Project Log
Project Name : Smart Parking System
Begin Date: 19/1/2021
Target Ending Date:26/1/2021
Scheduled Actual Task Action List Initial
19/1/2021 21/1/202 19/1/202 20/1/2021 Start to design the model of Finish earlier
1 1 system
Give solutions
Meeting
22/1/2021 24/1/202 22/1/202 23/1//202 Present Idea We spend 2-3
1 1 1 Get feedback from partner and days to make
customer interview and
Choose methods the develop survey. By
Ready to design using Google
form which is
useful tool to
help us collect
survey fsater
24/1/2021 26/1/202 24/1/202 26/1/2021 Meeting On time
1 1 Choose method to design
Testing & QA
25/1/2021 26/1/202 25/1/202 27/1/2021 Writng report Later than 1
1 1 day
Project Log
Project Name : Smart Parking System
Begin Date: 27/01/2021
Target Ending Date: 04/01/2021
Scheduled Actual Task Action List Initial
27/01/202 29/01/2021 27/01/202 29/01/2021 Meeting, review requirement On time
1 1 Test Plannning
Project Log
Project Name : Smart Parking System
Begin Date: 04/02/2021
Target Ending Date:08/02/2021
Scheduled Actual Task Action List Initial
4/2/2021 6/2/2021 4/1/2021 5/2/2021 Meeting On time
Review Testing
6/2/1/2021 8/2/2021 6/2/2021 7/2/2021 Make second survey We spend 2-3
Collect information days to make a
Evaluation survey survey about
new features.
By using
Google form
which is useful
tool to help us
collect survey
faster and
easier
7/2/2021 8/2/2021 7/2/2021 8/2/2021 Writing report On time
Project Log
Project Name : Smart Parking System
Begin Date: 22/02/2021
Target Ending Date:01/03/2021
Scheduled Actual Task Action List Initial
22/02/202 24/02/2021 22/02/202 23/02/2021 Change requirement Finish earlier
1 1 ( Includes add and remove
few functions)
Meeting
24/02/202 27/02/2021 24/02/202 27/02/2021 Test Planning Finish on time
1 1 Develop ( add and remove
few functions)
Analysis and evaluation test
result
27/02/202 28/02/2021 27/02/202 28/02/2021 Get feedback from partner FINISH ON
1 1 and customer TIME
28/02/202 01/03/2021 28/02/202 02/03/2021 Writing report FiNISH LATER
1 1 DUE TO STAFF
SUBMITTED
LATE
Project Log
Project Name : Smart Parking System
Begin Date: 02/03/2021
Target Ending Date:10/03/2021
Scheduled Actual Task Action List Initial
02/03/202 04/03/2021 02/03/202 04/03/2021 Test all requirements Fnish on time
1 1 Meeting
05/03/202 08/03/2021 05/03/202 08/03/2021 Analysis and evaluation Party on
1 1 result women’s day
Set up and installing in small (08/03/2021)
areas
Trial and get feedback
09/03/202 10/03/2021 09/03/202 10/03/2021 Submit report (Summary Finish on time
1 1 project plan and result
Finish project