SECTION 15122
PART 1 - GENERAL
1.1 Related Documents
1.2 Description Of Work
1.3 Quality Assurance
1.4 Submittals
PART 2 - PRODUCTS
2.1 Thermometers And Pressure Gauges
2.2 Pressure Range Chart
PART 3 - EXECUTION
3.1 Installation
SECTION 15122
PART 1 - GENERAL
A. Drawings and general provisions of Contract, including Special Conditions and Division-1 Specification
Sections, apply to work of this Section.
B. The requirements specified in this section apply to all related sections in this Division. The requirements
of all related sections, elsewhere in this division also apply to this section unless specified to the contrary.
A. The work includes the providing of all labour, supervision, materials, equipment, accessories, services
and tests necessary to complete and make ready for operation by Owner, all thermometers and gauges, in
accordance with Drawings and Specifications.
A. Manufacturers: Firms regularly engaged in manufacture of thermometers and gauges of the types and
materials, sizes and capacities required, whose products have been in satisfactory use in similar service
for not less than 5 years. Provide thermometers and gauges produced by a manufacturer listed as an
Acceptable Manufacturer in this section.
B. Standards Compliance: Make the complete installation in accordance with all state and local municipal
codes, all applicable codes and authorities having jurisdiction, and the applicable requirements and
standards outlined in section 15010
C. Warranty
- Provide two years manufacturer’s warranty
- Warranty : include the whole unit
1.4 SUBMITTALS
A. Shop drawings shall indicate sizes, types, and material with detail and attachment installations.
B. Samples, when requested.
C. Submit a schedule of all thermometers and gauges for approval. The submission should include the
type, location, ranges, scale readings, construction data and stem details of the devices.
D. Prior approval requirements:
- Manufacture name
- Figure number
- Engineering data
- Samples
PART 2 - PRODUCTS
A. Furnish and install pipe thermometers with separable sockets in the following locations. This applies to
all systems described in the specification.
- In and Out of each refrigerant condenser and evaporator.
- Thermometers as required under "Refrigeration Equipment."
- In and out of each converter and water to water exchangers (on water side).
- In and out of each chilled and hot water coil. A vertical bank of coil sections may have one
thermometer on inlet header and one on outlet header. For those systems with two vertical banks of
coils, then each bank shall have a thermometer on inlet and outlet headers.
- in condensate receiving or dilution tanks on labs.
- In and out of each domestic hot water generator in the primary & secondary circuit.
- In and out of each hot oil thermal generator.
- Fresh air intake ducts and mixed air plenums.
- Supply fan discharge air.
- Suction side of recirculation fans.
- at the supply and return of the hot and chilled pipe entrance to the building from thump
- as indicated on details and drawings.
B. Furnish and install pressure gauges in the following locations on water lines:
- At inlet and outlet of each circulating pump and upstream of inlet strainer. One gauge may be used
in lieu of two on suction side of pump with suitable valves and piping.
- at inlet and outlet of refrigerant water chiller.
- at inlet and outlet of refrigerant condenser.
- at inlet and outlet of each converter and water to water exchanger (on water side)
- at inlet and outlet of each coil bank. For those systems with two banks of three coils each, each
bank shall have separate gauges. Locate gauges immediately downstream of shut-off valve on
supply line and immediately upstream of shut-off valve on return line.
G. In addition to the above their must be provision for pressure and temperature test points in all system.
0 207
69 414
138 621
207 828
276 1035
345 1242
414 1449
PART 3 - EXECUTION
3.1 INSTALLATION
A. Install all thermometers and pressure gauges before piping is tested to facilitate field test procedures.
B. Adjust gauges for proper viewing angle.