 1
PC 1
Receiver 1
WOF Form 30
Power Cable
Relay 1
Timer 1
ELINE
NOV