DPR -IPU Site Date-

Shutt. Finish Granite& Kota


S. No. Description Sqm Steel MT RMC Cum Start date Date Brick Cum TILE SQM MarbleKo Plaster Rough/Br S.S 304 ALUMINIUM
wooden almirah
ta Sqm (KG) (Kg)
ick coba

July Month Planning

1 A Block
7th Floor slab (A1) 270 22 184 13-Mar 10-Jul

7th to 8th Floor column (A1) 280 15 47 11-Jun 20-Jul

8th Floor Slab(A1) 900 33 17-Jun 5-Aug

336 16 55 10-Mar 8-Jul


8th to Terrace level Column(A2)
400 14 50 3-Jun 22-Jul
Terrace Slab (A2)
3rd floor 80 1200

2nd floor 60 140 800

1st floor 40 150 250

Ground Floor 10 250 140 150 1000

Upper Basement 163 135 90 1000 A,B,C,D B

lower basement 20 180 100 A,B,C,D B

lower basement pcc 20

lower basement VDF 30

Total Qty. 2186 100 386 210 413 745 2590 2000

Total Manpower 525 700.0 93 325 157 238 505 0 0 200


Shutt. Finish Granite&
Kota S.S 304 ALUMINIUM
2 B Block Sqm Steel MT RMC Cum Start date Date Brick Cum TILE SQM MarbleKo Plaster
Rough (KG) (Kg)
ta Sqm
50 1-Jun 2-Jul
Terrace slab (B1)

Terrace slab (B2) 400 16 60 10-Mar 15-Jul

5th Floor 80

4th floor 8 400

3rd floor 40 300

2nd floor 80 600

1st floor 25 600

Ground Floor 20 120 110 700 1000

Upper Basement

lower basement pcc


Lower basement VDF

Total Qty. 400 16 110 253 120 110 2600 0 0 1000

Total Manpower 96 112.0 26 392 46 35 507 0 0 100

Granite&
Shutt. Finish Kota S.S 304 ALUMINIUM
3 C Block Sqm
Steel MT RMC Cum Start date
Date
Brick Cum TILE SQM MarbleKo Plaster
Rough (KG) (Kg)
ta Sqm

Mumty & Lift room 150 2.2 20 18-Mar 30-Jul

Parapet wall 320 18 18-Mar 30-Jul

1st Floor 40

Ground Floor 30 120 80 700 500

Upper Basement

lower basement

Total Qty. 470 2.2 38 70 120 80 700 0 0 500

Total Manpower 113 15.0 9 108 46 26 137 0 0 50

Granite&
Shutt. Finish Kota S.S 304 ALUMINIUM
4 D Block Sqm Steel MT RMC Cum Start date Date Brick Cum TILE SQM MarbleKo Plaster
Rough (KG) (Kg)
ta Sqm

Terrace level slab 1400 54 280 6-Mar 30-Jul

1st Floor 60

Ground Floor 30 600

Upper basement 25

Lower basement

Total Qty. 1400 54 280 115 0 0 600 0 0 0

Total Manpower 336 378.0 67 178 0 0 117 0 0 0


Shutt. Finish Granite&
Kota S.S 304 ALUMINIUM
5 Sports Sqm Steel MT RMC Cum Start date Date Brick Cum TILE SQM MarbleKo Plaster
Rough (KG) (Kg)
ta Sqm

Retaining Wall (Balance top layer) 30 8 29-Mar 10-Jul 30

Ground floor slab (Balance) 8 3 8.5 1-Mar 10-Jul

1st Floor slab 350 8 52 16-Mar 15-Jul

1st to 2nd level column 108 8 34 11-Jun 31-Jul

Basement 150

Basement PCC 40

Total Qty. 496 19 142.5 0 0 0 0 180 0 0

Total Manpower 119 133.0 34 0 0 0 0 75 0 0

Granite& Kota
6 Girls Hostel Shutt.
Sqm Steel MT RMC Cum Start date Finish
Date Brick Cum TILE SQM Marble/K Plaster Rough/Br S.S 304 ALUMINIUM
(KG) (Kg)
ota Sqm ick coba

Mumpty 15 200

3rd Floor 90

2nd Floor 6 140 1000

1st Floor 30 130 450

Ground Floor 30

Basement pcc 60

Total Qty. 0 0 60 171 0 270 1450 200 0 0

Total Manpower 0 0.0 14 265 0 86 283 83 0 0

Granite&
Shutt. Finish Kota S.S 304 ALUMINIUM
Steel MT RMC Cum Start date Brick Cum TILE SQM MarbleKo Plaster
Sqm Date ta Sqm Rough (KG) (Kg)
7 Boys Hostel
Part I MNF
3rd floor slab 295 8.5 81 20-Feb 20-Jul

3rd to Terrace column 200 7.5 22 15-Mar 30-Jul

Ground Floor 50

Part II Kabita
1st to 2nd column 200 7 23 21-Mar 5-Jul

2nd floor slab 600 14 76 1-Jun 15-Jul

2nd to 3rd floor column 200 7 23 15-Jun 25-Jul

3rd Floor slab 600 25-Jun 10-Aug

Ground Floor 40

Part III Sridhama


GF slab 488 14 76 26-Feb 20-Jul

GF to 1st column

Part IV Sridhama
Plinth Beam & column up to GF 120 15 25 11-Jun 30-Jul

Total Qty. 2703 73 326 90 0 0 0 0 0 0

Total Manpower 649 511.0 78 139 0 0 0 0 0 0

8 Auditorium
Stair case Upper to Ground 2.4 16 1-Mar 10-Jul

1st to 2nd column 3 nos 27 1.35 4.7 15-Mar 15-Jul

Half Radius grid wall north-south side 138 3.5 24 16-Jun 31-Jul

lower basement PCC 60 200

lower basement VDF 70

Total Qty. 165 7.25 174.7 0 0 0 200 0 0 0

Total Manpower 40 51 42 0 0 0 39 0 0 0

9 4 A- Type
Terrace 75

3rd floor 150 75 400 6

2nd floor 150 75 400 6

1st floor 150 75 400 6

Ground Floor
Total Qty. 0 0 0 0 450 300 0 0 0 1200

Total Manpower 0 0 0 0 0 171 96 0 0 0 120

10 4 B -Type
Terrace 400

3rd floor 16 5 380

2nd floor

1st floor

Ground Floor

Total Qty. 16 0 5 0 0 0 380 400 0 0

Total Manpower 4 0 1 0 0 0 74 166 0 0

Granite&
Shutt. Steel MT RMC Cum Start date Finish Brick Cum TILE SQM MarbleKo Plaster Kota S.S 304 ALUMINIUM
Sqm Date Rough (KG) (Kg)
ta Sqm
11 5 A-Type
Terrace

3rd floor 200 1250

2nd floor 600

1st floor

Ground Floor 480 75 400

Total Qty. 0 0 0 0 480 75 0 0 200 2250

Total Manpower 0 0 0 0 182 24 0 0 5000 225

Shutt. Finish Granite&


12 Steel MT RMC Cum Start date Brick Cum TILE SQM MarbleKo Plaster Kota S.S 304 ALUMINIUM
Sqm Date ta Sqm Rough (KG) (Kg)
5 B-Type
Mumty & water tank 150 2.2 20 21-Mar 10-Jul

3rd Floor 91

2nd Floor 12

1st floor

Ground Floor PCC 20 10

Total Qty. 150 2.2 40 113 0 0 0 0 0 0

Total Manpower 36 15 10 175 0 0 0 0 0 0

Granite&
Shutt. Steel MT RMC Cum Start date Finish Brick Cum TILE SQM MarbleKo Plaster Kota S.S 304 ALUMINIUM
Sqm Date Rough (KG) (Kg)
ta Sqm
13 III- Type
Plinth beam 115 3.5 12 10-Mar 5-Jul

Column upto Ground Floor slab 120 12 20 13-Jun 10-Jul

Ground Floor slab 700 18 60 19-Jun 25-Jul

Total Qty. 935 33.5 92 0 0 0 0 0 0 0

Total Manpower 224 235 22 0 0 0 0 0 0 0

14 II- Type
Pedastal & Plinth beam 80 5.8 16 4-Jun 15-Jul

Column upto Ground Floor slab 110 9 18 16-Jun 25-Jul

Ground Floor slab 500 21-Jun 10-Aug

Total Qty. 690 14.8 34 0 0 0 0 0 0 0

Total Manpower 166 104 8 0 0 0 0 0 0 0

15 Teacher Hostel
Pile cap 125 20 220 20-Mar 10-Jul

PCC 4 15-Mar 5-Jul

Plinth Beam & column up to GF 180 22 30 18-Jun 30-Jul

Total Qty. 305 42 254 0 0 0 0 0 0 0

Total Manpower 73 294 61 0 0 0 0 0 0 0

16 WTP
Pile Cap/Footing 20 6 62 27-Feb 20-Jul

Outer Wall 205 3.5 45 14-Mar 5-Jul

Internal Wall & Stair case 506 9 35 1-Jun 20-Jul

Top Slab 410 21-Jul 16-Aug

Water proofing 180


Total Qty. 1141 18.5 142 0 0 0 0 180 0 0

Total Manpower 274 130 34 0 0 0 0 150 0 0

17 Open Theatre
PCC 25 3-Mar 10-Jun

VDF 2 35 12-Mar 20-Jun

Total Qty. 0 2 60 0 0 0 0 0 0 0

Total Manpower 0 14 14 0 0 0 0 0 0 0

Total 11057 384.45 2144.2 1022 1583 1580 8520 960 200 6950

Acheived till date


Balance
PCC 229 Vertical Kota 210
VDF 135 Horizontal Ko 150
RCC below 335 Brick Coba 200
25-06.2020

Remarks

A,B,C,D Blocks

A,B,C,D Blocks

Remarks

Remarks

Remarks
Remarks

Remarks

Remarks
Remarks

Remarks

Remarks
Planning for the Month July-2020-IPU Delhi
Name of Work:- Construction of East Delhi Campus of Guru Gobind Singh Indraparastha University at Surajmal Vihar , Shahadara, Delhi.
Item No. Activity BOQ Units BOQ Rate BOQ Billed Qty Amount as Balance Qty Target Target
Qty Amt. Amount as in 21st in 21st RA to be July-20 Amt in Man Power
in Cr.Rs. RA Bill executed Cr. Rs.

Lab Labour
Description Unit Coffecie Reqd Rate
Labour
nt
1.1.2 Excavation 174344 Cum 155.60 2.71 219733.95 3.42 -45390 600 0.01 ###
1.1.2 Back filling 63410 Cum 112.40 0.71 16733.99 0.19 46676 3000 0.03 ###
2.1.1 PCC-M-10 @275 Kg /Cum. 4989 Cum 5495.29 2.74 2866.76 1.58 2122 229 0.13 Mason Nos. 0.240 55 500

2.4 DPC 1:2:4 465 sqm 257.80 0.01 282.76 0.01 182 - Mason Nos. 0.012 0 500

3.1.1 RCC-M-25 below PL 30001 Cum 6296.15 18.89 29416.16 18.52 585 335 0.21 Mason Nos. 0.240 80 500

3.1.2 RCC-M-25 above PL 22795 Cum 7014.55 15.99 16747.34 11.75 6048 1580 1.11 Mason Nos. 0.240 379 500

3.5.1 RCC-M-30 instead of M-25 52606 Cum 76.50 0.40 24997.7 0.19 27608 1580 0.01 Mason Nos. 0.002 3 500

3.7 Steel Reinforcement-TMT Bars 7904869 Kg 68.10 53.83 10882628 74.11 -2977759 384450 2.62 Barbender Nos. 0.007 2691 500
3.8 Centering and shuttering 239970 Sqm 380.00 9.30 178383.26 6.78 61587 11057 0.42 Carpenter Nos. 0.240 2654 500
Brick Work in Foundations 4089 cum 4677.25 1.91 1480.01 2609 100 0.05 Mason No. 1.548 155 500
4.1 0.69

4.2 Brick work in C.M.1:6 in SS 11865 cum 5455.85 6.47 2903.22 1.58 8962 873.125 0.48 Mason No. 1.548 1352 500

4.4.1 Half Brick work in C.M.1:4 9035 sqm 672.35 0.61 1893.31 0.13 7142 425 0.03 Mason No. 0.348 148 500

8.9.1 Steel Work in builtup tubular 379190 Kg 115.10 4.36 0 0.00 379190 20000 0.23 0

8.12 Structural Steel Work 14345 Kg 90.10 0.13 0.00 14345 2000 0.01 Fabricator No. 0.023 45 500
8.14 Stainless Steel Work 23300 Kg 619.40 1.44 0.00 23300 200 0.01 Fabricator No. 0.023 5 500
9.2 P&L Glazed Ceramic Floor Tiles 4669 sqm 950.05 0.44 0.00 4669 100 0.01 Mason No. 0.380 38 500
9.10 Waterproofing Kota wall
P/L Glazed Ceramic in V.Tiles
Sueface 14107 Sqm 836.65 1.18 0.00 14107 350 0.03 Mason No. 0.380 133 500
9.11 P/L Vitrifiedto
conforming floor Tiles in the
IS:2645 14555 Sqm 1405.95 2.05 0.00 14555 1133 0.16 Mason No. 0.380 431 500
11.1 6/12/15/18mmproportion
recommended plaster over the 209289 Sqm 156.37 3.27 25813.89 0.40 183475 8520 0.13 Mason Nos 0.195 1661 500
17.1 leveling
Aluminum course (leveling course to
D/Wwork 53737 Kg 377.75 2.03 0.00 53737 6950 0.26 Fabricator Nos 0.100 695 500
be
Kota paid separately).
Stone Joints
Slab flooring 506
9.4 sealed and grouted with cement 42100 Sqm 1141.40 4.81 5759.5 0.66 36341 1580 0.18 Mason No. 0.320 500
18.1 Waterproofing
slurry mixed with Kota in H.proofing
water Surface
23550 Sqm 1022.45 2.41 21923.31 1626.69 150 0.02 Masson Nos 0.341 51 500
compound. 2.24
conforming
(ii) 2nd layertoofIS:2645
25 mmin the cement
thick
recommended proportion
18.2 mortar 1:3 (1 cement: 3 coarse over the 12540 Sqm 1243.25 1.56 8403.17 4137 210 0.03 Masson Nos 0.414 87 500
leveling
sand) mixed with water proofingto
course (leveling course 1.04
be paid separately). Joints
18.5 compound
Brick
sealed coba
and
in recommended
waterproofing
grouted with cement 8214 Sqm 1019.05 0.84 600 0.06 0
proportions. 0.00
slurry
(iii) mixed with
Finishing water
top with proofing
stone
16.1 compound.
RCC Pile of 10 mm to 12 mm
aggregate 62000 RMT 3629 22.50 83718.00 30.38 -21718 - Mason Nos. 0.593 0 500
(ii)
nominallayer of 25 mm thick cement
2nd
E.I.2 mortar
Stone Pile
1:3 (1 cement:
size spreading 3 coarse
@ 8 cudm/sqm 21070 RMT 1780.11 3.75 16240.00 2.89 4830 - 0 ###
sand)
thoroughly embedded inproofing
mixed with water the
Two coat putty, one coat primer &
E.I.3.5 compound
2nd layer.
two
in recommended
coat rough
distemper 79950 Sqm 171.2 0.03 79950 3000 0.04 Painter Nos. 0.030 90 500
proportions.
(a) Using kota stone 0
(iii) Finishing top with stone
aggregate of 10 mm to 12 mm 156.56 6.26 11258
nominal
size spreading @ 8 cudm/sqm
thoroughly embedded in the
2nd layer.
(a) Using rough kota stone
Less: Rebate 7.2% 11.27 0.45

Net Payable 145.29 5.81