You are on page 1of 3

PRE-COMMISSIONING CHECK SHEET E-201B1

ELECTRICAL
Sheet 1 of 2
ELECTRICAL MOTORS (HV&LV) REV 5
(CAGE-INDUTION TYPE- INCLUDING RCU)

PROJECT
PROJECT WBS No.
DESCRIPTION

SUB-SYSTEM
SUB-SYSTEM No.
DESCRIPTION

TAG
TAG No.
DESCRIPTION

A. MOTOR DATA
Manufacturer: ……………………… Duty: ……………….. Mounting: ………………..
Frame: ……………………………… IP: …………. Serial No:
Motor Type: ………………………... Rated output: ………………………..KW Rated speed: …………….. RPM
Rated voltage:……………………..V Rated current:……………………… A Frequency: ........................ HZ
PF: ………. Connection: ……………………… No. of phases: ……………
Insulation class: …….. Temperature class: ……………….. Hazardous area class: …….
Motor Certification: ……………. Certifying authority: ……………… Certificate No: ……………
DE Bearing: …………….. NDE Bearing: …………………….. Lubrication: ……………….
Ambient temp: ……………………. Switch Board: …………………….. Feeder No: …………………….
B. INSPECTION / TEST:
NOTE: Tests marked (A) may be waived for motors below 30 kW rating.
Tests marked (B) may be waived for motors below 100 kW rating driving centrifugal pumps.
* Delete as necessary.

01 Ensure Construction check sheet completed for the motor Sheet No.: E-201A

02
Earthing
- Check the condition of earthing connections at: motor .................................
control unit .................................
- Continuity measurement earth
Return path on 20% of motors, test #8 Appendix 13 of DEP 63.10.08.11- GEN ............................. 
03
Winding Resistance Measurement:
R-Phase Y-Phase B-Phase R-Y Y-B B-R
Ω Ω Ω Ω Ω Ω

04 Insulation resistance tests:


- Insulation resistance of motor (phases to earth)
R-YBE Y-RBE B-RYE
MΩ MΩ MΩ

- Polarisation Index measurement:


After 1 min. .................................... M After 10 min. ................................... M(A)
Polarizing index. .......................................... (A)
After connecting cable:
- Check cable connection ..............................................
- Insulation resistance motor + cable (phases to earth) ..................................... M
- Insulation resistance control unit + cable to earth ..................................... M
PRE-COMMISSIONING CHECK SHEET E-201B1
ELECTRICAL
Sheet 2 of 2
ELECTRICAL MOTORS (HV&LV) REV 5
(CAGE-INDUTION TYPE- INCLUDING RCU)

PROJECT
PROJECT WBS No.
DESCRIPTION

SUB-SYSTEM
SUB-SYSTEM No.
DESCRIPTION

TAG
TAG No.
DESCRIPTION

05 Special items(if applicable):


- Check anti-condensation of heater installation .................................
- Test resistance of anti-condensation heater 

- Test insulation resistance of heater at 500V ......................... M


- Test insulation resistance of temperature detectors ......................... M
- Inspect system aux. motors .................................
- Test bearing insulation (if fitted) ......................... M
- Check magnetic centre

REMARKS/ OBSERVATIONS:

COMPLETED BY CONTRACTOR APPROVED BY CONTRACTOR ACCEPTED BY PDO

NAME NAME NAME

COMPANY COMPANY REF. IND.


PRE-COMMISSIONING CHECK SHEET E-201B1
ELECTRICAL
Sheet 3 of 2
ELECTRICAL MOTORS (HV&LV) REV 5
(CAGE-INDUTION TYPE- INCLUDING RCU)

PROJECT
PROJECT WBS No.
DESCRIPTION

SUB-SYSTEM
SUB-SYSTEM No.
DESCRIPTION

TAG
TAG No.
DESCRIPTION

SIGN& DATE SIGN& DATE SIGN& DATE