and Quantity Takeoff Design In The Construction Industry Construction Design Spectrum It is important to understand the construction design process and how it relates to cost management and estimating project costs.
Following design stages are explained in the next screens:
• Order of Magnitude (OOM)
• Schematic Design (SD) • Design Development (DD) • Construction Design (CD) Overview of Design Stages Design Stages – Order of Magnitude Design Stages – Schematic Design Design Stages – Design Development Design Stages – Construction Design 601 Lexington Avenue – Case Study
The most interesting fact about this
building is that it contained a major design flaw. The major columns were placed in the center of the building, not on the edges, to accommodate the location of a church. So, large structural steel beams had to be created much later, spanning eight floors within the building, in order to support the structure. 601 Lexington Avenue – Cost vs. Phase The entire building had to be re-welded without any knowledge of any of its occupants or for the greater population of Manhattan. The welds were completed afterhours and came to a total cost of $8 million in 1978, which adjusts for roughly $30 million in 2016. Tips in Design Understanding Types of Cost Estimates Types of Cost Estimates All estimates are approximations based upon judgment and experience where the estimator first builds the project on paper, and then assesses quantities not only of the contracted materials, but also of the temporary materials, e.g. formwork, temporary plant, etc. considering various alternative methods of construction.
Types of Cost Estimates
Conceptual and Preliminary Estimates – Cost Indices Cost indices is a price of a total constant package of resources, construction resources that serves as input to a typical construction project. The index is computed by dividing this cost, the cost of the index by the cost of the resources in a base reference period. This will allow us to show changes in cost over time. Cost Indices Computation and Limitations
Differing resource proportions,
Productivity, changes in technology, differing projects competitiveness of contractors, geographic and demographic factors, etc. Conceptual and Preliminary Estimates – Cost-Capacity Factor Cost-Capacity Factor – Examples Conceptual and Preliminary Estimates – Component Ratios Conceptual and Preliminary Estimates – Parameter Costs Detailed Estimate (Steps) Step 1: Break Project into Cost Centers: • Earthwork, Concrete, Structural Steel, Brick & Masonry, Electrical, Painting, Insulation, Construction Equipment, etc.
Step 2: Estimate Quantities:
• Estimate the following per cost center: • Physical items: Perform quantity takeoff • Nonphysical items: Builder’s risk insurance; amount of the required bonds, etc.
Step 3: Price out Quantities:
• Price out quantities from step 2 using historical data, supplier catalogs, and other sources
Step 4: Calculate Total Price:
• Calculate for each cost center by multiplying the required quantities by the unit price.
Types of estimates: engineer’s estimate, contractor’s estimate
Finishes Wall Finishes Common Types of Wall Finishes Measurement Recap Cut and Fill Cut and Fill Takeoff Cut and Fill Software Deep Foundations Constructions with Deep Foundations
New York London
Sydney Abu Dhabi
Construction Piles Construction Caissons Deep Foundations Concrete Foundations Concrete Foundation Concrete Mixing Concrete Slump Concrete Curing Concrete Break Tests Concrete Takeoff Concrete Reinforcing Standard Rebar Sizes Concrete Formwork