Plan Semanal de Perforación y Tronadura

07 al 13 de Junio
Distrito Centinela
rev. 2

10 de Junio 2021

Du massen
KPI´S Perforación Esperanza
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 07-jun 08-jun 09-jun 10-jun 11-jun 12-jun 13-jun Total
%Di s p 86% 83% 86% 86% 83% 86% 86% 85%
% Uti l 73% 62% 68% 65% 65% 65% 65% 66%
Rdto 32 32 32 32 32 32 32 32
PE1
Metros 482 397 449 429 416 429 429 3.032
ton/m 71 71 71 71 71 71 71
ton 34.204 28.196 31.880 30.474 29.561 30.474 30.474 215.263
%Di s p 86% 88% 88% 86% 88% 88% 86% 87%
% Uti l 40% 40% 68% 62% 68% 40% 62% 54%
Rdto 33 36 44 44 44 46 48 42
PE5
Metros 272 306 635 562 635 391 613 3.413
ton/m 71 143 143 143 143 71 71
ton 19.287 43.712 90.823 80.329 90.823 27.732 43.509 396.215
%Di s p 50% 0% 25% 87% 87% 84% 87% 60%
% Uti l 72% 76% 68% 40% 68% 65% 67% 62%
Rdto 34 34 34 36 44 44 44 41
PE8
Metros 291 0 137 300 623 578 614 2.544
ton/m 71 71 71 71 151 151 151
ton 20.690 0 9.753 21.299 94.120 87.272 92.735 325.869
%Di s p 91% 91% 91% 91% 7% 31% 91% 71%
% Uti l 58% 57% 40% 58% 20% 50% 52% 52%
Rdto 55 55 55 55 55 55 55 55
PE3
Metros 699 687 482 699 19 203 627 3.416
ton/m 143 143 143 143 143 178 178
ton 99.953 98.229 68.933 99.953 2.761 36.125 111.546 517.499
%Di s p 72% 89% 89% 89% 84% 89% 89% 86%
% Uti l 52% 55% 62% 62% 40% 40% 56% 53%
Rdto 34 34 34 34 34 34 34 34
PE4
Metros 306 401 452 452 273 291 408 2.581
ton/m 71 71 71 71 71 143 143
ton 21.712 28.442 32.061 32.061 19.357 41.661 58.325 233.620
%Di s p 91% 91% 91% 89% 91% 91% 7% 79%
% Uti l 58% 58% 58% 44% 55% 55% 20% 54%
Rdto 54 54 54 54 54 54 54 54
PE6
Metros 686 686 686 509 651 651 19 3.889
ton/m 151 151 151 151 189 189 189
ton 103.625 103.625 103.625 76.931 122.994 122.994 3.582 637.378
%Di s p 91% 91% 85% 91% 91% 91% 91% 90%
% Uti l 54% 58% 57% 40% 55% 55% 55% 53%
Rdto 53 53 53 53 55 55 55 54
PE10
Metros 624 671 617 462 660 660 660 4.354
ton/m 151 151 151 189 189 189 189
ton 94.269 101.252 93.120 87.402 124.712 124.712 124.712 750.179
%Di s p 97% 97% 33% 97% 97% 89% 97% 87%
% Uti l 60% 60% 60% 60% 60% 60% 60% 60%
Rdto 44 44 44 44 44 44 44 44
PE49
Metros 614 614 211 614 614 561 614 3.841
ton/m 149 149 149 149 149 149 149
Ton 91.456 91.456 31.469 91.456 91.456 83.589 91.456 572.339
%Di s p 97% 89% 97% 97% 89% 97% 97% 94%
% Uti l 57% 57% 57% 57% 57% 40% 57% 55%
Rdto 34 34 34 34 34 34 34 34
PE51
Metros 451 412 451 451 412 316 451 2.942
m/m 8 8 8 8 8 8 8
Ton 54 50 54 54 50 38 54
%Di s p 97% 89% 97% 97% 89% 97% 97% 94%
% Uti l 0% 0% 40% 20% 20% 20% 20% 55%
Rdto 34 34 44 44 44 44 44 41
PE50
Metros 0 0 409 205 187 205 205 1.210
m/m 8 8 8 8 8 8 8
Ton 0 0 51 26 23 25 25
CENTINELA m 3.360 3.147 3.458 3.413 3.277 3.203 3.369 23.228
EECC m 1.064 1.026 1.071 1.269 1.213 1.082 1.269 7.993
TOTAL m 4.425 4.173 4.529 4.682 4.490 4.284 4.638 31.222
Perforación Esperanza
Traslados Camabaja
Dia Fecha Equipo Modelo Ton Origen Destino F07B2248_2264
Martes 08-06-2021 PE05 DMM3 110 Sulfuro Fase 06 Sulfuro Fase 07 4 PE-05-PE03 + ROC
Martes 08-06-2021 D64 DM50 45 Tesoro Central Fase 10 Tesoro Sur Fase 02
Miércoles 09-06-2021 PE50 SmartRoc 30 Sulfuro Fase 06 Sufuros Fase 07
3 Prioridad de Perforación
Miércoles 09-06-2021 PE53 SmartRoc 45 Tesoro Central Fase 10 Tesoro Sur Fase 02
Jueves 10-06-2021 PE08 DMM3 110 Sulfuro Fase 06 Sulfuro Fase 07
Jueves 10-06-2021 PE503 DM45 45 Tesoro Sur Fase 02 Tesoro Mirador F04 PATIO MANTENCION
Viernes 11-06-2021
Sabado 12-06-2021 PE05 DMM3 110 Sulfuro Fase 07 Sulfuro Fase 06
PERFORADORAS PE-05
Sabado 12-06-2021 PE51 SmartRoc 30 Sulfuro Fase 06 Sulfuro Fase 08
Domingo 13-06-2021 PE503 DM45 45 Tesoro Mirador F04 Tesoro Sur Fase 02
Domingo 13-06-2021 PE51 SmartRoc 30 Sulfuro Fase 08 Sulfuro Fase 06
Lunes 14-06-2021 PE49 SmartRoc 31 Sufuros Fase 08 Sulfuro Fase 06
Traslados Camabaja
Viernes 11-06-2021 PE04 PIT VIPER 351 190 Sulfuro Fase 06 Sulfuro Fase 07 F07B2248_2264
Sábado 12-06-2021 PE04 PIT VIPER 351 190 Sulfuro Fase 06 Sulfuro Fase 07 PE04 + ROC

F06B1784 1
PE-01+ PE08 + PE04 + 02 ROC

2
F08B2104 1 3
PE08+ PE10 + 02 ROC 2

6 F08B2120
PE06 + 01 ROC

4 1
3
F08B2120
PE06 + 01 ROC
Tronadura Esperanza
Lunes Ma rtes Mi ércol es Jueves Vi ernes Sá ba do Domi ngo
Fa s e Ba nco Precorte 07-jun. 08-jun. 09-jun. 10-jun. 11-jun. 12-jun. 13-jun.
F06 1784 299
F06 1784 PRE
F07 2248 PRE 428
F07 2264 328
F08 2104 PRE 381
F08 2120 420
F08 2120 PRE 769
F08 2120 394
Tonel a je a trona r [kt] 420 299 0 1.097 394 428 381

Fa s e 06 Fa s e 07 Fa s e 08 Tota l Sema na
Trona dura s 0 kt 299 kt 756 kt 1.965 kt 3.020 kt
La s tre 0 kt 0 kt 756 kt 1.965 kt 2.721 kt
Mi nera l 0 kt 299 kt 0 kt 0 kt 299 kt

B2248

B2264

B1784

B2104

Lunes
Martes
Miércoles
Jueves
B2120
Viernes
Sábado
Domingo
Ajuste Tronaduras Semanal 24 al 30 May_21

B2248 Pozos:
Prec: Pz
Pozos: Pz
Ton: 283 kt (est.)

B2264 Pozos:
Prec: Pz
B1784Pozos: Pozos: Pz
Prec: Pz Ton: 283 kt (est.)
Pozos: Pz
Ton: 175 kt (est.)

B1784 Pozos:
Prec: -- Pz
B2104 Pozos: Pozos: Pz
Prec: Pz Ton: 163 kt (Est.)
Pozos: Pz
Ton: 484 kt (est.)

Tronaduras de
borde con
interferencia

B2120 Pozos:
Prec: Pz
Pozos: Pz B2120 Pozos:
Ton: 684 kt (est.) Prec: Pz
Pozos: Pz Lunes
B2120 Pozos:
Ton: 715 kt (est.) Martes
Prec: Pz
Pozos: Pz Miércoles
Ton: 283 kt (est.) Jueves
Tronadura se modifica un día para Viernes
generación de cara libre efectiva. Sábado
Domingo
Programa de Perforación Tesoro F10
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 07-jun 08-jun 09-jun 10-jun 11-jun 12-jun 13-jun Total
%Disp 75% 75% 75% 75% 75% 75% 75% 75%
% Util 57% 57% 57% 57% 57% 57% 57% 57%
Rdto 48 48 48 48 48 48 48 48
D-07
Metros 492 492 492 492 492 492 492 3.447
ton/m 98 98 98 98 98 98 98
ton 48.263 48.263 48.263 48.263 48.263 48.263 48.263 337.841
%Disp 75% 75% 75% 75% 75% 75% 75% 75%

F10 D-64
% Util
Rdto
57%
48
40%
48
0%
48
0%
48
0%
48
0%
48
0%
48
14%
48
Metros 492 346 0 0 0 0 0 838
ton/m 98 98 98 98 98 98 98
ton 48.263 33.869 0 0 0 0 0 82.132
%Disp 97% 97% 89% 97% 97% 89% 97% 94%
% Util 40% 55% 40% 0% 0% 0% 0% 19%
Rdto 44 44 44 44 44 44 44 44
PE53
Metros 409 563 374 0 0 0 0 1.346
ton/m 54 54 54 54 54 54 54
ton 22.097 30.383 20.196 0 0 0 0 72.676
CENTINELA m 0 0 0 0 0 0 0 0
CONTRATO m 902 1.055 866 492 492 492 492 4.793
TOTAL m 902 1.055 866 492 492 492 492 4.793

4
Programa de Perforación Tesoro Sur
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 07-jun 08-jun 09-jun 10-jun 11-jun 12-jun 13-jun Total
%Di sp 87% 87% 87% 85% 87% 87% 87% 87%
% Uti l 68% 68% 68% 40% 0% 0% 0% 35%
Rdto 48 48 48 48 48 48 48 48
DM45-503
Metros 685 685 685 391 0 0 0 2.446
ton/m 98 98 98 98 98 98 98
ton 67.145 67.145 67.145 38.317 0 0 0 239.753

F02
%Di sp 75% 75% 75% 75% 75% 75% 75% 75%
% Uti l 0% 20% 57% 57% 57% 57% 57% 44%
Rdto 44 44 44 44 44 44 44 44
SE-D-64
Metros 0 158 451 451 451 451 451 2.416
ton/m 98 98 98 98 98 98 98
ton 0 15.523 44.241 44.241 44.241 44.241 44.241 236.729
%Di sp 97% 97% 89% 97% 97% 89% 97% 94%
% Uti l 55% 55% 55% 55% 55% 55% 55% 55%
Rdto 45 45 45 45 40 40 40 43
PE25
Metros 575 575 526 575 512 468 512 3.743
ton/m 76 76 76 76 76 76 76
ton 43733 43733 39971 43733 38874 35530 38874 284.449
%Di sp 97% 97% 89% 97% 97% 89% 97% 94%
% Uti l 0% 0% 20% 40% 40% 40% 40% 26%
Rdto 45 45 45 45 40 40 40 43
PE53
Metros 0 0 191 419 372 340 372 1.694
ton/m 76 76 76 76 76 76 76
ton 0 0 14535 31806 28272 25840 28272 128.725
CENTINELA m 685 685 685 391 0 0 0 2.446
ROCMIN m 575 575 717 994 884 808 884 5.437
TOTAL m 1.261 1.261 1.402 1.385 884 808 884 7.883

6 F02
5

4 2

1 3
Programa de Perforación Mirador
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Equipos KPI´s 07-jun 08-jun 09-jun 10-jun 11-jun 12-jun 13-jun Total
%Disp 87% 87% 87% 85% 87% 87% 87% 87%
% Util 0% 0% 0% 20% 68% 68% 68% 32%
Rdto 48 48 48 48 48 48 48 48
DM45-503
Metros 0 0 0 195 685 685 685 2.251
ton/m 98 98 98 98 98 98 98
F04 ton
%Disp
0
75%
0
75%
0
75%
19.159
75%
67.145
75%
67.145
75%
67.145
75%
220.594
75%
% Util 57% 57% 57% 57% 57% 57% 57% 57%
Rdto 48 48 48 48 48 48 48 48
STA-ELVIRA D-05
Metros 492 492 492 492 492 492 492 3.447
ton/m 126 126 126 126 126 126 126
ton 62.052 62.052 62.052 62.052 62.052 62.052 62.052 434.367
CENTINELA m 0 0 0 195 685 685 685 2.251
EECC m 492 492 492 492 492 492 492 3.447
TOTAL m 492 492 492 688 1.178 1.178 1.178 5.698

3 F04
1
4

2
Programa de Tronaduras Tesoro Óxidos
Lunes Martes Miércoles Jueves Viernes Sábado Domingo
Fas e Banco Precorte 07-jun. 08-jun. 09-jun. 10-jun. 11-jun. 12-jun. 13-jun.
F02 2310 318
F02 2325 218 F02 TSUR
F04 2325 458
F04 2332,5 PRE 79
F10 2075 PRE 97
F10 2075 92
F10 2075 PRE 104 B2317,5
Tonelaje a tronar [kt] 318 79 97 218 196 458 0

Fas e 02 TSUR Fas e 04 MIR Fas e 10 TC Total Semana B2310


Tronaduras 0 kt 536 kt 458 kt 293 kt 1.287 kt
Las tre 0 kt 318 kt 458 kt 189 kt 965 kt
Mineral 0 kt 218 kt 0 kt 104 kt 322 kt

F10 TC Lunes
Martes
Miércoles
Jueves
Viernes
Sábado B2325
B2075 Domingo

B2332,5 F04 MIR

B2075

B2325
Protocolo tronaduras Tesoro Sur

• Para tronadura entre los 100 - 200 m, se adiciona en protocolo que no se cortara energía de la línea 23 Kv, pero si se realizará Post tronadura inspecciones y chequeos, por parte
de la mina: Jefe de Turno P&T y por parte de planta: Patricio Gutierrez & Sandra Espinoza
• El horario de las tronaduras comprendidas en zonas entre los 100-200 m y bajo los 100 m, serán a las 14:30 hrs.
• Respecto de las tronaduras que tengan afectación a las áreas críticas, se deben especificar según planificación de extracción. Estas serán incluidas en Plan Semanal de P&T y en
el correo diario de tronadura será enviado a todos los involucrados según lista entregada por Sandra Espinoza.
• Responsables de áreas operativas: instalaciones cercanas y línea eléctrica 23 KV, enviaran el programa mensual de mantenciones, con el fin de tener input en planificación de
tronaduras hacia zona segura.
• Para tronaduras bajo los 100 m, se acuerda que se debe avisar eventos con dos días de anticipación, para que áreas comprometidas puedan tener planes de acción al respecto. Y
además deben estar comprendidas entre los días lunes a jueves de cada semana por los turnos 4x3 encargados de la revisión.
• Se revisará el tema de que si se planifican tronaduras en zona critica bajo los 100 m. está sea la única tronadura del día en rajos Tesoro. También quedó que esta tronadura sea a
las 14:30.
• En temas de suspensión de tronaduras por motivos planta fuerza mayor (quiebre de plan), se deberá enviar un correo formal con la justificación correspondiente antes de las
16:00 hrs del día anterior, copiando en correo: Luis Canales PLANIF. PYT, Carolina Aguilar ING. QAQC, Jorge Nuñez SI PYT, Víctor Ponce ING. PROG. OP. y Gustavo Campillay ING.
PROG. OP.
Programa de Tronaduras Esperanza Sur

Polígono en revisión

Lunes
Martes
Miércoles
Jueves
Viernes
Sábado
Domingo
Programa de Tronaduras Oxe

Se modifica polígono para sacar dos Se ajusta polígono a los


eventos en contorno por consideración 75 metros de borde
geotécnica.

Lunes
Martes
Miércoles
Jueves
Polígono de Apertura de Fase 03 Viernes
OXE siguiente semana se debe Sábado
Domingo
modificar para no quedar
empotrado a lado caja.