Professional Documents
Culture Documents
90% P&S
Option 1: with Anchor Shaft
Crystal Ball Report
Simulation started on 11/3/03 at 12:35:13
Simulation stopped on 11/3/03 at 12:35:60
Summary:
Display Range is from 6,736,607 to 9,401,632
Entire Range is from 6,251,220 to 9,933,632
After 20,000 Trials, the Std. Error of the Mean is 3,637
Statistics:
Trials
Mean
Median
Mode
Standard Deviation
Variance
Skewness
Kurtosis
Coeff. of Variability
Range Minimum
Range Maximum
Range Width
Mean Std. Error
Forecast: E36
.016 312.7
.010 208.5
.005 104.2
.000 0
.016 312.7
.010 208.5
.005 104.2
.000 0
Contingency Analysis
$ 7,032,396
Confidence
Level Value Contingency
0% 6,251,220
5% 7,231,566 3%
10% 7,402,887 5%
15% 7,527,590 7%
20% 7,630,292 9%
25% 7,716,363 10%
30% 7,798,895 11%
35% 7,869,458 12%
40% 7,939,069 13%
45% 8,005,411 14%
50% 8,074,771 15%
55% 8,140,537 16%
60% 8,207,003 17%
65% 8,276,751 18%
70% 8,350,223 19%
75% 8,432,349 20%
80% 8,519,636 21%
85% 8,619,660 23%
90% 8,744,227 24%
95% 8,931,577 27%
100% 9,933,632 41%
Confidence Level: 80% would mean, For a project cost of $8,519,636 using
21% contingency would have a 80% confidence level that project cost would
not exceed this amount.
L ik e lih o o d o f O c c u rr e n c e Sample (Feasibility Phase/Recommended Plan) - PDT Risk Register
Project Scope
Risk Level
This project consists of constructing a debris boom upstream of the dam spillway and installing a temporary coffer dam around the
Very
construction area to dewater the bridge and spillway notch construction zones for the fish passage. A prefabricated concrete bridge is planned
Low Moderate High High High to extend across the notch in the spillway; and, will include a stop log water control structure and improved roadway access to the lock and
Likely
dam storage yard. The fish passage ramp and riffle structure is constructed of rock materials and will also incorporate hydraulic dredging
Likely Low Moderate High High High operations to use dredge spoil to fill voids in the large rock materials of the fishway.
This is a 100% Federal project and no lands and damage costs are included. No relocation costs were expected for this project.
Unlikely Low Low Moderate Moderate High
Cost Impacts
Very
Unlikely
Low Low Low Low High For the Sample Project, any cost impact of $500K or higher should be considered at least "Significant."
Anything over $250 K should be considered at least "Marginal."
Negligible Marginal Significant Critical Crisis
Schedule Impacts
Impact or Consequence of Occurrence For the Sample Project, any schedule impact of 3 months or greater should be considered at least "Significant."
Anything over 1 month should be considered at least "Marginal."
Contract Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.)
Project competing with other Other priorities threaten the funding and timely receipt of Has a significant impact on schedule, and marginal impact Captured by
PPM-3 projects for funding funding to complete the milestones for this project. on costs. Very Likely Marginal Moderate Schedule Very Likely Significant High 7.2 Months Uniform Project Manager Project Schedule
Functional and Technical Staff There is an increased workload that is outpacing the Has a significant impact on schedule, and marginal impact Captured by Captured by Risk
PPM-4 overloaded current staff level's ability to keep pace. on costs. Very Likely Marginal Moderate Schedule Very Likely Significant High PPM-2 N/A Resource Providers Project Schedule
Product Development by Several The regional PDT includes members from other U5
Sources/Communication Districts, as well as external agencies at the Federal and The coordination of staff and communication presents
PPM-5 Challenges State level. challenges that could impact the cost and schedule. Likely Marginal Moderate $1.1 M Unlikely Significant Moderate 1.8 Months Triangular Project Manager Project Cost & Schedule
Confusing and contradictory advice regarding continuously This issue presents a project management challenge in the
changing program and project requirements (i.e. Model ability to plan, schedule, and produce, design and develop
Timely Response to Critical Certification, Science Panel, Risk Assessment, ITR/ATR, documents due in some instances to indecision or lack of
PPM-7 Decision EPR). action at higher levels. Likely Significant High $2 M Likely Significant High 4.8 Months Uniform EST-1 District Management Project Cost & Schedule
CONTRACT ACQUISITION
The PDT feels that the structural portion will likely go out as
Contract Acquisition Strategy Not full and open RFP, whereas the rock portion could to go to If an 8(a) or small business was selected for the rock Contract Cost & Project
CA-1 Determined an 8(a) or small business. portion of the work, it could significantly impact costs. Likely Significant High $2.7 M Likely Marginal Moderate 3.8 Months Triangular TASB/Contracting Schedule
TECHNICAL
This is the first time that a hydraulic dredge has been used If the technique does not perform as planned, there will be
to place material to fill voids in the rock ramp to prevent some rework or modification necessary to complete the
T-1 Uncertainty with Filling of Voids seepage though the bottom of the fishway. work. Unlikely Significant Moderate $40 K Unlikely Marginal Low Not Studied Uniform Geotech Lead Contract Cost
There is a potential that there will be other contracts Project currently assumes access to small lay-down/staging
Conflicts with potential hydro-plant occurring simultaneously (hydro-plant and/or lock area footprint. Simultaneous contracts could impact Captured by Risk Captured by Risk
T-4 and lock expansion project. expansion) that could affect the coordination and access. availability and congestion. Likely Marginal Moderate PR-5 Likely Marginal Moderate PR-5 N/A Project Manager Project Cost & Schedule
ENVIRONMENTAL/
REGULATORY
Plan is currently to construct from a barge. If DMMP
required, then there could be some cultural clearance
L&D facility listed on historical sites listing. Dredge material issues. There are potential adverse effects to the L&D
EN-1 Historical/Cultural Site placement issue also could be involved as a contingency. facility. Very Unlikely Negligible Low Not Studied Very Unlikely Critical Low Not Studied N/A Environmental Lead Project Cost & Schedule
There is inherent risk of getting a contractor that is not as Cost Contract Cost & Project
C-2 Inefficient Contractor efficient as planned in the baseline estimate. Could affect cost and schedule. Unlikely Significant Moderate $1.4 M Unlikely Significant Moderate 2.5 Months Triangular Engineering/Construction Schedule
The plan currently assumes multiple contracts for this There is the possibility for conflicts between the contractors Contract Cost & Project
C-3 Conflicts with Other Contracts acquisition. on this program, as well as other non-related projects. Unlikely Significant Moderate $519 K Unlikely Significant Moderate 1.8 Months Triangular PR-5 Construction Schedule
All materials and access is contemplated to be via river or Site access issues are currently captured in the baseline Cost Contract Cost & Project
C-4 Site access/restrictions on the Illinois side. There is limited access to the site. estimate. Unlikely Marginal Low Not Studied Unlikely Marginal Low Not Studied N/A Engineering/Construction Schedule
Marine based and bridge labor force would likely come from May increase costs due to housing and subsistence for the
C-5 Labor Forces from Outside Area outside the local area. labor force. Likely Significant High $1.2 M Likely Negligible Low Not Studied Triangular Cost Engineering Contract Cost
The project site has not been surveyed since the last flood There is the possibility for differing conditions due to the
C-7 Differing Site Conditions event. effects of the last flood event. Likely Marginal Moderate $1.3 M Likely Negligible Low Not Studied Uniform Construction Contract Cost
PDT is not confident in the current contract phasing as This could have significant impact on the overall project Captured by
C-8 Contract Sequencing currently scheduled and contemplated. schedule. Likely Marginal Moderate Schedule Likely Significant High 2.7 Months Triangular Contracting Project Schedule
REAL ESTATE
COST ESTIMATING/
ENGINEERING
Programmatic Risks (External Risk Items are those that are generated, caused, or controlled exclusively outside the PDT's sphere of influence.)
There are currently several competing projects that may There are other contemplated major projects happening
Market Conditions (saturated draw contractors away from this project and onto others, potentially simultaneously. This could significantly affect
PR-2 construction market) limiting the field of prospective bidders. costs. Unlikely Significant Moderate $947 K Unlikely Marginal Low Not Studied Triangular Cost Engineering Contract Cost
There is a concern that the rise in costs could price the If this concern became reality, the project would not occur. Occurrence Occurrence
Political Factors Change at project out of the ecosystem restoration business line's This item likely will not be studied in the analysis, as if it would prevent would prevent
PR-4 Federal, State, or Local Level ability to execute. occurs, the project will not occur. Likely Significant High the project Likely Significant High the project N/A Project Manager Project Cost & Schedule
Hydropower development is being considered in the Fewer fish will use the fishway for migration if they can't Occurrence Occurrence
spillway which may change the flow patterns that attract find the entrance. Entrainment mortality from hydropower would prevent would prevent
PR-5 Hydropower fish to the fishway entrance. generation would negatively affect fish populations. Likely Significant High the project Likely Significant High the project N/A C-3 Project Manager Project Cost & Schedule
Stakeholders could choose to strip the adaptive If this concern became reality, the project would not occur. Occurrence Occurrence
Stakeholders choose cost or time management component, or change certain features such This item likely will not be studied in the analysis, as if it would prevent would prevent
PR-6 over quality that project assumptions are no longer valid. occurs, the project will not occur. Likely Significant High the project Likely Significant High the project N/A Project Manager Project Cost & Schedule
*Likelihood, Impact, and Risk Level to be verified through market research and analysis (conducted by cost engineer).
1. Risk/Opportunity identified with reference to the Risk Identification Checklist and through deliberation and study of the PDT.
2. Discussions and Concerns elaborates on Risk/Opportunity Events and includes any assumptions or findings (should contain information pertinent to eventual study and analysis of event's impact to project).
3. Likelihood is a measure of the probability of the event occurring -- Very Unlikely, Unlikely, Moderately Likely, Likely, Very Likely. The likelihood of the event will be the same for both Cost and Schedule, regardless of impact.
4. Impact is a measure of the event's effect on project objectives with relation to scope, cost, and/or schedule -- Negligible, Marginal, Significant, Critical, or Crisis. Impacts on Project Cost may vary in severity from impacts on Project Schedule.
5. Risk Level is the resultant of Likelihood and Impact Low, Moderate, or High. Refer to the matrix located at top of page.
6. Variance Distribution refers to the behavior of the individual risk item with respect to its potential effects on Project Cost and Schedule. For example, an item with clearly defined parameters and a solid most likely scenario would probably follow a triangular or normal distribution. A risk item for which the PDT has little data or probability
of modeling with respect to effects on cost or schedule (i.e. "anyone's guess") would probably follow a uniform or discrete uniform distribution.
7. The responsibility or POC is the entity responsible as the Subject Matter Expert (SME) for action, monitoring, or information on the PDT for the identified risk or opportunity.
8. Correlation recognizes those risk events that may be related to one another. Care should be given to ensure the risks are handled correctly without a "double counting."
9. Affected Project Component identifies the specific item of the project to which the risk directly or strongly correlates.
10. Project Implications identifies whether or not the risk item affects project cost, project schedule, or both. The PDT is responsible for conducting studies for both Project Cost and for Project Schedule.
11. Results of the risk identification process are studied and further developed by the Cost Engineer, then analyzed through the Monte Carlo Analysis Method for Cost (Contingency) and Schedule (Escalation) Growth.
Project Scope
Contingency on Base Estimate 80% Confidence Project Cost
Baseline Estimate Cost (Most Likely) -> $40,014,944
This project consists of constructing a debris boom upstream of the dam
Baseline Estimate Cost Contingency Amount -> $13,741,700
spillway and installing a temporary coffer dam around the construction area
to dewater the bridge and spillway notch construction zones for the fish Baseline Estimate Construction Cost (80% Confidence) -> $53,756,644
passage. A prefabricated concrete bridge is planned to extend across the
notch in the spillway; and, will include a stop log water control structure and Contingency on Schedule 80% Confidence Project Schedule
improved roadway access to the lock and dam storage yard. The fish Project Schedule Duration (Most Likely) -> 46.0 Months
passage ramp and riffle structure is constructed of rock materials and will Schedule Contingency Duration -> 29.3 Months
also incorporate hydraulic dredging operations to use dredge spoil to fill
Project Schedule Duration (80% Confidence) -> 75.3 Months
voids in the large rock materials of the fishway.
Project Schedule Contingency Amount (80% Confidence) -> $2,111,954
This is a 100% Federal project and no lands and damage costs are included.
No relocation costs were expected for this project. Project Contingency 80% Confidence Project Cost
Project Contingency Amount (80% Confidence) -> $15,853,654
Project Contingency Percentage (80% Confidence) -> 40%
65%
80%
0%
5%
10%
20%
25%
30%
35%
40%
45%
50%
55%
60%
70%
75%
85%
90%
95%
100%
95% $59,268,192 48.12% ###
100% $67,240,463 68.04% ###
Confidence Levels
Contingency Analysis BASELINE ESTIMATE CONTINGENCY DEVELOPMENT (Does not Include Escalation)
Most Likely
$40,014,944
Cost Estimate
at 80% Confidence
30% $48,517,176 21.25% ### Corresponding Contingency Level
60,000,000 Amount
35% $49,044,633 22.57% ###
40% $49,586,489 23.92% ###
45% $50,090,006 25.18% ###
50% $50,584,341 26.41% ###40,000,000
55% $51,083,142 27.66% ###
60% $51,542,773 28.81% ###
65% $52,025,214 30.01% ###
70% $52,543,790 31.31% ###20,000,000 "Most Likely"
Baseline Cost
75% $53,088,118 32.67% ###
80% $53,756,644 34.34% ###
85% $54,430,091 36.02% ###
90% $55,298,936 38.20% ### 0
50%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
Contingency Analysis
Most Likely
46.0 Months
Cost Estimate Schedule Contingency (Duration) Analysis
Duration
25% 60.9 Months 32.27% 64 Project Duration at
100 80% Confidence
30% 62.3 Months 35.36% 64 Level
Corresponding Variance
35% 63.6 Months 38.20% 64 Duration
80
40% 64.9 Months 40.94% 64
45% 66.1 Months 43.63% 64
50% 67.3 Months 46.24% 64 60
55% 68.6 Months 49.02% 64
60% 69.9 Months 51.87% 64 40
65% 71.2 Months 54.69% 64
70% 72.5 Months 57.49% 64 Current Project
75% 73.8 Months 60.29% 64 20 Duration
65%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
70%
75%
80%
85%
90%
95%
100%
95% 82.5 Months 79.31% 64
100% 98.4 Months 113.78% 64 Confidence Levels
Contingency Analysis
Most Likely
$40,014,944 Schedule Contingency (Amount) Analysis
Cost Estimate
Level
Corresponding Schedule
35% $1,316,148 3.29% ### Contingency
###$44,000,000
Amount
40% $1,401,568 3.50%
45% $1,485,617 3.71% ###$42,000,000
50% $1,567,351 3.92% ###
55% $1,654,105 4.13% ###$40,000,000
60% $1,743,263 4.36% ###$38,000,000
65% $1,831,324 4.58% ###
70% $1,918,726 4.80% ###$36,000,000
75% $2,006,287 5.01% ###$34,000,000
80% $2,111,954 5.28% ### "Most Likely"
$32,000,000 Baseline Cost
85% $2,235,411 5.59% ###
90% $2,373,524 5.93% ###$30,000,000
10%
45%
80%
0%
5%
15%
20%
25%
30%
35%
40%
50%
55%
60%
65%
70%
75%
85%
90%
95%
100%
Variance Correlation
Risk No. Risk/Opportunity Event Discussion and Concerns Likelihood* Impact* Risk Level* Distribution to Other(s) Low Most Likely High Low Most Likely High Percentages are calculated as the
variance from the assumption value to
facilitate iteration of the model should
Internal Risks (Internal Risk Items are those that are generated, caused, or controlled within the PDT's sphere of influence.) the cost values change throughout the
project phases. Uniform distribution
percentages reflect variation from the
PROJECT & PROGRAM MGMT total project cost.
CONTRACT ACQUISITION
TECHNICAL
ENVIRONMENTAL/REGULATORY
CONSTRUCTION
COST ESTIMATING/ENGINEERING
There is a concern that the rise If this concern became reality, the
in costs could price the project project would not occur. This item This Risk Item is not being
out of the ecosystem likely will not be studied in the quantitatively studied.
Political Factors Change at restoration business line's analysis, as if it occurs, the project Occurrence would prevent the
PR-4 Federal, State, or Local Level ability to execute. will not occur. Likely Significant High project.
Contingency Contingency
Percentile Forecast values
TOTAL PROJECT Amount %
SCHEDULE 0% 35.7 Months -10.3 Months -22.36%
(BASELINE) 5% 52.1 Months 6.1 Months 13.25%
10% 55.3 Months 9.2 Months 20.08%
15% 57.4 Months 11.4 Months 24.72%
20% 59.2 Months 13.2 Months 28.62%
25% 60.9 Months 14.9 Months 32.27%
30% 62.3 Months 16.3 Months 35.36%
35% 63.6 Months 17.6 Months 38.20%
40% 64.9 Months 18.8 Months 40.94%
45% 66.1 Months 20.1 Months 43.63%
50% 67.3 Months 21.3 Months 46.24%
55% 68.6 Months 22.6 Months 49.02%
60% 69.9 Months 23.9 Months 51.87%
65% 71.2 Months 25.2 Months 54.69%
70% 72.5 Months 26.5 Months 57.49%
75% 73.8 Months 27.7 Months 60.29%
80% 75.3 Months 29.3 Months 63.68%
85% 77.1 Months 31.1 Months 67.63%
90% 79.2 Months 33.2 Months 72.05%
95% 82.5 Months 36.5 Months 79.31%
100% 98.4 Months 52.4 Months 113.78%
39920822.796
47879342.361
49755944.601
51175947.967
52391087.8
53436537.928
54404040.843
55369007.171
56296401.168
57191455.73
58057715.8
58993474.558
59931683.628
60897196.228
61940032.855
62894655.254
63994740.82
65225732.27
66720886.435
68882273.726
77260091.279
Sample (Feasibility Phase/Recommended Plan) - Schedule Risk Analysis
Estimated Total Project Cost (Price Level) $40,014,944
Max. Anticipated Annual Amount $10,439,613
Enter Current OMB Escalation Rate 2.06%
Enter Current Project Location Escalation Rate 2.14%
Enter Assumed Hotel Rate 7.50%
Notes: This item captures the risk that the schedule will significantly vary due to its preliminary
nature.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 6 months.
High High assumes that the worst case is that the schedule could increase by up to 9 months
(approximately 20%).
Notes: This item captures the risk that the limited control over assigned staff resources could
cause delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that competition for funding with other priorities and projects
could cause delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High High assumes that the worst case is that the schedule could increase by up to 9 months
(approximately 20%).
Notes: This item captures the risk that product coordination and communication challenges could
impact the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 2 months.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that losing staff at critical project milestones could cause
delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 3 months.
Notes: This item captures the risk that the inability to obtain timely decisions could cause delays
to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 6 months.
Notes: This item captures the risk that losing staff at critical project milestones could cause
delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could decrease by up to 9 months
(approximately 20%).
High High assumes that the worst case is that the schedule would not vary from the baseline
schedule.
Notes: This item captures the risk that the lack of contract acquisition planning could cause
significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 6 months.
High High assumes that the worst case is that the schedule could increase by up to 9 months
(approximately 20%).
Notes: This item captures the risk that the uncertainty with the current riffle design could cause
significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 3 months.
High
High assumes that the worst case is that the schedule could increase by up to 3 months.
Notes: This item captures the risk that delays in obtaining necessary permits could cause
significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 2 months.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that challenges in obtaining the water quality permit could
cause delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that the nature of performing in-water work, specifically with the
cofferdam, could cause significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 2 months.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that the eventual contractor could be more or less efficient than
contemplated, causing significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 4 months.
High
High assumes that the worst case is that the schedule could increase by up to 6 months.
Notes: This item captures the risk that conflicts with other contractors performing non-related
projects (notably hydropower) could cause significant variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 2 months.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Risk Refer No. Risk Event Low Most Likely High Removed from Risk Study - This item is captured by the
C-6 Material availability and delivery Cost Risk Study
Sample (Feasibility Phase/Recommended Plan) - Schedule Risk Analysis
Notes: This item captures the risk that contract sequencing challenges could cause significant
variance in the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is that the schedule could improve by up to 3 months.
High
High assumes that the worst case is that the schedule could increase by up to 6 months.
Notes: This item captures the risk that uncertainty regarding timing and results of multiple review
processes could result in delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Notes: This item captures the risk that a 10-year flood event could result in delays to the
schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 4 months.
Assumption: Flooding
Percentile Assumption values
0% 0.0 Months
10% 0.4 Months
20% 0.8 Months
30% 1.2 Months
40% 1.6 Months
50% 2.0 Months
60% 2.4 Months
70% 2.8 Months
80% 3.2 Months
90% 3.6 Months
100% 4.0 Months
Sample (Feasibility Phase/Recommended Plan) - Schedule Risk Analysis
Notes: This item captures the risk that challenges in receiving adequate incremental funding
outlays in a timely manner could result in delays to the schedule.
Likely Likely assumes no variance from baseline schedule.
Low Low assumes that the best case is no variance from baseline schedule.
High
High assumes that the worst case is that the schedule could increase by up to 6 months.
Risk Refer No. Risk Event Low Most Likely High This Risk Item is not being quantitatively studied.
PR-5 Hydropower Occurrence would prevent the project.
Sample (Feasibility Phase/Recommended Plan) - Schedule Risk Analysis
Risk Refer No. Risk Event Low Most Likely High This Risk Item is not being quantitatively studied.
PR-6 Stakeholders choose cost or time over quality Occurrence would prevent the project.
Risk Analysis
Concrete Demolition TV #3 Shaft (Incl. Setting bulkheads on either side of TV, dewater -15% -10% 15% 30%
5 shaft and culvert (Project pumps are inadequate, extra pumping capacity will be required)) $ 299,713 $ 317,344 $ 352,604 $ 405,495 $ 458,385
6 Concrete Demolition Monolith 8 and Monolith 27 $ 72,669 $ 76,706 $ 80,743 $ 92,854 $ 100,929 -10% -5% 15% 25%
7 Plug Rock Drain Pipe and French Drain $ 1,225 $ 1,293 $ 1,361 $ 1,701 $ 2,042 -10% -5% 25% 50%
8 Repair Concrete and Cracks in elevation 263 Gallery $ 29,379 $ 31,011 $ 32,643 $ 48,965 $ 65,286 -10% -5% 50% 100%
9 Replace Monolith 6 uplift Pressure Instruments $ 11,751 $ 12,404 $ 13,057 $ 19,586 $ 26,114 -10% -5% 50% 100%
10 Drill Flow Breccia Consolidation Grout Holes and Rock Drain Abandonment Holes $ 369,780 $ 462,225 $ 616,300 $ 770,375 $ 924,450 -40% -25% 25% 50%
11 Flow Breccia Consolidation Grouting and Rock Column Drain Grouting $ 1 $ 1 $ 1 $ 2 $ 2 -10% -5% 50% 100%
Epoxy Grout TV Shaft #3, Monoliths 8 and 27 Bulkhead Slots (incl. Epoxy surface patching,
-10% -5% 15% 35%
12 installing 6' grout tubes, and epoxy grouting) $ 59,493 $ 62,798 $ 66,103 $ 76,018 $ 89,239
13 Grout Monoliths 6, 8, and 27 Lock Chamber Cracks and Lift Lines $ 221,802 $ 234,125 $ 246,447 $ 283,414 $ 332,703 -10% -5% 15% 35%
14 Install Post-tensioned Anchors elevation 170' and below $ 1,642,562 $ 1,564,345 $ 1,564,345 $ 1,955,431 $ 2,190,083 -5% 0% 25% 40%
15 Install Post-tensioned Anchors elevation above 170' $ 1 $ 1 $ 1 $ 2 $ 2 -10% -5% 50% 100%
Install Tainter Valve Shaft #3 Pre-Cast Concrete Panels (incl. Panel fabrication, drilling and -15% -10% 20% 30%
16 grouting dowels, and grouting behind panels) $ 330,918 $ 350,384 $ 389,315 $ 467,178 $ 506,110
Repair Monolith 6 Concrete Spall Area (Incl. Demo, drilling and grouting dowels,
-15% -10% 20% 30%
17 reinforcement, new cnc.) $ 124,482 $ 131,804 $ 146,449 $ 175,739 $ 190,384
18 Repair Monolith 27 Bulkhead Slot Concrete Spalls $ 32,412 $ 32,412 $ 32,412 $ 48,618 $ 64,824 0% 0% 50% 100%
Braced Excavation (incl. Contractor design, excavation, dewatering, anchor block
-15% -5% 25% 40%
19 fabrication, backfill, piezometer cable rerouting) $ 316,563 $ 353,806 $ 372,427 $ 465,534 $ 521,398
Load Cells and Strain Gages (incl. Wire routing in to be constructed slots in lock face, and
-10% -5% 25% 40%
20 terminus) $ 110,343 $ 116,473 $ 122,603 $ 153,254 $ 171,644
Drain Line Installation (incl. Drilling from within brace excavation, open excavation behind
-15% -10% 30% 40%
21 most of lock, MH's and weirs, drilling at D/S to terminus) $ 120,329 $ 145,446 $ 161,607 $ 184,032 $ 198,188
Pave Embankment Dam Access Road (incl. Subgrade prep, line stripes, Guard Rail
-10% -5% 30% 50%
22 Replacement). $ 7,601 $ 8,024 $ 8,446 $ 10,980 $ 12,669
23 Services of Skilled Craftsmn $ 14,598 $ 15,409 $ 16,220 $ 17,842 $ 18,653 -10% -5% 10% 15%
24 Temp Demob & Remob $ 51,054 $ 54,057 $ 60,063 $ 72,076 $ 78,082 -15% -10% 20% 30%
25 Standby for Temp Demob $ 108,113 $ 114,120 $ 120,126 $ 138,145 $ 150,158 -10% -5% 15% 25%
26 Tainter Valve Wrapper $ 77,180 $ 81,720 $ 90,800 $ 108,960 $ 118,040 -15% -10% 20% 30%
27 TV Weld Repair [9/16 cjp] $ 85,000 $ 95,000 $ 100,000 $ 120,000 $ 130,000 -15% -5% 20% 30%
28 TV Weld Repair [3/8 fill] $ 42,500 $ 47,500 $ 50,000 $ 60,000 $ 65,000 -15% -5% 20% 30%
Weather and other jobsite conditions $ - $ - $ 200,000 $ 500,000 $ 200,000 $ 500,000
Overall Job (Bidding Climate) $ (300,000) $ (100,000) $ - $ 100,000 $ 300,000 $ (300,000) $ (100,000) $ 100,000 $ 300,000