You are on page 1of 31

Replacement of existing chillers – 1 no.

at DCHQ-
Dubai Customs

Technical Proposal
INSTALLATION AND TESTING ANDCOMMISSIONING
AIR COOLED PACKAGE CHILLERS

CLIENT

CONTRACTOR

Al Turath Al Aseel Contracting L.L.C.


Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

TABLE OF CONTENT

1.0 PURPOSE

2.0 SCOPE

3.0 REFERENCES

4.0 STANDARDS AND CODES

5.0 HEALTH, SAFETY & ENVIRONMENT

6.0 DELIEVERY STORAGE AND HANDLING

7.0 INSTALLATION PROCEDURE

8.0 PROCEDURE FOR TESTING OF AIR COOLED PACKAGED CHILLERS

9.0 STARTUP PROCEDURE OF THE AIR COLLED PACKAGED CHILLERS

10.0 LIST OF TOOLS AND EQUIPMENTS

11.0 LIST OF MATERIAL

12.0 DATA SHEET FOR MAJOR EQUIPMENT


Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

1.0 PURPOSE:

This document deals with detail method of Replacement and testing and commissioning of existing chillers –
1 no. at DCHQ-followed by commissioning activity to be undertaken for the Carrier chiller Model No 30XB
0750 in order to make the Air conditioning system functioning and working probably.

2.0 SCOPE:
This method statement is applicable for the installation, startup, testing and commissioning of air-cooled
package chiller /Chilled Water Pump for DCHQ along with associated Piping , connection, and water
Balancing

3.0 REFERENCES:
▪ Site visit and existing condition
▪ Approved Shop Drawing.
▪ Approved drawing for location and load calculations of the chillers.
▪ Technical Specification section – as per tender documents

4.0 HEALTH /SAFETY AND ENVIRONMENT:

▪ Work site shall be kept clean and tidy.

▪ Place and secure anchorage devices. Use setting drawings, templates, diagrams, instructions, and
directions furnished with items to be embedded.

▪ Install anchor bolts to elevations required for proper attachment to supported equipment.
▪ Maintain minimum clearances and workspace at equipment according to manufacturer's written
instructions, drawings & specification.

5.0 PRECAUTIONS / ACTIONS


▪ All materials received at the site will be handled and installed properly. Inspection request will be issued for
material inspection upon receipt.
▪ Any damage, miss and other discrepancies will be recorded and notified to the concerned for further action.
▪ Any materials or its part found not suitable for site will be removed from site and actions will be taken for
proper replacement.
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

6.0 STORAGE DELIEVERY AND HANDLING:


▪ Chillers will be delievered as a complete factory assembled unit with protective crating and covering.
▪ Chillers will be transported in a fully charged condition.
▪ Chillers will be stored and handled in accordance with manufacturer’s instructions.
▪ Chillers will be shipped with all refrigerant piping and control wiring factory installed.
▪ Chillers shall be shipped pre charged with refrigerant as specified on the equipment schedule.
▪ Unit shall be shipped with firmly attached metal name plates that indicate name of manufacturer.
Chiller unit model number compressor type and refrigerant used.
7.0 TOOLS AND EQUIPMENT
▪ Crane Tower
▪ Cantilever
▪ Hydraulic Jack (Option)
▪ Chain Block (3 Ton)
8.0 INSTALLATION PROCEDURE:
8.1 COORDINATION

1. Coordinate sizes and locations of concrete bases with actual equipment provided.

8.2 EXAMINATION

1. Before air cooled chiller installation, anchor-bolt sizes and locations, Piping, and electrical
connections to verify actual locations, sizes, and other conditions affecting water chiller
Performance, maintenance, and operations. Water chiller locations indicated on Drawings are
approximate. Determine exact locations before roughing-in for piping and electrical connections.

2. Proceed with installation only after unsatisfactory conditions have been corrected.

3. Comply with requirements for vibration isolation devices specified in technical specification
section 21 07 00 "Vibration and Seismic Controls for HVAC Piping and Equipment."

8.3 INSTALLATION PROCEDURE

• Chiller

A. Installation of air-cooled chiller shall be in line with manufacturer’s recommendation, technical

specification and site conditions.


Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs
B. Equipment Mounting: Install chiller on concrete bases using spring isolators with 97% efficiency

and as recommended by manufacturer. Vibration isolation springs provided by chillers

manufacturers shall only be considered if they meet the above mentioned requirements.

C. The machine must be moved and lifted by using cables, spacing bars and scales of appropriate

dimensions to the machine weight as per manufacturer’s recommendation and also please refer to

attachments for lifting operation as per manufacturer’s recommendation.

D. Machine not to be pulled or pushed from any part other than the base frame.

E. Crane to be arranged with accessories and as per safety procedures.

F. Connect the cables hook to lifting points of chiller frame.

G. Ensure the chiller location is free of obstacles.

H. Machine to be installed on a perfectly levelled base foundation as mentioned in technical

specification.

I. Position the vibration isolators under the frame structure as per specified in technical

specification.

J. Land the chiller on its location smoothly on the place assigned for chiller Installation, drawing

also attached for the proposed location of the Chillers.

K. Disconnect lifting cables and proceed for connections.

▪ Chilled WATER Pumps


a. We will ensure that the installation of Chilled water pump shall be as per the approved
material submittals.

b. We will ensure that the location and details of Chilled water pump shall be as per the
approved shop drawings and coordinated with other services.

c. Before installation, two numbers of chain blocks (03 Tons per each), steel structural
cantilever provided and marking on foundation will be provided where Chilled water pump
will be installed.
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

d. Lift the Chilled water pump sections by Tower crane and place it on the foundations
provided.

e. If tower crane cannot reach then place the unit/sections on the cantilever/platform provided
and Start moving the Chilled water pump Sections in horizontal way by hydraulic jack and
transfer the Air Handling Units on to the foundation.

f. Levelling of the unit after the installation of the unit with inertia base.

g. Chilled water pump will be connected to Chilled Water Pipes (Return and Supply). Ensure
that test point is provided.
h. Electrical connections should be at the nearest accessible point .

i. We will provide and ensure the accessibility for maintenance

8.4 CONNECTIONS

8.4.1 Arrangement of the pipes and fittings to be as per technical specification and
Existing PIPES AND TUBES

8.4.2 All the refrigerant pipes connections to be as per Section- 23 18 00 AIR CONDITIONING
PIPING, Drawings indicate general Arrangement of piping, fittings, and specialties.

8.4.3 Install piping adjacent to chiller to allow service and maintenance.

8.4.4 Evaporator Fluid Connections: As shown in detail drawings. Connect to evaporator inlet with
shutoff valve, Strainer, flexible connector, thermometer, and plugged tee with pressure gage
and drain connection with valve. Make connections to chiller with a union, and flanges.

8.4.5 Refrigerant Pressure Relief Valve Connections: For water chillers installed indoors, extend vent
piping to the outside without valves or restrictions.

8.4.6 Connect each drain connection with a union and drain pipe, and extend pipe, full size of
connection, to floor Drain. Provide a shutoff valve at each connection if required.
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

9.0 PROCEDURE FOR TESTING OF AIR COOLED PACKAGED CHILLERS


All chillers dispatched from factory are run tested and. As precautionary measure every chiller
should be subjected to pre-commissioning procedures to ensure trouble free operation and chillers
might need fine tuning after commissioning.

9.1 CHECKS ON MICRO TECH PANEL


Visual check of the unit controller shall be carried out to ensure all components such as Transformers,
relays, contactor, controllers are in good condition. All pressure sensors, temperature sensors, etc. shall
be checked for proper connections.

9.2 STARTER PANEL


Confirm the Megger test, Perform the control logic test as per the drawing of the starter panel before
proceeding to commissioning work. Check the wiring connections, phase sequence, supply voltage.
Check phase sequence of the main power in coming with help of phase sequence meter.

9.3 MEGGER TEST OF THE MOTORS

Phase to Earth’ and ‘Phase to Phase’ megger value shall not be less than 20 mega-ohms (this test should
be conducted after keeping the heaters on for at least 24 hours). A suitable megger of 500V shall be used
to carry out the test.

9.3.1 PHASE TO EARTH:


Connect one terminal of megger terminal probe(red color) to one end of motor terminal T1 and other end
of megger terminal probe (black color) shall be connected to motor earth terminal. Rotate the handle of
megger at constant speed OR press the button provided on megger and note the reading shown in
display. Keep the black colored megger terminal probe at motor earth terminal and change the red color
megger terminal to the remaining motor terminals viz. T2, T3, and take readings. In all above three tests
megger shall show not less than 20 mega-ohms.
After performing the tests specified in step 3.a, discharge the residual voltage stored in the winding by
earthing all the six motor terminals momentarily using an electric wire.
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs
9.3.2 PHASE TO PHASE:
Connect one terminal of megger terminal probe ( red color) to one end of motor terminal T1 and other
end of megger terminal probe (black color) shall be connected to other motor terminal T2. Rotate the
handle of megger at constant speed OR press the button provided on megger and note the reading shown
in display. Repeat this procedure for the terminals T1 & T3 and T2 & T3. In all above three tests megger
shall show not less than 20 mega-ohms.
After performing the tests specified in step 8.3.1 discharge the residual voltage stored in the winding by
earthing all the three motor terminals momentarily using an electric wire.
The motor insulation is healthy if all the readings taken during the above procedure are above 20 mega-
ohms.

10.0 STARTUP OF THE CHILLERS


10.1.1 With main disconnect open, check all electrical connections in control panel and starter to be
sure they are tight and they provide good electrical contact. Although all the connections are
tightened at the factory, they might have loosened enough in shipment, which may cause system
malfunction.

10.1.2 Check the actual line voltage to the unit to make sure it is the same as specified in the
compressor nameplate within + 10% and that phase voltage unbalance does not exceed 2 %.
Verify that adequatepower supply and capacity is available to meet the required load.
10.1.3 Make sure all interlock wiring is completed as per Carrier wiring diagram.
10.1.4 Turn the main power switch ON; this will energize the crankcase heaters of the compressor.
Please note the crankcase heaters should be kept on at least 24 hours prior to start up, crankcase
should be warm.
10.1.5 The unit might have been shipped from factory with the valves in position, ensure that all the
valves are open.
10.1.6 Check and inspect evaporator water piping. Make sure that the flow direction is correct and
piping is made to correct water nozzle connections on the respective heat exchangers and
open the isolation valves of secondary side. Check the proper connections and settings of differential
water pressure switch/Flow switch.

10.1.7 Start manually evaporator water pumps. Check all piping for leaks. Vent the air from the
evaporator water headers/ from the entire secondary system. The secondary circuit in the
evaporator side should contain clean, non-corrosive liquid.
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

10.1.8 Set the required water flow valve with the help of pressure drop and ensure that adequate load is
available for initial start-up.
10.1.9 Once again check all the set points fed in the controller.
10.1.10 Check and inspect evaporator water piping. Make sure that the flow direction is correct and
piping is made to correct water nozzle connections on the respective heat exchangers and open
the isolation valves of secondary side. Check the proper Connections and settings of differential
water pressure switch/Flow switch.

10.1.11 Start manually evaporator water pumps. Check all piping for leaks. Vent the air from the
evaporator water headers/ from the entire secondary system. The secondary circuit in the
evaporator side should contain clean, non-corrosive liquid.
10.1.12 Set the required water flow valve with the help of pressure drop and ensure that adequate load is
available for initial start-up.
10.1.13 Once again check all the set points fed in the controller.
10.1.14 By keeping the main power wire of compressor disconnected, give start command from
control Panel and observe the starting sequence and check the compressor input/output and unit
input/output. If the sequence and other input and output signals are healthy, make the electrical
connections and now it is safe to start the Chiller.
10.1.15 After taking the control test as specified in the last point of above procedure make the power and
control connections and power supply to the unit is to be established.
10.1.16 Check the physical rotation of the compressor. Observe the chiller parameters during start up.
10.1.17 After initial pull down, at stable operating conditions; the startup data shall be filled in the Carrier
startup Form for individual chiller
Replacement of existing chillers – 1 no. at DCHQ-
Dubai Customs

11.0 LIST OF MATERIAL

Material Brand
1 air-cooled package chiller Carrier
2 Chilled water Pump Xylem Bell & Gosset
3 Chilled water Pipe Nippon
4 Chilled water Pipe Insulation Kimco
5 Chilled water Valves Crane
6 Cable DUCAB
7 BMS Integration Siemens
8 Chilled water accessories Hunter/VDH
9 Aluminum Cladding Hindalco
10 Water Balancing and testing Prime tech
Commission
Standard Report

Date: 04/04/21 15:00 Prepared By: Hayan Shaltoni

30XB 0750
Air-cooled chiller with fixed-speed screw compressor
Performance Information
Mode Cooling
Cooling Capacity (1) kW 657.9
Cooling Efficiency (EER) (1) kW/kW 2.382
Unit Power Input (1) kW 276.2
Sound Power Level (LwA) (1) dBA 97
Sound Pressure Level at 10.0 m (LpA) (1) dBA 64
Minimum Capacity (2) kW 58.09
Maximum Capacity kW 657.9
(1) All performances are compliant with AHRI Standard 551/591 (SI). Sound Power level according to 9614-1.
(2) Due to the minimum flow rate allowable, a lower inlet water temperature might have to be specified to Non contractual picture
achieve this performance. Seasonal Efficiency (3)
Allowed applications for CE mark:
Unit cannot be sold in countries where CE marking is mandatory
Operating Conditions
System element Cooling IPLV.SI kW/kW 4.401
Evaporator (3) All data related to seasonal efficiency are given for standard units
and main options (Brine, pump, energy efficiency,« 
Fluid Type Fresh Water
Fouling Factor (4) (sqm-K)/kW 0.0176 Unit Information
Fluid

Leaving Temperature °C 7.00 Manufacturing Source Montluel


Entering Temperature °C 12.00 Refrigerant Type R134a
Fluid Flow l/s 31.36 Refrigerant Weight kg 123
Total Pressure Drop kPa 32.5 Tonnes CO2 Equivalent Tonnes 176
Condenser Number of Refrigerant Circuit 2
Entering Air Temperature °C 46.0 Number Of Passes 2
Air

(Evaporator)
Altitude m 0
Number Of Compressor 2
(4) The impact of fouling factor is calculated as per AHRI 550/590-551/591 method
Number Of Fan 12
Operating / Shipping Weight kg 5532/5434
Unit Configuration
Unit Dimensions (LxWxH) mm 7186x2253x2322
149 Bacnet over IP
15 Low noise level Electric Information
159A Under voltage relay Unit Voltage V-Ph-Hz 400-3-50
20A IP54 control box Standby Power kW 0.2000
23A Enclosure panels Power Factor 0.87
25C Low inrush current Circuit 1
281 Evaporator with aluminum jacket Maximum Current A 514
318 Compliance with UAE regulation Start Up Current A 676
93A Compressor discharge valves Current at Eurovent A 402
Conditions
Documentation
PSD
IOM
Technical Drawing
Revit File

Certified in accordance with the AHRI Air-Cooled Water-Chilling Packages Certification Program, which is based on AHRI Standard 550/590 (I-P) and AHRI Standard 551/591 (SI).
Certified units may be found in the AHRI Directory at www.ahridirectory.org.

Package Chiller Builder-EMEA v4.17.0.0


WIZE-86BB9D 06/25/2020

38 l/s
40 M
Model: 4x6x17.5A 0M
70.5 %
0.0 %
13.625 in
40 hp
29 bhp
1500 rpm
1480 rpm
8.95 ft
44.3 M
12 l/s
52.2 l/s
68 ºF
Water
0 lbs
12.69 ft²

4x6x17.5A
1480 RPM

WIZE-86BB9D
Performance curve meets 14.6 / ISO 9906 acceptance criteria
WIZE-86BB9D
WIZE-86BB9D
DOUBLE REGULATING VALVE

DM921 DM921

Double Regulating Valve (DRV)


PN16
BALANCING VALVES

Features & Benefits


• Y-Pattern globe valve with a characterised throttling disc
• The Double Regulating feature allows the valve to be used for
isolation and to be reopened to its pre-set position to maintain
required flow rate
• In two unit systems, the DM921 has sufficient authority to regulate
flow in circuits incorporating a flow measurement device
• The valve opening may be set to control flow at a pre-determined rate
• Fitted with 2 x 1/4" BSPT plugs for conversion to DM931 if required
Dimensional Drawing
• Operation of the valve is by means of a hand wheel incorporating
a micrometre device

Materials
PART MATERIAL
Body Ductile Iron - BS EN 1563 GJS-450-10
Bonnet Ductile Iron - BS EN 1563 GJS-450-10
Bonnet Gasket Non-asbestos
Disc (All sizes) EPDM
Coated Cast Iron
Disc Bush Bronze
Stem 410 SS
Gland (65 to 150mm) Brass
Gland (200 to 300mm) Cast Iron
Pressure/Temperature Ratings
Gland Nut Brass TEMPERATURE (°C) -10 to 120
Packing Non-asbestos PRESSURE (BAR) 16.0
Seat Ring Bronze
Ratings align with BS EN 1092-2 PN16 (formerly
BS 4504).

Dimensions & Weights Coefficients*


SIZE FACE- CENTRE- WEIGHT SIZE FLOW HEAD
TO-FACE TO-TOP LOSS
(DN) A (mm) B (mm) (kg) (DN) (Kv) (K)
65 290 262 15.8 65 85 4.9
80 310 267 19.5 80 111 5.5
100 350 300 28.0 100 146 9.2
125 400 325 37.5 125 250 7.3
150 480 340 50.5 150 380 6.5
200 600 525 123.0 200 600 7.8
250 730 575 192.0 250 1211 4.6
300 850 645 251.0 300 1521 6.0

*Fully open position.


Valid as of 160418

END CONNECTIONS:
Ends flanged to BS EN 1092-2 PN16.

Every effort has been made to ensure that the information contained in this publication is accurate at the time of publishing. Crane Ltd assumes no responsibility or liability for typographical errors or
omissions or for any misinterpretation of the information within the publication and reserves the right to change without notice.

TECHNICAL HELPLINE: +44 (0)1473 277400


6
E: enquiries@cranefs.com W: www.cranefs.com
BALLVALVES
GATE VALVES

FM63 FM63

Cast Iron Gate Valve


Non rising Stem PN16
GENERAL VALVES

Features & Benefits


• Crane cast iron gate valves offer the ultimate in dependable service
wherever minimum pressure drop is important.
• Each valve is manufactured in accordance with BS EN 1171: 2002
• Hydrostatically tested to BS EN 12266-1: 2003

Materials
NO. PART MATERIAL
1 Body Cast Iron BS EN 1561 GJL-250
2 Bonnet Cast Iron BS EN 1561 GJL-250 Dimensional Drawing
3 Disc Cast Iron BS EN 1561 GJL-250
4 Body Seat Ring Bronze BS EN 1982 (CC491K)
5 Disc Seat Ring Bronze BS EN 1982 (CC491K)
6 Stem Stainless Steel BS 970: 410S21
7 Gasket Graphite Graphite (Asbestos Free)
8 Gland Packing Nut Stainless Steel BS 970: 304S31
9 Handwheel Grey Iron BS EN 1561 EN-GJL-250
10 Stem Retaining Ring Stainless Steel BS 970: 304S31
11 Disc Stem Nut Bronze BS EN 1982 (CC491K)
12 Packing Ring Graphite Graphite (Asbestos Free)
13 Body/Bonnet Bolt Steel BS 3692 GR 8.8
14 Body/Bonnet Nut Steel BS 3692 GR 8
15 Handwheel Retaining Nut Steel BS 4190 GR 4
16 Handwheel Washer Steel BS 4320
17 Body ID Plate (Not Shown) Aluminium

Dimensions & Weights


SIZE WEIGHT A B C D E F
(mm) (kg) (mm) (mm) (mm) (mm) (mm) (mm)

65 18.7 190 20 185 262 190 118


80 23.9 203 22 200 286 190 132
100 37.6 229 24 220 356 220 156
125 50.7 254 26 250 426 300 184
150 63.8 267 26 285 463 300 211
Pressure/Temperature Ratings
200 104.3 292 30 340 578 350 266
250 194.5 330 32 405 773 406 319 TEMPERATURE (°C) -10 to 120 200
300 275.5 356 32 460 860 457 370 PRESSURE (BAR) 16 12.8

All dimensions are nominal. Intermediate pressure ratings shall be determined by


Please note size 50mm is also available, please refer to the website. interpolation.

PRESSURE RATING: PN16 SPECIFICATION: Wedge Disc, Non-Rising Stem, Inside Screw, Handwheel operated.
PRESSURE/TEMPERATURE OPERATING RANGE: This valve is not suitable for use on group 1 gases or unstable fluids, as defined by the
-10 to 120°C at 16 bar, 200°C at 12.8 bar Pressure Equipment Directive 2014/68/EU.*
UK END CONNECTION: Flanged BS EN 1092-2: PN16 AVAILABLE OPTIONS: Flanges Undrilled
Vaild as of 081220

Every effort has been made to ensure that the information contained in this publication is accurate at the time of publishing. Crane Ltd assumes no responsibility or liability for typographical errors or
omissions or for any misinterpretation of the information within the publication and reserves the right to change without notice.

TECHNICAL HELPLINE: +44 (0)1473 277400


100
E: enquiries@cranefs.com W: www.cranefs.com
HUNTER DIN / EN STANDARD
INDUSTRIAL PRESSURE GAUGES

DIN EN Standard 837-1 / 2


supersedes DIN 16063 / 64

#GP 100.24 Casing steel sheet, black, dia. 100 mm / 4"


#GP 100.24 SS Casing stainless steel, dia. 100 mm / 4"
#GP 100.14 Casing ABS, black, dia. 100 mm / 4"

Purpose measurement of positive and negative pressures

Application for all liquids and gases except for those having high viscosity or which tend to crystalize

Window acrylic glass - snap-in-window


Dial aluminium, white (black resp. black/red lettering)
Thread connections radial / bottom brass G 1/2" BSP - others on request (stainless steel on request)
Measuring system Cu-alloy: upto 40 bar Bourdon tube, from 60 bar coiled (stainless steel on request)
Mechanism copper alloy
-1.... 600 bar (or equivalent)
Ranges lb/in2 lb/in2 + bar feet of water or others
2 Class 1.6
kg/cm inHg kPA on request

max. operating pressure 75% of full scale value for steady pressures or 60% for
Operating range
fluctuating. Occasional short time peaks to full scale permissible.

ambient temperature -25/ +60°C resp. process temper ature +60°C (calibration
Temperature range
reference temperature +20°C approx.)

every 10°C deviation from the calibration reference temperature will produce an error
of 0.3% of indicated pressure - error will be plus for higher temperatures and minus
Technical remarks
for lower (temperature used for the correction of the indicated pressure is the
temperature of the gauge system and not the medium)

All details and data are subject to final confirmation


08-2003 HUNTER

HERMANN JAEGER GMBH


P.O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +4 9 4 0 ] 30 69 27 14 Fax: [+4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
HUNTER DIN Standard V-Form
INDUSTRIAL THERMOMETERS
HUNTER Industrial Thermometers are well-known and widely used in many
applications where the correct and safe measuring of temperature is necessary.
HUNTER Industrial Thermometers are known for their quality as well as reliability.
These instruments can be used for many applications:
airconditioning / refrigeration - ship's engines - chemical plants - power stations etc.
and are the prefered measuring instruments for even difficult or safety relevant projects.
Additional advantages: maintenance-free and operation without energy consumption.
anodised gold-colored surface, resistant
Alu alloy casings against aggressive vapours, double scale:
°C in black / °F in red color
a fibre-glass reinforced thermoplastic
NYPAC casings polyester resin, gold-colored, with scale as
mentioned above
casing is adjustable to any viewing position
Viewing position
and locked by a brass nut

110 x 36 mm Alu alloy / NYPAC


Casing sizes 150 x 36 mm Alu alloy / NYPAC
and locations 200 x 36 mm Alu alloy / NYPAC
of stem
Alu alloy: straight / 90° angle / 135° angle
NYPAC: straight / 90° angle
Measuring
liquid expansion
principle

abt. 1% of full scale value


Accuracy rating
acc. to DIN 16195

rod shape - prismatic blue color


(ranges -30.... +200°C)
Glass capillaries rod shape - mercury yellow prismatic
(ranges above +250°C)
on request: red filling (-30.... +200°C)
standard dual scale black °C / red °F
Scales
(on request only °C or °F)

All details and data are subject to final confirmation


03-2014 HUNTER

HERMANN JAEGER GMBH


P. O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +49 4 0 ] 30 69 27 14 Fax: [+4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
HUNTER DIN Standard V-Form
INDUSTRIAL THERMOMETERS

Form B - with male screw socket 1/2" BSP (STANDARD) Standard length of stem L 1 :
other forms (see above drawing) and threads are available on request 110 mm = 40 / 63 / 100 / 160 mm
brass Ms58 for temperature ranges up to 300°C 150 mm = 63 / 100 / 160 / 200 mm
steel for temperature ranges above 300°C 200 mm = 63 / 100 / 160 / 200 mm
on request: stainless steel / seawater resistant brass / other materials other lengths on request

All details and data are subject to final confirmation


03-2014 HUNTER

HERMANN JAEGER GMBH


P. O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +4 9 4 0 ] 30 69 27 14 Fax: [+ 4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
HUNTER DIN Standard V-Form
INDUSTRIAL THERMOMETERS

Case 110 x 36 mm
Form B male thread (standard 1/2"BSP - other threads on request)

straight 90° angle 135° angle

Article numbers refer to straight version

Form C with coupling nut 1/2" BSP: on request (only straight and 90° versions)

Other threads or even special stem lengths: on request

All details and data are subject to final confirmation


03-2014 HUNTER

HERMANN JAEGER GMBH


P. O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +49 4 0 ] 30 69 27 14 Fax: [+4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
HUNTER DIN Standard V-Form
INDUSTRIAL THERMOMETERS

Case 150 x 36 mm
Form B male thread (standard 1/2"BSP - other threads on request)

straight 90° angle 135° angle

Article numbers refer to straight version

Form C with coupling nut 1/2" BSP: on request (only straight and 90° versions)

Other threads or even special stem lengths: on request

All details and data are subject to final confirmation


03-2014 HUNTER

HERMANN JAEGER GMBH


P. O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +49 4 0 ] 30 69 27 14 Fax: [+4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
HUNTER DIN Standard V-Form
INDUSTRIAL THERMOMETERS

Case 200 x 36 mm
Form B male thread (standard 1/2"BSP - other threads on request)
straight 90° angle 135° angle

Article numbers refer to straight version

Form C with coupling nut 1/2" BSP: on request (only straight and 90° versions)

Other threads or even special stem lengths: on request

All details and data are subject to final confirmation


03-2014 HUNTER

HERMANN JAEGER GMBH


P. O. Box 5 00 7 52 – 2 27 07 Ha mbur g
Phone : [ +49 4 0 ] 30 69 27 14 Fax: [+4 9 4 0] 3 8 7 5 23
mailto: info@hunter-hamburg.de www.hunter-hamburg.de
REF : QFM_WAR_A/C CHILLERS – 02 (Rev. # 0, Issue # 1 Issue date 05/05/2014)

EXTENDED WARRANTY CERTIFICATE - UTS CARRIER L.L.C


Project name & Location : Date:

MEP Contractor :

Main Contractor :

Client :

Consultant : DRAFT
Sales Order :

Sales Engineer :

Invoice numbers / dated :

Serial Numbers :

Date of Commissioning :

Material Type / Description : 30XB-0750 - Air Cooled Screw Chillers

This is to certify that the equipment supplied with the above mentioned invoices are covered under UTS Carrier standard
warranty policy as detailed in the attached three pages of the UTS Carrier Standard Warranty Policy.

Chillers are covered for 3 years warranty against manufacturing defects of parts from the date of commissioning of chiller
unit.

Chillers compressor parts are covered for 5 years warranty against any manufacturing defects from the date of Commissioning.

Any routine maintenance,labour,consumables is excluded from UTS Carrier scope, in all cases.

In order to validate the warranty a proof of preventive maintenance as per Carrier O & M manual has to be provided to UTS
Carrier L.L.C.

Yours faithfully
for UTS Carrier L.L.C

CMS Sales Manager CMS BU Manager Finance Manager General Manager


*Commissioning report to be read in conjunction with warranty certificate
Enclosed : UTS Carrier L.L.C warranty policy Doc ref; Q_Policy_WAR —002 / 5th May 2014 (2 pages)

You might also like