You are on page 1of 4

July 2001

Vol. 1, Issue 2

Power RE-View

Contents Equivalent Operating Hours


Equivalent Operating Hours 1
The concept of equivalent operating equivalent operating hours (a standard
Passing Grades 2 hours is extensively used in steam interval often used in the overhaul
turbine applications where frequent business) may, therefore, have lower
What To Do With “Retired” start-ups of the turbines can be very actual operating hours. The purpose of
or “Old” Boilers 3 taxing on the turbine internals. Steam the equivalent operating hour concept is
turbines typically operate under very to avoid turbine failures that may result
Gas Turbine News 3
high internal pressures which result in because of severe operating conditions.
Harvesing The Wind With hefty casing cross sections and require For example, a turbine being started
Power Farms 4 slow start-ups in order not to experience every day and run for 3 years (at 12
excessive thermally induced stress. hours per day) accumulates 13,140
actual operating hours and will have
Gas turbines in contrast have smaller
1,095 starts during this time period. One
cross sections and can tolerate quicker
method to account for frequent starts is
start-ups and, therefore, may be not as
to use a “load factor.” If a factor of 10 is
sensitive to start-up cycles when
used in our example, it will add 10,950
compared to steam turbines. In a
hours for a total of 24,090 equivalent
combined cycle plant (steam turbine and
hours. This is a substantial increase over
Points of Interest gas turbine), the recommended start-up
the 13,140 actual hours. It means that
time is usually set by the limitations of
in this Newsletter the steam turbine when starting up from
the plant needs to spend money for
inspection and overhaul much sooner
• How useful are Equivalent Operating cold. It may take 4 to 12 hours to start a
than if only operating hours are
Hours in steam turbine applications? steam turbine, while a gas turbine
considered. This example is somewhat
• Performance testing for new usually can be brought to full load in less
extreme since most of the larger gas
power plants than one hour.
turbine installations are more likely to
• Underwriting issues for old boilers Some manufacturers of gas turbines run in a base-load mode (24 hours, 7
distinguish between fired hours days each week) with infrequent shut-
• Increasing power supply with
(sustained operating hours) and down periods.
wind farms
equivalent operating hours. The thought
The “load factor” varies by manufacturer
is that a turbine experiencing frequent
depending on the particular operating
starts exhausts more quickly the useful
experience of their turbine models.
life of internal parts (especially
(Siemens-Westinghouse Power seems to
combustors and turbine blading). A
be using a load factor of 10.) During
turbine being overhauled at 25,000
erection and commissioning/testing of a Conclusions • Manufacturer’s
unit, the turbine will see an unusually maintenance
The absence of a common industry
high number of starts (as many as 400 schedules must be
standard in measuring operating hours
starts in less than a year, especially when followed.
(equivalent or otherwise) leaves
software bugs are encountered). There
underwriters with no simple means of • Scheduled internal
are no typical numbers for starts during
evaluating the performance of gas inspections (especially
field test because each installation may
turbine technology and equipment. One hot gas path
have unique circumstances as well as the
can only utilize the data available on a inspections) to
need to test instrumentation. Once in
particular model when attempting to validate the
operation, the turbine will usually
determine if a certain model is “proven.” condition of
experience much fewer starts.
However, there are a number of other turbine parts
Some turbine manufacturers do not use factors to consider in the evaluation and to make or
equivalent operating hours, and they process. After reaching an initial schedule the
adjust their maintenance schedules conclusion based on the operational necessary
depending on operating specifics (base experience of a model, the individual unit repairs. This
load or frequent starts). While the reason with its own local operating should be done
for not using equivalent operating hours characteristics should be looked at in for turbines that
is not entirely known, it’s probably consideration of the following factors: are new, and is
because gas turbines starts are not as
• Operational mode (base
stressful to the hardware as steam
load versus peaking
turbine starts.
mode) determines
“2/3 of all gas turbine
Furthermore, according to statistics
collected and published by a major
maintenance schedules. failures are product failures”
• Some manufacturers may
insurance company, about 2/3 of all gas
also track equivalent
turbine failures are product failures
operating hours to determine a especially recommended before
(design, installation errors, repair and
suitable maintenance schedule. the manufacturer’s warranty period
material faults) with only about 10%
expires.
caused by operational influences.

Passing Grades
A critical point in the construction of a Any boiler & machinery occurrences or procedures for these tests must be well-
new power plant is the passing of a property damages during the test period defined upon signing the contract for
series of performance or “hot” tests after are normally covered under Builders’ All construction, equipment procurement
the initial plant operation is achieved. Risk or EAR Policies. Since the equipment and installation for a new power plant.
The purpose of these tests is for the is operated in a manner to pass its The justification for this requirement is to
plant contractors and equipment performance tests which are at or avoid claims resulting from contract
suppliers to demonstrate that the new beyond normal operating levels, the interpretation issues such as those
plant meets or exceeds the performance power generated is generally sold to the associated with test run durations (and
levels stated in the project’s contracts. electric grid. During this test period how to deal with interruptions), number
Once successfully shown, the operational stops and starts can be more of stops or restarts allowed before
contractors generally receive their final numerous than the expected during starting over, the extent of
payment, the owners accept the project, normal operation as equipment is often contractor/manufacturer control of
and the unit enters into Commercial “tweaked” to optimize performance. The operations, and the test methods
Operation (CO). unit’s operational control is typically especially for some very low quantities
shared between new operators learning of emissions. Since it is not normal duty,
The power plant owner’s Boiler &
the systems and the contractors/ a high number of stops/starts adds stress
Machinery and Property policies usually
manufacturers start-up representatives. to the machinery and can possibly
start upon Commercial Operation as the
Delays incurred in completing the tests contribute to premature failures in the
Builders’ Risk policy terminates.
may result in liquidated damages for the “bath tub curve” of a power plant’s
There are several aspects of performance contractors, and if an insurable claim life cycle.
tests that have significant insurance occurs, significant business interruption
Underwriting exposures can be limited
implications. Although losses during the (ALOP or DSU) losses may result as well.
by verifying that the performance test
actual physical construction of the
There are generally several procedures and remedies are well-
power plant are not unusual, the test
performance tests conducted. Heat defined, contractual responsibilities are
period often represents the maximum
Rate, environmental emissions, and identified, and that insurance coverages
exposure under the Builders’ All Risk
reliability are among the performance- are sufficient to address all possible loss
Policy for several reasons.
related parameters verified. The actual scenarios.
2 GeneralCologne Re
What To Do With Gas Turbine
“Retired” or “Old” Boilers? News
There are many factors that caused older the fact is that many of these assets have Air-Cooled Generators
boilers to be retired or “mothballed.” The been well maintained, with judicious
The size and ratings of air-cooled
significant ones include: replacements of worn components over
electrical generators used in gas
the years under the regulated utility
• Uncompetitive Heat Rates (require turbine plants have steadily increased
environment.
more BTUs to make Kw-Hr; therefore over the past decades. Continuing this
more costly to operate) With the advent of deregulation and trend, Alstom Power recently
competitive power, the same level of introduced an air-cooled generator of
• Environmental Compliance Issues
investment in maintaining these units 500 MVA size. The Topair 25 (as it is
(require adding expensive
becomes a serious question. With the called) is aimed at the 50 Hz market. A
control systems)
shortage of power and peak reserve version for the 60 Hz market (450
• Condition—not simply the capacity, power plant owners are MVA) is planned for later. Although
age of the equipment! assessing the value of returning these bigger and slightly less efficient than
The last factor directly impacts insurance previously retired units to service. This is the equivalent hydrogen-cooled
issues. Just because equipment is old the case for seasonal peak applications generators, air cooled generators have
does not necessarily make it unfit for its where the high sale price for peak power an advantage: they eliminate the need
intended duty. In fact, older equipment allows for compensation despite their for hydrogen as a coolant for the
may have been designed with more inherent operating inefficiencies. generator. This is an important aspect
robustness than newer components due from an insurance perspective since
Prudent Underwriting the storage of hydrogen on site and
Questions the very real potential of hydrogen
leaks and fires is a concern that affects
• When were the boilers last inspected
the overall risk of the plant.
and by whom? (Obtain a copy of
the report.) (Source: Turbomachinery International,
March/April 2001)
• Were the boilers truly mothballed, or
were they kept on standby readiness Product Field Testing
with or without partial load being
maintained? Or worse case scenario, Testing a newly developed product
were they simply abandoned and left under actual field conditions is
to rust? If on standby, how often are important before releasing the design
they used and to what capacity? for general manufacturing. A case in
point is Mitsubishi’s installation of
• Does the original owner, who knows their newest H-technology large gas
their history, still own the boilers? turbine 701H at the Higashi Niigata
to the philosophies of boiler designers of Power Station of Tohoku Electric
• What are the operating demands on
that period. Routinely, boilers were Power during November 1998 for
the boilers?
operated at 20% (or more) over capacity testing purposes. After various test
because everyone knew that safety • Has environmental control
measurements, the 701 H unit was
margins were built into the design to equipment been added or updated to
removed in July 1999 and the
handle these conditions. However, this is current environmental standards? If
previously installed 701 G unit was re-
not the case with newer equipment, yes, this reflects a significant
installed just prior to the summer
primarily due to increased market commitment on the part of the
peak demand as agreed with Tohoku
competitiveness and lack of favorable owners to operate these units well
Electric earlier. The 701 H model
evaluations for these factors by buyers. into the future.
features steam cooling of rows 1
• Were there any scheduled or through 3 in the turbine that increases
Underwriting Impact unplanned outage reports that would the overall thermal efficiency of a
As stated in the GeneralCologne Re provide insights into persistent combined cycle plant to about 60%.
Boiler & Machinery Utilities Reference equipment problems? According to the article, the two 701
Manual, the average age of coal-fired G turbines (steam cooled combustors)
Old isn’t necessarily bad. What is
boilers is more than 37 years, exceeding have performed well logging a
important is how the boilers have
the conventional design life of 30 years. reliability of 100% in their first year.
been maintained.
Although on the surface this sounds bad, (Source: Turbomachinery International,
January/February 2001)

Power RE-View, Vol. 1, Issue 2, July 2001 3


Harvesting The Wind With Power Farms
Wind farms are appearing with far more • Offshore locations are increasingly
regularity on the landscape of many being considered—potentially
countries and throughout the United impacting the appropriateness of the
States. During 1998-99, 1,000 Mw of type of insurance coverages required.
new wind projects were installed in the
• Environmental concerns about birds
U.S., with the European Community
and noise lead to possible unique
continuing to be the world leader of
environmental exposures.
installed capacity.
The important aspect of harvesting the
Wind turbine capacities are increasing,
wind is that the technology is rapidly
but a typical unit size is 225-300 Kw.
evolving with prototype machines, on-
Although efforts are being made to
shore and off-shore applications—and
develop larger capacity machines, there
costs that are as variable as the wind.
has been only one 1 Mw unit in
successful commercial operation. Lower
operating and maintenance costs and
greater content of locally manufactured
components (which are helping to lower More Gas Turbine News
capital costs), plus increased reliability, being constructed so fast that the fuel
Thriving Gas Turbine
are expected market drivers to realize a supply and infrastructure may not
Repair Business
25% annual growth rate of installed keep up. As reported in the July 9 issue
capacity. Still, wind power accounts for While OEMs (Original Equipment of Engineering News Record, the
only 0.3% of the global installation Manufacturers) still perform most of Williams Capital Group, New York City
generation capacity. the repairs on large gas turbines; claims that fewer than half of the
operators of gas turbine plants are powerplants now being developed are
Technology issues that contribute to
utilizing an ever-increasing number of likely to be completed because they
underwriting concerns involve: unit
non-OEM shops. This is especially the will not be able to procure fuel.
capacity scale-up; sophisticated blading
case once the OEM’s warranty period Moreover, what natural that is available
designs; and variable speed and pitch
has expired. Even a capability of will cost more. During the 1990s,
designs that impact gearbox designs.
refurbishing or repairing single crystal wellhead gas prices (in 1999 dollars)
Other factors to be assessed include: blades is currently being developed by hovered between $1.61 to $2.32 per
some of the non-OEM repair firms. million Btu. Even until mid-April 2000,
• The intermittent nature of wind—
There are at least 14 such companies the spot prices in Louisiana were under
there are additional costs if
within the continental USA that can $3 per million Btu but later broke the
replacement power must be
refurbish and repair most of the heavy- $4 barrier. After the 2000-2001 heating
provided.
duty gas turbines. Because they are season, prices are expected to average
• Average wind speed dictates relatively new and employ near $4.38 per million Btu for the
production and costs, making wind’s sophisticated technology, almost all of spring and summer season. Extreme
competitiveness volatile and business the F and G class gas turbines are still summer weather could aggravate this
interruption very difficult to evaluate. being serviced by the OEMs. situation even further. (Source:
• Staying power of the smaller (Source: POWER, March/April 2001) Engineering News Record & Energy
manufacturers of smaller firms in the Information Administration, U.S. DOE)
wake of large companies such as Fuel Availability & Prices
In either case, financial balance sheets
Siemens, BP, Shell and Enron In North America there is growing of potential projects will undoubtedly
becoming actively involved. concern, especially among analysts, be getting a second look.
that natural gas fired power plants are

About This Newsletter


The Power RE-View reports on evolving issues of interest to
The People Behind the Promise TM
underwriters relevant to today’s global electric power
generation industry.
© 2001 General Re Corporation, Stamford, CT
This information was compiled by GeneralCologne Re and is intended to provide
Contact Information
background information to our professional staff, as well as to our clients. The For more information, please contact Michael A. Pero
information may need to be revised and updated periodically. You should consult
with your own appropriate professional advisors before relying on it. at 203 328 5703 or mpero@gcr.com.

You might also like