Over-consumption and under-consumption in


Sucontracting.
1399 Views
Follow
RSS Feed

Hi,

how can I manage an over-consumption and under-consumption in subcontracting.

What are the related activities that must be done in this cases?

Best regards

 Add a Comment
 Alert moderator

Assigned Tags

 MM (Materials Management)
 SAP ERP

Similar Questions

 Bi Monthly MRP Run

Asad FarooqMay 19, 2020


 Over Consumption in Subcontracting

Former MemberNov 23, 2019

4 Answers
Sort by:
Votes
Newest
Oldest
Best Answer
2
Vote up Vote down

Former Member
Jan 25, 2008 at 01:45 PM

Hi

How can I manage an over-consumption and under-consumption in subcontracting?

for that you have to do subsequent adjustment in T.Code: MIGO....

For eg.) As per your BOM....you have sent 10kg. of Grease to your Sc-Vendor useing
M.Type:541....for assembling of your FG...Now after completion of the Assembling,you
found that only 7kg. of Grease only used by Sc-Vendor for your assembling and 3kg of
Grease is still lying at SC-Vendor's Place.......Now you have to do Subsequent
adjustment in MIGO and take back the balance under consumed Grease from SC-
Vendor...To Do this,

Goto -

> T.Code: MIGO...choose the transaction "Subsequent Adjustment" and ref. doc. as
your SC-PO...

And in Itm View,for the Line item Grease....you maintain the underconsumed qty( ie.
3kg) and Check the Under Consumption check box ....
Now if you execute the subsequent Adjustment....this 3kg of Grease will be regenerated
in 544 O- movement type as under consumed component and it will be Lying at Sc-
Vendor's place...and you have to get back this into Company's Stock separately in
MB1B useing M.Type:542...

Same this you can do for Over Consumption also....for this you should not Check the
Under Consumption Check Box....Here the Over consumed material will be consumed
in 543 O- movement type...and again you have to issue this Over Consumed qty to SC-
Vendor in M.Type:MB1B useing m.Type: 541...

The same subsequent Adjustment you can do for Scrap generation also....

Hope you will understand the subsequent Adjustment process in Sub-Contracting...

Reward if useful

S.Baskaran

 Add a Comment
 Alert moderator
 Share

Vote up 0 Vote down

Former Member
Jan 25, 2008 at 08:07 AM

do the gr of subcontracting and post the document

then again come to migo select the display variant as subsequent settlement form in
place of good reciept and then give the po no. then in front of u r component u can give
thequantity and then there is a check box if u mark it means it is under consumption if u
leave it blank then it means it is over consumption (please press F1 on check box and
get the exact info)

then post the documnet and save


 Add a Comment
 Alert moderator
 Share

Vote up 0 Vote down

SANTOSH POTE
Jan 25, 2008 at 08:12 AM

Thsi can be handled through MIGO--> subquent settlement

or

MB04

 Add a Comment
 Alert moderator
 Share

Vote up 0 Vote down

Former Member
Jan 25, 2008 at 08:23 AM

Hi,
Please refer following thread.

Subsequent Adjustment

Ishu