Daily Progress Report

Chiange Length
S.NO Date Remark
(Rmt).
From To
Foundation work is
1 207+143 207+116 27 8/1/2021
completed

2 207+320 207+168 152 8/1/2021 Foundation work is


completed
Excavator Reading
Chiange Reading Total
S.NO Date Remark
From To From To Reading

Foundation work is
1 207+143 207+168 1261.20 1264.8 3.60 8/1/2021
completed
MREPL Signatory AG Imrat Signatory
Material Reconcilation Sheet
Work done By
contractor Material Record

Exumptio
Consumption Factor Theoretic n under
Sr.No Material Work description al
Unit Qty. per unit tollerence
Consump
tion Limit @
3% (+/-)

Bags per
R.R Masonry(1:6) Cum 840.00 1.65 1386 42
cum
1 Cement
Bags per
P.C.C(1:4:8) Cum 14.90 3.4 51 1.53
cum
Qtl. per
R.R Masonry(1:6) Cum 840.00 5.66 4754 143
cum
2 Stone Dust
Qtl. per
P.C.C(1:4:8) Cum 14.9 7.95 118 4
cum
Qtl. per
R.R Masonry(1:6) Cum 0 0 0 0
cum
3 Aggregate
Qtl. per
P.C.C(1:4:8) Cum 0 15.06 0 0
cum
Total amount against material consumed for w
Total Amou
et
aterial Record Financial Impact

Net
balance Rate Amount
qty.

1394 400 557556.00

4611 100 461100.00

114 100 11400.00

0 100 0

0 100 0.00

gainst material consumed for work 1030056.00


Total Amount 1030056.00