Professional Documents
Culture Documents
CB 712 – E
By
Dr. Emad Fayez Gaid
Course Objectives
Introduction to
Cost Engineering/Estimating Profession
and Types of Cost
Cost is the value of an activity or asset. Generally, this value is determined by the
cost of the resources that are expended to complete the activity or produce the
asset. Resources used are categorized as equipment, labor, material, and others.
Although money and time are sometimes thought of as resources, they only
implement and/or constrain the use of the physical resources previously listed.
17/4/2021 Project Cost Engineering -CB 712-E -Dr. Emad Fayez 7
Introduction
The Project Triangle or Iron Triangle expresses the Triple Constraint of time,
cost and quality or scope that must be managed in project delivery. Each
constraint is connected and moving one point of the triangle will impact the other
two points.
Direct costs are those resources that are expended solely to complete the
activity or asset. In other words, “Any cost that is precisely identified with
a final cost objective, but not necessarily limited to items that are
incorporated in the end product as material, equipment or labor. Thus, the
direct cost of a foundation for a house includes trenching for the footings,
the wooden forms (depreciation), the concrete, and the labor to place and
finish the concrete. Direct costs for making a metal work include the scrap
from the stamping process, less any salvage value.
Indirect costs are those resources that need to be expended to support the
activity or asset but are also associated with other activities and assets. In
other words, “Any cost not directly identified with a single final cost
objective but identified with two or more final cost objectives.
Indirect costs also may be referred to as site overhead costs. Indirect costs
include general administrative activities associated with operating the
business, costs for providing and maintaining field equipment or a
manufacturing facility, and expenses for utilities, mobilization and
demobilization, site installations.
Fixed costs are those cost elements that must be provided independent of
the volume of work activity or asset production that they support. These
can be either direct or indirect costs. Fixed costs often include rent,
buildings, machinery, etc. The tools are an indirect fixed cost only if they
are owned. If they are leased or provided as part of the labor charge, they
would fall into a different classification.
Variable costs are those cost elements that must be provided and are
dependent on the volume of work activity or asset production that they
support. Variable costs are costs that vary with output. Generally variable
costs increase at a constant rate relative to labor and capital. Variable costs
may include wages, utilities, materials used in production, etc. Again, these
can be either direct or indirect costs.
In small scope projects cost estimating and budgeting are very closely
linked and considered as a single process that can be performed by a single
person.
17/4/2021 Project Cost Engineering -CB 712-E -Dr. Emad Fayez 18
Cost Estimating
summed to estimate the cost of the WBS work element. Costs are then
usually rolled up to estimate the total project cost in a manner like bottom-
estimated and rolled up, thus this method provides higher accuracy as
Pre-tendering Stage
Estimates in the pre-tendering stage are usually conducted for the owner
by owner’s staff and/or the consultant. With the initial stages of the
project, the owner needs to conduct a feasibility study and set a budget for
the project, even before any schematic designs are prepared. Conceptual
Tendering Stage
complete and submit a bid for the project, where a Detailed estimate
prepared.
Construction Stage
construction.