Professional Documents
Culture Documents
E
tion for the new No. 7 New York City subway and is occupied
by a 6-story subway ventilation building. Another unique aspect
R
of the 55 Hudson Yards structure was the use of a post-tensioned
lightweight concrete flat slab floor system for a high rise com-
U
righ
t mercial office building.
T
y
Cop
C
Project Evolution
55
e
U
The developer behind 55 Hudson Yards, Related/Oxford Properties,
n
acquired the 55 Hudson Yards site from another major New York
i
R
City (NYC) developer in early 2000.
z
T
While the initial developer pursued potential tenants, early designs
g a for a steel diagrid building were proposed, and negotiations with the
S
Metropolitan Transit Authority (MTA) took place to accommodate
a the infrastructure for the new No. 7 subway line. The negotiations
m resulted in an agreement to build the 34th Street-Hudson Yards
subway station with portions directly below the office tower, includ-
ing two major entrance escalators and a 6-story ventilation building.
The agreement included a provision for the ventilation building
and the below-grade subway station to have adequate capacity to
HUDSON YARDS support the proposed vertical and lateral loads imposed by the
commercial office tower. Towards the end of 2007, construction
of the station and adjoining ventilation building began and, by
By Jeffrey Smilow, P.E., F.ASCE, Ahmad Rahimian, Ph.D., P.E.,
the fall of 2015, they were in service.
S.E., F.ASCE, and Lan-Cheng (Peter) Pan, Ph.D., P.E.
During the construction of the MTA infrastructure below and
next to 55 Hudson Yards, the original developer sold the prop-
erty and air rights to Related/Oxford Properties, which was
constructing high-rise buildings adjacent to the 55 Hudson
Yards site. Related/Oxford Properties immediately pursued the
modification of the original tower design to meet their vision
of a 51-story tower with 1.3 million square feet of gross area
for commercial use. These changes resulted in architectural and
STRUCTURE magazine
structural modifications specific to the tenant base considered by drilled caissons, ranging from 4.5
the new developer. The redesign of the 55 Hudson Yards tower to 5.5 feet in diameter, and the
included two key structural considerations: remaining 40% was carried by
• Use of alternative structural materials, namely cast-in-place the existing 6-story MTA ventila-
concrete, to meet the financial requirements of Related tion building. The caissons were
Properties. (This original concept was converted into lightweight the primary support system for
concrete to reduce the loading upon the existing subway the concrete core and shear walls,
structure.) carrying loads ranging from
• Redirecting the loads of the new tower to meet acceptable 10,000 to 33,000 kips.
vertical and lateral load limits of the already built underground Complicating the foundation
subway station and the 6-story subway ventilation building. design was the fact that the loca-
tion of the caissons was limited
to the area between the two
Project Description previously constructed subway
The 55 Hudson Yards project is located in the western half of the block entrance escalators (Figure 2). Figure 2. Foundation overview with
limited by West 34th and West 33rd streets to the north and south, respec- The acceptable diameter and detail®of caissons between escalators.
E
tively. To the east, the project neighbors Hudson Park, where the main location for the caissons required the reinforced concrete core and
entrance of the 34th Street-Hudson Yards subway station is located (Figure shear walls to cantilever beyond the caissons, resulting in a 20-foot
R
1). Furthermore, the new building neatly extends above and along the deep caisson cap. All caissons utilized 12,000-psi grout and were
north side of the existing 6-story subway ventilation building in the embedded into rock sockets below the escalator base to adequately
U
southwest corner of the lot. The architects of the project are Kohn Pedersen ht transfer their loads into the rock below the escalator shafts (Figure 3).
yrig
T
Fox and Kevin Roche (John Dinkeloo and Associates). WSP USA Cop Inc. The length of rock sockets ranged from 35 feet to approximately 100
provided integrated engineering services for structural and MEP systems. feet. To limit the caissons diameter and maximize their load-carrying
C
The building is 51 stories high, divided into a 10-story podium and a capacity, No. 28 reinforcing bars with 75-ksi yielding strength were
e
U
41-story tower, reaching 760 feet. The geometry of both the podium and used. In exceptional cases, a solid steel section was provided in lieu
the tower is approximately rectangular with column-free spans reach-
n
of reinforcing bars.
i
R
ing almost 50 feet in the podium and more than 40 feet in the tower.
z
T
The combination of site-related constraints triggered by the MTA
infrastructure and the limitations associated with the original design
g a Superstructure
S
posed engineering challenges addressed by unique and highly innova- The superstructure of the 55 Hudson Yards project is based on a cen-
tive structural solutions. a tral reinforced concrete shear wall core and exterior moment frames
Foundation System
m connecting perimeter columns with a spandrel beam around the slab
edge of the tower. It is complemented by a partial outrigger and belt
system at the top (Figure 4, page 38). The structural solution provided
The main objectives of the foundation system envisioned for 55 by WSP addressed three main design objectives:
Hudson Yards were to address the large interaction with existing MTA • To follow the main architectural intent, which required long-
underground facilities and to minimize the impact in terms of loads span, column-free spaces.
transmitted to those facilities. • To minimize the structural weight and thus meet the load-
The vertical load demands of the building were divided into three carrying limitations of the existing 6-story MTA ventilation
major components to provide adequate load-carrying capacity. building and the underground subway station.
Approximately 20% of the vertical load was transferred to the rock • To provide flexibility for future modification to the floor
substrate by means of a reinforced concrete mat and footing foun- plans, specifically allowing for additional slab openings in
dations, about 40% was transferred using 10 reinforced concrete selected locations.
continued on next page
Figure 3. General layout of foundation system with details of caissons and caisson sockets.
E
concrete, which went through an extensive pre-construction
sample mix design study to assure its suitability, pumpability, and
R
constructability under the project conditions. Three-dimensional
laser scans were carried out at each floor level to determine the pre-
U
righ
t cise final location of post-tensioning strands (Figure 5) to address
T
y
Cop floor plan flexibility for future tenants. The post-tensioned slab
utilized a banded system, thereby grouping the post-tensioning
C
bands on either side of potential future slab openings.
e
U
The 9th floor is used as the primary mechanical floor and also
Figure 4. Structural overview. 3D view from Northwest.
n
serves as the interface between the podium and the tower floors. At
i
R
this level, all the perimeter columns of the tower were transferred
z
T
from a smaller tower footprint to the larger podium footprint. The
S
the 10th-floor slab carries in-plane compression loads, and the
a 9th-floor level carries in-plane tension loads. The 9th-floor tension
m forces were efficiently counteracted with undraped horizontal post
tensioning (Figure 6).
Finally, to limit lateral deflections and accelerations due to wind
events, a full-story height, partial outrigger and belt system con-
necting the central shear wall core with a number of perimeter
columns on the north end of the tower was incorporated at the
51st floor of the tower.
E
had bypassed a specific loca- light weight concrete, a rarity on commercial high rises, is
tion, the supporting structure proven to be an economical alternative to structural steel
R
was engaged using steel plate framing. See Figure 8 for an overall view of the project
shims which then created a under construction as of May 2017.▪
U
new continuous load path ht
yrig
T
Figure 8. 55 Hudson Yards tower under Cop
through the initially bypassed
Jeffrey Smilow, P.E., F.ASCE, is Executive Vice President and USA
construction as of May 2017. support points.
C
Director of Building Structures at WSP USA, Principal in Charge
of the project.
e
U
Material and Construction Innovations
n
Ahmad Rahimian, Ph.D., P.E., S.E., F.ASCE, is Technical Director
i
R
High-performance structural materials were used in 55 Hudson Yards and USA Director of Building Structures at WSP USA.
z
T
to provide adequate stiffness, strength, and resilience. For columns and
shear walls, a concrete compressive strength of 12,000 psi was used in
g a Lan-Cheng (Peter) Pan, Ph.D., P.E., is Senior Associate of Building
S
Structures at WSP USA, Project Manager.
all podium floors, which gradually reduced to 7,000 psi at the 51st floor.
a
m
ADVERTISEMENT–For Advertiser Information, visit www.STRUCTUREmag.org