Professional Documents
Culture Documents
E2.0 Summary
It is common practice to slow roll standby turbines as a means of incident preven-
tion. This is an expensive, inefficient practice and can be avoided in most cases
without compromising rapid and reliable startups.
This Best Practice covers:
1. The paradigm of slow roll operation
2. Economic Incentive to stop slow rolling
3. Legitimate slow rolling
4. Steps to eliminate slow rolling:
– Proper turbine trapping
– Proper supply piping layout
– Good insulation practices
– Turbine testing
– Auditing
– Training
– Inclusion of Training material in Operating Manuals
By implementing this best practice, most turbine slow rolling can be eliminated.
This Best Practice requires involvement by Operations, Maintenance, Engineering,
and Inspection.
rapid startup. To alleviate this problem, facilities began slow rolling these standby
turbines in an attempt to:
1. Keep the condensate blown out of the turbine case or, if that was not possible.
2. At least have a turbine wheel that has already overcome the initial resistance
that a condensate filled case will have to movement. Slow rolling was a
common way to help the turbine come up to operating speed quickly and
smoothly.
mented cases of plant shutdowns when the primary electric failed and the slow
rolled or standby steamer did not start fast enough to prevent a trip.
steam from the exhaust header. The turbine outlet valve (if there is one) is kept
open. The steam from the exhaust header is the steam that condenses in the turbine
and must be continuously trapped out. For more details on trap selection refer to
the steam trap specialist at your facility.
Turbine traps should be installed so they are accessible for maintenance. Proper
block valves and drains should be installed for checking and repairing the traps.
Traps are designed to fail open unless they become plugged. A failed open trap in
this service will keep the turbine case dry and meet the objectives of this Best Prac-
tice, but will be costly in steam losses. Installing a strainer upstream of the trap, or
integral with the trap, and frequently blowing it down will minimize the risk of a
trap failing closed. Traps should be tested periodically to assure they are func-
tioning properly. A recommended test frequency is at least once a year. For more
details on trap testing refer to the steam trap specialist at your facility.
Supply Piping
Turbine supply piping must be properly configured to insure the turbine is supplied
with dry steam. Figure E-2 shows a typical supply piping installation. Supply
piping preferably originates from overhead. Control valves, associated block
valves, and bypass valves must be in a horizontal position. The distance from the
control valve to the turbine inlet should be minimized. This minimizes condensa-
tion during hot standby and insures that this section of line does not store enough
potential energy to continue acceleration and cause possible damage after an emer-
gency trip. A drip leg must be installed to separate and collect any condensate in
the header just upstream of the turbine’s steam supply isolation valve. Drip legs
should be properly sized and installed as shown on Figures E-2 and E-3. The first
valves off of the header should be bellows seal valves (if the valve cannot be
isolated for repacking). Traps should be sized for operating conditions and be
installed on the side of the dripleg, not the bottom of the dripleg.
Insulation
Reason for Insulation. The turbine case should be insulated (especially in cold
climates). This is not critical to eliminate slow rolling, but if not done, the large
surface area of the case will cool, increasing the rate of condensation (increasing
steam consumption). The accumulation of condensate in the case will compound
turbine problems if not properly trapped. An uninsulated case also doesn’t allow
the turbine to be kept as warm as it should, making quick starts more difficult. Insu-
lation is an all or none item. To partially insulate, can cause differential expansion
problems that will result in mechanical failure.
Installation Details. Removable insulation pads work well for the turbine case.
They can be easily removed and reinstalled for turbine maintenance. The pads
should be well fitted around the entire case and governor housing (to prevent
condensation and differential expansion and subsequent case warpage). It is impor-
tant that steam leaks on the turbine are minimized. Steam leaks will cause the insu-
lation pads to become wet, causing a negative insulation effect. Removable
insulation pads may not be the best for extremely wet climates for the same reason.
Steam supply and exhaust piping should also be properly insulated to local require-
ments to minimize condensation of steam.
Turbine Testing
When modifications are made on any turbine per this Best Practice, it is necessary
to test the turbine to be certain all expectations are met. It should be routinely done
to verify: 1) the turbine comes up to speed quickly and smoothly from hot standby
as desired and 2) that the case is dry. If expectations are not met, then additional
work must be done. Additional traps may be required, piping modified, the turbine
repaired, etc.
Adequacy Testing. Successful testing will help build confidence in the turbine that
used to be slow rolled. The testing should be done soon after the modifications
have been completed and the turbine has been left stopped. Time must be provided
to allow the turbine to reach standby temperature and to allow condensation to
occur in the case. Tests may be done as follows:
1. Initiate a start with the APS system. This will allow the turbine to come up to
speed with the main driver on line. On turbines that have no APS, the steam
supply block valve should be opened manually while the main driver is on
line. After testing is complete, return the system to normal operation.
2. On systems with an APS, shut-off the on-line driver. This is a true test but may
be risky if the spare pump fails to come on-line as needed. This also tests the
APS instrumentation, when the on-line pump is shut-off. The APS should auto-
matically start the turbine.
Periodic testing of turbines (also see - Mechanical Integrity Spare Run Program
for Rotating Machinery - IMI Machinery Best Practices Team)
Turbines must be tested routinely (some facility’s test weekly). This will help
assure back-up equipment is:
1. in running condition in case the primary equipment is lost and
2. help maintain confidence that the equipment will start without slow rolling. A
survey of 60 turbines at one facility revealed:
– 10% of the turbines would not start for various reasons such as bad APS,
poor trapping, and plugging problems
– 25% of the spares (including the 10% that would not start) would not
supply the same capacity as the primary’s.
The results highlight the need to test turbines to help prevent incidents and test the
adequacy of trapping on the turbine.
Auditing
Facility wide audits should be performed on a regular basis (at least annually) to
identify turbine(s) that are slow rolling unnecessarily. Findings should be reported
and corrective action should be taken as appropriate.
Training
Training is the key to sustaining the results and benefits of implementing this Best
Practice. Through training, everyone will understand the importance and basic
details of properly installing and maintaining turbines to eliminate slow rolling.
• Operations must know how to operate their properly installed turbines and
know how to audit them for correct operations.
• Maintenance removes and repairs turbines, and upgrades installations. They
must know how to put the turbine back after it is repaired; i.e. proper trap
installations, proper suction piping, putting the insulation pads back on, etc.
• Engineering should know how to properly design new installations and retro-fit
existing installations. Operations, Maintenance, Engineering, or Inspection
should be able to recognize an installation that is incorrect and correct it when
the turbine is reinstalled.
Attachments (all attachments are available on the Lotus Notes, EM&U data
base)
• Typical Drip Leg (Figure E-3)
• Typical turbine inlet piping (Figure E-2)
• Typical turbine trapping (Figure E-1)
A spreadsheet to calculate $ to target is on the EM&U Lotus Notes data base