ESTIMATE FOR demolishing qurters , Puttlum.

Item
no
Description of work Units Qty Rate Amount
calicut pattern tile roofing with timber frame work
1.0 includung removel valunce/barge boarde eve gutters down m2 180.0 1073.15
pipe etc.. Single story 193167.00
Brick work in cement demolished, serviceble bricks
2.0 stacked at site and debris cleared. m2 125.0 826.00
103250.00
Ceiling framework removed stacked at site and debris
3.0 cleared. m2 75.00
375.00 28125.00
Door or window sash only, size over 3.7 sq.m. removed
4.0 from wall and stacked at site.. Nr
10.0 936.00 9360.00
disposal of dibris away 10 Km frome the site includung
5.0 hanling ,loding & unloding . m3
35.00 1700.00 59500.00
Total 393,402.00

Prepared by

Nomal
Item
no
Description of work Units Qty Rate Amount
U/Ski
llDay
Romoving roof calicut tile s 8.00 1800.00 14400.00
U/Ski
llDay
Removing timber frame work s 6.00 1800.00 10800.00
U/Ski
llDay
romoving door & window s 4.00 1800.00 7200.00
Removing Brick wall Use for Backo Loder hr 8.00 3000.00 24000.0
disposal of dibris away 10 Km use for 3 cube Lory 30000.0
Sub Total 86400.0
Profit % O/H 20% 17280.0
Total 103680.0
845 27% 228.15 1073.2

1340 27% 361.8 1701.8