Professional Documents
Culture Documents
1.0 Scope :
This Method Statement defines the procedures to be followed for the Testing and
Commissioning of UPS System.
2.0 PURPOSE :
3.0 REFERENCES
3.1.1 Project Specification
3.1.2 Project Drawing
3.1.3 Electrical Equipment Data Sheets
4.0 DEFINITION
None
5.0 RESPONSIBILITIES
5.3 Commissioning Team:
5.3.1 All Pre-Commissioning and Commissioning activities are the responsibility of
Commissioning Team.
5.3.2 Pre-commissioning and Commissioning shall be carried out by Specialist Contractor
under the direct supervision of MEP Electrical Commissioning Engineers.
5.3.3 Contractor Commissioning manager shall check the commissioning works prior to
submission to the Commissioning Agent for witnessing and approval.
5.3.4 In case of failure in any test, the Specialist Contractor will rectify, and MEP
Commissioning team to re-offer the test to Commissioning Agent for re-witnessing
and approval.
5.3.5 Final Testing & Commissioning Report shall be submitted to consultant for approval.
5.4.1 Tool Box talk has to be conducted and all the hazards have to be identified before
starting the commissioning.
5.4.2 To make sure that the Personnel Protective Equipment (PPE) are used by the Task
Force during executions of work at site.
5.4.3 Risks related to the activity shall be assessed and addressed as required.
5.4.4 To provide training for the work force in order to execute the activity safely.
6.0 METHOD OF WORK
6.1 Material
6.1.1 None
6.3 Preliminary Checks
6.3.1 All Electrical works are installed as per the approved construction drawings.
6.3.2 Proper cable size should be installed for the input and output.
6.3.3 Check type, size and rating of all protective devices and compare with the approved
drawing and schedules.
6.3.4 All material uses must have an approved material submittal.
6.3.5 Make sure that the temperature in the installation room for UPS system and
batteries is within the manufacturer’s recommendations as given below:
UPS: 0 to +40 ċ.
Batteries: 20 to 25 ċ
6.3.6 Ensure proper cleanliness in the Installation room.
6.3.7 The position where the UPS system is installed should not be exposed to direct
sunlight.
Positioning
6.3.8 Make sure that the floor is strong enough to withstand the weight of UPS and
battery cabinets.
6.3.9 A place of at least one meter should be available in front of the UPS for easy
access.
6.3.10 Minimum 20 Cm should be available at the rear side of the UPS for flow of Air from
the cooling fans and Min 40 cm for Maintenance operation of the Fan.
6.3.11 No objects should be kept at the top of the UPS.
6.3.12 UPS Identification (Label) to be done.
6.3.13 Proper Cable size is installed for Earthing at all the Equipment’s. (UPS & its
associated equipment’s).
Cable Termination:
6.3.14 Connect the Input power cable to the SWIN breaker or switch provided inside the
UPS when opened from the front.
6.3.15 Connect the Output power cables to the SWOUT breaker or switch provided.
6.3.16 Pull out the battery cables from the battery cabinet to the UPS and connect it to the
battery terminals shown in the UPS.
6.3.17 Labelling to be done for each cable & Panels.
6.5 Commissioning
6.6 Ups Start-up: (Refer Functional & Commissioning Report)
6.6.1 Verify that all breakers or switches and fuses in the UPS are kept open.
6.6.2 Verify that the fuses in the battery cabinet are kept open.
6.6.3 Apply mains voltage to the UPS input and record:
R - Y………………. R - N ………………….
R - B………………. Y - N …………………
B - Y………………. B – N …………………
6.6.4 Make sure that the recorded input voltage is within the limit of the UPS.
6.6.5 Measure the overall battery voltage from the battery cabinet to the UPS and make a
record of it.
6.6.6 Close reserve input breaker or switch inside the UPS and wait for a while for the
UPS to display the absence of battery & output.
6.6.7 Close fuses in the battery cabinet.
6.6.8 Close battery fuse holder in the UPS.
6.6.9 Close UPS output breaker or switch and now the UPS displays Normal Operation.
6.6.10 Make sure that the SWMB switch in the UPS is always kept open under Normal
operation.
6.6.11 Initiate the battery test manually via the Mimic panel for checking the healthiness of
the battery.
6.6.12 Check that the UPS is upgraded with the latest version of the firmware.
The switches/fuses/breakers, those are connected internally to the UPS & as well as
external for distribution, are in accordance with the rating of the UPS system.
Procedure:
Check the following
6.12.1 The switches/fuses of the UPS’s are rated as per the specified
6.12.2 Input / output power cable are sized to carry the designed load
6.12.3 The UPS stream breakers installed are set to carry the current that UPS will incur during its
permissible overload condition.
6.12.4 The downstream breaker ratings are selected & installed in accordance to the load
connected
6.12.5 External maintenance bypass switch ratings are equivalent to the UPS ratings.
S. No Check Result
1 All the ratings of the components installed & connected shall be sized
in sequence to its distribution with a permissible tolerance to sustain
the overload
6.12.6 Light Load test
This test is carried out to verify that the UPS switch is correctly connected and all
manual/automatic functions operate properly. It is also to verify the operation of in-built alarm
& communication status availability. The load applied is limited for economic reasons to a
percentage of rated value.
The following points should be checked
a) Output voltage and frequency and the correct operation of LCD panel;
b) Operation of all control switches, meters and other means to put units into operation;
Procedure:
6.12.7 The UPS is loaded lightly up to about 25% load.
6.12.8 Check the operation of all MCB, Isolators & control switches.
6.12.9 Measure the UPS parameters such as Output voltage, frequency & other analog values.
6.12.10 Monitor and record the various display messages, measurement values of UPS
parameters, alarm messages etc for correctness, by simulating fault conditions.
6.12.11 Refer the various alarm messages as per enclosed list.
6.12.12 Check and record the various parameters programmed /set at factory, through control and
display panel
S. No Check Result
1 The proper operation of UPS system with respect to all functions and
parameters are ensured before loading the UPS system to its full
capacity. The output voltage is 400V+ 2% and output frequency is
50 + 0.05% Hz.
6.13 Analog signals
S. No Check Result
1 AC input voltage (each phase of AC Mains input to UPS & Static
Bypass)
2 AC input current (each phase of AC Mains input to UPS & Static
Bypass)
3 AC output voltage (each phase of AC output of UPS inverter/Static
Bypass)
4 AC output current (each phase of AC output of UPS inverter/Static
Bypass)
5 AC input Mains frequency
6 AC UPS inverter output frequency
7 DC voltage (of Battery system)
6.14 Status signals
S. No Check Result
1 Static bypass Switch positions (given by corresponding LED
indication on display panel)
2 Inverter running in synchronized/free running mode (appears as
”Normal operation” for synchronized mode and “disturbances on
3 bypass line/ bypass volt fail or SWBY, FSCR off display” for free
running
mode on LCD panel)
4 Other status signals as per standard design.
6.15 Alarm signals
S. No Check Result
1 Battery Low voltage alarm (appears as “pre-alarm, low voltage on
battery”)
2 Loss of input power (appears as “main line voltage fail or SWIN off”)
3 Loss of output power (appears as “output off, close SWOUT or
SWMB”)
4 Other alarm signals as per standard design.
Restart Test
Automatic or other restart means are to be tested after a complete shutdown of UPS
Procedure:
6.17.23 To simulate a complete shutdown of the UPS, the upstream input breaker to UPS is switched off.
6.17.24 The UPS load is fed by the batteries.
6.17.25 The batteries are disconnected.
6.17.26 The UPS will automatically shutdown.
6.17.27 The input switch of the Rectifier of the UPS and input switch of static bypass is switched On.
S. No Check Result
1 The UPS should automatically restart after a complete shutdown.
6.18 Safety
7.0 ATTACHMENT