You are on page 1of 7

Here Comes the Judge—Duties and Responsibilities

of Design Professionals When Deciding Disputes


Steven G. M. Stein1 and Ryan Hiss2

Abstract: Frequently during the progression of a construction project, the design professional is forced into the role of a judge of project
disputes between the owner and contractor. These disputes generally involve substantial claims for extra compensation or extra time and
have significant impact on the owner and contractor’s financial position on the project. The architect or engineer will be pressured by the
owner, who controls whether the design professional gets paid. The contractor, however, may threaten to pursue legal claims against
design professionals if they make the contractor’s job more expensive or fail to give it the appropriate time extension. In many cases,
design professionals must admit or deny whether their services were defective in some nature. In addition to these pressures, the design
professional is not necessarily trained or comfortable with acting as a judge and interpreting the meaning of contract terms. Generally,
when an architect or engineer performs this judicial function, they are immune from any liability for the results of decisions. However, the
design professional must make the decision in good faith and with impartiality. In addition, design professionals must only decide those
matters that their contract obligates design professionals to decide. This paper will address the nature of the designer’s role as judge and
the limits of the designer’s immunity with respect to the designer’s contract obligations and good faith and impartiality requirements.
DOI: 10.1061/共ASCE兲1052-3928共2003兲129:3共177兲
CE Database subject headings: Architects/engineers; Legal factors; Contract administration; Construction methods; Dispute
resolution.

Understanding Your Judicial Role to the contractor and subcontractors. However, when design pro-
fessionals step into the role of judge or arbiter of disputes, the
Generally, the design professional performs three different duties common law generally protects them from liability for the deci-
on a construction project. First, the design professional acts as an sions rendered. 共See Wilder v. Crook, 34 So.2d 832 共Ala. 1948兲,
independent contractor. In this role, the design professional pre- engineer not liable in damages for failure to exercise care or skill
pares the design drawings and specifications for the project. Sec-
in the performance of ‘‘judicial’’ functions; City of Durham v.
ond, the design professional acts as the owner’s representative for
Reidsville Engineering Co., Inc., 255 N.C. 98, 102-103, 120
the project. In this role, the design professional inspects work
S.E.2d 564, 567 共N.C. 1961兲, Engineers are immune from liability
performed, certifies payment, and otherwise supervises the
for interpretations of the meaning and intent of the plans and
project. 关See John W. Johnson, Inc. v. Basic Construction Co.,
Inc., 292 F.Supp. 300, 302, 共D.D.C. 1968兲, When an architect specifications, the authorization that additional work not ex-
prepares plans, advises the owner and supervises performance, pressly authorized in the contract be performed, and any decisions
she is acting as owner’s agent rather than as a judge.兴 Third, the on matters in dispute; Lundgren v. Freeman, 307 F.2d 104, 117
design professional acts as a ‘‘judge’’ of disputes. In this ‘‘quasi- 共9th Cir. 1962兲, architects protected from liability when acting as
judicial’’ role, as it is usually referred, the design professional judges over disputes; contra, Sutcliffe v. Thackrah, 1974 A.C.
decides disputes between the owner and contractor. The first two 727, In England, the immunity privilege may not apply.兲 This is
roles are delegable; the last role is not 共Id.兲. known as quasi-judicial immunity. This means that design profes-
When acting as an independent contractor and an owner’s rep- sionals are generally unable to be sued by parties that are disap-
resentative, design professionals are legally liable for their acts pointed with their decisions or for errors in their decisions. 共See
共Douglas 1993兲. If design professionals fail to act as reasonable Lundgren, 307 F.2d at 118, architect not liable for errors in deci-
design professionals should when carrying out these obligations, sion.兲 If disgruntled parties could sue judges or arbiters rendering
they may be held liable to the owner and in some circumstances their decisions, there would be no end to litigation. In addition,
judges or arbiters would be governed more by the fear of a re-
1
Partner, Stein, Ray, Harris, 222 West Adams St., Suite 1800, sulting lawsuit than by their own unfettered judgment as to the
Chicago, IL 60606. merits of the matter they must decide. 共See id. at 117, architect
2
Associate, Stein, Ray, Harris, 222 West Adams St., Suite 1800, not liable for errors in decision.兲 That is one of the main reasons
Chicago, IL 60606. why courts have recognized immunity for design professionals’
Note. Discussion open until December 1, 2003. Separate discussions decisions of disputes for well over 50 years 共Douglas 1993兲.
must be submitted for individual papers. To extend the closing date by The immunity does not apply to every decision. In order for
one month, a written request must be filed with the ASCE Managing
immunity to apply, there must be an actual dispute, unless the
Editor. The manuscript for this paper was submitted for review and pos-
sible publication on October 25, 2002; approved on March 31, 2003. This contract provides otherwise, and design professionals must be act-
paper is part of the Journal of Professional Issues in Engineering Edu- ing within the scope of their contract duty to render decisions on
cation and Practice, Vol. 129, No. 3, July 1, 2003. ©ASCE, ISSN 1052- that dispute. In addition, the decision must be made in good faith
3928/2003/3-177–183/$18.00. and be impartial. A closer look at each of these prerequisites will

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003 / 177
assist design professionals in understanding what they can do to AIA Standard Terms
maintain immunity. AIA A201, which is part of the Contract Documents referred to in
B141, provides two instances in which the design professional is
Contractual Obligation to Act as Judge to act in a quasi-judicial capacity. The first instance of quasi-
judicial activity is when the design professional decides claims or
The duty of the design professional to determine disputes is a disputes presented for a decision under the dispute process in the
creature of contract. 共See E.C. Ernst, Inc. v. Manhatten Const. Co. contract documents 共AIA A201, ¶ 4.4.1兲 共AIA 1997兲.
of Texas, 551 F.2d 1026, 1033兲 共5th Cir. 1977兲 Therefore, the 4.4.1 Claims, including those alleging an error or omission
terms of the contract determine the scope of the design profes- by the Architect but excluding those arising under Para-
sional’s duty. 共See Lundgren, 307 F.2d at 117, architect acts as graphs 10.3 through 10.5, shall be referred to the Architect
judge within immunity rule when it acts within the guidelines of for decision . . .
this specific contract duty.兲 If the contract does not obligate the
The decision by the design professional is final and binding 共AIA
design professional to decide disputes, then the architect or engi-
A201, ¶ 4.4.5兲 共AIA 1997兲.
neer is under no obligation to do so, unless all parties otherwise
The dispute must be submitted to the design professional in
agree. Sometimes, especially where the American Institute of Ar-
writing and must meet the formal claims requirements 共AIA
chitects 共AIA兲 201 General Conditions are used 共AIA 1997兲, the
A201, ¶ 4.3.1兲 共AIA 1997兲. If the claim does not comply with the
owner and contractor may agree to submit disputes to the design
requirements under AIA 201 ¶ 4.4, design professionals must not
professional even when the design professional has not agreed to
such role. In such instances, if a dispute in accordance with the decide the claim or they will be acting outside of the scope of
contract is submitted to the design professional, the decision their authority. Design professionals must make sure that they
should be protected by immunity. 共See Mayfair Const. Co. v. comply with the timing requirements and other formalities of the
Waveland Associates Phase Limited Partnership, 619 N.E.2d dispute procedure, including, issuing a written decision 共AIA
144兲 共Ill. 1st Dist. 1993兲 A201, ¶ 4.4.5兲 共AIA 1997兲. Finally, the dispute must be between
Generally, when the design professional is required to decide the owner and contractor 共AIA A201, ¶ 4.4.1兲 共AIA 1997兲. If both
disputes the contract states that the decision must be rendered in of these parties are not involved on opposing sides of the dispute,
good faith and be impartial. In such circumstances, or when the the decision is outside of the design professional’s contractual
contract is silent on the requirements for performing this function, obligations. Although neither AIA 201 article 4.3 or 4.4 specifi-
immunity will apply if the decision is rendered in good faith and cally provides for immunity, immunity would likely be provided
is impartial. However, design professionals can contract away in all jurisdictions under the common law.
their immunity by agreeing to a more stringent standard of per- The second instance in which the design professional acts in a
formance. For example, if design professionals agree in the con- quasi-judicial capacity is when, even without a formal dispute, the
tract that they are liable if the decision is unreasonable or negli- owner or contractor submits a written request for an interpretation
gently made, they will be held to that standard. If the decision is or determination of performance under, and requirements of, the
determined to be unreasonable under the circumstances, the de- contract documents 共AIA A201, ¶ 4.2.11兲 共AIA 1997兲.
sign professional may be held liable for that decision. The negli- 4.2.11 The design professional will ‘‘interpret and decide
gence standard also imposes liability exposure. There is no reason matters concerning performance under, and requirements
for design professionals to agree to such standards and they of, the Contract Documents on written request of either the
should refuse to act as the arbiter under such circumstances. Owner or Contractor. The Architect’s response to such re-
There is at least one circumstance where even if the contract quests will be made in writing within any time limits
requires design professionals to act as judges of disputes, they agreed upon or otherwise with reasonable promptness.’’
may be released from that duty. 共M.J. Daly & Sons, Inc. v. City of The AIA specifically provides for immunity when rendering
West Haven, 2001 WL 1132403兲 共Conn. 2001兲 If a design profes- these decisions 共AIA A201, ¶ 4.2.12兲 共AIA 1997兲. Notice that in
sional takes over a project for another design professional, the order for this interpretation duty to arise and for immunity to be
courts will likely require that the contractor approve that person provided, the interpretation request must be in writing 共AIA
as the judge of disputes before acting in that capacity. This re- A201, ¶ 4.2.11兲 共AIA 1997兲. It is possible that an oral request will
quirement is to dissuade owners from firing design professionals not be considered within the design professional’s scope of duties,
who may be ‘‘friendly’’ to contractors and replacing them with and any decision on an oral request may be denied immunity.
design professionals friendly to the owner, when the owner is Therefore, when such an oral request is made, ask for it in writing
aware of upcoming disputes that it wants decided in its favor. to insure immunity protection.
However, under AIA 201, ¶ 4.1.3, when a design professional is When interpreting contract documents, AIA B141 also re-
terminated from the project, the ‘‘Owner shall employ a new Ar- quires the design professional to endeavor to secure faithful
chitect against whom the Contractor has no reasonable objection performance by both owner and contractor in addition to
and whose status under the Contract Documents shall be that of making the interpretation in good faith and with impartiality
the former Architect’’ 共AIA 1997兲. Therefore, if AIA 201 is used, 共AIA B141, ¶ 2.6.1.8兲 共AIA 1997兲.
and the contractor does not object to the replacement design pro- 2.6.1.8 Interpretations and decisions of the Architect shall
fessional, the new design professional would have the same be consistent with the intent of and reasonably inferable
quasi-judicial responsibilities as the original design professional. from the Contract Documents and shall be in writing or in
the form of drawings. When making such interpretations
Standard Contract Terms and initial decisions, the Architect shall endeavor to secure
The terms of AIA B141 共1997兲, A201 共1997兲, and the Engineers faithful performance by both Owner and Contractor, shall
Joint Contract Document Committee 共EJCDC兲 Owner-Engineer not show partiality to either, and shall not be liable for the
and General Condition agreements are illustrative of contract ob- results of interpretations or decisions so rendered in good
ligations to decide disputes. faith.

178 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003
In order to maintain immunity, be sure to make efforts to se- professional must render a written decision within 30 days after
cure faithful performance and carefully document such efforts in receipt of the last submittal of the claimant or opposing party. If
letters or memos. any of these procedural requirements are not met, a court may
As one would presume, the AIA does not place any additional consider the design professional’s decision to be outside of his or
restrictions on the design professional’s decision-making obliga- her scope of authority.
tion above those normally required to trigger immunity protec- Also like the AIA, the EJCDC does not hold the design pro-
tion. The design professional is simply to act in good faith and not fessional to a higher standard than the general immunity standard.
be partial to either the owner or contractor. The only other re- Design professionals need only render their decisions in good
quirements that the design professional must follow are the pro- faith and with impartiality in order to comply with the contract
cedural requirements of rendering a written decision with reason- requirements and maintain immunity. Therefore, if the procedural
able promptness and following the timing requirements of ¶ 4.4.2. steps are followed and the design professional is fair and renders
AIA B141 and AIA A201 are good examples of contract provi- a decision in good faith, the architect or engineer will not be
sions requiring the design professional to act in a judicial capacity liable for the impact of the decision.
and maintain immunity.
Acting within Scope of Contract Obligation
EJCDC Standard Terms
In order for immunity to apply, design professionals must be act-
Not surprisingly, the EJCDC 共1996兲 standard contracts also give ing in their role as judge. 共See E.C. Ernst, Inc., 551 F.2d at 1033,
the design professional authority over disputes between owners The immunity arises from the architect’s resemblance to a judge
and contractors. EJCDC 共1996兲 A1.05共13兲 provides: and once this resemblance ends, the immunity ends.兲 There is no
13. Disagreements between Owner and Contractor. Render bright line test for determining when design professionals are
formal written decisions on all claims of Owner and Con- acting as judge, or their other contract capacities of owner’s agent
tractor relating to the acceptability of Contractor’s work or or independent contractor. However, in order for design profes-
the interpretation of the requirements of the Contract Docu- sionals to be acting as judges, they must be presented with a
ments pertaining to the execution and progress of Contrac- dispute, unless the contract provides otherwise. 共See Craviolini v.
tor’s work. In rendering such decisions, Engineer shall be Scholer & Fuller Assoc. Architects, 357 P.2d 611 共Ariz. 1961兲,
fair and not show partiality to Owner or Contractor and When the allegations against a design professional arise out of her
shall not be liable in connection with any decision rendered determination of an Owner-Contractor dispute, she is usually im-
in good faith in such capacity. mune against the allegations; however, if the allegations concern
Under the EJCDC General Conditions between owner and conduct which is remote from and in no way associated with the
contractor, the design professional’s role as ‘‘judge’’ of disputes is performance of her arbitrator function, she may be held liable.兲
also set forth. Section 9.09 EJCDC 共1996兲 of the contract pro- By a dispute, the courts mean the owner and the contractor have
vides: different positions with regard to the interpretation of the contract
A. Engineer will be the initial interpreter of the require- documents or the acceptability of the contractor’s work. If there is
ments of the Contract Documents and judge of the accept- no dispute, then there is nothing for the design professional to
ability of the Work there under. Claims, disputes and other decide. Rather than act as a judge, the design professional would
matters relating to the acceptability of the Work, the quan- be acting as an independent contractor or as owner’s agent, roles
tities and classifications of Unit Price Work, the interpreta- for which immunity does not apply. Therefore, if the owner or the
tion of the requirements of the Contract Documents pertain- contractor is simply seeking advice or guidance, there is no
ing to the performance of the Work, and Claims seeking decision-making process for the immunity to attach, and the de-
changes in the Contract Price or Contract Times will be sign professional may be liable for that advice 共Little 1976兲.
referred initially to Engineer in writing in accordance with Design professionals are only to decide disputes that they are
the provisions of paragraph 10.05, with a request for a for- expressly given jurisdiction to decide. If design professionals de-
mal decision. cide a matter to which they have not been given jurisdiction in the
B. When functioning as interpreter and judge under this contract, they could be liable for the ramifications of that deci-
paragraph 9.09, Engineer will not show partiality to Owner sion, including a claim for interference with the contractor’s con-
or Contractor and will not be liable in connection with any tract by making the contractor perform additional work or redo
interpretation or decision rendered in good faith in such services for no extra cost 共see Lundgren, 307 F.2d at 118兲. In
capacity. . . . addition, the design professional must reasonably comply with the
Unlike the AIA, the EJCDC has one trigger of the design procedures and time deadlines for decisions set forth in the con-
professional’s ‘‘judicial’’ obligations. The owner or contractor tract documents. If they are presented with a dispute but fail to
must submit a written request pursuant to paragraph 10.05, in- act, to the extent that failure causes harm to the owner or the
cluding a request for a formal decision 共EJCDC 1996兲. If the contractor, design professionals will not be immune from liability
written request does not comply with 10.05 or does not make a for that failure.
request for a formal decision, the design professional is not au-
thorized to render a decision, and any decision made is likely not Finality of Decisions
cloaked with immunity.
Similar to the AIA, the dispute must be between the owner and The design professional’s determination of a dispute is final and
contractor and not between one of those parties and someone else. binding only when the contract expressly so provides. Under the
The formal claims procedure in paragraph 10.05 of the EJCDC AIA and EJCDC, the decisions are initial and are appealable to an
General Conditions must be followed. The claim must contain the arbitrator under the dispute resolution provisions set forth in the
documents and information required in 10.05共A兲, and the oppos- contract. However, if the owner or contractor does not timely
ing party must be given an opportunity to respond. The design appeal the decision, it is final and binding on the parties. Notwith-

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003 / 179
standing, under AIA B141 ¶ 2.6.1.9-1997, any decision by the One lesson in impartiality that can be gleaned from Lundgren
design professional regarding matters ‘‘relating to the aesthetic is the utilization of a dispute procedure that is fair and allows both
effect shall be final 关and not appealable兴 if consistent with the parties to properly present their evidence. In Lundgren, the con-
intent expressed in the Contract Documents.’’ 共AIA 1997兲 tractor was not given prior notice of a meeting to decide its ter-
mination, thereby giving an impression of bias and malicious in-
tent. Without due notice, the contractor could not properly prepare
Impartiality and Good Faith its evidence and argument 共Id.兲. Also, the design professional
waited until after the decision to hire an independent company to
prepare a report on the contractor’s performance 共Id.兲. The deci-
No Bias or Favoritism sion was based on potentially unreliable information that was not
verified by the design professional.
On its surface, the requirement to act impartially and in good faith
The design professional should adopt a procedure, unless one
seems reasonable and easily accomplished. The reality of the situ-
is dictated by the contract, that allows for due process 共see John
ation is much different. The interdependency of the various roles
W. Johnson, Inc., 292 F.Supp. at 304兲. All parties should be given
of the design professional on a project makes this requirement ample notice of the request for a decision, time to present docu-
none too easy to fulfill. The design professional has contracted mentation of their positions, and an opportunity to be heard, if
with the owner and must satisfy the owner to avoid termination desired. The design professional should then review the informa-
and to keep getting paid. Any decision against the owner’s inter- tion provided by both sides. If an independent analysis is neces-
est does not make the owner happy and has potentially harmful sary, that analysis should be performed prior to making a deci-
ramifications for the design professional. On the other hand, any sion, and both sides should have an opportunity to rebut the
ruling against the contractor will likely result in increased project findings of the independent analysis. If steps such as these are
costs and less profits for the contractor, who will then look to followed, the process will clearly give an impression of fairness,
obtain compensation for these losses from the person making the and it will be difficult to prove any malicious intent on the part of
decision on grounds that the design professional’s interpretation the design professional.
of the contract documents is unreasonable and more burdensome Furthermore, to act in good faith, design professionals must
than anticipated. Regardless of these opposing pressures, the de- make decisions in a reasonably expeditious manner 共see E.C.
sign professional must treat the owner and contractor equally and Ernst, Inc., 551 F.2d at 1033兲. If the decision is unreasonably
fairly in deciding disputes and not render a decision on any type delayed or not made, the design professional will not be protected
of bias. by immunity. In E.C. Ernst, Inc. v. Manhatten Const. Co. of
Good faith and impartiality have commonly understood mean- Texas, the architect was to determine whether the generator units
ings. However, in order to understand exactly how the design submitted by the plaintiff contractor were acceptable under the
professional must act to maintain immunity, it is worth examining plans and specifications. The court determined that the architect,
the legal definitions of these terms. Good faith is ordinarily used after several months of requesting submittals, verifications, chas-
to describe that state of mind denoting honesty of purpose, free- ing different issues, changing his mind, and finally deciding that a
dom from intention to defraud, and, generally speaking, means new system was needed, acted unfairly by unreasonably delaying
being faithful to one’s duty or obligation 共Black 1991兲. If the making a decision and forfeited his right to immunity. Of particu-
design professional’s motive is to make the correct or appropriate lar concern to the court was that the architect never communi-
decision, then they are likely acting in good faith. Impartial cated his reason for disapproving submittals and requiring addi-
means favoring neither, disinterested, treating all alike, unbiased, tional information 共Id.兲. Presumably, if this had been done, the
equitable, fair, and just 共Black 1991兲. If design professionals set delay may have been considered reasonable.
aside their personal interests and any bias toward the owner or
contractor, the decision will be made with impartiality.
No Promotion of Self-Interest
In determining if the design professional acted in good faith,
the courts generally look for any fraud or willful and malicious Oftentimes, design professionals are presented with a dispute that
intent to injure the owner or the contractor. If the design profes- attacks the adequacy of their design. It is possible that the claim
sional is not attempting to intentionally or willfully harm one of or dispute arises out of alleged errors in the plans and specifica-
the project participants, the decision will likely be protected by tions. 共See Lundgren, 307 F.2d at 118, Architect is often called
immunity. In Lundgren v. Freeman, the architects were requested upon to pass upon the sufficiency, accuracy, and adequacy of his
to determine whether the contractor should be terminated from own plans and specifications thereby pushing him in a direction to
the project. The architect, without giving the contractor a suffi- be unfair to the contractor.兲 The design professional will be forced
cient opportunity to respond, decided for termination. The court into the uncomfortable position of having to determine whether
cited several factors that created a question of fact as to whether the owner will be required to pay more to the contractor because
the architect acted in bad faith and with bias toward the owner of the design professional’s error, or, will attempt to cover their
when deciding to terminate the contractor from the job. These own error and make the contractor correct its performance with-
factors included: past poor relations between the contractor and out additional pay or time caused by the error. It is difficult to act
architects, repetitive and significant cutting of the contractor’s impartially and in good faith in such circumstances. However, the
estimates, making assertions not backed by independent evidence, design professional must do so.
no prior notice of inadequate job performance, and ordering redo Design professionals must keep in mind that protecting their
work that was performed strictly in accordance with the plans and drawings and plans from attack may be costly. If a decision is
specifications. The court held that these factors, without any re- rendered against a contractor by design professionals solely on
buttal, could indicate favoritism for the owner, and the contrac- the basis of protecting their designs from attack and not on the
tor’s claim against the architect for interference with the contract merits of the claim, the contractor may succeed in avoiding im-
was not dismissed 共see Lundgren, 307 F.2d at 118-19兲. munity and bringing a claim for interference with the contract

180 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003
against the design professional. If the contractor were to succeed with the contract documents. The damages asserted against the
on such a claim, the design professional may be liable for the design professional would likely be the cost to tear out and re-
contractor’s increased costs, lost profits, and possibly punitive place the materials and any consequential damages, such as in-
damages if malice is involved. However, if the design profession- creased overhead.
al’s protection of the design is warranted and the decision is made In Dehnert v. Arrow Sprinklers, Inc., the court was presented
in good faith and with consideration of the design’s potential with a situation similar to the previous example, except that the
defects, the design professional will not be liable for a decision architect was not deciding a dispute but certifying a termination.
requiring strict compliance with the design. In Ballou v. Basic A school district entered into a construction contract with Arrow
Construction Co., the plaintiff fabricated and delivered 200 pre- Sprinklers, Inc. that specified the use of brass sprinkler heads or
cast concrete columns for the construction of Community Hospi- an approved equal 共705 P.2d 846, Wyo. 1985兲. The architect pre-
tal in Roanoke, Va. 共407 F.2d 1137, 4th Cir. 1968兲. The plaintiff
liminarily approved a product substitution; however, the contract
sued the architects for determining that all but 45 of the columns
required that any changes in the work, including the substitution
were in compliance with the plans and specifications. Plaintiff
of an equal, had to be approved by the school district pursuant to
fabricator argued that the decision by the architects was fraught
with excessive rigidity to the plans and specifications and poor a formal written change order prepared by the architect and
judgment, in that the plans could not be exactly complied with signed by the school district. Without obtaining prior approval or
and the variance in the prefabricated columns was very minor. a written change order, Arrow installed plastic sprinkler heads.
However, the court, recognizing the application of the immunity 共The plastic heads had been indicated on a shop drawing ap-
doctrine, held that poor judgment or excessive rigidity does not proved by the architect and on which the architect did not take
demonstrate malice or bad faith and held that the architects were specific exception to the substitution.兲 The architect directed
not liable for their decision 共Id. at 1141兲. Also, there was no Arrow to replace the heads after they had been installed. When
evidence that the architect rendered his decision in a manner Arrow refused, the school district terminated the contract upon
solely to cover his own liability. If proof had been submitted the architect’s advice. Arrow sued the architect for intentional
showing that the architect’s decision was based solely on self- interference with a contractual relationship and bad faith. The
interest and that maybe the plans and specifications were to blame lower courts held in favor of Arrow and assessed damages against
and not the contractor, the court would have held the architect the architect. However, the Wyoming Supreme Court held that the
liable for the ramifications of his decision. evidence did not clearly establish that the architect acted in bad
faith, and therefore ruled in favor of the architect and dismissed
the claim.
Liability Exposure for Failing to Act in Good Faith There are other cases in which design professionals have been
and Impartially sued for intentional interference with contract rights that do not
directly concern the design professional’s obligation to decide
If design professionals fail to act in good faith or impartially in
disputes but can be analogized to that situation. In Certified Me-
rendering a decision or if they act outside of the scope of their
contract obligations to decide disputes, they will be subject to chanical Contractors, Inc. v. Wight & Company, Inc., an architect
liability. Generally, the design professional will likely be faced was sued for interfering with a general contractor’s contract with
with a claim for tortious interference with the contract or defama- an owner when the architect caused the owner to halt the project
tion. in order to permit the architect to test the general contractor’s
work 共515 N.E.2d 1047, 1987兲. The testing lasted more than 4
Tortious Interference with Contract months and the general contractor filed suit against the architect
for interfering with the progress of its project and to collect its
Tortious interference consists of intentional and improper inter- expenses for the delay. Fortunately for the architect, but after
ference with the performance of a contract or a prospective con- incurring significant legal fees, the court held that there was no
tract relation. Generally, there are three legal elements to this evidence of bad faith or actual malice, and the interference claim
claim. The design professional must: 共1兲 know of the existence of was dismissed.
a valid contractual relationship between the owner and the con- In Waldinger Corp. v. CRS Group Engineers, Inc., the me-
tractor; 共2兲 intentionally and improperly interfere with the con-
chanical contractor sued the project engineer for interference with
tract by inducing either the owner or the contractor to breach or
the contract when the engineer required strict compliance with
terminate the relationship; and 共3兲 cause damage to the party
allegedly unnecessarily restrictive specifications 共775 F.2d 781,
共owner or contractor兲 whose contract is breached 共Dehnert v.
7th Cir. 1985兲. The engineer prepared specifications for two
Arrow Sprinklers, Inc., 705 P.2d 846, Wyo. 1985兲. For example, a
wastewater treatment facilities. The mechanical subcontractor
design professional is presented with a dispute between the owner
and the contractor over whether the materials used by the con- claimed it was unable to supply sludge dewatering equipment as
tractor conform to the specifications and other contract docu- specified in its subcontract due to the restrictive specifications,
ments. The design professional, without reviewing any of the which the engineer refused to change. The subcontractor was ex-
documentary evidence presented by the contractor or owner, rules cused from performing its subcontract and the mechanical con-
in favor of the owner because the design professional and the tractor blamed the engineer for the termination of the subcontrac-
owner have worked on several projects together and does not tor. The appellate court sent the case back to the trial court with
want to disrupt that relationship. The decision is rendered in bad instructions that if the mechanical contractor could produce evi-
faith. The contractor is now required to tear out and replace the dence that the engineer insisted on strict compliance with the
materials, even though he previously complied with the contract specifications in order to injure the subcontractor or to further
and obtained all necessary approvals to use those materials. The his/her own personal goals the engineer would be liable for the
contractor may sue the design professional for interfering with its costs incurred by the mechanical contractor to procure substitute
contract by requiring it to redo work that was done in compliance performance.

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003 / 181
Defamation In Alfred A. Altimont, Inc. v. Chatelain, Samperton & Nolan,
an architect was sued for defamation for statements made about a
Defamation is a communication that tends to harm or lower the contractor to the contractor’s surety. The case involved the con-
reputation of another in the estimation of the community or to struction of a church. When the project fell behind schedule, the
deter a third person from associating or dealing with that person. architect wrote to the contractor’s surety expressing distress at the
If the defamatory language is in writing or some other permanent slow construction process 共374 A.2d 284, D.C. App. 1977兲. The
medium, the defamation constitutes libel. Spoken defamation letter indicated that there were many days when no one was on
constitutes slander. If the defamatory statement adversely reflects the job, that the contractor was not promptly and faithfully per-
on a person’s abilities, business, trade, or profession, it constitutes forming the contract, and might be in default. In a second letter,
libel or slander per se and malice, falsity, and damage to reputa- the architect blamed the contractor for the delays and stated that it
tion are presumed without proof. considered them ‘‘extremely negligent.’’ At a subsequent meeting,
There are several defenses to defamation. Truth is a complete a representative of the architect refused to retract the statements
and absolute defense to common law defamation. There is also an and stated that he thought the contractor should get out of the
absolute privilege for those communications shielded by the pub- construction business.
lic policy of protecting honest communications in certain situa- On the basis of the architect’s letters and statement, the con-
tions to facilitate the availability of accurate information. A con- tractor sued the architect for defamation, interference with his
ditional or qualified privilege arises in those circumstances where business with bonding companies, and intentionally or mali-
the communicator is making the statement to those with a com- ciously interfering with his contract with the church. The court
mon interest in the subject matter. In order for the statement to be held that there was no evidence of malice, and therefore, the
privileged, the communicator must make the statement while act- statements were not actionable.
ing within the scope of the common interest and the statement Under both defamation and tortious interference with contract,
must be free from malice. punitive damages may be assessed if the acts of the design pro-
In an Illinois case, Quality Granite Construction Co., Inc. v. fessional were malicious. Therefore, it is important from a liabil-
Hurst-Rosche Engineers, Inc., an engineering company was held ity perspective that the design professional act solely in good faith
liable to a general contractor for defamation 共261 Ill.App.3d 21, and without intent to protect the owner or the design professional
Ill.App. 5 Dist. 1994兲. The engineering company, Hurst-Rosche from liability when deciding disputes.
Engineers, after the general contractor allegedly completed the
project, wrote a letter to the general contractor’s bonding com-
pany indicating that the general contractor ‘‘may be considered in Summary
default.’’ The letter went on to state that the default was caused by
‘‘the contractor’s failure to complete the project in a timely man- The design professional has many responsibilities on a project.
ner, substandard workmanship, reluctance to complete punch list When undertaking the judicial role, the design professional ren-
items, and an inability to interpret contract documents, plans, and ders decisions that have significant financial impact on the owner
specifications as bid.’’ The general contractor alleged that this and the contractor. Fortunately for the design professional, when
letter was sent to the bonding company solely to pressure the acting as a judge of disputes, the design professional is cloaked
general contractor into compromising its claims. As a result of the with immunity from liability. However, this immunity is not ab-
letter, the bonding company temporarily suspended bonding. In solute. It is critical that in order to maintain immunity, the design
addition, the general contractor was only able to obtain bonding professional must act in accordance with the judicial obligations
on a limited basis in the future. set forth in the contract. By acting outside the scope of the ex-
The general contractor sued the engineering company for defa- pressed judicial function, the design professional may lose immu-
mation. The engineering company argued that because it was sim- nity. In addition, design professionals must always exercise their
ply fulfilling its contract duty to advise whether or not the work duty to decide disputes in good faith. It would be very easy for
complied with job plans and specifications and to report any de- design professionals to be biased toward the owner because that is
ficiencies, its communication was privileged. Further, the engi- who pays them and who may hire them for additional jobs. How-
neers argued that it is a matter of custom, contract, and sound ever, if design professionals fail to carry out their duties in good
public policy that design professionals are required to evaluate faith, they will likely find themselves subject to a claim for inter-
and report on a contractor’s work. The court disagreed and judg- ference with the contract and/or defamation.
ment was rendered against the engineering company for defama-
tion and punitive damages. Conclusion
In another case, an engineer was sued for defamation for state-
ments made regarding the abilities of the lowest bidder to a public When undertaking the role of project judge or arbiter of disputes,
project. In Riblet Ramway Co. v. Ericksen Associates, Inc., the the design professional must strictly adhere to the contract re-
State of New Hampshire engaged Ericksen as an engineering con- quirements. Design professionals must be very familiar with the
sultant to renovate and repair ski lifts 共665 F. Supp. 81, D.N.H. scope of their obligation and the procedural requirements for de-
1987兲. Ericksen’s duties included reviewing bids of compliance ciding disputes. By deciding disputes over which design profes-
with specifications. At a public hearing before the Governor and sionals have no contractual duty to decide, design professionals
Executive Council, a councilor asked the engineer ‘‘Are you say- may expose themselves to liability for negligently rendered deci-
ing there is a risk to the public safety if the state was to go with sions. However, if design professionals only decide those disputes
Riblet 关the low bidder兴?’’ The engineer answered, ‘‘That’s cor- that the contract requires them to decide, immunity will likely
rect.’’ Riblet claimed that the engineer, through the exchange at apply, as long as the decision is fair, impartial, and independently
the public hearing, slandered him and tortiously interfered with made.
his prospective agreement. Fortunately for the engineer, the court The design professional must render decisions in good faith. In
found that the statements were not defamatory. order to accomplish this requirement, the design professional

182 / JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003
must adhere strictly to the contract procedure for deciding dis- John W. Johnson, Inc. v. Basic Construction Co., Inc., 292
putes. If the contract does not provide a procedure, the design F.Supp. 300 共D.D.C 1968兲.
professional should establish one that follows the basic due pro- Lundgren v. Freeman, 307 F.2d 104 共9th Cir. 1962兲.
cess principles of affording each side an adequate opportunity to Mayfair Const. Co. v. Waveland Associates Phase Limited Part-
present evidence of their position and rebut the evidence of the nership, 619 N.E.2d 144 共III.App. 1st Dist. 1993兲.
opposition. Also, the design professional should follow a proce- M.J. Daly & Sons, Inc. v. City of West Haven, 2001 WL
dure that provides for a timely decision. The more unnecessary 1132304 共Conn. 2001兲.
delay in rendering a decision, the more suspicious the decision Quality Granite Construction Co., Inc. v. Hurst-Rosche Engi-
appears. Furthermore, the design professional should document neers, Inc., 261 III.App.3d 21 共III.App. 5th Dist. 1994兲.
the decision in writing, setting forth the reasoning of the decision. Riblet Tramway Co. v. Ericksen Assocs., 665 F.Supp. 81
The document will provide evidence of the design professional’s 共D.N.H. 1987兲.
good faith. Finally, design professionals should be careful with Santucci Construction Company v. Baxter & Woodman, Inc.,
their written communications. E-mails are discoverable, and if 151 III.App.3d 547 共Ill.App. 2nd Dist. 1986兲.
design professionals make any statements in e-mails that support V.M. Solis Underground Utility & Paving Co. v. City of Lardo,
a claim that they were not independent or fair in rendering their et al., 751 S.W.2d 532 共Tx. Appl. 1988兲.
decision, the e-mails will become documentary evidence in an Waldinger Corp. v. CRS Group Engineers, Inc., 775 F.2d 781
interference with contract and defamation case brought by the 共7th Cir. 1985兲.
contractor or owner against the design professional. Wilder v. Crook, 34 So.2d 832 共Ala. 1948兲.

Endnotes
References
Alfred A. Altimont, Inc., v. Chatelain, Samperton & Nolan, 374
A.2d 284 共D.C. App. 1977兲. American Institute of Architects 共AIA兲. 共1997兲. ‘‘General conditions of
Ballou v. Basic Construction Co., 407 F.2d 1137 共4th Cir. 1968兲. the contract for construction.’’ AIA, A 201-1997, 共4兲, 4.4, 4.4.1-4.4.8,
Certified Mechanical Contractors, Inc., v. Wight & Company, Inc. Washington, D.C.
Black. 共1991兲. Black’s law dictionary, 6th Ed., West Group, Eagan,
162 III.App.3d 391 共III.App. 2nd Dist. 1987兲.
Minn., 693, 752.
City of Durham v. Reidsville Engineering Co., Inc., 225 N.C. Douglas, B. S. 共1993兲. ‘‘Reassessing the architect’s role as arbiter.’’
98, 120 S.E.2d 564 共N.C. 1961兲. U.S.F.L. Rev., 共27兲 873, 877-81.
Craviolini v. Scholer & Fuller Assoc. Architects, 357 P.2d 611 Engineers Joint Contract Document Committee 共EJCDC兲. 共1996兲. ‘‘Stan-
共Az. 1961兲. dard general conditions of the construction contract.’’ ASCE, Reston,
Dehnert v. Arrow Sprinklers, Inc., 705 P.2d 846 共Wyo. 1985兲. Va., 共10兲10.05.
E.C. Ernst, Inc. v. Manhatten Const. Co. of Texas, 551 F.2d 1026 Little, D. C. 共1976兲. ‘‘The architect’s immunity as arbiter.’’ St. Louis Univ.
共5th Cir. 1977兲. Law Journal, 共23兲, 339.

JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE © ASCE / JULY 2003 / 183

You might also like