Professional Documents
Culture Documents
Vol. 1, Issue 2
Power RE-View
Passing Grades
A critical point in the construction of a Any boiler & machinery occurrences or procedures for these tests must be well-
new power plant is the passing of a property damages during the test period defined upon signing the contract for
series of performance or “hot” tests after are normally covered under Builders’ All construction, equipment procurement
the initial plant operation is achieved. Risk or EAR Policies. Since the equipment and installation for a new power plant.
The purpose of these tests is for the is operated in a manner to pass its The justification for this requirement is to
plant contractors and equipment performance tests which are at or avoid claims resulting from contract
suppliers to demonstrate that the new beyond normal operating levels, the interpretation issues such as those
plant meets or exceeds the performance power generated is generally sold to the associated with test run durations (and
levels stated in the project’s contracts. electric grid. During this test period how to deal with interruptions), number
Once successfully shown, the operational stops and starts can be more of stops or restarts allowed before
contractors generally receive their final numerous than the expected during starting over, the extent of
payment, the owners accept the project, normal operation as equipment is often contractor/manufacturer control of
and the unit enters into Commercial “tweaked” to optimize performance. The operations, and the test methods
Operation (CO). unit’s operational control is typically especially for some very low quantities
shared between new operators learning of emissions. Since it is not normal duty,
The power plant owner’s Boiler &
the systems and the contractors/ a high number of stops/starts adds stress
Machinery and Property policies usually
manufacturers start-up representatives. to the machinery and can possibly
start upon Commercial Operation as the
Delays incurred in completing the tests contribute to premature failures in the
Builders’ Risk policy terminates.
may result in liquidated damages for the “bath tub curve” of a power plant’s
There are several aspects of performance contractors, and if an insurable claim life cycle.
tests that have significant insurance occurs, significant business interruption
Underwriting exposures can be limited
implications. Although losses during the (ALOP or DSU) losses may result as well.
by verifying that the performance test
actual physical construction of the
There are generally several procedures and remedies are well-
power plant are not unusual, the test
performance tests conducted. Heat defined, contractual responsibilities are
period often represents the maximum
Rate, environmental emissions, and identified, and that insurance coverages
exposure under the Builders’ All Risk
reliability are among the performance- are sufficient to address all possible loss
Policy for several reasons.
related parameters verified. The actual scenarios.
2 GeneralCologne Re
What To Do With Gas Turbine
“Retired” or “Old” Boilers? News
There are many factors that caused older the fact is that many of these assets have Air-Cooled Generators
boilers to be retired or “mothballed.” The been well maintained, with judicious
The size and ratings of air-cooled
significant ones include: replacements of worn components over
electrical generators used in gas
the years under the regulated utility
• Uncompetitive Heat Rates (require turbine plants have steadily increased
environment.
more BTUs to make Kw-Hr; therefore over the past decades. Continuing this
more costly to operate) With the advent of deregulation and trend, Alstom Power recently
competitive power, the same level of introduced an air-cooled generator of
• Environmental Compliance Issues
investment in maintaining these units 500 MVA size. The Topair 25 (as it is
(require adding expensive
becomes a serious question. With the called) is aimed at the 50 Hz market. A
control systems)
shortage of power and peak reserve version for the 60 Hz market (450
• Condition—not simply the capacity, power plant owners are MVA) is planned for later. Although
age of the equipment! assessing the value of returning these bigger and slightly less efficient than
The last factor directly impacts insurance previously retired units to service. This is the equivalent hydrogen-cooled
issues. Just because equipment is old the case for seasonal peak applications generators, air cooled generators have
does not necessarily make it unfit for its where the high sale price for peak power an advantage: they eliminate the need
intended duty. In fact, older equipment allows for compensation despite their for hydrogen as a coolant for the
may have been designed with more inherent operating inefficiencies. generator. This is an important aspect
robustness than newer components due from an insurance perspective since
Prudent Underwriting the storage of hydrogen on site and
Questions the very real potential of hydrogen
leaks and fires is a concern that affects
• When were the boilers last inspected
the overall risk of the plant.
and by whom? (Obtain a copy of
the report.) (Source: Turbomachinery International,
March/April 2001)
• Were the boilers truly mothballed, or
were they kept on standby readiness Product Field Testing
with or without partial load being
maintained? Or worse case scenario, Testing a newly developed product
were they simply abandoned and left under actual field conditions is
to rust? If on standby, how often are important before releasing the design
they used and to what capacity? for general manufacturing. A case in
point is Mitsubishi’s installation of
• Does the original owner, who knows their newest H-technology large gas
their history, still own the boilers? turbine 701H at the Higashi Niigata
to the philosophies of boiler designers of Power Station of Tohoku Electric
• What are the operating demands on
that period. Routinely, boilers were Power during November 1998 for
the boilers?
operated at 20% (or more) over capacity testing purposes. After various test
because everyone knew that safety • Has environmental control
measurements, the 701 H unit was
margins were built into the design to equipment been added or updated to
removed in July 1999 and the
handle these conditions. However, this is current environmental standards? If
previously installed 701 G unit was re-
not the case with newer equipment, yes, this reflects a significant
installed just prior to the summer
primarily due to increased market commitment on the part of the
peak demand as agreed with Tohoku
competitiveness and lack of favorable owners to operate these units well
Electric earlier. The 701 H model
evaluations for these factors by buyers. into the future.
features steam cooling of rows 1
• Were there any scheduled or through 3 in the turbine that increases
Underwriting Impact unplanned outage reports that would the overall thermal efficiency of a
As stated in the GeneralCologne Re provide insights into persistent combined cycle plant to about 60%.
Boiler & Machinery Utilities Reference equipment problems? According to the article, the two 701
Manual, the average age of coal-fired G turbines (steam cooled combustors)
Old isn’t necessarily bad. What is
boilers is more than 37 years, exceeding have performed well logging a
important is how the boilers have
the conventional design life of 30 years. reliability of 100% in their first year.
been maintained.
Although on the surface this sounds bad, (Source: Turbomachinery International,
January/February 2001)