Project Log

Project Name : Smart Parking System


Begin Date: 11/1/2021
Target Ending Date:18/1/2021
Scheduled Actual Task Action List Initial
11/1/2021 12/1/202 11/1/202 12/1/202  Identify problems ( All staffs and Finding
1 1 1 manager hava meeting) information is
 Collect , research data and quite difficult
information because this is
a new field to
us
We fnish it on
time

12/1/2021 15/1/202 12/1/202 15/1/202  Setting question, objectives, We spend 2-3


1 1 1 ready to survey days to make
 Ready to interview with specific interview and
objective survey. By
using Google
form which is
useful tool to
help us collect
survey fsater
15/1/2021 17/1/202 15/1/202 17/1/202  Analysing and evaluation survey On time
1 1 1  Meeting
 Choosing study to design
 Synthesize information
18/1/2021 18/1/202 18/1/202 18/1/202  Writng report On time
1 1 1

Project Log
Project Name : Smart Parking System
Begin Date: 19/1/2021
Target Ending Date:26/1/2021
Scheduled Actual Task Action List Initial
19/1/2021 21/1/202 19/1/202 20/1/2021  Start to design the model of Finish earlier
1 1 system
 Give solutions
 Meeting
22/1/2021 24/1/202 22/1/202 23/1//202  Present Idea We spend 2-3
1 1 1  Get feedback from partner and days to make
customer interview and
 Choose methods the develop survey. By
 Ready to design using Google
form which is
useful tool to
help us collect
survey fsater
24/1/2021 26/1/202 24/1/202 26/1/2021  Meeting On time
1 1  Choose method to design
 Testing & QA
25/1/2021 26/1/202 25/1/202 27/1/2021  Writng report Later than 1
1 1 day

Project Log
Project Name : Smart Parking System
Begin Date: 27/01/2021
Target Ending Date: 04/01/2021
Scheduled Actual Task Action List Initial
27/01/202 29/01/2021 27/01/202 29/01/2021  Meeting, review requirement On time
1 1  Test Plannning

29/1/2021 01/02/2021 29/1/2021 02/02/2021  Do the test (Unit,Intergration, We spend 3-


Performance,Security) 4 days to do
the test.
Due to IT
staff got
virus Covid-
19 so we
have to
replace
antoher
person

02/02/202 03/02/2021 02/02/202 03/02/20211  Get feedback,update new On time


1 1 feature
03/02/202 04/02/2021 03/02/202 04/02/2021  Regression testing On time
1 1  Writing report

Project Log
Project Name : Smart Parking System
Begin Date: 04/02/2021
Target Ending Date:08/02/2021
Scheduled Actual Task Action List Initial
4/2/2021 6/2/2021 4/1/2021 5/2/2021  Meeting On time
 Review Testing
6/2/1/2021 8/2/2021 6/2/2021 7/2/2021  Make second survey We spend 2-3
 Collect information days to make a
 Evaluation survey survey about
new features.
By using
Google form
which is useful
tool to help us
collect survey
faster and
easier
7/2/2021 8/2/2021 7/2/2021 8/2/2021  Writing report On time

Project Log
Project Name : Smart Parking System
Begin Date: 22/02/2021
Target Ending Date:01/03/2021
Scheduled Actual Task Action List Initial
22/02/202 24/02/2021 22/02/202 23/02/2021  Change requirement Finish earlier
1 1 ( Includes add and remove
few functions)
 Meeting
24/02/202 27/02/2021 24/02/202 27/02/2021  Test Planning Finish on time
1 1  Develop ( add and remove
few functions)
 Analysis and evaluation test
result
27/02/202 28/02/2021 27/02/202 28/02/2021  Get feedback from partner FINISH ON
1 1 and customer TIME
28/02/202 01/03/2021 28/02/202 02/03/2021  Writing report FiNISH LATER
1 1 DUE TO STAFF
SUBMITTED
LATE

Project Log
Project Name : Smart Parking System
Begin Date: 02/03/2021
Target Ending Date:10/03/2021
Scheduled Actual Task Action List Initial
02/03/202 04/03/2021 02/03/202 04/03/2021  Test all requirements Fnish on time
1 1  Meeting
05/03/202 08/03/2021 05/03/202 08/03/2021  Analysis and evaluation Party on
1 1 result women’s day
 Set up and installing in small (08/03/2021)
areas
 Trial and get feedback
09/03/202 10/03/2021 09/03/202 10/03/2021  Submit report (Summary Finish on time
1 1 project plan and result
 Finish project