You are on page 1of 50

Qatar General Electricity & Water Corporation

TENDER NO. GTC 177/2007


Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

APPENDIX

SCOPE OF WORK & SPECIFICATIONS

Tender Documents GTC 177/2007 Page 1 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Table of Contents
1.1 Contract Description and Scope of Works 5
1.2 Time for Completion. 17
1.3 Warranty Period 17
1.4 Material Delivery 17
1.5 Government Published Specifications, Regulations, Notices and Circulars
18
1.6 Copies of Specifications 18
1.7 Soil investigation at Site 18
1.8 Datum Levels 19
1.9 Climatic Conditions on Site 19
1.10 Site for Additional Accommodation 20
1.11 Access to Site 20
1.12 Clearance of Site 20
1.13 Reinstatement of Site after Clearance 21
1.14 Existing Properties, Facilities and Utilities 21
1.15 Use of Public Highways 21
1.16 Permits 21
1.17 Archaeological Remains and Historical Sites 22
1.18 Execution Program of Works 22
1.19 Standard Specifications 22
1.20 Materials and Suppliers of Materials 23
1.21 Natural Materials 23
1.22 Works to be Kept Clear of Water 24
1.23 Discharge of Water in to Existing Streams 24
1.24 Water Supply 24
1.25 Electricity Supply 24

Tender Documents GTC 177/2007 Page 2 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.26 General Hygiene and Medical Examination of Contractor’s Employees and


Labors 25
1.27 Water Supply, Sanitation and First Aid Facilities for Contractor’s Staff 25
1.28 Testing of Works 25
1.29 Contractor’s Site Facilities 26
1.30 Assistance for KAHRAMAA'S Staff 26
1.31 Survey Instruments 26
1.32 Submittals 27
1.33 Progress Reports 27
1.34 Forms for Monthly Statements 27
1.35 Equipment and Labour Returns 27
1.36 Quality of Materials, Workmanship and Tests 27
1.37 Loading Tests for Executed Concrete Structures 28
1.38 Cost of Tests for Materials and Workmanship 28
1.39 Examination of Work Before Covering Up 28
1.40 Uncovering and Making Openings 28
1.41 Removal of Improper Work 29
1.42 Photographs 29
1.43 Progress Meetings 29
1.44 Contract Signboards 30
1.45 Operating and Maintenance Instructions 30
1.46 Drawings for the Project Components 31
1.47 Issued Drawings 31
1.48 Record Documents 32
1.49 Protecting the Works from the Inclement Weather and Damage 33
1.50 Working in Urban Areas 33
1.51 Access to Existing Buildings and Associated Areas 33
1.52 Cleaning the Works on Completion 34

Tender Documents GTC 177/2007 Page 3 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.53 Control of Noise and Pollution 34


1.54 Qatar Petroleum (QP) Pipelines (Gas and others) 34
1.55 Prevention of Impacts on Urban Amenity 34
1.56 Witness Tests 34
1.57 Co-Ordination with Other Contractors 35
1.58 Site Safety Policy 35
1.59 Operation, Maintenance & Training to be provided by the Contractor 37
1.60 Quality Standards and Control 38
1.61 Data for setting out the Works 42
1.62 Temporary Working Areas 42
1.63 Work in Public Highways 42
1.64 Traffic Control 42
1.65 Adjoining Property 43
1.66 Road Closures 43
1.67 Obstructions 43
1.68 Site Roads and Access 43
1.69 Claims for Damage to Persons or Property (Procedure) 43
1.70 Security of the Works 44
1.71 Site to be Kept Tidy 44
1.72 Safety 44
1.73 Offices for KAHRAMAA and KAHRAMAA’S Engineer 45
1.74 Non-Disruptive Pipeline Specification 45
1.75 Works at Road Crossings 50

Tender Documents GTC 177/2007 Page 4 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

SCOPE OF WORKS AND SPECIFICATIONS

1.1 Project Description and Scope of Works


1.1.1- Project Description:
As part of the ongoing developments projects to improve services of supplying
potable water to customers and due to the expected high growth of demand all
over Qatar within coming few years, a group of various replacement and
upgrading works to the water supplying system involving replacement,
upgrading and extensions of some distillate main & rising mains and construction
of new reservoirs at various locations of Doha city, Salwa industrial area and
Messaieed town were merged in the GTC-177 Tender.

1.1.2- Brief Scope of Work:


The scope of this contract is to provide detailed design, supply material &
equipments and construction (erecting, testing and commissioning) of the
contract components details here-under:
• Hydraulic study for piping system provided in this contract including existing
piping linked with new piping.
• Surge & transient analysis for the complete piping system provided in this
contract as well as other related piping.
• New concrete reservoir of 9 million gallon total capacity at reserved space
located inside the existing water site of airport including all necessary works of
piping, electrical, instrument, landscaping, drainage, sewers etc.
• New concrete reservoir of 6 million gallon total capacity at reserved space
located inside existing the water site of Messaieed town including all necessary,
piping, electrical, instrument, landscaping, drainage, sewers etc.
• Replacement of approximately 13.15 kilometers of new 1200 mm distillate
transmission pipeline and associated works chambers from inside RAF-A
desalination plant up to New Salwa reservoirs & pumping station site) along Al
Matar and E-ring roads.
• Extension of approximately 20.5 kilometers of new 1200 mm distillate
transmission pipeline and associated works chambers from proposed
interconnection point to proposed 1200 mm pipe near Abu Hamour R/A along al
Montazah road and up to industrial area including branch line to future site of
"Doha Southwest" reservoirs.
• Extension of approximately 9.0 kilometers of new 900 mm distillate transmission
pipeline and associated works chambers from interconnection point to proposed

Tender Documents GTC 177/2007 Page 5 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

900 mm pipe near Ras Abu Aboud flyover R/A and along old Ras Abu Aboud
road and future Doha express highway to supply Airport RPS.
• Upgrading of approximately 4.8 kilometers of new 900 mm distillate transmission
pipeline and associated works chambers from interconnection point to proposed
900 mm pipe near Abu Hamour R/A along Al Montazah road and up to old Salwa
RPS.
• Replacement and upgrading of approximately 1.5, 6.5 and 13.5 kilometers of new
400, 600 and 900 mm respectively rising mains located inside the industrial area,
zone No.57.

• Fiber optic cables parallel to all new 1200 and 900 distillate mains.

• Provision of flow control system to the new 900 mm distillate inlet supplying Old
Salwa RPS, new 1200 mm distillate inlet supplying new Salwa RPS and new 1200
mm distillate inlet supplying small and medium scale industries reservoirs.

The contractor is required to All required activities shall be performed,


completed in accordance the rules, regulations, restrictions, obligations and
codes of practices of the state of Qatar and to Kahramaa latest Specifications and
Standards.

1.1.3 – Detailed Scope of Work


General
The scope of this contract is to provide detailed design, supply materials &
equipments and construction of the contract components detailed here-after.
The project is primarily composed of construction of new distillate and rising
mains pipelines located south east of Doha, industrial areas and construction of
new concrete reservoirs and installation of internal piping system inside
Reservoir & Pumping station (RPS) of Airport and Messaieed town.
The tender drawings provided by Kahramaa for this contract are indicative and
to be used to assist in pricing as well as providing the main parameters (Data) for
reservoir, pipes, fittings and valves & valve chamber sizes etc. and not to be
used for construction.
The reservoir drawings provided in this tender are for some similar Kahramaa
existing reservoirs and to be used to help contractor in design works and not
necessary to be followed.
The contractor shall use a consultant who is well reputed, professional and
approved by Kahramaa to produce comprehensive detailed design packages for
whole tender components including the pipelines profiles, reservoirs, valve

Tender Documents GTC 177/2007 Page 6 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

chambers, instruments and equipments as well as hydraulic study and surge


analysis reports.
The materials quantities shown on the bills of quantities are minimum required
and to be used for guidance and pricing only. Any materials or equipments not
mentioned in the BOQ's or not adequate but proved to be required to
complete work or to maintain normal operation to Kahramaa satisfaction,
requirements and as per latest standards shall be assumed considered by
contractor in his price and shall be the contractor's responsibility to design,
supply and construct at no additional charge to the contract price.
KAHRAMAA Power Supply:
Power supply for power requirements of new lighting, valves and equipment and
all field instruments, indicators & records required for the new reservoirs of
airport and Messaieed town works and for the flow control system required at
other three reservoirs sites shall be provided from existing panels using spare
feeders. In case spare feeders were not available, modification of existing panel
by adding suitable breakers will be required.

Documents and Drawings


The Contractor shall provide all required details for construction of reservoirs
and chambers and installation of the pipelines and mark them in relevant
drawings in accordance with Kahramaa GIS Specifications (Appendix A). The
required details can be listed but not limited to the followings:

9 Survey of the pipeline routes and produce plan and longitudinal sections for
the pipeline as per Kahramaa Specifications.
9 Specifying the locations of the different chambers and hydrants.
9 Specifying and listing the pipes, fittings & materials required for the project.
9 Locating the existing underground utilities along the pipeline route such as
cables pipes, drainage, poles …etc.
9 Preparing the structural design and calculations for the reservoirs and valve
chambers and thrust blocks.

The Contractor shall provide the following documents and drawings:

a) All administrative documents, correspondence, permits, approvals …etc,


from the authorities for smooth execution of the works.
b) Final approvals for the pipeline routes, road crossings, temporary removal
and/or by-passing of existing facilities along the pipeline route such as
cables pipes, drainage, poles …etc.
c) Working/ shop drawings of the proposed secondary mains including all
valves, fittings, hydrants and service connections…etc.

Tender Documents GTC 177/2007 Page 7 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

d) Reservoirs and Chamber’s working/ shop drawings of the proposed


pipework, meters, valves and support, including structural drawings and bar
bending schedules.
e) Confirm soil bearing strength and thrust block dimensions, provide final
thrust blocks drawings and details.
All new or modified drawings and documentation shall be submitted to
Kahramaa’s Representative for an approval prior to installation.
Documentation and Drawings required for the project components shall be as
specified in Clauses 1.46 & 1.47 of Appendix ‘A’ and Appendix ‘F’ of the Tender
Documents.

Supply & Installation of Pipework


The Contractor shall supply from approved manufacturers, deliver to Site, install,
test and commission all proposed pipes, fittings, couplings, valves, pipe
markers, etc.
The Contractor shall comply with the requirements of the Scope of Works, BOQ,
Contract Drawings, Project Particulars and Standard Specifications, in addition to
the Government Published Specifications, Regulations, Notices and Circulars as
listed in Clause 1.5 of Appendix ‘A’ of the Tender Documents.
Valves, pipework and accessories shall be installed in the position provided/
agreed for such arrangements.
For isolation purposes, Butterfly valves shall be used for 400mm and above,
Sluice/gate valves shall be used for diameters less than 400mm.
All pipework shall be suitably jointed, positioned and supported to withstand the
maximum test pressure as specified and shall be easily dismantled for
maintenance work. All pipe work shall be of ductile iron with PN 16 rating.
The Contractor shall confirm the centre lines and invert levels of the proposed
pipe work and pipe in the trench before jointing and produce working/shop
drawing for approval to Kahramaa prior to pipe work and valves order.
The Contractor shall supply, construct and test all valve chambers and hydrants
required for the optimum operating conditions of the networks system as
specified and to Kahramaa satisfaction.

Detailed Scope:
1.1.3.1 New reservoir at Airport Water Station:
The required works related to construction of the new 9 MIGD reservoir at
airport reservoirs site shall consist but not limited to followings:
1-Conduct geotechnical investigation works to provide complete solid base of
information on the existing soil, and groundwater conditions at the location of

Tender Documents GTC 177/2007 Page 8 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

new reservoir and provide engineering recommendations to perform the


design for the new reservoir. The soil investigation shall be comprised, but not
limited to the drilling of sufficient boreholes to sufficient depth below the
existing ground level, conducting laboratory tests for samples recovered from
the boreholes to determine the characteristics of the soil and rock in the project
area and submit the detailed program with the different activities of the field
work and laboratory tests to Kahramaa for review and approval.
2-Upon end of investigation and finalizing the design criteria, contractor shall
prepare detail design for the new reservoir, associated chambers and piping
including but not limited to all required, reports calculations, and detail
construction drawings for the reservoir and its related structural, civil,
electrical, instrument and mechanical works.
The exact location and size of reservoir, valve chambers and lagoon provided
in the tender drawings are approximate and not final and shall be determined
during detail design stage and after verifying under ground existing services
and conducting all tests, report and verifications for the best location for the
new reservoir.
3-Construction works for one (1) x 9 million gallon capacity reservoir of cast in-
situ reinforced concrete structure and associated chambers. The Height of
reservoir shall be 5.5 meters or equivalent to existing reservoirs heights and
divided into three equal separate compartments. Each compartment shall have
its own inlet, outlet, and washout and overflow connection pipes and chambers.
The work shall be including also, installation and commissioning of all required
mechanical, electrical and instrumentation equipments. Drain collection system
shall be constructed toward lagoon.
As the old and new reservoirs outlet pipes will be connected together to supply
pumps, the Contractor shall make sure that the top and low water levels of both
reservoirs are identical and as a result, the outlet flow from each reservoir shall
be continuous and proportional to the storage capacity of each relevant
reservoir.
The actual operating capacity of new reservoir (water volume from low level to
high level) shall not be less than 8.25 MIG and the contractor shall adhere to
this capacity at all circumstances regardless of reservoir length or width.
The contractor shall include in the design and reservoir construction a provision
of technique to guarantee satisfactory water circulation and avoid water
stagnancy in the reservoir three compartments.
4-Site work related to reservoir construction and including all civil, mechanical,
instrumentation and electrical works like interior roads, paving, lighting, valve
chambers, pipe works, cabling, landscaping, SCADA system and any other
work not mentioned in the scope but deemed necessary to complete the job
according to Kahramaa latest Standards, Specifications and regulations.

Tender Documents GTC 177/2007 Page 9 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

5-Works for Inlet Mains piping to Reservoirs and other piping comprise of
followings:
a- Design, supply materials and construction of approximately 55 meters of
new 600 mm and 140 meters of new 900 mm ductile iron pipes of reservoir
inlet piping inside the fenced area from tie-in point at existing 900 mm pipe
up to new reservoir inlet chambers as shown on Tender drawing no.
56/05/01 & drawing no TED-HWC-021 along with all required fittings,
valves, instruments and chambers and as per tender documents.
b- Design, supply and construct hydraulically actuated and full automatic flow
control valve on the new inlet line to new reservoir capable of being
controlled locally and remotely from control building and complying with
SCADA requirements.
The flow control valve shall be easy to use, maintenance free and able to
control inlet flow capacity over wide range of flow values at fixed pressure.
The selection of required flow control valve shall be developed during
design stage.
c- Design, supply material and construction of all required chambers of flow
meter with by pass valve, flow control valve, interconnection and isolation
as shown in details on tender drawings No. TED-HWC-017 and associated
bill of quantities.
6- Design, supply materials and construction of approximately 65 meters of new
600 mm and 140 meters of new 900 mm ductile iron pipes of outlet piping from
new reservoir outlet chambers and up to existing 700 mm suction header
located outside the pump house as shown on tender drawing No . TED-HWC-
021
7-Installation of pressure transmitters :( 0-10) bar on main 900 mm inlet pipe and
(0-2) bar on 900 main outlet pipe to monitor pipelines pressures.
8-Miscelinious works:
Along with construction of new 9 MIGD reservoir and associated piping at
airport, the following normal works should be also there:
a- Landscaping around new reservoir to Kahramaa satisfaction, requirements
and approval and shall be consisting of following:
a1)-Soft landscaping: includes plantation and complete irrigation system all
around new reservoir.
a2)-Hard landscaping: as per tender drawings and to Kahramaa satisfaction
includes:
a2.1- Asphalting required roads around new reservoirs.
a2.2- Pavement and interlocks around new reservoir.
b- Electrical lighting for all new asphalt roads around lagoon and reservoir,

Tender Documents GTC 177/2007 Page 10 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

c- New lagoon provided with boreholes, hand rail, concrete to protect walls
slope etc. as specified in tender documents.
d- All additional necessary works required during pipelines connection like
shutdowns, isolating, cutting and abandoned in place of existing piping,
temporary supply, dewatering etc.
e- Design, supply materials and install all vital instruments, cables, sampling
and pressure transmitters to monitor the incoming water pressure, flow and
chemical conditions and integration in the telemetry and local control
system of the added new facilities (reservoir, valves etc.) to the Water
SCADA System.
f- Perform all necessary Modification to all the existing monitoring and control
equipments, facilities and accessories available in the airport control room
(mimic panel, enunciator, control desk, software's etc.) to allow for
incorporating the new facilities added in the station control and mentoring
system.

1.1.3.2 New reservoir at Messaieed town Water Station:


The required works related to construction of the new 6 MIGD reservoir shall
consist but not limited to followings:
1- Conduct geotechnical investigation works to provide complete solid base of
information on the existing soil, and groundwater conditions at the location of
new reservoir and provide engineering recommendations to perform the
design for the new reservoir. The soil investigation shall be comprised, but not
limited to the drilling of sufficient boreholes to sufficient depth below the
existing ground level, conducting laboratory tests for samples recovered from
the boreholes to determine the characteristics of the soil and rock in the project
area.
2-Upon end of investigation and finalizing the design criteria, contractor shall
prepare detail design for the new reservoir, associated chambers, piping,
electrical & instruments items including but not limited to all required, reports
calculations, and detail construction drawings for, structural, civil, electrical,
instrument, mechanical works.
The exact location and size of reservoir, valve chambers and lagoon provided
in the tender drawings are approximate and not final and shall be determined
during detail design stage and after verifying under ground existing services
and conducting all tests, report and verifications for the best location for the
new reservoir.
3-Construction works for one (1) x 6 million gallon capacity reservoir of cast in-
situ reinforced concrete structure and associated chambers. The Height of
reservoir shall be 5.5 meters or equivalent to existing reservoirs heights and
divided into two equal separate compartments. Each compartment shall have

Tender Documents GTC 177/2007 Page 11 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

its own inlet, outlet, and washout and overflow connection pipes and chambers.
The work shall be including also, installation and commissioning of all
mechanical, electrical and instrumentation equipments required. Drain
collection system shall be constructed toward lagoon.
As the old and new reservoirs outlet pipes will be connected together to supply
pumps, the Contractor shall make sure that the top and low water levels of both
reservoirs are identical and as a result, the outlet flow from each reservoir shall
be continuous and proportional to the storage capacity of each relevant
reservoir.
The actual operating capacity of new reservoir (water volume from low level to
high level) shall not be less than 5.5 MIG and the contractor shall adhere to this
capacity at all circumstances regardless of reservoir length or width.
The contractor shall include in the design and reservoir construction a
provision of technique to guarantee satisfactory water circulation and avoid
water stagnancy in the reservoir two compartments.
4-Site work related to reservoir construction and including all civil, mechanical,
instrumentation and electrical works like interior roads, paving, lighting, valve
chambers, pipe works, cabling, landscaping, SCADA system and any other
work not mentioned in the scope but deemed necessary to complete the job
according to Kahramaa latest Standards, Specifications and regulations.
5-Works for Inlet Mains piping to Reservoirs and other piping comprise of
followings:
a- Design, supply materials and construction of approximately 90 meters of
new 600 mm and 160 meters of new 900 mm ductile iron pipes of reservoir
inlet piping inside the fenced area from tie-in point to existing 1200 mm
pipe up to new reservoir inlet chambers as shown on Tender drawing no.
92/03/00 and drawing No. TED-HWC-022 along with all required fittings,
valves, instruments and chambers and as per tender documents.
b- Design, supply materials and construction of approximately 140 meter of 600
mm ductile iron of interconnection piping inside the fence area between the
new 900 reservoir inlet described in above item and existing 600 mm pipe
supplying existing reservoir as shown on Tender drawing No. 92/03/00 and
TED-HWC-022 along with all required fittings, valves, instruments and
chambers and per tender documents.
d- Design, supply and construct hydraulically actuated and full automatic flow
control valve on the new 900 mm inlet line to new reservoir capable of
being controlled locally and remotely from control building and complying
with SCADA requirements.
The flow control valve shall be easy to use, maintenance free and able to
control inlet flow capacity over wide range of flow values at fixed pressure.

Tender Documents GTC 177/2007 Page 12 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

The selection of required flow control valve shall be developed during


design stage.
e- Construction of all required chambers of flow meter with by pass valve, flow
control valve, interconnection and isolation as shown in details on tender
drawings No. TED-HWC-017 and associated bill of quantities.
6-Design, supply materials and construction of approximately 120 meters of new
600 mm ductile iron pipe of outlet piping from outlet chambers of new
reservoir and up to existing 900 mm outlet piping from existing reservoir. Both
lines will join to supply existing pumps suction header as shown on Tender
drawing no. 92/03/00 along with all required fittings, valves, instruments and
chambers and per tender documents.
7-Installation of pressure transmitters :( 0-10) bar on main 900 mm inlet pipe and
(0-2) bar on 600 main outlet pipe to monitor pipelines pressures.
8-Miscelinious works:
Along with construction of new 6 MIGD reservoir and associated piping at
airport, the following normal works should be also there:
a-Landscaping around new reservoir to Kahramaa satisfaction, requirements
and approval and shall be consisting of following:
a1)-Soft landscaping: includes plantation and complete irrigation system all
around new reservoir.
a2)-Hard landscaping: as per tender drawings and to Kahramaa
satisfaction includes:
a2.1-Asphalting required roads around new reservoir .
a2.2-Pavement and interlocks around new reservoir.
b- Electrical lighting for all new asphalt roads around lagoon and reservoir,
c- New lagoon provided with boreholes, hand rail, concrete to protect walls
slope etc. as specified in tender documents.
d- All additional necessary works required during pipelines connection like
shutdowns, isolating, cutting and abandoned in place of existing piping,
temporary supply, dewatering etc.
e- Install all vital instruments, cables, sampling and pressure transmitters to
monitor the incoming water pressure, flow and chemical conditions and
integration in the telemetry and local control system of the added new
facilities (reservoir, valves etc.) to the Water SCADA System.
f- Perform all necessary Modification to all the existing monitoring and control
equipments, facilities and accessories available in the airport control room
(mimic panel, enunciator, control desk, software's etc.) to allow for

Tender Documents GTC 177/2007 Page 13 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

incorporating the new facilities added in the station control and mentoring
system.

1.1.3.3 1200/900/600/400 mm pipelines:


The scope of work required by the contractor for the purpose of construction the
new 1200/900/600/400 mm distillate and rising mains indicated in the tender
drawings shall include but not limited to followings:
1-Prepare Comprehensive hydraulic study report for the complete water piping
system in the contract comprising but not limited to: 1200/900/600/400
transmission & rising mains pipes, reservoirs, pumping system, existing and
future pipelines systems connected or to be connected to this contract piping
and to proposed control system of old reservoirs included in this tender.
Contractor shall collect all required information's from all parts. Study shall
include all recommendations and suggestions including technical data for
required equipments necessary to maintain contentious delivery and safe
operation.
Contractor shall be responsible for all design, supply materials and construct of
these equipments.
2-Perform surge & transient analysis for the complete piping system of
1200/900/600/400 mm pipes shown on tender drawings as well as other related
existing and future pipelines systems connected or to be connected to this
contract piping
Contractor shall submit comprehensive reports attached with all required
recommendations and conclusions. The study shall recommend some
equipment to be installed on piping system to protect from surge effects.
Contractor shall be responsible for all design, supply materials and construct of
these equipments.
Upon award of this contract, all existing drawings and available information
useful to carry out above studies shall be handed over to the successful bidder.
3-Perform studies; carry out required tests & laboratories tests, make bore holes,
conduct survey works to determine correct route, pipes profiles and best
locations and quantities for required isolation, air and washout chambers
Based on above study, the contractor shall carry out design works and submit
detail construction drawings of pipeline layout & long section details,
mechanical and structural detail drawings for all civil works including valve
chambers etc for all pipelines indicated in the tender drawings and detailed
below.
4-Supplying materials and constructing of approximately 13150 meters of 1200
mm ductile iron pipes of the distillate transmission line from tie-in point to
existing 1200 mm RL-A distillate pipe located inside Ras Abu Fontas

Tender Documents GTC 177/2007 Page 14 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Desalination Plant and up to the new Salwa reservoirs & pumping station site
along Al Matar road, E-ring road and Al Maathed road. (Refer to tender
drawings no 56/05/00 to 56/05/17) (Tie-in point to new 1200 mm pipe shall be
near RAF-A pump house No. 1 and to be determined later)
5-Supplying materials and constructing of approximately 17200 meters of 1200
mm ductile iron pipes of distillate transmission line from interconnection point
to proposed 1200 mm line done by others near Abu Hamour R/A and along al
Montazah road and 33 street and up to small & medium scale industrial
reservoir & pumping station area located in industrial area.
The work is also including Supplying materials and constructing of
approximately 3350 meters of 1200 mm ductile iron pipes of distillate
transmission line branch from 1200 mm pipe descried in previous item and up
to the proposed site of "Doha SouthWest" reservoirs. (Refer to tender drawings
no 56/06/00 to 56/06/22)
6-Supplying materials and constructing of approximately 4800 meters of 900 mm
ductile iron pipes of distillate transmission line from interconnection point to
proposed 900 pipe done by others near Abu Hamour R/A along al Montazah
road and up to Old Salwa reservoir & pumping station site. (Refer to tender
drawings no 56/05/09, 56/05/11, 56/05/12, 56/05/13 and 56/05/14).
7-Supplying materials and constructing of approximately 8750 meters of 900 mm
ductile iron pipes of distillate transmission line from interconnection point to
proposed 900 mm line pipe done by NDIA project near Ras Abu Aboud flyover
along old RAS Abu Aboud road and future Doha express highway and up to tie-
in to existing 900 mm pipe in Al Matar road (Refer to tender drawings no
48/03/00 to 48/03/10).
8-Supplying materials and constructing of approximately 270 meters of 900 mm
and 280 meter of 600 mm ductile iron pipes near and inside airport water
station site (Refer to tender drawings no 56/05/00RPS)
9-Supplying materials and constructing of approximately 1500 meters of 400 mm
pipes, 6500 meters of 600 mm pipes and 13500 meters of 900 mm ductile iron
pipes of rising mains lines in zone No. 57 located in the east industrial area.
(Refer to tender drawings no 57/04/00 to 57/04/16 and 57/05/00 to 57/05/05).
The works for above pipelines from item 1 to item 9, shall include all required
construction works for all required valve chambers, washouts, air valve based
on study and best pipelines profiles, works for road crossing, thrust blocks,
pipe protections ,pipes cuttings abandoned in place for existing pipelines, etc.
as specified and detailed in tender documents.
10- Design, supply materials and laying of approximately 47800 meters of fiber
optic cable parallel to and in the same trench of the 1200 & 900 distillate lines.
The fiber optic cable installation shall be started from inside the security fence
of RAF-A desalination plant parallel to 1200 mm pipes and new 900 mm

Tender Documents GTC 177/2007 Page 15 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

distillate pipe supplying old Salwa station and parallel to 1200 mm from RAF-B
all the way and up to the control building of new Salwa, Old Salwa, Airport and
Salwa medium & small industries reservoirs& pumping stations sites. The
installation details and materials required shall be per tender drawings and
specifications.( details of fiber optic cable starting point inside plant will be
provided later).
11-Installation of 150mm District Meter and chamber on 150 mm main directly
connected to a 1200mm Distillate as shown in the Tender Drawing No.
56/05/01.

12- Provision of flow control systems:

As the new distillates lines will be connected to the existing inlet piping
supplying reservoirs of new Salwa, old Salwa and small & medium industries, it
will be necessary to provide the followings electromechanical works in order to
allow for controlling amount of flow needed to be delivered by the new distillate
lines to all above mentioned existing reservoirs. These works shall be provided
based on results of hydraulic study included in this tender and after careful study
to the existing supplying and flow controlling systems for these stations:

12.1-Design, supply and construct hydraulically actuated and full automatic flow
control valves on the new 1200,900,1200 distillate inlet lines supplying
existing reservoirs of new Salwa, old Salwa and small & medium scale
industrial reservoirs respectively capable of being controlled locally and
remotely from control building and complying with SCADA requirements.
The Size and performance of these valves shall be based on hydraulic study
results
The flow control valves shall be easy to use, maintenance free and able to
control inlet flow capacity over wide range of flow values at fixed pressure.
The selection of required flow control valves shall be developed during
design stage.
12.2-Design, supply material and construction of all required chambers of flow
meter with by pass valve, flow control valve, and isolation as shown in details
on tender drawings and associated bill of quantities.
12.3-Installation of pressure transmitter (0-10) bar on new distillates supplying
these stations to monitor pipelines pressure
12.4-All additional necessary works required during pipelines connection like
shutdowns, isolating, abandoned in place of existing piping, temporary
supply, dewatering etc.
12.5-Design, supply materials and install all vital instruments, cables, sampling
and pressure transmitters to monitor the incoming water pressure, flow and

Tender Documents GTC 177/2007 Page 16 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

chemical conditions and integration in the telemetry and local control system
of the added new facilities to the Water SCADA System
12.6-Perform all necessary Modification to all the existing monitoring and control
equipments, facilities and accessories available in existing control room of
new Salwa, old Salwa and small & medium scale industrial reservoirs (mimic
panel, enunciator, control desk, software's etc.) if required to allow for
incorporating the new facilities added in the station control and mentoring
system.

1.2 Time for Completion


1.2.1-milestone-1:
The Contractor shall achieve Completion for milestone-1, which is the construction
of the two New reservoirs at airport and Messaieed town RPS's and their associated
pipe works as detailed in sections1.1.3.1 & 1.1.3.2 and as listed in Appendix B (Bill
No. 2,3,4 & 5) within 21 months from effective date of contract.

1.2.2-milestone-2:
The Contractor shall achieve Completion for milestone-2, which is the construction
of all 1200/900/600/400 mm pipelines other than pipe works included in milestone-
1 and provision of flow control system to other stations as detailed in sections
1.1.3.3 and as listed in Appendix B (Bill No. 6 & 7) within 30 months from effective
date of contract.
The liquidated damages for delay in completion shall be applied for each
milestone.

1.3 Warranty Period


All the works executed by the CONTRACTOR shall be under the CONTRACTOR’S
Warranty for Two Calendar Years from the COMPLETION DATE shown on the Taking-
over Certificate(s).

1.4 Material Delivery


Materials delivery procedure shall be carried out in accordance with Article 6 of the
General Conditions of Contract and Appendix "I".
To ensure early start for the Works, the Contractor subject to Kahramaa approval shall
place order for the supply of minimum 60% of the quantities listed in the Schedules of
Prices starting from the Effective Date of contract, and prior to any required survey
works intended to verify the required quantities.

Tender Documents GTC 177/2007 Page 17 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Contractor to ensure that at all times there will be available on Site approved materials
enough for 4 months continuous working.

1.5 Government Published Specifications, Regulations, Notices and


Circulars
The works shall be executed in accordance with the following Government
specifications, regulations, notices and circulars:
1. The General Specification of Main Laying Materials for Waterworks published by
Qatar General Electricity & Water Corporation (KAHRAMAA) latest Version 2005.
2. KAHRAMAA General Specification for Main laying Contracts latest Version.
3. The Qatar Construction Specification (QCS) published by the Ministry of
Municipality Affairs & Agriculture.
4. The Code of Practice and Specification for Road Openings in the Highway.
5. The Guide for Civil Users of Explosives in Qatar.
6. The Survey Manual.
7. The Qatar Traffic Manual.
8. Q.Tel, Electrical Cables relative regulations and standard.
9. The Regulations for the Installation of Electrical Wiring, Electrical Equipment and
.Air Conditioning Equipment.
10. Any current and relevant regulation, notice or circular issued by the Ministry of
Municipality affairs & Agriculture (including the previous Ministry of Public Works
and the previous Ministry of Industry and Public Works), the previous Ministry of
Electricity and Water, or the appropriate local Municipality prior to the date of the
letter of invitation to Tender.

1.6 Copies of Specifications


The Contractor shall be deemed to have his own copy of the Government specifications,
regulations, notices and circulars given at (1) to (10) above.

1.7 Soil investigation at Site


The Contractor shall comply by himself soil investigation along the route of pipelines as
shown in the drawings.
The Contractor shall also carry out a detailed topographic survey of site and shall
prepare a map showing surface levels.

Tender Documents GTC 177/2007 Page 18 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.8 Datum Levels


The Contractor shall establish a benchmark on each site and along the route of
pipelines, and shall be entirely responsible for all levels and settings used by him in the
Works.

1.9 Climatic Conditions on Site


The Conditions under which the plant is required to operate is considered to be tropical
climatic conditions, with excess of heat dust and humidity at time
The Contractor shall take account of the climatic conditions at the site of the works for
the construction of the works.
a. The site conditions shall be assumed to be as follow for tendering purpose:
Maximum ambient temperature 50o C
Minimum ambient temperature 5o C
Design ambient temperature 50o C
Maximum metal temperature under the sun 85o C
Maximum ambient Humidity 100%
Minimum ambient humidity 20%
Design ambient humidity 100%
Design wind velocity 150 km/hr
Yearly rainfall 80-150 mm
b. The temperature is relatively mild from October to May and hot from June to
September.
c. The relative ambient humidity is generally low from October to May and
generally high from June to September.
d. Under certain climatic conditions, considerable condensation may take place.
e. A considerable amount of salt is contained in atmosphere, which together with the
relative high ambient humidity, can produce sever corrosion problems.
f. Distribution and occurrence of rainfall events are very erratic. Rainfall events are
generally of a high intensity with a short duration and usually occur between
December and March.
g. The prevailing wind directions are forming the north and west.

Tender Documents GTC 177/2007 Page 19 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.10 Site for Additional Accommodation


In the event of the Contractor making use of accommodation acquired by him or any tip
for the disposal of surplus materials he shall obtain the written consent of the owner and
occupier or authority having charge of the land in which such way leave accommodation
or tip is situated and shall make a record agreed by the owner, occupier or authority as
aforesaid of the condition of that land before entering thereon.
The Contractor shall permit KAHRAMAA’S Representative and KAHRAMAA’S Engineer
to use for the purpose of the Contract any such special or temporary wayleave or
additional accommodation at no extra cost to KAHRAMAA.
In the event of the Contractor making use of any special or temporary wayleave or
additional accommodation made available to him by the Employer for the purpose of the
Contract the land in which such wayleave or accommodation is situated shall be deemed
to be part of the Site.

1.11 Access to Site


Before the commencement of any part of the Works, the Contractor shall make
temporary access tracks including temporary diversions and bridge works which may
be necessary from time to time to the part of the Site concerned, all to the approval of
KAHRAMAA. The Contractor shall maintain such access tracks in a condition suitable for
the safe and easy passage of plant and vehicles until they are no longer required for the
purpose of the Contract.
The Contractor shall make a record to be agreed by KAHRAMAA of the Conditions of the
surfaces of any private lands or of any public cultivated or maintained lands over which
access to the Site lies before any work is commenced to make them suitable for access
and he shall keep such surfaces in a reasonable state of cleanliness and repair during
the execution of the Works. On the termination of the Contractor’s use of such access he
shall restore the surfaces to a condition at least equal to that pertaining before his first
entry on them. The Contractor shall negotiate such access to the Site over private land as
is required when no alternative access exists.
The Contractor shall not first enter any part of the Site in private lands without the prior
permission of KAHRAMAA, and without first having obtained the consent of the owner of
such lands.

1.12 Clearance of Site


The Contractor shall clear the parts of the Site subsequently to be occupied by the
Works and shall maintain it clear of vegetation.
The Contractor shall not clear the Site of any structure or mature tree without the prior
written permission of KAHRAMAA.
The clearance certificate shall be obtained from the concerned authorities/ Department.

Tender Documents GTC 177/2007 Page 20 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

The material arising from the clearance of the Site shall be the property of KAHRAMAA.
The Contractor shall remove it from the Site and dispose it off in a manner and at a
location to the approval of KAHRAMAA.
The Contractor shall maintain the Site in a neat, tidy, and healthy condition.

1.13 Reinstatement of Site after Clearance


The Contractor shall fill and make good with appropriate materials those cavities and
losses of soil, which result from clearing the parts of the Site not subsequently to be
occupied by the Works.

1.14 Existing Properties, Facilities and Utilities


The Contractor shall locate and notify to KAHRAMAA any existing properties, facilities,
underground or overhead utilities or any other obstructions that shall be encountered
during the execution of the Works. In undertaking this task, the Contractor shall co-
ordinate with utility owners and concerned government departments. In the presence of
KAHRAMAA the Contractor shall co-ordinate with utility owners and concerned
government departments. In the presence of KAHRAMAA the Contractor shall make
records of the position and extent of such properties, facilities, underground or
overhead utilities or any other obstructions.
The Contractor shall protect, uphold, support, temporarily divert and maintain all
existing properties, facilities, underground or overhead utilities or any other
obstructions. The Contractor shall make good any damage due to any cause within his
control at his own expense or pay any costs and charges in connection therewith.

1.15 Use of Public Highways


The Contractor shall ensure that roads and thoroughfares used by him for the
transportation of Constructional Plant, labor and materials are not dirtied as a result of
such transport, and in the event of they becoming thus dirtied in the opinion of
KAHRAMAA, the Contractor shall take all necessary steps to clean them, at no extra cost
to KAHRAMAA.

1.16 Permits
The Contractor shall be responsible for locating any services.
The Contractor shall be fully responsible for obtaining all necessary
excavation permits and permissions, except those normally obtained by the
Employer, prior to commencement of the Works.
These shall include but not limited:

Tender Documents GTC 177/2007 Page 21 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

a. General excavation permits;


b. Specific excavation permits relating to road crossings… etc.
c. Provision of all necessary bonds required by the permits;
d. Permission in respect of erection of site offices, labor camps, stores … etc;
e. Permission for shut down of water pipelines from Water Authorities;
f. Permissions associated with working in proximity to electric and communication
cables, gas lines, Qtel cables…etc

1.17 Archaeological Remains and Historical Sites


The Contractor shall take all necessary precautions not to disturb archaeological
remains and historical sites in the vicinity of the Works including those shown on the
drawings.
During construction of the works the Contractor will check for the discovery of any
artifacts such as pottery, bones, beads and coins. Should any such artifacts be found the
Contractor shall inform KAHRAMAA and the Department of Archaeology and Antiquities
of the Ministry of National Heritage and Culture?

1.18 Execution Program of Works


The Contractor shall submit a detailed and annotated bar charts and critical path method
(C.P.M) by Primavera Program showing a proposed program of design (if any),
delivery, construction, installation and commissioning.
The Program to be submitted by the Contractor shall include the planned monthly rates
and location of progress between the program date for commencement and completion
for each major item of work for various stages of construction, including dates by which
major items and related drawings if any requiring approval will be submitted. A period
not exceeding three weeks shall be allowed from date of receipt of these drawings by
KAHRAMAA to enable his approval to be given, subject to the accuracy of the submittal.
The program shall be updated throughout the project to ensure that all work items are
completed by the Completion Date of the project.

1.19 Standard Specifications


Plant, materials and workmanship shall comply with the requirements of Qatari
Construction Standards (QCS) and British Standards (BS) and Codes of Practice (BSCP)
current at a time three months prior to the time of Tender. KAHRAMAA can accept
equivalent International Standards subject to their requirements are no less stringent.
The electrical installations shall comply with the current KAHRAMAA / Standards.

Tender Documents GTC 177/2007 Page 22 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

The Contractor shall obtain and keep on-site at least one copy of each BS and BSCP and
other approved National or International Standard which is referred to in the
Specification and of each such other Standard which applies to materials which are
being supplied to, or workmanship which is being executed on the works. Copies of
these Standards shall at all times be available for inspection and use by KAHRAMAA but
shall remain the property of the Contractor.
All materials and workmanship not covered by a BS or BSCP or equivalent international
standard shall be of such kind as is used in first class work and suitable for the climate in
the area where the works are to be constructed all shall be subject to KAHRAMAA
approval.

1.20 Materials and Suppliers of Materials


Before ordering or obtaining materials of any description intended for the permanent
works, the Contractor shall submit for the approval of KAHRAMAA the names of the
makers or suppliers proposed, together with country of origin, a specification of the
materials and details of their place of manufacture. The Contractor may be required to
supply to KAHRAMAA for his retention, a copy of each order placed.
The Contractor shall provide samples and third party test certificates of the materials at
the request of KAHRAMAA.
All materials, which are to come in contact with potable water, shall be approved for such
use by the World Health Organization (W.H.O.), European Guidelines (EU) and. The
General Specification of Main Laying Materials for Waterworks published by Qatar
General Electricity & Water Corporation. At KAHRAMAA’S Discretion, materials, which have
been approved by similar National or International bodies, may be allowed.
KAHRAMAA’S decision in such matters is final and the Contractor shall have no right of
appeal.

1.21 Natural Materials


The Contractor shall make all arrangements for locating, selecting and processing natural
materials in accordance with the specification and shall submit to the Engineer for
approval full information regarding the proposed location well in advance of
commencement of working of the material. Approval of a source does not imply that all
material in that source is approved. The Contractor's attention is drawn to the fact that
royalties will be payable on materials from borrow areas and quarries and that it is his
sole responsibility for the payment of such royalties. There shall be no unregulated
quarrying and aggregates shall only be obtained from licensed suppliers or if project
specific sites are proposed the Contractor will be responsible for obtaining the necessary
Environmental Permit.

Tender Documents GTC 177/2007 Page 23 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.22 Works to be Kept Clear of Water


In addition to what mentioned in the Technical Specifications Appendix A, the
Contractor shall keep the works well drained until KAHRAMAA certifies that the whole of
the works is substantially complete and shall ensure that so far as is practicable all work
is carried out in the dry. Excavated areas shall be kept well drained and free from
standing water.
The Contractor shall obtain land, construct, operate and maintain all temporary dams,
watercourses and other works of all kinds, including pumping, that may be necessary to
exclude water from the Works while construction is in progress. Such temporary works
and plant shall not be removed without the approval of KAHRAMAA.

1.23 Discharge of Water in to Existing Streams


The Contractor shall make provision for the discharge or disposal from the works of all
water and waste products however arising and the methods of disposal shall be to the
satisfaction of KAHRAMAA. The requirements of this clause shall not limit any of the
Contractor's obligations or liabilities and shall be at his cost.

1.24 Water Supply


The Contractor shall provide and maintain at his cost suitable supplies of water for
drinking, washing, sanitation and general cleaning in addition to any required for the
construction, testing and maintenance of the Works.
All water for drinking shall be clean according to standards.
The Contractor shall supply all temporary plumbing pipework and storage tanks that
may be required.
He shall pay all fees for connection, disconnection and reinstatement as original for the
site network to main supply and all charges for water consumed.
In case of failure of the city water supply the Contractor is obliged to provide at his own
expense all necessary water requirements to the site to continue all the works in the
project and he may use water tankers for transportation to fulfill this object.

1.25 Electricity Supply


The Contractor shall install, operate, maintain and subsequently remove sufficient
temporary supplies of electricity for the temperature control, lighting and ventilation of
all offices, stores, laboratories and other temporary buildings used by the Contractor
and by KAHRAMAA and by KAHRAMAA in addition to any supplies he may require in
connection with the construction and maintenance of the Works.
He shall pay all fees for connection, disconnection and reinstatement as original and all
charges for electricity consumed.

Tender Documents GTC 177/2007 Page 24 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.26 General Hygiene and Medical Examination of Contractor’s


Employees and Labors
Before commencing work on the site, the Contractor shall ensure that all his employees
and labors are instructed in the necessity for the prevention of pollution and they should
have a health certificate from the concerned authorities. The Contractor shall
immediately dismiss and remove from the site any employee, who has been polluting or
fouling the sites or any of the water supply installations and shall take appropriate
remedial measures to prevent a repetition of the occurrence and to disinfect the areas
concerned, all to the satisfaction of KAHRAMAA.
The Contractor shall not employ upon the site, or on periodic visits thereto, a person
who is known to have any disease or who is suffering from an illness or who are
otherwise unsuited, on medical grounds, to be employed in or around water supply
installations.

1.27 Water Supply, Sanitation and First Aid Facilities for Contractor’s
Staff
The Contractor shall provide on site, to the satisfaction of KAHRAMAA, an adequate
supply of safe drinking and other water and suitable approved sanitary facilities for the
use of the Contractor’s staff and workpeople.
He shall also ensure that sanitary facilities provided for the use of his employees are
kept disinfected and clean at all times during the progress of the Works and cleared
away on completion of the Contract including making good the ground thereafter. The
location of the facilities must be approved prior to erection.
The Contractor shall provide complete first-aid facilities for his staff until the issue of the
certificate of completion. The first aid facilities shall be accommodated in a clean and
tidy office, held in a dustproof cupboard stocked to the satisfaction of KAHRAMAA and
regularly replenished. They shall include an adequate supply of sterile bandages,
disinfectants, spray disinfectants, plasters, scissors, etc.
The toilet and first aid facilities shall be fully available within one week of
commencement of work on site.
The Contractor's disposal methods and areas or tip shall be approved by KAHRAMAA.
No wastes or sewage shall be disposed off or dumped within the site.
Any water connections, pipe runs and drainage pipework provided by the Contractor
shall be to the approval of KAHRAMAA.

1.28 Testing of Works


All tests of the works such as soil compaction, concrete compression …etc, shall be
carried out by third party laboratory approved by KAHRAMAA

Tender Documents GTC 177/2007 Page 25 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.29 Contractor’s Site Facilities


The Contractor shall provide and maintain adequate air-conditioned offices and other
temporary accommodation and facilities for the use of the Contractor’s staff, in addition
to a conference room for site meetings suitable for a minimum of 8 people with table and
chairs.
The Contractor shall provide and maintain temporary facilities for the storage of
materials, tools and tackle and equipment used by all persons employed on site
including sub-Contractors. Those used for the storage of cement and other perishable
materials and the like shall have raised floors.
Based on the organization chart, prior to establishing the site the Contractor shall submit
proposals for the accommodation its facilities and support services for approval by
KAHRAMAA and appropriate government bodies.
The Contractor shall at the completion of the woks be responsible for the removal of his
site facilities, foundations.. etc. and for the general leveling of the area.

1.30 Assistance for KAHRAMAA'S Staff


The Contractor shall provide every assistance to KAHRAMAA and his staff in carrying out
their duties and shall provide a sufficient supply of pegs, poles, paint, lines, spirit levels
and other materials, instruments, gauge and small tools for checking and setting out the
Works. The Contractor shall also provide for KAHRAMAA and his staff (Maximum three)
such waterproof clothing, safety helmets, rubber boots, torches and the like as may
reasonably be required by them. These articles shall remain the property of the
Contractor, and they shall be repaired or replaced by him to the extent necessitated by
fair wear and tear.

1.31 Survey Instruments


The Contractor shall provide all survey and measuring instruments of every kind
necessary for his own use in the execution of the Works, and for KAHRAMAA as per
QCS, Section 1 part 11.
The Contractor shall also provide at the site, and maintain for the sole use of KAHRAMAA
and his staff, the instruments needed which shall revert to the Contractor not later than at
the issue of the Certificate of Acceptance;
Each item shall be approved by KAHRAMAA before being accepted and shall be new at
the start of the Contract.
The Contractor shall be solely responsible for all such instruments and equipment and
shall ensure that they are at all times in good repair and adjustment and shall make good
any loss or damage howsoever caused.

Tender Documents GTC 177/2007 Page 26 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.32 Submittals
All submittal shall be submitted to KAHRAMAA as a minimum two copies and in digital
form as otherwise mentioned and the format of the submittal to be approved / advised
by KAHRAMAA.

1.33 Progress Reports


The Contractor shall submit to KAHRAMAA during the first three days of each month a
progress report in such form that actual progress to the end of the preceding month may
be compared with the Contractor's Program for the site as detailed in Appendix (D).
From time to time KAHRAMAA will call meetings in his office or at the Contractor's or
other office or at the site, as he deems necessary for the purpose of control of the
Contract. Responsible representative of the Contractor shall attend such meeting.

1.34 Forms for Monthly Statements


The Contractor shall provide standard forms for his monthly statements. Such forms
shall be printed or duplicated to A4 size to the approval of the Engineer as soon as
practicable after the order to commence the Works has been given and their layout
shall be as agreed with the Engineer.

1.35 Equipment and Labour Returns


The Contractor shall furnish KAHRAMAA with the following:
¾ Detailed schedules having the form and sub-clauses approved by KAHRAMAA,
stating the number of supervisors of the Works, the number and type of the
several classes of labour employed by the Contractor and his Sub-Contractors
from time to time as required by KAHRAMAA.
¾ Data in respect of Contractor's Equipment as may be required by KAHRAMAA.

1.36 Quality of Materials, Workmanship and Tests


All materials and workmanship shall be of the respective kinds described in the
Contract and in accordance with KAHRAMAA'S instructions and shall be subjected from
time to time to such tests as KAHRAMAA may direct at the place of manufacture or
fabrication, or on the Site or at all or any of such places.
The Contractor shall provide such assistance, instruments, machines, labour and
materials as are normally required for examining, measuring and testing any work and
shall supply samples of materials before incorporation in the Works for testing as may
be selected and required by KAHRAMAA.

Tender Documents GTC 177/2007 Page 27 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.37 Loading Tests for Executed Concrete Structures


The Engineer may direct that a loading test be made or cutting cores from the
structures or any part thereof if he deems such test to be necessary for one or
more of the following reasons:
¾ Failure of ‘Test cubes’ to attain the specified minimum strength.
¾ Premature removal of shuttering.
¾ Overloading of structure during construction.
¾ Improper compaction or curing of concrete.
¾ Any other circumstances attributable to alleged negligence on the part of the
Contractor, which, in the opinion of the Engineer may result in a structure being
of less than expected strength

1.38 Cost of Tests for Materials and Workmanship


The cost of making any test shall be borne by the Contractor if such test is clearly
intended or provided for in the Contract. In the cases only when KAHRAMAA asks for a
test under load or of a test to ascertain whether the design of any finished or partially
finished work is appropriate for the purposes which it was intended to fulfill,
KAHRAMAA shall bear the cost of such tests if they show the workmanship or materials
to comply with the Contract or KAHRAMAA'S instructions.

1.39 Examination of Work Before Covering Up


No work shall be covered up or put out of view without the approval of KAHRAMAA and
the Contractor shall afford full opportunity for KAHRAMAA to examine the works and any
such things before the Permanent Works are placed thereon. The Contractor shall give
due notice to KAHRAMAA whenever such work is ready or about to be ready for
examination and KAHRAMAA shall advises the Contractor accordingly; attend for the
purpose of examining such work or of examining such foundation and any such thing.

1.40 Uncovering and Making Openings


The Contractor shall uncover any part or parts of the Works or make openings in or
through the same as KAHRAMAA may from time to time direct and shall reinstate and
make good such part or parts to the satisfaction of KAHRAMAA. If any such part or parts
have been covered up or put out of view after compliance and are found to be executed
in accordance with the Contract, the expense of uncovering or making openings in or
through or reinstating and making good the same, shall be borne by KAHRAMAA.

Tender Documents GTC 177/2007 Page 28 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.41 Removal of Improper Work


KAHRAMAA shall during the progress of the Works have power to order in writing from
time to time:
¾ The removal from the Site, within such time or times as may be specified in the order,
of any plant and materials which, in the opinion of KAHRAMAA are not in accordance
with the Contract and the substitution by proper and suitable Plant and materials.
¾ The removal and proper re-execution, notwithstanding any previous test thereof or
interim payment therefore, of any work or plant which in respect of materials or
workmanship is not, in the opinion of KAHRAMAA, in accordance with the Contract.

1.42 Photographs
The Contractor shall supply color photographs of such portions of the works, in progress
or completed and indicating the work progress, all as may be directed by KAHRAMAA
and specified herein. The negatives and prints shall not be retouched. The negative of
each photograph shall be the property of KAHRAMAA and shall be delivered to
KAHRAMAA with the prints. No prints of these negatives shall be supplied to any other
person without the written permission of KAHRAMAA.
The photographs shall be in two categories:
¾ Progress photographs – 150 mm x 100 mm
¾ Record photographs – 250 mm x 200 mm
Both categories of photographs shall be properly referenced to the approval of
KAHRAMAA, and on the back of each print shall be recorded the date of the photograph,
the direction in which the camera was facing, and identifying description of the subject,
and the reference.
Photographs taken for record purposes as ordered by KAHRAMAA or as specified
herein shall be supplied with two prints, having the reverse of one subscribed with the
signatures of the Contractor and KAHRAMAA (or their authorized representatives) for
the purpose of attestation. If required the Contractor may at his own expense have an
additional print similarly attested for his retention.
The Contractor shall supply one negative and two prints of each progress photograph
ordered by KAHRAMAA. He shall supply two additional prints of progress photographs
selected by KAHRAMAA for incorporation in albums. He shall supply two sets of albums,
mount the prints and title the prints and albums all to the approval of KAHRAMAA.

1.43 Progress Meetings


The Contractor shall attend regular progress meetings on site, which will be convened
by KAHRAMAA. Monthly meetings will also be held in KAHRAMAA’S Office for which the
Contractor shall submit Progress Reports 2 copies + digital form) containing detailed

Tender Documents GTC 177/2007 Page 29 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

information of progress, resources and progress photographs, at least 72 hours prior to


the monthly meetings.

1.44 Contract Signboards


The Contractor shall supply erect numbers of the contract Signboard in locations to the
approval of the concerned authorities and maintain Contract Sign Boards. The design of
the Contract Sign Board, in line with KAHRAMAA standard details, shall be submitted by
the Contractor to KAHRAMAA for approval. The Contractor shall be responsible for the
structural stability of the signboards but shall submit details of his proposals for support
to KAHRAMAA for approval.

1.45 Operating and Maintenance Instructions


The Contractor shall provide 4 sets suitably bound operating and maintenance
instructions for all plant installed in the works. The introduction shall include a general
description of the works and its operation.
Operating instructions shall give a step procedure for any operation likely to be carried
out during the life of the Plant including erection, commissioning, testing, operation,
maintenance, dismantling and repair.
A separate section shall be allocated for each type of equipment, which shall contain all
relevant information concerning construction and operation of that item.
The manuals shall include but not be limited to the following sections:
¾ An introduction to and general description of the Plant and its operation.
¾ Details of the mechanical and electrical equipment and how they are designed to
operate.
¾ Instructions for routine operation, monitoring and control of processes.
¾ Details of chemicals used for treatment and limits of their normal dosing ranges.
¾ Details of safety considerations and safety procedures and equipment
¾ Instructions for routine maintenance with charts show the quantity and type of
lubricant to be used together with the recommended frequency of application.
¾ Instruction for the stripping, inspection, re-assembly, testing and re-commissioning of
the equipment.
¾ Instructions for the emergency shutdown and start-up procedures including
emergency contacts and phone numbers.
¾ Where applicable, faultfinding charts to assist in locating faults.
¾ Spare parts lists with names and addresses of suppliers and the procedures to be
followed for the purchase of such parts.
¾ A complete list of the equipment supplied with details of manufacturers, model types
and serial numbers.

Tender Documents GTC 177/2007 Page 30 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

¾ Reduced copies of all designs and drawings required to be submitted for approval.
Reduced copies shall be reduced only to a size at which detail is still discernible.
¾ Copies of all test certificates, pump performance curves, etc…
¾ Application software listings.
¾ Maintenance schedules detailing recommended frequency of inspection,
maintenance and overhaul.
¾ Commissioning data and tests.
Reference to Record Drawing shall be included in the instructions.
A collection of manufacturer’s pamphlets, instruction sheets and such like will not be
accepted in place of Operating or Maintenance instructions but may form part of
them.
Information supplied by specialist manufacturers for particular plant items shall be
reproduced in the same detail and shall be included in the appropriate section of the
instructions.
The operations and maintenance manual shall include names, addresses, telex,
contact person … etc, for all manufacturers as well as those of their authorized
representative in the State of Qatar.
As soon as possible after delivery of an item of the plant to the site, and prior to
commencement of commissioning, the Contractor shall submit to the Engineer for his
approval, draft copies in duplicated of the Operating and Maintenance instruction,
applicable to that item. The documents shall be reviewed by the Engineer and the
Contractor shall incorporate all the required additions and alterations. After the
Engineer has given written approval of the documents, the Contractor shall supply 5
copies of the final Operating and Maintenance Instructions
The submission for the approval by the Engineer and subsequent delivery of the
approved instructions shall be condition, which must be fully satisfied prior to the
issue of a Certificate of Completion.

1.46 Drawings for the Project Components


The drawings for the project components shall include the following:

1.47 Issued Drawings


Drawings supplied to the Contractor as part of the Tender Documents for the purposes
of tendering. Such drawing shall be deemed to have been issued for the guidance of
Tenderers and shall be referred to for the interpretation of the Contract

Tender Documents GTC 177/2007 Page 31 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.47.1 Alterations Required By Engineer


Any alteration required by KAHRAMAA to be made to the drawings submitted for
approval shall be made by the Contractor without extra charge, provided that it does not
involve a change in the specification.

1.47.2 Approved Drawings


A drawing, which has been approved by KAHRAMAA and has received his stamp of
approval, will be termed an “Approved Drawing”. A copy of each Approved Drawing
will be retained by the Contractor.
Approved drawings may be required to be amended according to instruction given. In
such case the Contractor shall submit new or amended drawings for approval and when
approval has been given all copies of the superseded Approved drawing shall either be
destroyed or clearly marked “Superseded”.

1.48 Record Documents


1.48.1 Record Drawings
Prior to the issue of the Taking Over Certificate (T.O.C.) of final completion, the
Contractor shall provide two copies on paper of the draft Record Drawings. Within 28
days of receiving KAHRAMAA’S comments on those drafts the Contractor shall make the
necessary amendments and corrections and submit two further copies for approval.
Upon approval, the Contractor shall provide the following:
i) Four bound sets (A1 size) of Record Drawings on paper.
ii) Four bound sets (A3 size) of Record Drawings on paper.
iv) Three sets of CDs (or similar approved format) containing the Record Drawings in
AutoCAD 2000 format.
The drawings shall include but not limited:
¾ General arrangement drawings of the permanent works and longitudinal sections
of all pipelines. All pipeline structures and chambers shall be labelled as shown on
the Issued drawings or as agreed by KAHRAMAA.
¾ Pipeline drawings shall be drawn to a horizontal scale of 1:1000, or as agreed by
KAHRAMAA. They shall contain the full level of detail but also show details of the
washout and air valve branch sizes and the coordinated of all branches and
changes in direction and level.

1.48.2 Record Sheets


The Contractor shall complete the following Record Sheets:-
¾ Pipeline Record Sheet
¾ Pipe Test Record Sheet
¾ Valve Chamber Record Sheet

Tender Documents GTC 177/2007 Page 32 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

¾ Valve Inventory Sheet


Individual Record Sheets shall be prepared for each length of pipeline and each valve
chamber and shall be submitted to KAHRAMAA’S Representative for approval within 14
days of completion of the individual section of the works after which they shall become
the property of KAHRAMAA.
Submission of completed record sheets shall be a prerequisite for payment for the
individual sections of the works in interim valuations.

1.49 Protecting the Works from the Inclement Weather and Damage
The Contractor shall carefully cover up and protect the works or any adjoining property
exposed by the works from inclement weather or severe weather conditions.
The contractor shall properly cure all cement-based construction in order to keep
shrinkage cracks to a minimum and to ensure that the cement becomes fully set.
The Contractor shall protect the installed works from being damaged by any means
whatsoever.

1.50 Working in Urban Areas


The Contractor is advised that a substantial proportion of the Works are to be
constructed in an urban area. As such he should be familiar, and take heed of, the
requirement s and regulations for working in an urban area with respect to the allowable
hours, traffic regulations, noise and pollution mitigation measures and the like. In
particular construction activities within 500 m of a mosque should not occur during
prayer times.
The Contractor shall ensure that roads and thoroughfares used by him for the
transportation of Construction Plant, labour, materials and excavated materials are not
dirtied because of his operations. If, in the opinion of KAHRAMAA, that the Contractor’s
operations result in dirty conditions, the Contractor, upon notification by KAHRAMAA,
shall take all necessary steps to clean roads and thoroughfares so dirtied, at no extra
cost to KAHRAMAA.

1.51 Access to Existing Buildings and Associated Areas


The Contractor shall programme and execute the Works in such a manner to maintain
access to existing buildings; etc at all times as far as is practicably possible. Where
disruption of access is unavoidable, the Contractor shall advise occupants in writing in
advance of the disruption and take all necessary steps to minimize the period of
disruption.
The cost of such work, together with all associated administration, supervision and
incidental costs will be deducted from the Contractor’s monthly payments

Tender Documents GTC 177/2007 Page 33 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.52 Cleaning the Works on Completion


The Contractor shall clean the structures inside and out, removing stains and touching
up paintwork and polished work and leaving the whole of the works clean and ready for
occupation to the satisfaction of KAHRAMAA.
The Contractor shall clear the site and work area completely of all his temporary
installations on completion of the works and shall grade the area he has occupied to
remove all traces of his occupation and leave the site as close to its original condition as
possible.

1.53 Control of Noise and Pollution


The Contractor shall take all necessary precautions to control the level of noise and
pollution, including dust, caused by the progress of the works. Speed limits are to be
imposed on all graded roads in order to minimize dust pollution.

1.54 Qatar Petroleum (QP) Pipelines (Gas and others)


The Contractor shall obtain approvals and excavation permits for all excavation within
25 m of any QP pipelines, and shall comply with all requirements of the permit.
At all QP pipelines crossings, or where QP pipelines are proposed, the DI pipelines shall
have double wrapping of PVC tape with bitumen rubber adhesive or similar of total
thickness 1000 microns giving a zero cathodic effect.
The Contractor shall duly notify QP of all pipeline testing carried out under the Contract
in the Vicinity of QP pipelines sufficiently beforehand so that a QP representative can be
present during the testing. Only hand excavation methods are to be used for QP
pipelines crossings. Crossings shall be made in accordance with the drawings.

1.55 Prevention of Impacts on Urban Amenity


The works should be constructed to avoid, wherever practicable, the destruction of
existing trees. Should any urban trees be destroyed by the works, the Contractor will be
responsible for the provision of an equivalent replacement tree.

1.56 Witness Tests


KAHRAMAA or KAHRAMAA shall be entitled to attend the premises of any of the
Contractors suppliers to witness test for materials, equipment and plant to be
incorporated in the works. The procedures for notice of tests shall be as according to
General Conditions of Contract and shall be on his cost.

Tender Documents GTC 177/2007 Page 34 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.57 Co-Ordination with Other Contractors


The Contractor shall liaise with and co-ordinate his activities with the other Contractor(s)
working at the same site. KAHRAMAA shall not be responsible for any payment or
extension of time arising from or relating to more than one Contractor working in close
proximity to each other.

1.58 Site Safety Policy

1.58.1 General
The Contractor shall submit an organization plan and arrangements for the
implementation of a plan that specifies responsibilities and guidance relating to health
and safety for all employees.
The Contractor must be committed to ensuring that the necessary resources are in place
and are devoted to meeting their objectives. This includes the provision of information
training and instruction required as the needs arise. The performance and standards of
health and safety in each activity will be monitored and reviewed on a continual basis.
The Contractor shall take every opportunity to liaise with the work force. KAHRAMAA
expects every employee to play their part and be committed to high standards of health
and safety at work.

1.58.2 Traffic Regulations


The Contractor shall ascertain and comply with any regulations concerning authorities
for traffic and parking in addition to the obligation imposed by the Conditions of
Contract and by law.

1.58.3 Traffic Control


The Contractor shall provide and maintain all necessary diversions, diversion signs,
barricades, fencing, lighting, flagmen or stop/go signs where the Works affect the safety
of traffic on existing roads or temporary diversion roads.

1.58.4 Noise, Pollution and Nuisance


The Contractor shall ascertain and comply with any regulations concerning noise,
pollution and other nuisance in addition to the obligations imposed by the Conditions of
Contract and by law.

1.58.5 Noise
Compressors, percussion tools and vehicles are to have effective silencers of a type
recommended by the manufacturers of the equipment. Pneumatic drills and other noisy

Tender Documents GTC 177/2007 Page 35 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

appliance shall not be used during days of rest or after normal working hours without
consent of KAHRAMAA’s Representative.

1.58.6 Fire Precautions


The Contractor shall take all necessary measures to prevent personal injury or death or
damage to the Works or other property, including but not limited to:
Provision of fire fighting facilities in all vulnerable areas and as instructed by
KAHRAMAA.
Marking escapes routes and illuminating them if necessary.
Instructing workmen in fire precautions and use of fire fighting equipment.
Displaying notices on fire safety and procedures in the event of a fire on Site.

1.58.7 Nuisance
The Contractor shall take necessary precautions to prevent nuisance from smoke, dust,
rubbish, water, polluted effluent and other causes.

1.58.8 Explosives
Explosives are not to be used. Rock excavation is to be carried out by the use of
jackhammers or other approved methods, however in some cases it can be used upon
the approval of KAHRAMAA and the concerned authorities.

1.58.9 Protection of the Works


Security: The Contractor shall take all measures necessary, including watching and
lighting at night, to prevent unauthorized entry to the Site and to safeguard the Site, the
Works, Materials, Plant, Contractor’s Equipment and Temporary Works against damage
from trespass and theft.
Protection: The Contractor shall cover up and protect each section of completed work
from damage by water, extreme heat and inclement weather or from damage caused by
later operations and shall make good any damage to the satisfaction of KAHRAMAA.
Stability: The Contractor shall ensure that stability and structural integrity of the Works
are maintained during construction and shall provide temporary supports where
necessary and shall not overload any part of the Works with materials. Plant or
Contractor’s Equipment.
Moisture: The Contractor shall prevent any part of the Works from becoming wet or
damp where this may cause damage and shall provide fuel, equipment and attendance
as necessary, to dry out the Works in such a manner as to prevent blistering and failure
of adhesion, damage due to entrapped moisture or excessive movement.

Tender Documents GTC 177/2007 Page 36 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Rubbish: The Contractor shall remove rubbish and debris from the Site as it
accumulates and keep the Works clean and tidy. Rubbish, dirt and debris shall be
removed from voids and cavities before they are sealed.

1.58.10 Protection of Other Property and Services


Roads and Footpaths: The Contractor shall protect public and private roads, footpaths
and the like from damage by site traffic or other causes arising from the execution of the
Works and shall repair any damage to the satisfaction of the relevant public authority or
private owner.
Existing Services: The Contractor shall:
¾ Notify all service authorities and private owners before commencing any work,
which may affect or damage existing drains and services and observe all service
authorities’ regulations and/or recommendations for work adjacent to existing
services.
¾ Ascertain the positions of all services not indicated in the Contract Documents and
check the positions of those, which are so indicated.
¾ Adequately protect, maintain and prevent damage to all services and shall not
interfere with their operation without the consent of the service authority or owners.
If any damage is caused to existing services as a result of execution of the Works, the
Contractor shall notify KAHRAMAA’s Representative and the service authority or private
owner and make arrangements to repair the damage to the satisfaction of the service
authority or private owner as appropriate.
Adjoining Property: The Contractor shall:
¾ Take all reasonable precautions to prevent damage to adjoining property and, if
any damage is caused as a result of the execution of the Works, make good to the
satisfaction of the owner.
¾ Obtain permission of the owners if it is necessary to erect Temporary Works or
otherwise use adjoining property and pay all charges.
¾ Advise owners or occupiers of adjoining property of the dates on which work,
which may affect them, is to be executed.
Existing Condition of roads, paths, features, services and adjoining property, which is at
risk from damage, shall be recorded by photographs or surveys as appropriate.

1.59 Operation, Maintenance & Training to be provided by the


Contractor
Upon the issue of the Certificate of Completion of the Works the Contractor will be
required to provide suitable experienced staff, under the guidance of an Operations /
Training Specialist, to provide day-to-day hands-on training in operation and
maintenance services would be provided to the authority to be responsible for the
operation and maintenance of the works. The services would be required for a period of

Tender Documents GTC 177/2007 Page 37 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

3 calendar months. In addition to the Operations / Training Specialist the staff to be


provided will include a treatment specialist, a SCADA control system specialist and a
mechanical and electrical specialist. The Engineer will have the right to reduce the
number of staff to be provided based on the operating authorities eventual requirement.
The Contractor’s staff will be resident in the project area and all costs associated with the
contractor’s staff will be borne by the Contractor. Three months prior to the expected
completion date of the works the Contractor will submit to the Engineer CV’s of his
proposed staff, who must have the following minimum qualifications.
¾ Operation / and Maintenance Specialist, 15 years total experience, 5 years in the
water supply.
¾ Instrumentation Specialist, 15 years total experience, 5 years in the water supply.
¾ SCADA Control System Specialist, 10 years total experience, 5 years in the water
supply.
¾ Mechanical and Electrical Specialist, 10 years total experience, 5 years in the water
supply.
¾ The engineer will have the right to reject nominated staff without qualification

1.60 Quality Standards and Control

1.60.1 General
The Contractor shall submit a quality control plan for review and approval of
KAHRAMAA. Inspection and test plans shall include hold, witness, review and
certification points.
Good Practice: Where and to the extent that materials, products and workmanship are
not fully specified they are to be of a standard appropriate to the Works and suitable for
the purposes stated in or reasonably to be inferred from the Contract Documents, and in
accordance with good building practice, including the relevant provisions of current
standards, regulations, … etc.

1.60.2 Setting Out and Accuracy


Site Survey: Before commencing Work on Site, the Contractor shall carry out a
topographical survey of the Site, in conjunction with, or as instructed by, KAHRAMAA, or
of such parts of the Site as KAHRAMAA may direct, to record the Site limits, dimensions,
ground levels, obstructions and other features and to establish base lines and points for
future setting out and to record the basis for re-measurement of excavation and
earthwork, where applicable.
Setting Out: Details of methods and equipment to be used in setting out the Works shall
be submitted to KAHRAMAA. The Contractor shall inform KAHRAMAA when setting out
is complete and before commencing construction and shall provide instruments and
assistance for checking the setting out if required by KAHRAMAA.

Tender Documents GTC 177/2007 Page 38 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Record Drawings: The Contractor shall record details of all grid lines, existing ground
level, setting-out stations, bench marks and profiles on the site setting-out drawings;
retain on the Site throughout the duration of the Contract and hand to KAHRAMAA on
completion.
Non-Compliance: Work which fails to meet the specified levels of accuracy must not be
rectified without approval. Submit proposals for such rectification or removal and
replacement and meet all costs arising, including effects on other work.

1.60.3 Materials
Products are to be new unless otherwise specified and are to be handled, stored and
fixed with care to ensure they are not damaged when incorporated in the work.
Standards. For products and materials specified to a national standard, such as BS or
ASTM, certificates of compliance are to be obtained from manufacturers when requested
by KAHRAMAA.
Single Sources: Where a choice of manufacturer or source of supply is allowed for any
particular product or material, the whole quantity required to complete the work must
be of the same type, manufacture and source. Written evidence of sources of supply are
to be provided when requested by KAHRAMAA and sources are not to be changed
without approval.
Checking Compliance of Products and Materials: The Contractor shall check all
delivery tickets, labels, identification marks and where appropriate, the goods
themselves, to ensure that all products comply with the Specification. Where different
types of any product are specified, he shall ensure that the correct type is being used in
each location. In particular, the following shall be checked.
¾ Sources, types, qualities, finishes and colours are correct, and match any
approved samples.
¾ Accessories and fixings, which should be supplied with the goods, have been
supplied.
¾ Sizes and dimensions are correct.
¾ Goods are clean, undamaged and in good condition, with intact protective
coverings and unbroken seals.
¾ Materials, which have a limited shelf life, are not out of date.
¾

Protection of Products and Materials: The Contractor shall:


¾ Prevent over-stressing and any other type of physical damage.
¾ Keep clean and free from contamination and staining.
¾ Keep dry and in a suitably low humidity atmosphere to prevent premature setting,
moisture movement and similar effects. Where appropriate allow free air
movement around and between stored components.

Tender Documents GTC 177/2007 Page 39 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

¾ Prevent excessively high or low temperature and rapid changes of temperature in


the material.
¾ Protect adequately from rain, sun and other elements as appropriate.
¾ Keep different types and grades of materials separately and adequately identified.
So far as possible, keep materials in their original wrappings, packing or containers,
with unbroken seals, until immediately before they are used.

1.60.4 Workmanship
Work is to be carried out by or under the close supervision of experienced tradesmen
skilled in the particular type of work.
Manufacturer’s Recommendations: Products shall be handled, stored, prepared and
used in accordance with manufacturer’s recommendations. The Contractor shall inform
KAHRAMAA if this conflict with any other specified requirement and submit copies of
manufacturer’s recommendations to KAHRAMAA when requested.
Suitability of Previous Work and Conditions: Before starting each new type or section
of work the Contractor shall ensure that:
¾ Previous related work is appropriately complete, in accordance with the project
documents, to a suitable standard and in suitable condition to receive the new
work.
¾ All necessary preparatory work has been carried out including provision for
services, damp proofing, priming and sealing.
Defects in Existing Work: The Contractor shall report to KAHRAMAA if any existing
work is defective and obtain his instructions before proceeding with new work which
may cover up the defective work or which may be adversely affected by the defective
work.
Rectification of Defective Work: If any part of the work is known or is suspected to be
not in accordance with the Contract. The Contractor shall submit proposals to
KAHRAMAA for opening up, inspecting, testing and rectification and carry out
KAHRAMAA’S instructions in relation thereto, including, where so instructed, removal
and reconstruction.

1.60.5 Samples and Approvals


Samples: Where approval of products or materials is specified, the Contractor shall
submit samples or other evidence of suitability. Orders shall not be confirmed or
materials used until approval has been obtained. Approved samples are to be retained
on the Site for comparison with products and materials used in the Works and removed
when no longer required.
Where samples of finished work are specified the Contractor shall obtain approval of
stated characteristics before proceeding with the Works and shall retain approved

Tender Documents GTC 177/2007 Page 40 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

samples on the Site for comparison with the Works. Samples, which are not part of the
finished works, shall be removed when no longer required.
Approvals: Where and to the extent that products, materials or work are specified to be
approved, or KAHRAMAA instructs or requires that they are to be approved, the same
must be supplied and executed to comply with all other requirements and, in respect of
the stated or implied characteristics, either to the express approval of KAHRAMAA, or to
match a sample expressly approved by KAHRAMAA as a standard for the purpose.
Inspection or any other action by KAHRAMAA must not be taken as approval of
materials, products or work unless KAHRAMAA so confirms in writing in express terms
referring to:
¾ Date of inspection
¾ Part of the work inspected
¾ Respects or characteristics, which are approved
¾ Extent and purpose of the approval.
¾ Any associated condition.
Approval, inspection or any other action by KAHRAMAA shall not in any way relieve the
Contractor from his responsibility for the suitability and fitness for purpose of materials,
products or work.

1.60.6 Work at Completion


The Contractor shall clean the Works thoroughly inside and out, removing all splashes,
deposits, and efflorescence, rubbish and surplus materials consequent upon the
execution of the work. Cleaning is to be carried out using both cleaning materials and
methods as recommended by manufacturer of product being cleaned, or in the absence
of such recommendations, cleaning materials and methods approved by KAHRAMAA.
Temporary Markings coverings and protective wrappings shall be removed unless
otherwise instructed by KAHRAMAA.
Partial Possession by Employer: Where the Works are to be completed in sections
and any such section depends for its adequate functioning on work located elsewhere
on the Site, such other work shall be completed in time to permit sectional completion as
required.
Partial Possession by Employer: During execution of the remainder of the Works the
Contract shall ensure that:
Completed sections or parts of the Works have continuous and adequate provision of
services, fire precautions, means of escape and safe access.
Occupants and users are exposed to minimum inconvenience, nuisance and danger.

Tender Documents GTC 177/2007 Page 41 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.61 Data for setting out the Works


The Contractor shall carry out all survey and leveling work to establish reference points
in order to fulfill his obligations.

1.62 Temporary Working Areas


Where any part of the Works are to be constructed on, over, under, in or through land
other than the specified areas or public highways the Contractor shall arrange for
temporary occupation of temporary working areas and such areas shall be deemed to
be part of the Site during the period of occupation.
The Contractor shall arrange also for the serving of any notices required by law in
connection with temporary working areas and the Contractor shall give to the occupier
of each such area 15 days written notice of his intention to enter and shall ensure that his
method of working causes the minimum of disturbance to the land and to its owners and
occupiers. Where necessary similar arrangements shall apply to provide access routes
to temporary working areas and such routes shall be deemed to form part of the
temporary working areas.
The extent of each temporary working area and the period of time for its occupation
shall be such as KAHRAMAA considers necessary having regard to the Contractor’s
reasonable requirements which shall be submitted to KAHRAMAA as soon as practicable
after commencement of the Works and to the Contractor’s programme.
The Contractor shall reinstate temporary working areas to a tidy condition as soon as
possible after other work in those areas has been completed so as to keep the period of
occupation to a minimum.

1.63 Work in Public Highways


Where any work is to be carried out in or adjacent to a public highway (which term for
the purpose of the Specification shall be deemed to mean any street, road, footway or
verge maintainable at public expense), the Contractor shall comply with, amongst other
things, the requirements and recommendations of the police or other authorized body
regarding traffic safety measures for road works current at the time such work is carried
out.

1.64 Traffic Control


Wherever single file traffic is necessary on a highway by reason of the construction of
the works, the Contractor shall provide and maintain a minimum carriageway width in
accordance with the requirements of the Road Traffic and concerned Authorities or in
the absence of any instructions of not less than four meters, or wider where necessary at
curves and junctions, and shall provide operate and maintain sufficient suitable traffic
signs.

Tender Documents GTC 177/2007 Page 42 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

When alternate one-way working of traffic is required, the Contractor shall provide,
operate and maintain sufficient and suitable traffic signs and electric traffic control
lights. Manually operated “Stop-Go” signs will be permitted only if previously agreed
with KAHRAMAA. All written traffic signs shall be in Arabic and English.

1.65 Adjoining Property


If the Contractor’s work will cause unavoidable interference with access to adjoining
property, the Contractor shall first give seven days notice in writing to the occupier of
such property and shall provide temporary means of access for vehicles and
pedestrians.

1.66 Road Closures


No provision has been made for the closure of any road but if the Contractor wishes to
apply for any road closure he shall make all the proper arrangements for the same with
the appropriate person and concerned authorities.
The Contractor shall bear the full responsibility for and cost of any road closure which
may be permitted and shall indemnify KAHRAMAA against any claim whatsoever arising
there from. The Contractor shall not be entitled to any extra payment as a result of
permission for a road closure being refused.

1.67 Obstructions
Should there be any obstructions, which would prevent the Contractor from reasonably
carrying out the Permanent Works, then the Contractor shall inform KAHRAMAA at the
earliest opportunity in order that the Permanent Works may be relocated or the
obstruction removed.

1.68 Site Roads and Access


Except as may be otherwise provided in the Contract, the Contractor shall arrange for,
construct, maintain and afterwards remove and reinstate all temporary site roads and
accesses required for and in connection with the execution of the Works. Reinstatement
shall include restoring the area of such roads and access to at least the degree of safety,
stability and drainage that existed before the Contractor entered the Site.

1.69 Claims for Damage to Persons or Property (Procedure)


Any claim received by KAHRAMAA in respect of matters in which the Contractor is
required under the Contract to indemnify KAHRAMAA will be passed to the Contractor
who shall likewise inform KAHRAMAA of any such claim which is submitted directly to
him by a claimant.

Tender Documents GTC 177/2007 Page 43 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

The Contractor shall do everything necessary, including notifying the insurers of claims
received, to ensure that all claims are settled properly and expeditiously and shall keep
KAHRAMAA informed as to the progress made towards settlement, failing which
KAHRAMAA shall be entitled to make direct payment to claimants of all outstanding
amounts due to them in KAHRAMAA’S opinion and without prejudice to any other
method of recovery to deduct by way of set-off the amounts so paid from sums due or
which become due from KAHRAMAA to the Contractor. If the Contractor receives a
claim, which he considers to be in respect of the matters in which he is to be
indemnified by KAHRAMAA under the Contractor, he shall immediately pass such claim
to KAHRAMAA. All information as aforesaid shall be given in writing and shall be copied
to KAHRAMAA.

1.70 Security of the Works


Watching of the Works shall be provided by the Contractor at his own expense. If
KAHRAMAA considers it necessary he will order in writing that additional watchmen be
provided all at the Contractor’s expense.
Unfenced openings and surface obstructions accessible by the public shall be attended
by day and night and shall be adequately lit at night and where applicable with hazard
warning lights to pedestrians and traffic and in accordance with applicable Traffic Police
Regulations.

1.71 Site to be Kept Tidy


Throughout the progress of his work, the Contractor shall keep the Site and all working
areas in a tidy condition and free from rubbish and waste materials.
Any Temporary Works, Contractor’s Equipment, materials or other things which for the
time being are not required for use by the Contractor may with the written consent of
KAHRAMAA be removed from the Site but otherwise shall be dispersed about the Site in
an orderly fashion and shall be properly and securely stored.

1.72 Safety
KAHRAMAA shall be notified by the Contractor immediately any accident occurs
whether on Site or off Site in which the Contractor is directly involved which results in
any injury to any person whether directly concerned with the Site or whether a third
party. Such initial notification may be verbal and shall be followed by a written
comprehensive report within 24 hours of the accident.
Transportation of any materials by the Contractor shall be in suitable vehicles which
when loaded does not cause spillage and all loads shall be suitably secured. Any
vehicle, which does not comply with this requirement or any of the local traffic
regulations and laws, shall be removed from the Site.

Tender Documents GTC 177/2007 Page 44 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.73 Offices for KAHRAMAA and KAHRAMAA’S Engineer


Within one month of the date of order to commence, the Contractor shall have provided
and erected on site in a location approved by KAHRAMAA an office for the exclusive use
of KAHRAMAA and KAHRAMAA Engineer. The Contractor shall submit his proposals for
the site office to the Engineer for approval before starting construction. The offices shall
be as specified in BOQ 1 items B page 1/3 and QCS.
A car park for two cars shall be constructed adjacent to each office building to provide
shaded accommodation for the sole use of the Engineer’s staff. Vehicle and pedestrian
access to the office shall be maintained and kept free of obstruction at all times.
The office and the materials, surface fittings and furniture shall be new at the start of the
Contract.
The Contractor shall supply soft drink (tea, coffee, cold drink) and daily maintain, clean
all rooms, furniture, fittings and WC’s, throughout the period of the Contract. The offices
shall be heated and air conditioned and lit by electricity. The Contractor shall provide
and replace as necessary gas cylinders and office supplies adequately, plus separate
toilet facilities and bottled potable water for the exclusive use of the Engineer. The
Contractor shall provide full time attendance on site to carry out these duties. Before
placing any orders or delivery any materials or fittings for the office the Contractor shall
obtain the approval of the Engineer in writing as to the location and type of the structure
and the furniture, fittings, and equipment to be supplied. The office and contents shall be
maintained until the Works have been completed and the Certificate of Acceptance has
been issued after which time they shall be removed by the Contractor and the site is
cleared.

1.74 Non-Disruptive Pipeline Specification


1.74.1 Non-Disruptive Pipeline Construction Method - General
A. Method – This section of the Specification details the general requirements for the
design and installation of pipelines by non-disruptive (trenchless) method using
Horizontal Directional Drilling (HDD).
B. Location - The locations of the piping to be installed by Non-Disruptive Methods
are to be agreed during the construction and they are subject to approval by the
Engineer. The Contractor may elect to install additional lengths of pipelines by
non-disruptive method at no extra cost, after approval by the Engineer.
C. Geotechnical - The Contractor shall determine the geotechnical nature of the sub-
soil in the project area and shall satisfy himself as to the requirements for carrying
out non-disruptive pipeline construction in these areas. He shall be responsible for
carrying out any additional geotechnical investigation works prior to tendering
should he consider these necessary. No additional payments shall be made on the
basis of geotechnical nature of the subsoil in the project areas.

Tender Documents GTC 177/2007 Page 45 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

D. Tender Submittal - The Contractor shall provide a method statement for horizontal
directional drilling as part of his tender submittal. The method statement shall
include but not be limited to:
9 Description of method and equipment to be used.
9 Equipment and sub-contractor to be employed.
9 Plan showing location of launch and reception pits
9 Drilling mud or other lubricant to be used as applicable.
9 Pipe material to be used for non-disruptive method.
9 Method of support to pit excavations, watching and lighting.
9 Method of dealing with groundwater, if applicable.
9 Time schedule for completion of work.

E. Permits - Permission to construct non-disruptive pipelines beneath or across roads


must be obtained from the PWA Road Affairs, Kahramaa or other authority if
requested. The approval is also subject to the requirements of the Traffic
Department of the Ministry of Interior. Any permits required related to this work
must be handed to the Engineer before work commences.

F. Quality Assurance – General - Prior to the start of the work, submit satisfactory
evidence to the Engineer that all requirements called for by the concerned
authorities have been complied with. All proposed construction methods and
materials for the under crossing shall be approved by the Engineer and
concerned authorities prior to the crossing operation, and no construction shall be
started until written approval to proceed from the concerned authorities has been
submitted to the Engineer.

G. Submittals: Contractor shall submit detailed engineering shop drawings and


method statement for the final layout and elevations of each non-disruptive
crossing. The Contractor shall be responsible for the design and construction of
the crossings.

H. Experience: Contractor shall provide evidence of experience in non-disruptive


construction techniques proposed for pipes the size of this project or larger and
for lengths equal to or longer than on this project. Contractor shall demonstrate
that he or his sub-contractor has a minimum of ten years experience in the use of
HDD methods.

Tender Documents GTC 177/2007 Page 46 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

I. Standards: Non-Disruptive Method shall be in conformity with the standards


detailed in the Horizontal Directional Drilling Manual published by the North
American Society for Trenchless Technology (NASTT). In addition, the
specifications of the US Pipeline Research Committee publication “Installation of
Pipelines by Horizontal Directional Drilling – Engineering Design Guide” (1995)
as well as DCA “Technical Guidelines for the use of Horizontal Directional Drilling
Techniques” (1995) shall also be followed.

J. Equipment – As a minimum, the Contractor demonstrate the availability of the


following equipment as part of his HDD set-up:
9 HDD Drilling Rig – Minimum 12 Ton Capacity
9 Down-Hole Survey Probe Steering Tool of the wireless probe-type (Radio
detection, Digitrak or equivalent) or the wired type (Russel tool or equivalent) for
mounting inside the drill string.
9 Field Hydraulic Power Pack Unit and Control Cabin
9 Magnetic Grid Surface Tracking System (Tru-Tracker or equivalent)
9 Drill Bits of required sizes capable of drilling through rock as well any other
expected material.
9 Drill extension rods.
9 Reamers of sizes to open pilot hole to required diameter
9 Prefabricated Pulling Heads, swivels, universal joints
9 Butt Fusion Welding Machine

1.74.2 Horizontal Directional Drilling Method


General: The HDD process shall include the installation of launching and reception pits,
boring pilot hole under the road crossing, reaming to enlarge pilot hole to carrier pipe
diameter, application of drilling mud or other lubricating agent as required, and pull
back of carrier pipe through reamed hole.
Routing – Prior to defining the exact route of horizontal directional drilling, the
Contractor shall locate all buried structures and utilities within 3 meters of the proposed
drill-path for mini-HDD applications. The Contractor shall select the crossing route to
keep it to the shortest reasonable distance, where the pipeline can be constructed in one
continuous length; or at least in long multiple segments fused together during insertion
use as straight a drill path as possible, avoid entry and exit elevation differences in
excess of 10 meters. Contractor shall clearly identify space requirements for equipment

Tender Documents GTC 177/2007 Page 47 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

and launching of HDD drilling and pipe pull-back works on plans and obtain approval of
Engineer for his proposed site.
Launching / Reception Pits - The Contractor shall select the location of the drive and
reception pits based on required locations as shown on drawings. The location of
launching and reception pits shall in no case be allowed within the road carriageway.
The location of launching and reception pits shall be designed to minimize the number of
curves and maximize their radii of curvature in the right-of way. The initial pipe side exit
pit shall not exceed 1.25 m Wide x 2.00 m Long. These pits may be incorporated as part
of the permanent works for the Water Main (e.g. Valve Chambers), where possible, with
the approval of the Engineer. All modifications to the pits converting them into Valve
Chambers shall be completed at the contractor’s own expense. Detail of the
modifications shall be submitted to the Engineer for approval, and shall conform to those
shown on the Drawings for chambers.
Pilot Hole - Boring of pilot hole shall be carried out with a continuous string of steel drill
rod. Drilling the pilot hole shall establish the path of the drill rod (drill-path) and
subsequently the location of the pipe to be installed. The bore-head shall be tracked
electronically so as to guide the hole to a pre-designed configuration. The drill-path shall
be designed to creating as large a radius of curvature as possible within the limits of the
right-of-way, thus minimizing pipe curvature, which induces bending stresses and
increases the pull-back load due to the capstan effect.
Pilot Hole Reaming - The Reaming operation shall be carried out using an appropriate
back reamer cutting tool subject to Engineer approval. Cutting tool shall be
appropriately designed for the type of soil to be excavated. The Reaming tool shall be
capable of opening the pilot hole to a diameter slightly larger than the carrier pipeline.
The percentage oversize shall range from 120% to 150% of the carrier pipe diameter.
The Contractor shall detail the number of required reaming passes to the Engineer as
part of his method statement.
Drilling Mud – Drilling mud shall be used where required to stabilize the hole and
remove soil cuttings. Drilling mud shall be used in all locations where drilling hole is not
in rock. Drilling mud shall be bentonite clay (sodium montmorillonite). In rock
excavation another lubricating agent such as water shall be applied. Material shall be
submitted to Engineer for approval as part of method statement.
Pull-Back – The Contractor shall submit to the Engineer all calculations showing expected
pull-back forces on pipe as well as pipe resistance to pull-back based on selected pipe
class and SDR. The pull-back operation shall be carried out to pull the entire carrier
pipeline length in one segment back through the reamed-hole pathway. Proper pipe
handling, cradling, bending minimization, surface inspection, and fusion welding
procedures shall be applied. Axial tension force readings, constant insertion velocity,
mud flow circulation/exit rates, and footage length installed shall be recorded. The
maximum pullback speed shall not exceed 0.5 meters per minute.

Tender Documents GTC 177/2007 Page 48 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

Pipe Material - Pipes to be used for Horizontal Directional Drilling shall be DI pipe as
specified or any other material approved by the Engineer. The Contractor shall submit
full details of the pipes as part of the Tender submission, together with details of previous
works undertaken using similar pipes. The contractor shall submit design calculations for
the pipes including, but not limits to:
a) Pipe and borehole resistance to permanent service traffic loads
b) Pipe resistance to temporary loads encountered during installation including, but
not necessarily limited to pull-back tensile stress.

I. Tolerances - The finished pipeline vertical alignment (invert level) shall be within
+10 cm of the level shown on the drawings. The finished pipeline horizontal
alignment shall be within +10 cm of the alignment shown on the drawings. All
costs associated with the consequent changes in alignment shall be borne by the
Contractor.

J. Survey and Records - The Contractor shall record ground levels prior to
commencement of works. Reliable temporary benchmarks and reference stations
shall be established. The locations of these shall be agreed with the Engineer.
Four reference stations shall be set around each site. Levels shall be taken along
the line of the pipe centerline and at offsets of 5 meters and 10 meters each side of
the pipeline, at meter intervals between launching and

K. Reception Pits - Levels and position shall be tracked using both down-hole
surveyor equipment as well as magnetic field surface-tracking as a cross-check.
Levels shall be taken and recorded on all of the above points at regular intervals
during HDD works. The Contractor shall submit daily records of progress (i.e.
drilling and pull-back forces, torque, penetration rate, pull-rate, volume of
bentonite used, volume of ground water pumped, and any other information as
may be required by the Engineer. The Contractor shall provide As-Built drawings
in plan and profile based on the final course followed by the reamer and the
installed pipeline.

Tender Documents GTC 177/2007 Page 49 of 50 Scope of Works and Specifications


Qatar General Electricity & Water Corporation
TENDER NO. GTC 177/2007
Head works Construction at Airport, Old Salwa,
Doha SW & Messaieed Town

1.75 Works at Road Crossings


Subsequent to trench excavation at road crossings, all pipe works shall be backfilled and
reinstated (either permanently or with minimum 100 mm thick grade 20 temporary
concrete without additional cost) such that trenches at road crossing are not kept open
more than three calendar days without Kahramaa prior approval. A successful hydraulic
test for water mains at road crossings remains the contractor's responsibility.

Tender Documents GTC 177/2007 Page 50 of 50 Scope of Works and Specifications

You might also like