Professional Documents
Culture Documents
Unit 2 Introduction To Contracts
Unit 2 Introduction To Contracts
UNIT 2:
INTRODUCTION TO
CONTRACTS
1. To Understand Contract & Contract Documents
Contracts:
2. To General Conditions of Contract
3. To Understand the various Special Conditions
of Contract
4. To Understand about Specifications, Bill of
Quantities, Measurement of Works and
Payment to Contractor
5. To Understand Various Advances made to the
Contractor and their Recovery, Also Bonus and
Penalties.
23
Unit 2: Syllabus:
Introduction to Contracts - Articles of Agreement and Conditions of Contract (IIA document) Contents
of a Tender - Terms of Reference - Specifications - Bill of Quantities - Billing, Measurement of work
and Payments - Advances and recovery - Bonus and Penalties, etc.
2. 1 Contract:
2.1.1 Definition: A Contract is a written or spoken agreement, especially one concerning
employment, sales, tenancy, or service provision that is intended to be enforceable by law.
A Written Contract is a document that records an agreement between various parties, and is framed
and validated by the Indian Contract Act, 1872. The Contract Act is one of the most central laws that
regulates and oversees all the businesses wherever a deal or an agreement is reached. A written
Contract is enforceable as per the Contract Act and any breach or failure to abide by the agreement
contained within is punishable by the Law.
2.1.2 Contract Document: After the Tendering process the Award is declared in favor of some
Contractor who is first given a Letter of Intent, and then a Work Order often called a Purchase
Order in Corporate circles and then invited to sign a formal legal Contract with the Owner.
The documents that will become a part of the Legal Contract are required to be clearly specified. The
Contract will include the Articles of Agreement, the Letter of Intent and Work Order, the Terms and
Conditions of the Contract, the B.O.Q with the Schedule of Item Specifications and Quantities, the
Mode of Measurement, and all other contents of the Tender, except the preliminary Tender purpose
drawings. The Good-for-Construction (GFC) Working Drawings issued by the Architect from time to
time may be declared as the Contract Drawings unless otherwise stipulated by mutual consent.
2.1.3 Contract Drawings: The preliminary "Tender Purpose" drawings included with the Tenders
issued to Contractors for quotation are generally NOT considered in the Contract as Contract
Drawings because they are only intended to give a the Contractors an overview of the work
before Tendering their Quotation for the work.
The Good-for-Construction (GFC) Working Drawings issued by the Architect from time to time signed
by the Architect are declared as the Contract Drawings, unless otherwise stipulated for any reason.
Working Drawings must be scaled and issued with all dimensions and details as may be required by
the Contractor for clarity of construction. Any work which is not according to the Contract Drawings
is liable to be rejected by the Architect. Adequate copies of Working Drawings must be issued by the
Architect to the Contractor
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
24
2. 3 Conditions of Contract:
PREAMBLE: When a Contractor is assigned a Construction Contract, the Owner and the Architect
may set specific Terms and Conditions which the Contractor will have to follow during his contract
period.
The purpose of these Terms and Conditions (or 'Terms of Reference") is to ensure that the
Contractor follows specific prescribed procedures of the Tender system and delivers the completed
construction within the Time, Cost and Quality that has been prescribed by the Owner & Architect.
The Conditions of Contract are generally of Two Types: Special and General:
a. Specific or Special Conditions - which are Specific to the project in hand with respect to Type,
scale, location, complexity and specific requirements of the Owner, if any.
b. General Conditions - are typically those that would apply to Any construction project - since
they are mostly in respect of good construction practices and prescribed procedures of
Tendering. These can be used in any Tender of any construction project as these are Standard
and Typical to construction work in General.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
25
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
26
• This is an initial money deposit enclosed with the tender and could be in the form of a Cheque
of a Nationalised Bank, Multi-National or a Scheduled Co-Op Bank , Pay Order, D.D. payable at
the place of the Owner, or even a Bank Guarantee or even Cash.
• This is generally fixed at 1% of the estimated cost of works.
• The E.M.D Cheque / Draft is to be submitted Outside the sealed envelope containing the Tender
document - and Not within, - since the payment is required to be checked and verified before
accepting the Tender submission.
• The amount remains with the Owner till the Contractor is selected and may be extended till the
job is awarded.
• E.M.D of the selected contractor is converted to a Security Deposit. E.M.D of Contractors whose
offers are rejected is given back.
• E.M.D does not bear interest and no one can claim interest on same.
• E.M.D is forfeited by
A Contractor whose Tender is selected but is unwilling or refuses to undertake the work
A Contractor whose Tender is selected but Delays payment of Security Deposit
A Contractor whose Tender is selected but Intentionally delays the commencement of work
• In any of the above events, the Owner / Architect are free to select any other Contractor from
the pre-qualified list, or the Tender can be re-called and the entire process repeated.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
27
absolutely discretionary for the Owner / Architect to accept or reject such an offer, and,
the Contractors cannot 'demand' such a concession
• The Purpose of S.D.A is as follows
Contractor fulfils all terms and conditions of Contract
Carries out work to entire Satisfaction
Maintains expected progress of work
• If the Contractor fails to comply with all conditions then S.D.A is forfeited.
• Contractor cannot demand any interest on the S.D.A. This is returned to the Contractor after
Deflects Liability Period if the Contractor attends and cures Defects brought to his notice and
within the stipulated time allotted for attending the repairs. If Provision for Deduction of
Retention Money is made in the Tender the Security Deposit is returned along with the Final Bill.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
28
• As a clerk of works, or site inspector, he would oversee the quality and safety of work on
a construction site, making sure that building plans and specifications are being followed
correctly. He should have a good ability to pay attention to detail. He should have good
problem solving skills. He should have good knowledge of the construction industry and
of Building Regulations. He should have good written and oral communication skills. He
should also have an ability to meet targets.
His duties would include.
Performing regular inspections of the work on site and comparing completed work
with drawings and specifications
Measuring and sampling building materials to check their quality
Recording results either on paper or a hand-held Personal Digital Assistant.
Identifying defects and suggesting ways to correct them
Liasoning with other construction staff, such as contractors, engineers and surveyors
Monitoring and reporting progress to Construction Managers, Architects and Clients
Supervising the workforce on the building site during a project.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
29
Previous, Present and Balance Quantity of each Item of work in the B.o.Q and also the Paid, Due
and Balance amounts against each Item. This system helps keep track of the Work done and
Work remaining throughout the course of the construction.
• Running Account (R.A) Bills can be raised by the Contractor by two principal parameters which
are set by the Architect in the special Conditions of Contract: Time and Value. In the initial
negotiations of the Contract, a mutually agreed period (like once every month or twice every
month), and / or a mutually agreed amount (like minimum 5 Lakhs or minimum 10 Lakhs) is fixed
as a criteria for raising Interim RA Bills. Contractors, therefore, cannot demand payments
anytime or for any amount unless the prescribed criteria are met.
• Normally, the number of Bills per month and minimum amount for Billing is fixed by dividing the
total value of the project over the total duration of work.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
30
• Recovery: Such a payment is called 'Ad-Hoc' payment and is generally deducted immediately
from the amount of the due Bill and only the 'balance' amount is paid to the Contractor. It is the
Architects discretion to recommend or refuse any such Advances, and thus, also the
responsibility to Recover such advanced payments in his scrutiny and certification of the Running
Account Bills.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
31
• For the contractor, it is likely to be more economical and efficient for him to carry out remedial
works itself than to pay the costs of another contractor hired by the employer. From the
employer's perspective, he will not need to hire an alternative contractor to carry out the work,
or to carry out the work itself and reclaim the cost. The employer will also not run the risk that
any warranties provided by the original contract may be affected by a third party carrying out
works on the site.
• If there is a contractual right for the contractor to rectify defects, and the employer either does
not notify the contractor that rectification is needed or refuses access to the site, then the
employer may be in breach of contract. Case law illustrates, however, that the contractor will
not normally be 'let off the hook' if this happens. The employer will still have a claim for the cost
of rectifying the defects, but the claim is likely to be limited to the amount it would have cost the
original contractor to carry out the works. He will not be able to claim for remedial works or
working methods found not to be strictly necessary.
• Employers should therefore give careful consideration to the provisions in the contract before
hiring a new contractor to carry out remedial works. This is especially important if the contract
stipulates that the employer must notify the original contractor that remedial works are needed
before it can make a claim for recovery of any costs of rectification.
• We also need to know two other terms : Latent Defects and Patent Defects: Defects in a
building are those aspects of any work that are not in accordance with the contract, with respect
to either the specifications or the drawings or general workmanship. These Defects are further
classified as Patent or Latent
Patent Defects are those that can be detected by reasonable inspection, e.g. the line
and level of flooring or walls or plumbing works.
The client during the Defects Liability Period may bring to the notice of the Contract Administrator
any defects that arise who may then decide whether they are a breach of contract or just
maintenance issues. In case they are defects he may issue a notice to the contractor who then has to
address these issues within a reasonable time and make good the defects. Since it is not the client’s
responsibility to detect defects (he not being a technical person) every time a defect is detected by
him, he should point out that this is not a comprehensive list of defects.
Latent Defects are those which cannot be discovered by reasonable inspection. for
example bad concrete used in foundation which may not become apparent until several
years after completion when settlement causes cracking in the building.
It is the intrinsic nature of construction projects that many a times, faults or Defects in
Workmanship or Materials may not become apparent or readily detectable until many years after
completion of project and long after the end of the Defects Liability Period. Such Defects are called
Latent Defects.
Examples of Latent Defects are
1. Wrongly placed reinforcement allowing movement damage to the structure.
2. Under strength concrete used leading to cracks in the structure.
3. Defective Basement Tanking allowing water penetration.
4. Bad Water used in concreting leading to bad concrete and finally failure of Structure.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
32
As an incentive to provoke the Contractor into providing his Best services and using the best quality
of recommended materials, Architects often encourage the Owners to declare a Bonus for good
work. The 'Bonus' can be a Lump-sum amount or a small percentage of the project cost payable over
and above the Contract amount. It is mandatory for the Architect to get the consent of the Owner, in
writing, prior to inclusion of a Bonus Clause in the Tender.
In respect of a 'Penalty Clause' however, the Architect may specify the circumstances for invoking
the provisions of the clause to penalize the Contractor. These reasons may primarily be delay
beyond the date of completion, dis-obedience of Architects instructions, or consistent sub-standard
workmanship of construction.
It is NOT mandatory to include either the Bonus Clause or the Penalty Clause in a construction
Tender. As a gesture of transparency and fairness, if a Penalty Clause is included in the Tender as a
punishment, there should also be a Bonus Clause to appreciate and encourage good and timely work
by the Contractor.
2.4.13Escalation Clause:
An Escalation Clause is provision in a contract for increasing the quoted Item Rates of Contractors in
tune with the market prices or by an agreed percentage or a parameter such as the Consumer Price
Index (CPI). Inclusion of an Escalation Clause in a private sector Tender must be done with a clear
and absolute consent of the Owner, since it is NOT a mandatory provision. In Govt. or Public
projects, however, this provision is always made to compensate the annual rise in costs to
Contractors in long duration projects.
Once a Tender is accepted and a Contract is signed, the Contractors are bound to carry out the
construction at the Item Rates quoted and accepted. The quoted rates must remain valid up-to the
completion of the project if the time period is less than 12 months.
If the project time span is more than 12 months, however, an 'ESCALATION' Clause is often included
in the Tender to provide the Contractor relief from annual inflation. If, however, the provision of the
Escalation Clause is found to be misused by deliberately delaying the work beyond 12 months,
'Liquidated Damages' are levied as a Penalty.
In the private sector, the percentage of annual 'rise' in rates is often specified (say, 3% to 5% - for
example) considering market trends. In most Government Tenders, however, the Escalation Clause is
based on a formula developed by the CPWD and State PWD which derives the amount of rise in
direct proportion to the Consumer Price Index officially published by the Government every year.
2.4.14Liquidated Damages:
In the event of a Delay in the completion of a construction of a project - which may be due to any
reason for which the Contractor Can be indisputably held responsible - the Architect / Owner may
charge "Liquidated Damages" or a Penalty per day of delay beyond the stipulated date of
completion. Liquidated Damages are so called because they constitute an approximate gross value
of the loss which the Owner is likely to suffer on account of the delay distributed over the period of
the delay as compensation per day.
Where TIME is the essence of a Contract, the Liquidated Damages are pre-determined and included
as a condition in the Contract. Liquidated Damages age generally levied after the Contractor has
been given adequate Notice that the delay in the construction will NOT be tolerated beyond the final
/ extended date of Completion.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
33
When such damages are levied, the same may be deducted from the amount of any running bill
payable to the Contractor, OR, recovered from the Security Deposit of the Contractor held by the
Owner. It shall, however, be entirely discretionary for the Architect to waive the levy of Liquidated
Damages if it is established that it was impossible for the Contractor to avoid the delay. The
Architect can also set a Limit for the delay in completion
An Exception to the levy of Liquidated Damages is the Force Majeure clause where the work is
delayed due to natural calamities like floods, earthquakes or inclement weather, OR due to official
stoppage of work by any authority or Court-of Law for any reason for which the Contractor CANNOT
be held responsible.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
34
relaxation in the rates of these materials should benefit the owner or contractor. This will help
contractors to quote with the same parity
X. Conditions for Storage of Materials. A clause to ask the contractor to provide erect and
maintain proper sheds for the storage of materials at site.
XI. Testing of Materials and of Executed Work. This clause deals with testing of Materials and
executed work. All materials and workmanship shall be subject to testing and examination by
the Architect. The Architect shall have the right to reject defective material and ask for defective
workmanship to be corrected. The contractor shall promptly furnish without additional charges
all reasonable facilities, labour and material necessary for safe and convenient inspection and
testing that may be required by the Architect.
XII. Subletting of Contract. The clause deals with the fact that the contractor shall not sublet any
work or part of the work without written consent of the Architect. If so allowed the Sub-
Contractor shall carry out the sub contract works in every aspect to the entire and reasonable
satisfaction of the Architect.
XIII. Insurance and Risk Coverage for Labourers and Materials. E.S.I., Provident Fund etc. The
contractor shall be liable for and shall indemnify the owner against any liability, loss, claim, or
proceedings whatsoever arising under any statue or common law in respect to Personal Injury or
even Death. The Insurance shall be paid by the Contractor and such policies and receipts shall be
in the safe custody of the Architect.
XIV. Arbitration. A clause to cover the fact that In case of disputes between contractor and Client
sole arbitrator is the Architect. However if either party disagrees with the decision given they
would be free to seek Redressal in Courts.
XV. Termination Clause and Conditions. In case of poor quality being delivered or inordinate Delays
occurring (not in keeping with the schedule submitted) the contract may be terminated under
certain conditions.
There are certain issues that are very difficult to decide whether these are to be bracketed in Unit1:
Tenders, Unit 2: Contracts or Unit 4: Site Management and I will certainly briefly list and explain
them here but if necessary detail them out in Unit 4:
In case of B-1 ( Percentage Rate Tender ) The Bill of Quantities may contain the Specifications of the
DSR - giving the specific Item Code number - which refers to the detailed PWD specification in the
Red Book of the PWD or the current DSR of the District.
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
35
In case of C (Lump-Sum Tender) the specifications shall be in absolute detail for the Contractor to
include the cost in his Lump-Sum price quotation.
As a standard instruction to the Contractor, measurement of the work done Every Day has to be
recorded in the Measurement Book (MB) on the project site. This activity has to be carried out Daily
by the Contractor or his Site Supervisor Jointly with the Clerk of Works/Architects or Owners
representative/Construction Manager / PMC.
The Measurement Book has to record the dimensions of each item of work done on the site every
day, and the quantity jointly measured and accepted for record. The Architect has to cross-check at
random; some of the items in the measurement book, and sign the MB during his periodic visits to
the construction site. If any discrepancy is found in the recorded and actual measurements in the
cross check, ALL measurements are re-checked. A 'Mode of Measurements' is generally included in
the Tender to guide the way in which certain Items of Work are to be measured.
• The Contractor has to raise periodic Bills of Work for payment for the Architect to scrutiny
and verify and recommend payment to the Owner
• The Owner will pay the Contractor Only after the Bill of Work has been checked, verified on
site, and Certified for payment by the Architect.
Payments to the Contractor are made directly by the Owner by money transfer or cheques issued
after Certification of the R.A. Bills by the Architect. The Architect is expected to keep a record of
payments made to the Contractor, to monitor the final cost of the project
If the Owner delays the payment to the Contractor After due certification by the Architect, the
Contractor is entitled to compensation of Interest on the due amount over the period of the delay (if
this provision has to be made and included in the Tender Terms & Conditions)
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho
36
2. 6 Theory Questions:
1. Define a Construction Contract. List the Salient Features of a Construction Contract.
2. Explain in short what do we mean by General Conditions of Contract and Special
Conditions of Contract
3. List out the Special Conditions of a Construction Contract.
4. Write Short Notes on the Following
1. Earnest Money Deposit
2. Security Deposit Amount
3. Retention Amount
4. Clerk of Works
5. Mobilisation Funds and recovery
6. Material Advances and recovery
7. Ad-Hoc Payment and recovery
8. Interim or R.A. Bills
9. Final Bill
10. Defects Liability Period.
11. Virtual Completion Certificate
12. Latent and Patent Defects
13. Bonus Clause and Penalty Clause
14. Liquidated Damages
15. Escalation Clause
Unit 2 Introduction to Contracts Compiled by Ar. Rajiv Raje @ Ar. Arthur Cutinho