PROJECT PROGRESS PROGRESS CLAIM

Bahagian Bahagian Date of Bahagian


DATE GIATMARA MUKAH Date of Payment Amount Date of Signature Date Posted Date Date of
Binaan &
Description Amount (RM)
Submission Cert No Certfied (RM) Payment Cert Out Delivered to Selenggaraa Kemahiran Kewangan Received Payment
SCHEDULE ACTUAL STATUS Issued QS Architect C&S M&E MARA & Teknikal Unit Bajet Unit Harta Received
n
Progress Claim 196,106.15
No.1 (aug 20)
10/24/2020 7.65% 2.97% -4.68%
1 235,459.52 05-Nov-20 05-Nov-20 10-Nov-20 06-Nov-20 09-Nov-20 11-Nov-20 16-Nov-20 04-Dec-20 04-Dec-20 08-Dec-20 14-Dec-20 08-Jan-20
Progress Claim 125,005.18 02-Oct-20
No.2 (sept 20)
10/31/2020 7.94% 3.25% -4.69%

Progress Claim
404,874.13 31-Oct-20 2 240,794.74 07-Dec-20 07-Dec-20 14-Dec-20 08-Dec-20 11-Dec-20 14-Dec-20 16-Dec-20 04-Jan-21
No.3 (oct 20)
11/7/2020 8.30% 3.37% -4.93%

Progress Claim
432,855.10 24-Nov-20 3 148,843.59 6/Jan/21 26/Jan/21 2/Feb/21 26/Jan/21 27/Jan/21
No.4 (nov 20)
11/14/2020 8.83% 4.04% -4.79%

Progress Claim
736,186.92 29-Dec-20
No.5 (dec 20)
11/21/2020 9.27% 4.28% -4.99%

Progress Claim
1,010,269.18 28-Jan-21
No.6 (jan 21)
11/28/2020 9.61% 4.70% -4.91%
12/5/2020 9.96% 5.83% -4.13%
12/12/2020 10.41% 6.10% -4.31%
12/19/2020 11.08% 7.57% -3.51%
12/26/2020 11.67% 7.89% -3.78%
1/5/2021 12.55% 10.19% -2.36%
1/16/2021 13.90% 10.19% -3.71%
1/24/2021 15.33% 11.56% -3.77%
2/2/2021 18.43% 12.95% -5.48%
2/6/2021 18.43% 12.95% -5.48%
PROJECT PROGRESS PROGRESS CLAIM

Payment Amount Date of Date of DID Sibu Posted Date of DID Date of
DATE SG POI KANOWIT Amount Date of Signature Date Posted Date Of DID to DID
Description (RM) Submission Certificate Certified Payment Out Sibu Sibu Verified Kuching Kuching Payment
SCHEDULE ACTUAL STATUS No (RM) Cert Issued ASL Gertaq Received Received Received
Progress Claim No.1 30,152.74 17-Apr-20
10/24/2020 3.40% 2.58% -0.82% (mar 20)
Progress Claim No.2
36,028.80 17-Jun-20
10/31/2020 3.40% 2.95% -0.45% (may 20)
Progress Claim No.3
41,904.86 01-Jul-20 1 31,206.15 23-Sep-20 23-Sep-20 25-Sep-20 29-Sep-20 01-Oct-20 19-Oct-20 21-Oct-20 26-Oct-20 26-Nov-20
11/7/2020 5.13% 3.42% -1.71% (june 20)
Prgress Claim No.4 79,244.73 29-Jul-20
11/14/2020 6.94% 4.27% -2.67% (july 20)
Progress Claim No.5
276,836.85 01-Sep-20
11/21/2020 9.05% 5.56% -3.49% (aug 20)
Progress Claim No.2
467,074.13 19-Nov-20 2 262,262.70 03-Dec-20 03-Dec-20 03-Dec-20 03-Dec-20
11/28/2020 11.28% 5.59% -5.69% (nov 20) (signed in kuching by Mr Rudi)
Progress Claim No.3
558,063.50 14-Jan-21
*5/12/2020 10.14% 4.65% -5.49% (dec 20)
12/12/2020 11.28% 4.98% -6.30%
12/19/2020 12.60% 5.80% -6.80%
12/26/2020 13.70% 5.80% -7.90%
1/16/2021 17.55% 6.29% -11.26%
1/25/2021 19.47% 8.15% -11.32%
PROJECT PROGRESS PROGRESS CLAIM
Date of Date of
DATE ANJUNG SEMATAN Amount Date of Payment Amount Payment Signature DID Date of Date of
Description Submissio Certificate Certified Payment
SCHEDULE ACTUAL STATUS (RM) Cert BCISB Mussul samaraha DID HQ
n No (RM) Received
Issued n
11/30/2020 0.92% 0.00% -0.92%
12/5/2020 1.01% 0.00% -1.01%
12/12/2020 1.11% 0.00% -1.11%
12/19/2020 1.20% 0.00% -1.20%
12/26/2020 1.29% 0.00% -1.29%
1/2/2021 1.51% 1.00% -0.51%
1/9/2021 1.71% 1.00% -0.71%
1/16/2021 1.95% 1.00% -0.95%
1/23/2021 2.17% 1.00% -1.17%
1/30/2021 1.50% 1.50% 0.00%
PROJECT PROGRESS PROGRESS CLAIM
Date of Date of
DATE SINIAWAN WATERFRONT Date of Payment Amount Signature Date of
Amount Payment DID
Description Submissio Certificate Certified Date of DID HQ Payment
SCHEDULE ACTUAL STATUS (RM) n No (RM) Cert DDR Faltech samaraha Received
Issued n
11/5/2020 0.00% 0.00% 0.00%
12/12/2020 0.30% 0.00% -0.30%
12/19/2020 0.75% 0.00% -0.75%
12/26/2020 0.75% 0.00% -0.75%
16/01/2021 * 0.55% 0.09% -0.46%
1/25/2021 0.85% 0.26% -0.59%

* reschedule