Sl.No Title of Drawing Drawing Number No.of Sheets Revision Relased Date Approved Date Remarks
1 Foundation Detail of CRB C/ENGG/STD/132/CRB/STR/FDN/01 01 of 01 REV-02 1/22/2019 5/19/2017
01 of 02 REV-02 1/22/2019 5/19/2017
C/ENGG/STD/132/CRB/STR/02
2 Plinth Beam Plan & Details of CRB 02 of 02 REV-02 1/22/2019 5/19/2017
01 of 02 REV-02 1/22/2019 5/19/2017
C/ENGG/STD/132/CRB/STR/03
3 First Floor Slab Details of CRB 02 of 02 REV-02 1/22/2019 5/19/2017
01 of 02 REV-03 1/22/2019 5/3/2018
C/ENGG/STD/132/CRB/STR/04
4 Terrace floor Slab Details of CRB 02 of 02 REV-03 1/22/2019 5/3/2018
GA & RCC Details of Parpet column & C/ENGG/STD/132/CRB/STR/04A
5 Beam of CRB 01 of 01 REV-00 1/22/2019 7/15/2018
6 Internal Staircase Details of CRB C/ENGG/220/132/33kV/CRB/STR/05 01 of 01 REV-01 1/22/2019 11/15/2017
7 External Staircase Details of CRB C/ENGG/220/132/33kV/CRB/STR/06 01 of 01 REV-00 1/22/2019 6/27/2017
Ground Floor Lintel Beam Plan of CRB
8 ( With Switchgear Room) 01 of 02 REV-00 1/22/2019 6/9/2017
C/ENGG/220/132/33kV/CRB/STR/07
First Floor Lintel Beam Plan of CRB
9 ( With Switchgear Room) 02 of 02 REV-00 1/22/2019 6/9/2017
Ground Floor Lintel Beam Plan of CRB
10 (Without Switchgear Room) 01 of 02 REV-00 1/22/2019 6/9/2017
C/ENGG/220/132/33kV/CRB/STR/07
First Floor Lintel Beam Plan of CRB
11 (Without Switchgear Room) 02 of 02 REV-00 1/22/2019 6/9/2017
Mummty Room Slab & Beam Details of C/ENGG/220/132/33kV/CRB/STR/08
12 CRB ( With Switchgear Room) 01 of 01 REV-00 1/22/2019 7/6/2018
Ground Floor Plan of CRB
13 ( With Switchgear Room) 01 of 03 REV-01 1/22/2019 4/12/2018
First Floor Plan of CRB C/ENGG/220/132/33kV/CRB/ARCH/01
14 ( With Switchgear Room) 02 of 03 REV-00 1/22/2019 6/2/2017
Terrace & Mummty Room Plan of CRB
15 ( With Switchgear Room) 03 of 03 REV-00 1/22/2019 6/2/2017
Door Details of CRB
16 ( With Switchgear Room) 01 of 03 REV-00 1/22/2019 11/27/2017
Window Details of CRB C/ENGG/220/132/33kV/CRB/ARCH/02
17 ( With Switchgear Room) 02 of 03 REV-00 1/22/2019 11/27/2017
Ventilator Details of CRB
18 ( With Switchgear Room) 03 of 03 REV-00 1/22/2019 11/27/2017
CRB with Switchgear Room
19 Elevation -A 01 of 04 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
20 Elevation -B 02 of 04 REV-00 1/22/2019 6/2/2017
C/ENGG/220/132/33kV/CRB/ARCH/03
CRB with Switchgear Room
21 Elevation -C 03 of 04 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
22 Elevation -D 04 of 04 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
23 Section X-X 01 of 06 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
24 Section Y-Y 02 of 06 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
25 Section Z-Z 03 of 06 REV-00 1/22/2019 6/2/2017
C/ENGG/220/132/33kV/CRB/ARCH/04
CRB with Switchgear Room
26 Section W-W 04 of 06 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
27 Section X1-X1 05 of 06 REV-00 1/22/2019 6/2/2017
CRB with Switchgear Room
28 Section X2-X2 06 of 06 REV-00 1/22/2019 6/2/2017
Page 1 of 7
Sl.No Title of Drawing Drawing Number No.of Sheets Revision Relased Date Approved Date Remarks
Detail of Concrete Road (switchyard C/ENGG/STD/ROAD/411
47 area) 01 of 01 REV -00 1/22/2019 9/15/2014
48 Detail of Road Culverts C/ENGG/STD/ROAD CULVERTS -01 01 of 01 REV -00 1/22/2019
Page 2 of 7
Sl.No Title of Drawing Drawing Number No.of Sheets Revision Relased Date Approved Date Remarks
49 Detail of Drain C/ENGG/STD/DRAIN/01 01 of 01 REV -01 1/22/2019 1/14/2014
50 01 of 04 REV -00 1/22/2019 9/16/2016
51 Detail of Cable trench & Cable trench 02 of 04 REV -00 1/22/2019 9/17/2016
C/ENGG/STD/2016/RCT/01
52 Road crossings 03 of 04 REV -00 1/22/2019 9/18/2016
53 04 of 04 REV -00 1/22/2019 9/19/2016
54 Detail of Chainlink Fencing C/ENGG/CVL/SYD/FENCE/101 01 of 01 REV - 01 1/22/2019 11/10/2009
55 Details of Boundary Wall 01 of 07 REV -00 1/22/2019 1/16/2017
56 Details of Boundary Wall 02 of 07 REV -00 1/22/2019 1/16/2017
57 Layout & Plan Security Room & Gate 03 of 07 REV -00 1/22/2019 1/16/2017
58 C/ENGG/STD/BW-01 04 of 07 REV -00 1/22/2019 1/16/2017
59 05 of 07 REV -00 1/22/2019 1/16/2017
Security Room & Gate Details
60 06 of 07 REV -00 1/22/2019 1/16/2017
61 07 of 07 REV -00 1/22/2019 1/16/2017
C/ENGG/BIO/SLOPE/01
62 Slope Stabilisation in Bioengineering 01 of 01 REV -00 1/22/2019 11/24/2014
C/ENGG/STD/RWH-01
63 Detail of Recharge pit for Rain water 01 of 01 REV -00 1/22/2019 2/22/2019
Page 3 of 7
Sl.No Title of Drawing Drawing Number No.of SheeRevision
Contour Layout for 132/33kV TPL/PGCIL/BASAR SS/001
1 SS Basar 01 of 01 P0
Foundation Layout for
2 132/33kV SS Basar TCE-11207A-CV-3000-RC-31002 01 of 01 R1
11/20/2018 1
3/11/2019 1