You are on page 1of 2

KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI

POLITEKNIK NEGERI MALANG


JURUSAN TEKNIK SIPIL
Jalan Soekarno Hatta 9, Malang 65141

PROJECT
URBAN DRAINAGE
2MRK5 2022/2023

Please design the sustainable drainage channel and structures with the following conditions.

No Scope Week
1. Rainfall data preparation: analysis of missing value, consistency test, areal rainfall 3
2. Designed rainfall, goodness of fit test 4
3. Contour interpolation, layout of drainage channels, rainfall catchment area 5
4. Designed flood 6
5. Sustainable drainage (odd: Infiltration chamber; even: bio-absorption hole) 7
6. Channel accumulated discharge 8
7. Channel dimension 9
8. Channel drawing: long and cross section 10
9. Design and placement of inlet (odd: gutter inlet; even: curb inlet) 11
10. Flood modeling 12
11. Chapter I, II, III, example of calculation 13

Data needed are as follows.


1. Study area as attached.
2. Rainfall data as below.
Absent Data Missing Value Record
number Month Year Station + Date Month Year Station
1 All 2019 Sumenep 10 1 Nov 2020 Sumenep

2 All 2018 Saronggi 11 2 Dec 2019 Saronggi

3 All 2017 Kebonagung 12 3 Jan 2018 Kebonagung

4 All 2016 All 13 4 Feb 2017 Sumenep

5 All 2015 Sumenep 14 5 Mar 2016 Saronggi

6 All 2014 Saronggi 15 6 Nov 2015 Kebonagung

7 All 2013 Kebonagung 10 7 Dec 2014 Sumenep

8 All 2012 All 11 8 Jan 2013 Saronggi

9 All 2011 Sumenep 12 9 Feb 2012 Kebonagung

10 All 2010 Saronggi 13 10 Mar 2011 Sumenep

11 Jan 2009 Kebonagung 14 11 Nov 2010 Saronggi

12 Feb 2008 All 15 12 Dec 2009 Kebonagung

13 Mar 2020 Sumenep 10 13 Jan 2008 Sumenep

14 Apr 2019 Saronggi 11 14 Feb 2020 Saronggi

15 Mei 2018 Kebonagung 12 15 Mar 2019 Kebonagung

16 Jun 2017 All 13 16 Nov 2018 Sumenep

17 Jul 2016 Sumenep 14 17 Dec 2017 Saronggi

18 Agt 2015 Saronggi 15 18 Jan 2016 Kebonagung

19 Sep 2014 Kebonagung 10 19 Feb 2015 Sumenep

20 Oct 2013 All 11 20 Mar 2014 Saronggi

21 Jan-Jun 2012 Sumenep 12 21 Nov 2013 Kebonagung

22 Jul-Dec 2011 Saronggi 13 22 Dec 2012 Sumenep

Urban Drainage Project - 2022


KEMENTERIAN PENDIDIKAN, KEBUDAYAAN, RISET, DAN TEKNOLOGI
POLITEKNIK NEGERI MALANG
JURUSAN TEKNIK SIPIL
Jalan Soekarno Hatta 9, Malang 65141

Absent Data Missing Value Record


number Month Year Station + Date Month Year Station

23 Jan-Jun 2010 Kebonagung 14 23 Jan 2011 Saronggi

24 Jul-Dec 2009 All 15 24 Feb 2010 Kebonagung

25 Jan-Jun 2008 Sumenep 10 25 Mar 2009 Sumenep

26 Jul-Dec 2020 Saronggi 10 26 Nov 2008 Saronggi

3. Time return, channel material as below:


Absent number Time return (year) Channel material
1 10 Brick
2 2 Concrete
3 5 Stone Masonry
4 10 Brick
5 2 Concrete
6 5 Stone Masonry
7 10 Brick
8 2 Concrete
9 5 Stone Masonry
10 10 Brick
11 2 Concrete
12 5 Brick
13 10 Concrete
14 2 Stone Masonry
15 5 Brick
16 10 Concrete
17 2 Stone Masonry
18 5 Brick
19 10 Concrete
20 2 Stone Masonry
21 5 Brick
22 10 Concrete
23 2 Stone Masonry
24 5 Brick
25 10 Concrete
26 2 Brick
27 5 Concrete

4. Other necessary data can be assumed

Others:
1. Project is done personally
2. Deadline is week 15
3. Fine of late submission for overall project: 2 points/day

Urban Drainage Project - 2022