Professional Documents
Culture Documents
Standard
For
Supply of Precast Concrete Columns
~,
/,
3 Dec. 05 Issued for Voyageur Implementation
N~ 154
. ~ I!'fP
STANDARD NO. 1207
Standard
For
Supply of Precast Concrete Columns
!
Suncor Energy Supply o f Prec ast Rev. 3 Page 2 of 11
STD 1207 Conc rete Columns December, 2005
Index:
1.0 General
1.1 Scope
This standard covers the technica l requirements , in addition to the
requiremenl of Suncor Energy Inc. STD 1203, for malerials, fabrication and
delivery of precast concrete columns used to support the piperacks on the
Suncor Energy Inc. Oil Sands Group Site.
1.2 Definitions
1.4 Submittals
1.4.1 All submittals shall be delivered to the Owner's Engineer or the Owner.
1.4.2 The following information or materials shall be submitted with the bid
documents:
(a) Copies of welding certification and qualification documents of steel
hardware and reinforcement welding per Suncor Energy Inc. STD
0302, Clause 1.5.2 , as well as per CSA W186.
Suncor Energy Supply of Precast Rev. 3 Page 5 of 11
STD 1207 Concrete Columns December, 2005
2.0 Materials
2.1 General
2.1.1 All materials, including all ingredients for making concrete , reinforcement ,
and embedded items shall conform, as a minimum, to the requirements of
Suncer Energy Inc. STD 1203. CSA A23.1 and A2 3.4.
2.1 .2 Any materials or items that are not clearly specified in the project
documents shall have the approval of Owner's Engineer prior to use.
2.2 Concrete Materials
2.2 .1 Ingredients or materials for concrete production and curing shall conform
to the requirements of CSA A23.1 and Suncer Energy Inc. STD 1203.
Suncor Energy Supply of Precast Rev. 3 Page 6 of 11
STD 1207 Concrete Columns Oecember, 2005
2.2.2 Unless otherwise specified in the project documents, the specified 28-day
compressive strength of the concrete shall be 35 MPa, and cement shall
be Type 50 or Type 20 (moderate sulphate resistant) . Maximum
aggregate size shall not exceed y." (20 mm).
2.2.3 Unless otherwise specified in the project documents, the precast concrete
shall be proportioned to meet the requirements of Class C-1 and S-2
exposures as per CSA A23.1.
2.3 Reinforcement Materials
2.3.1 All reinforcement shall be billet steel deformed bars conforming to the
requirements of CSA G30.18, Grade 400. It shall be new material, free from
loose rust, mill scales, oil , grease or any foreign substances that may impair
the bonding between the re inforcement and concrete .
2.3.2 Weldable re inforcing bars shall be used when reinforcing bars are to be
welded to each other or to hardware.
2.5. 1 Supports, chairs and spacers for rebar and embedded items shall generally
be non-metallic type and shall be durable, strong and properly secured to
withstand the placing, compaction and consolidation of concrete. Metallic
supports, chairs and spacers that are placed inside the clear concrete cover
zone shall be galvanized or plastic coated.
2.5.2 Tie wire shall be soft annealed wire, minimum 16 gauge (1 .6 mm).
2.5.3 Curing com pound shall have the approval from the Owners Engineer
before use. It shall not discolor the finished concrete surface.
2.5.4 Other miscellaneous items used in the fabrication of precast columns shall
be as specified in the project documents or approved by the Owner's
Engineer.
Suncor Energy Supply of Precast Rev. 3 Page 7 of 11
STO 1207 Concrete Columns December, 2005
3.0 Fabrication
3.1 General
3.1.1 As a minimum, the procedures and conditions used to fabricate the
precast columns shall conform to the requirements of Suncor Energy Inc.
STD 1203, CSA A23.1 and A23.4.
3.1 .2 Welding of steel hardware and reinforcement shall conform to the
requirements of CSA W47.1, W59 and W186.
3.2 Forms
3.2 .1 Forms for precast concrete columns shall be made from metal or treated
plywood (specially design for concrete forming) per CSA S269 .3 to
produce a uniform and smooth form finish , meeting the requirements
"Smooth-Form Finish" as per Clause 24.3.3 of CSA A23.1.
3.2.2 Form release agent sha ll not discolor the finished concrete surface.
3.2.3 Forms shall be water tight to prevent leaking , and rigid enough to
withstand the placing and consolidation of the concrete without
appreciable deformations, and to meet the dimensional tolerance
requirements of the finished columns.
3.2.4 Hardware and reinforcement shall be properly placed and secured in
position to prevent any distortion or dislocation during concrete place ment
and consolidation.
3.4.4 Steam curing , if applied , shall not start until initial set, and shall not
exceed 20°C per hour of heating rate to the concrete , measured at a
location of 1 inch (25 mm) from the concrete surface. The Contractor
shall demonstrate, to the satisfaction of the Owner's Engineer, that the
timing , temperature rise rate and maximum temperature of the proposed
steam curing regime wi ll not jeopardize the specified 28-day compressive
strength of the concrete, using strength test results from cylinders cured
under exactly the same condition s.
3.4.5 The maximum concrete temperature during curing shall not exceed 65° C
under any ci rcumstances. W hen steam curing or external heating is used,
the Contractor shall monitor the temperature inside the concrete during
the curing period .
3.4.6 Unless otherwise approved by the Owner's Engineer, precast concrete
shall be cured (protected against moisture loss) under a minimum
temperature of 10° C for at least 7 days, or for the time necessary to
attain at least 70 % of it's specified 28-day compressive strength .
3.4.7 Forms shall not be stripped till concrete has reached at least 15 MPa of
compressive strength . If the forms are stripped prior to the specified
minimum curing duration as specified in Clause 3.4.6 has been reached ,
care shall be taken to prevent moisture loss during form stripping and
curing shall be resumed immediately after stripping.
3.5 Repair of Precast Concrete
3.5.1 The concrete surfaces shall be carefully examined immediately after form
stripping to identify any defects, such as honeycombs, larger voids,
excessive bug holes, segregation , discoloration, etc. The inspection
findings , including the nature/cause, dimension , location of the defects, if
any, shall be documented in the Q/e record.
3.5.2 Any repairs to defects shall be at the Contractor's own cost.
3.5.3 Material , application procedure and curing method for repa iring each type
of defect shall be approved by the Owne r's Engineer prior to use.
3.5.4 Any defects greater than 3/8" (10 mm) in depth or 1" (25 mm) in diameter
shall be repa ired .
3.5.5 Defects not exceeding 1" (2 5 mm) in depth or 3" (7 5 mm) in diameter shall
be considered as minor defects, and may be patched using approved dry
pack materials and procedures. The defect surfaces shall be cleaned prior
to patching to ensure bonding .
3.5.6 Defects greater than 1" (25 mm) in depth or 3" (75 mm) in diameter shall
be considered as major defects , and shall be reported the Owner's
Engineer immediately upon discovery. Depending on the nature, location
and extend of the defects, the Owner's Engineer may chose to reject the
affected piece or to accept it after being satisfactorily repaired . Repair
materials and procedures shall be established with the Owner's Eng ineer.
Suncor Energy Supply of Precast Rev. 3 Page 9 of 11
STD 1207 Concrete Columns December, 2005
4.1 Handling
4.1.1 The Contractor shall be responsible for providing holes for lifting the
precast columns in the fabrication yard and for erection. The holes shall
not exceed 1-112 " (40 mm) in diameter, and the location of the holes shall
requ ire prior approval from Owner's Engineer. The Contractor shall not be
permitted to include any embedded hooks, bolts, cab les or any device that
permanently protrudes through the co ncrete surface without the written
approval of the Owner's Engineer.
4.1.2 Care shall be taken during the ha nd ling and storing of the precast
concrete to preve nt any damages , cracking , discoloration or corrosion to
the finished concrete surface or the embedded items.
4.1.3 Finished co lumns shall be blocked off the ground and separated from
each other using wood blocks spaced at no more than 10 ft (3 m) .
4.2 Delivery
4.2. 1 The Contractor shall be responsible for loading , packing , transporting and
unloading the precast columns to deSignated location(s) at the Suncor
Energy Inc. Oil Sand Group Site.
4.2.2 The Contractor shall ensure proper supporting and protection of the
columns during handling and transportation to prevent damage to the
columns.
4.2.3 The columns shall not be moved or transported until they have reached at
least 75 % of the specified 28-day compressive strength.
5.1 General
5.1 .1 As a minimum, the materials, fabrication procedures, workmanship and
finished products of precast columns shall meet the requirements of
Suncor Energy Inc. STD 1203, CSA A23.1 , A23.4, A251 , W59 and W186 ,
in add ition to the requirements of this standard.
Suncor Energy Supply of Precast Rev. 3 Page 10 of 11
STD 1207 Concrete Columns December, 2005
surface by more than 1/10 of the plate thickness or 3/32" (2.4 mm)
whichever is sma ller.
5.3 .3 The precast concrete columns shall meet the following tolerance
requirements after delivered to the Suncor Energ y Inc. site:
(a) Length : + - 3/8" (10 mm)
(b) Width and depth: + 1/2" (12 mm), -1/4" (6 mm)
(c) Cross section skew: + - 1/4 " (6 mm) (per diagonal length)
(d) Plum (from top or bottom): + - 1/4" (6 mm) per 10 It 3 m) , + - 1/2"
(12 mm) max
(e) Straightness : + - 1/8" (3 mm) per 10 It (3 m) straight
edge.
(I) Embedded item locations: + - 1/4 " (6 mm) in location ,
(g) Location of anchor bolt hole group: + - 1/16" (3 mm) off the
design center.