E8 SECTION WORK DONE

01 MAR TO 15 APR 2020


WORK DONE (01 MAR 2020 TO 15 APR 2020) : SUMMARY

S No Item of Work Numbers Remarks

1 Suspension 05

2 Time Extension 06

3 Technical Check of Final Bill 07

4 Tender Uploading on CPPP 02

5 T-Bid Finalization 02

6 Q-Bid Finalization 08

7 Acceptance of Tender 06

8 Issue of Diligence Notice 02

9 Misc Cases 07
SUSPENSION CASES

S No Processed Cases Remarks

1 CA No CE (P) BCN/13/2019-20 Approved vide HQ CE (P) Beacon letter No


Resurf of H-L-N Rd execution of BM, 800419/Vol-II/39/E8 dated 07 Mar 2020.
BC and Rd Marking work

2 CA NO CE (P) BCN/02/2019-20 Approved vide HQ CE (P) BCN letter No


Resurf of B-K-C Rd execution of BM, 800417/Vol-II/43/E8 dated 17 Mar 2020.
BC and Rd Marking work

3 CA NO CE (P) BCN/19/2019-20 Approved vide HQ CE (P) BCN letter No


Resurf of Sopore By pass Rd 800428/Vol-II/19/E8 dated 17 Mar 2020.
execution of BM and BC work

4. CA NO CE (P) BCN/18/2019-20 Approved vide HQ CE (P) BCN letter No


Resurf of B-O-A Rd execution of BM 800431/Vol-II/29/E8 dated 17 Mar 2020.
and BC work

5 CA NO CDR 760TF/12/2019-20 Approved vide HQ CE (P) BCN letter No


Supply and Stacking of material on 800006/Contract Matter 760TF/29/E8 dated 20 Mar
R-B-D Rd 2020.
TIME EXTENSION CASES
S
Processed Cases Remarks
No
1 CA NO CE (P) BCN/27/2014-15 Approved vide HQ CE (P) BCN letter No
Constr of 60 Mtr PMT Br 800251/87/E8 dated 13 Mar 2020.
(Chak Nallah Bridge) on D-N-B-C-K Rd

2 CA NO CE (P) BCN/02/2019-20 Approved vide HQ CE (P) BCN letter No 800417/Vol-


Resurf of B-K-C Rd execution of BM, BC and II/42/E8 dated 17 Mar 2020.
Rd Marking work.

3 CA NO CE (P) BCN/20/2018-19 Approved vide HQ CE (P) BCN letter No 800404/Vol-


Resurf of B-K-C Rd execution of BM, BC and II/39/E8 dated 20 Mar 2020.
Rd Marking work

4 CA NO CE (P) BCN/10/2018-19 Approved vide HQ CE (P) BCN letter No


Resurf of H-Z-M Rd execution of BM, BC and 800394/85/E8 dated 28 Mar 2020.
Rd Marking work.

5 CA NO CDR 760TF/06/2018-19 Approved vide HQ CE (P) BCN letter No


Supply and Stacking of material on N-R-T 800006/Contract Matter 760TF/36/E8 dated 07 Apr
Rd. 2020.

6 CA NO CDR 760TF/01/2018-19 Approved vide HQ CE (P) BCN letter No


Risk and Cost of Supply and Stacking on 800006/Contract Matter 760TF/38/E8 dated 08 Apr
T-M-G-KB Rd 2020.
TECHNICAL CHECK OF FINAL BILL
S No Processed Cases Remarks
1 CA No CE (P) BCN/06/2019-20 Approved vide HQ CE (P) BCN letter No
Resurf of W-B-P Rd execution of BM, BC and Rd 800413/35/E8 dated 27 Mar 2020.
Marking work

2 CA No CE (P) BCN/04/2017-18 Approved vide HQ CE (P) BCN letter No


Resurf of G-S Rd execution of BM, BC and Rd 800378/46/E8 dated 28 Mar 2020.
Marking work

3 CA No CE (P) BCN/16/2019-20 Approved vide HQ CE (P) BCN letter No


Resurf of K-D Rd execution of BM and BC work. 800427/21/E8 dated 28 Mar 2020.

4 CA No CE (P) BCN/20/2018-19 Approved vide HQ CE (P) BCN letter No


Resurf of B-K-C Rd execution of BM, BC and Rd 800404/42/E8 dated 28 Mar 2020.
Marking work

5 CA No CE (P) BCN/22/2014-15 Approved vide HQ CE (P) BCN letter No


Resurf of P-B Rd execution of BM and BC 800289/76/E8 dated 30 Mar 2020.

6 CA No CE (P) BCN/01/2019-20 Approved vide HQ CE (P) BCN letter No


Resurf of C-C-J Rd execution of BM and BC 800397/30/E8 dated 30 Mar 2020.

7 CA No CE (P) BCN/14/2015-16 Approved vide HQ CE (P) BCN letter No


Resurf of P-B Rd execution of BM and BC 800321/27/E8 dated 30 Mar 2020.
UPLOADED TENDER
S No Processed Cases Remarks
1 Tender No CE (P) BCN/30/2019-20 Tender uploaded on CPP Portal as well as
Rehabilitation of JT BIMS on 04 Mar 2020.

2. CE (P) BCN/24/2019-20 Tender uploaded on CPP Portal on 03 Apr


Resurf of H-Z-M Rd execution of BM & BC 2020.
(3rd Call)
T-BID FINALIZATION
S No Tender No. T-Bid Opening Remarks
1 CE (P) BCN/23/2019-20 02 Mar 2020 Deficient docs sought by 15
Resurf of M-P-D Rd execution of BM Apr 2020.
& BC

2 CE (P) BCN/24/2019-20 12 Mar 2020 Since a no resultant bids recd


Resurf of H-Z-M Rd execution of BM hence, Re-Tendering for 3rd
& BC (2nd Call) Call uploaded on 03 Apr 2020.
Q-BID FINALIZATION
S No Tender No. Q-Bid Opening Remarks
1 CE (P) BCN/25/2019-20 L1 Bidder M/s Abdul Rashid
Resurf of D-G Rd execution of BM & 06 Mar 2020 Butt.
BC
2 CE (P) BCN/26/2019-20 CA Accepted on 18 Mar 2020.
Resurf of K-B-B-C Rd execution of 06 Mar 2020 CA No CE (P) BCN/26/2019-20.
BM & BC
3 CE (P) BCN/28/2019-20 CA Accepted on 18 Mar 2020.
Resurf wks on Nashri Bypass Rd 09 Mar 2020 CA No CE (P) BCN/27/2019-20.
execution of BM & BC
4 CE (P) BCN/22/2019-20 CA Accepted on 20 Mar 2020.
Resurf wks on Nashri Bypass Rd 09 Mar 2020 CA No CE (P) BCN/28/2019-20.
execution of BM & BC
5 CE (P) BCN/02/2019-20 CA Accepted on 02 Apr 2020.
Supply & Stacking of PCC Block on 20Mar 2020 CA No CE (P) BCN/01/2020-21.
J-S Rd
6 CE (P) BCN/17/2019-20 CA Accepted on 07 Apr 2020.
Resurf wks on S-S-G Rd execution 31 Mar 2020 CA No CE (P) BCN/02/2020-21.
of BM & BC
7 CE (P) BCN/16/2019-20 L1 Firm M/s Velley Rd Constr
Resurf wks on S-B Rd execution of 31 Mar 2020 Acceptance under process.
BM & BC
8 CE (P) BCN/27/2019-20 L1 Firm M/s Mirz Infra
Resurf wks on Sopore Bypass Rd 11 Apr 2020 Builders.
execution of BM & BC
ACCEPTANCE OF TENDER
S No CA No Name of Firm Remarks
1 CA NO CE (P) BCN/25/2019-20 M/s Jehlum Construction Coy HQ CE (P) BCN letter No
800442/23/E8 dated 02
Resurf wks on B-K-C Road (Rs 433.35 lakh) Mar 2020.

2 CA NO CE (P) BCN/26/2019-20 M/s Harish Gupta, Udhampur HQ CE (P) BCN letter No


800448/01/E8 dated 18
Resurf wks on K-B-B-C Road (Rs 175.34lakh) Mar 2020.

3 CA NO CE (P) BCN/27/2019-20 M/s Harish Gupta, Udhampur HQ CE (P) BCN letter No


800450/01/E8 dated 18
Resurf wks on Nashri Bypass (Rs 72.77 lakh) Mar 2020.
Road
4 CA NO CE (P) BCN/28/2019-20 M/s Valley Road Constr Coy HQ CE (P) BCN letter No
800444/02/E8 dated
Resurf wks on C-T-C Road (Rs 365.92 lakh) 20 Mar 2020.

5 CA NO CE (P) BCN/01/2020-21 M/s Harish Gupta HQ CE (P) BCN letter No


800424/01/E8 dated
PCC Blocks on J-S Road (Rs 299.83 lakh) 02 Apr 2020.

6 CA NO CE (P) BCN/02/2020-21 M/s Jehlum Constr Coy HQ CE (P) BCN letter No


800439/01/E8 dated
Resurf wks on S-S-G Road (Rs 299.21 lakh) 07 Apr 2020.
ISSUE OF DILIGENCE NOTICE

S No Processed Cases Remarks

1 CA No CE (P) BCN/15/2019-20 HQ CE (P) BCN letter No 800429/23/E8 dated


Execution of Surf work on G-S Rd 18 Mar 2020.

2 CA No CE (P) BCN/05/2019-20 HQ CE (P) BCN letter No 800410/63/E8 dated


Design and Construction of 04 Nos PSC Box 03 Apr 2020.
Girder Br on B-B-B Rd
MISC CASES
S No Processed Cases Remarks
AMENDMENT IN CA
1 CA No CE (P) BCN/14/2018-19 Approved vide HQ CE (P) BCN letter No
Supply and Stacking of material on R-G Rd 800392/25/E8 dated 17 Mar 2020.
2 CA No CE (P) BCN/21/2013-14 Approved vide HQ CE (P) BCN letter No 800270/E/8
Execution of Surf work on N-R-U-K Rd dated 20 Mar 2020.

MINUS DEVIATION
1 CA No CE (P) BCN/10/2018-19 Approved vide HQ CE (P) BCN letter No
Resurf of H-Z-M Rd execution of BM, BC and Rd Marking 800394/83/E8 dated 17 Mar 2020.
work.

FC CASE
1 Tender No CDR 32TF/12/2019-20 Approved vide HQ CE (P) BCN letter No
Supply & Stacking of Materials on M-T-S Rd 800006/Contract Matter 32TF/20/E8 dated 02 Apr 20
CANCELLATION OF CONTRACT
1 CA No CE (P) BCN/09/2016-17 Contract Cancelled vide HQ CE (P) Beacon letter
Supply and Stacking of Materials on B-B-B Road No 800357/92/E8 dated 14 Mar 2020.
CASE FWD TO HQ ADGBR (NW)
1 CA No CE (P) BCN/44/2007-08 Case for cancellation of Contract fwd to HQ
Design and Construction of 70 Mtr Steel superstructure ADGBR for approval vide HQ CE (P) BCN letter No
Maj PMT Br on U-S-K-P Rd 800650/55/E8 dated 24 Mar 2020.

GUIDELINES TO TFs
1 Processing of Final Bills: Timelines HQ CE (P) BCN letter No 800006/Gen/160/E8 dated
01 Apr 2020.