You are on page 1of 2

PROJEK JALAN MENALUN SG.

POI, KANOWIT, SARAWAK (FASA 2)

Analysis of Excessive Rainfall (10 mm and above) - From August until December, Year of 2015 - 2019

MONTH JAN FEB MAR APR MAY JUN JULY AUG SEP OCT NOV DEC
YEAR
2015 N/A N/A N/A N/A N/A N/A N/A 8 3 10 8 9
2016 N/A N/A N/A N/A N/A N/A N/A 1 8 9 3 12
2017 N/A N/A N/A N/A N/A N/A N/A 9 10 7 13 11
2018 N/A N/A N/A N/A N/A N/A N/A 3 9 7 8 14
2019 N/A N/A N/A N/A N/A N/A N/A 1 3 15 7 7
Average of the
0 0 0 0 0 0 0 4.4 6.6 9.6 7.8 10.6
previous 5 years
2020 N/A - - - - - - 6 13 9 8 10
No of Days Claimed N/A - - - - - - 2 6 0 0 0

Total of Days Claimed =8 days

CONCLUSION
Based on the above analysis, it can be concluded that the number of excessive rainfall for period of 1st of August to the end of December as
compared to the average of the previous 5 years with the exclusion of MCO and CMCO period, is 8 days.

NOTE

Rainfall data is obtained from Meteorology Department Malaysia (Sarawak Branch) for Uka Station of station number 1821001 as the nearest
station to Uka.
PROJEK JALAN MENALUN SG. POI, KANOWIT, SARAWAK (FASA 2)
CONTRACT NO.: JPS/P/SK/KPLB/02/2019

SUMMARY OF THE ANALYSIS OF EXCESSIVE RAINFALL

Item Description Days

1 Excessive rainfall for year 2020

August (Uka Station) 2


September (Uka Station) 6
October (Uka Station) 0
November (Uka Station) 0
December (Uka Station) 0

Total of Days Claimed 8